Central Emergency Control Center Emergency Plan Implementing Procedure Revision
ML20276A336
Person / Time
Site: Browns Ferry, Watts Bar, Sequoyah  Tennessee Valley Authority icon.png
Issue date: 10/02/2020
From: Jerrica Johnson
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
CNL-20-080
Download: ML20276A336 (2)


Text

Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-20-080 October 2, 2020 10 CFR 50.54(q) 10 CFR 72.44(f)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, 50-296, and 72-052 Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327, 50-328, and 72-034 Watts Bar Nuclear Plant, Units 1 and 2 Facility Operating License Nos. NPF-90 and NPF-96 NRC Docket Nos. 50-390, 50-391, and 72-1048

Subject:

TENNESSEE VALLEY AUTHORITY - CENTRAL EMERGENCY CONTROL CENTER EMERGENCY PLAN IMPLEMENTING PROCEDURE REVISION In accordance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 50.54(q) and 10 CFR 72.44(f), Tennessee Valley Authority (TVA) is submitting a description of changes to the TVA Radiological Emergency Plan (REP). The affected document is a Central Emergency Control Center (CECC) Emergency Plan Implementing Procedure (EPIP).

Document Revision Title Effective Date CECC EPIP-12 34 Operational Readiness Check of the CECC and 9/9/2020 the Field Coordination Centers for SQN, BFN, &

WBN and Joint Information Centers (JIC)

U.S. Nuclear Regulatory Commission CNL-20-080 Page 2 October 2, 2020 Description of Changes and Summary of Analysis CECC EPIP-12 TVA made editorial changes with this EPIP revision to correct the log for a prior revision, to list the revised storage location of CECC and NRC badges, to add lines related to the seal on the JIC cage, and to add portable generators to the inventory. Several other editorial changes with respect to positions, phone numbers, communications equipment, and audio/visual equipment were made as a result of the remodeling of the CECC.

The above changes were evaluated in accordance with 10 CFR 50.54(q)(3) and 10 CFR 72.44(f). TVA determined that the changes did not reduce the effectiveness of the TVA REP. The TVA REP, as revised, continues to meet the requirements in Appendix E to 10 CFR 50 and the planning standards of 10 CFR 50.47(b).

There are no new regulatory commitments associated with this submittal. If you have any questions regarding this information, please contact Gordon Williams, Senior Manager, Fleet Licensing (Acting) at (423) 751-2687.

Respectfully, Jonathan T. Johnson Director, Nuclear Regulatory Affairs (Acting) cc:

NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant NRC Project Manager - Sequoyah Nuclear Plant NRC Project Manager - Watts Bar Nuclear Plant NRC Director - Division of Spent Fuel Management, NMSS