October 18, 2019 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 Technical Requirements Manual Change Summary NRC 2019-0034 10 CFR 50.71(e)

In accordance with 10 CFR 50.71(e), NextEra Energy Point Beach, LLC (NextEra), is submitting changes made to the Point Beach Nuclear Plant Technical Requirements Manual (TRM).

The enclosure contains the TRM change summary for the period April 1, 2018, through October 1, 2019. NextEra previously submitted the TRM change summary for January 1, 2016, through March 31, 2018 on May 2, 2018.

This letter contains no new commitments and no revisions to existing commitments.

If you have any questions or require additional information, please contact me at (920) 755-7854.

Sincerely, NextEra Energy Point Beach, LLC Eric Schultz Licensing Manager Enclosure cc:

Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC NextEra Energy Point Beach, LLC 6610 Nuclear Road, Two Rivers, WI 54241

Affected Section TRM 4.5 TRM 4.19 TRM 4.18 TRM 4.13 TRM 4.11 TRM 3.7.9 TRM 4.1 TRM 4.2 TRM 4.4 TRM 4.11 TRM 4.15 ENCLOSURE NEXTERA ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 TECHNICAL REQUIREMENTS MANUAL CHANGE

SUMMARY

FOR April1, 2018-October 1, 2019 Affected Date of Change Page(s)

Summary 04/30/2018 All Changed the version of the software user's manual.

Removed "floppy disk", data; the data is maintained on a different media 04/30/2018 All New TRM -Surveillance Frequency Control Program 06/06/2018 4.18-1 Revised Fleet Procedure numbering 06/06/2018 4.13-1 Revised Fleet Procedure numberinq 07/27/2018 4.11.1 Revised procedure references and calibration frequency 4.11-2 per Engineering Change EC 287280, upgrades to the Z-46 gas analyzer system.

12/14/2018 3.7.9-1 Removed "Radiological, Smoke and Chemical Hazards" 3.7.9-3 as an APPLICABILITY-these are not MODES of applicability. Replaced an "OR" with an "AND" to align with the TS.

04/02/2019 4.1-4 Revised a Reference title 04/02/2019 4.2-3 Revised a Reference title 04/02/2019 4.4-3 Revised a Reference title 04/02/2019 4.11-3 Revised a Reference title 04/02/2019 4.15-3 Revised a Reference title Page 1 of 1