MONTHYEARML24023A0652024-01-23023 January 2024 Inservice Inspection Request for Information IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle ML23178A0892023-06-26026 June 2023 August 2023 Emergency Preparedness Program Inspection-Request for Information ML23118A3202023-05-0808 May 2023 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000313;05000368/2023010) ML22229A4862022-08-23023 August 2022 ANO Inspection Plan Letter 2022 Mid Cycle-FINAL ML22122A2952022-05-0404 May 2022 Notification of Inspection NRC Inspection Report 05000368/2022003 and Request for Information ML22075A2052022-03-31031 March 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection (05000313/2022002 and 05000368/20220020 and Request for Information ML22083A2182022-03-30030 March 2022 NRC Initial Operator Licensing Operating Test Approval 05000313/2022301 IR 05000313/20210062022-03-0202 March 2022 Annual Assessment Letter for Arkansas Nuclear One, Units 1 & 2 (Report 05000313/2021006 and 05000368/2021006) ML21286A7132021-10-15015 October 2021 ANO2022010 Tfp RFI Stg, Arkansas Nuclear One, Units 1 and 2 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000313/2022010 and 05000368/2022010) and Request for Information ML21232A2232021-09-0101 September 2021 ANO Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21215A2932021-08-0303 August 2021 Inservice Inspection Request for Information ML21109A2432021-04-19019 April 2021 Arkansan Nuclear One, Unit 1 - Notification of Inspection (NRC Inspection Report 05000313/2021003) and Request for Information ML21077A0162021-03-22022 March 2021 Notification of NRC Design Bases Assurance Inspection (Team) (05000313/2021010 and 05000368/2021010) and Initial Request for Information IR 05000313/20200062021-03-0303 March 2021 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2020006 and 05000368/2020006) ML21053A4032021-02-23023 February 2021 Document Request List - ANO IR 2021402 IR 05000313/20200052020-09-0101 September 2020 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Reports 05000313/2020005 and 05000368/2020005) ML20119A0982020-04-28028 April 2020 Notification of Inspection (NRC Inspection Report 05000368/2020003 and Request for Information ML20106E8522020-04-13013 April 2020 Information Request, NRC Inspection Report 05000313/2020410 and 05000368/2020410 IR 05000313/20190062020-03-0303 March 2020 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2019006 and 05000368/2019006) ML19331A3132019-11-27027 November 2019 ANO Unit 2 Request for Information IR 05000313/20190052019-08-30030 August 2019 Updated Inspection Plan for Arkansas Nuclear One, Unit 1 and 2, Report 05000313/2019005 and 05000368/2019005 ML19080A0372019-03-21021 March 2019 Notification of Inspection (NRC Inspection Report 05000313/2019003 and Request for Information ML18324A8052018-11-19019 November 2018 Notification of an NRC Triennial Fire Protection Baseline Inspection Report 05000313/2019010 and 05000368/2019010) and Request for Information IR 05000313/20180052018-08-31031 August 2018 Updated Inspection Plan for Arkansas Nuclear One (Report 05000313/2018005 and 05000368/2018005) ML18164A3892018-06-14014 June 2018 Arkansas, Notification of NRC Design Bases Assurance Inspection (Teams) (05000313/2018011 and 05000368/2018011), and Initial Request for Information IR 05000313/20170052017-08-28028 August 2017 Arkansas, Units 1 and 2, Update Inspection Plan (Report 05000313/2017005 and 05000368/2017005) IR 05000313/20160062017-03-0101 March 2017 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2016006 and 05000368/2016006) IR 05000313/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2016005 and 05000368/2016005) IR 05000313/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Arkansas Nuclear One NRC Physical Security Inspection Report Numbers 05000313/2016401 and 05000368/2016401) ML16237A4122016-08-31031 August 2016 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2016005 and 05000368/2016005) ML16223A4622016-08-0909 August 2016 Inspection Planning Considerations for ANO CAL Follow-Up Pkg IR 05000313/20150062016-03-0202 March 2016 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2015006 and 05000368/2015006) IR 05000313/20154012015-09-0101 September 2015 Non-Public Security Inspection Plan for Arkansas Nuclear One(Nrc Physical Security Inspection Report Numbers 05000313/2015401 and 05000368/2015401) IR 05000313/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2015005 and 05000368/2015005) IR 05000313/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Arkansas Nuclear One (NRC Physical Security Inspection Report Numbers 05000313/2014402 and 05000368/2014402) IR 05000313/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2014006 and 05000368/2014006) IR 05000313/20130012014-03-0404 March 2014 Annual Assessment Letter for Arkansas Nuclear One Units 1 and 2 (Report 05000313/2013001 and 05000368/2013001) IR 05000313/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313-13-006 and 05000368-13-006) IR 05000313/20128012013-03-0404 March 2013 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2012801 and 05000368/2012801) IR 05000313/20120062012-09-0404 September 2012 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 & 2 (Reports 05000313-12-006 and 05000368-12-006) IR 05000313/20120012012-03-0505 March 2012 Annual Assessment Letter for Arkansas Nuclear One - Units 1 and 2 (Report 05000313/2012001 and 05000368/2012001) ML1124403662011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - Arkansas Nuclear One, Units 1 and 2 IR 05000313/20110012011-03-0404 March 2011 Annual Assessment Letter for Arkansas Nuclear One Units 1 & 2 (Report 05000313-11-001 and 05000368-11-001) ML1024305372010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Arkansas Nuclear One IR 05000313/20100012010-03-0303 March 2010 Annual Assessment Letter - Arkansas Nuclear One (Report 05000313-10-001 and 05000368-10-001) 2CAN110904, Snubber Testing Program for Fourth Inspection Interval2009-11-10010 November 2009 Snubber Testing Program for Fourth Inspection Interval ML0924001192009-09-0101 September 2009 9/1/2009 Arkansas Nuclear One 2009 Midcycle Performance Review and Inspection Plan ML0906303132009-03-0404 March 2009 Annual Assessment Letter and Inspection Plan 2008 (NRC Inspection Report 05000313/368-2009001) 2024-01-23
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23019A0672023-01-19019 January 2023 Inservice Inspection Request for Information ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22213A1662022-08-0101 August 2022 Information Request, Security IR 2022401 ML22208A0542022-07-26026 July 2022 Request for Information ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22159A3242022-06-0909 June 2022 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000313/2022003 and 05000368/2022003) and Request for Information ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22122A2952022-05-0404 May 2022 Notification of Inspection NRC Inspection Report 05000368/2022003 and Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21286A7132021-10-15015 October 2021 ANO2022010 Tfp RFI Stg, Arkansas Nuclear One, Units 1 and 2 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000313/2022010 and 05000368/2022010) and Request for Information ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21236A3222021-09-19019 September 2021 Request for Information ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21204A0842021-07-28028 July 2021 ANO Phase 4 2021013 RFI Gap ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 0CAN042105, Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operation'S Quality Assurance Program Manual Description2021-04-30030 April 2021 Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operation'S Quality Assurance Program Manual Description ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping ML21105A0122021-04-0909 April 2021 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Adopt a Safety Function Determination Program ML21071A2172021-03-10010 March 2021 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Proposed Change to Quality Assurance Program Manual ML21026A2682021-01-26026 January 2021 Request for Information ML21022A0842021-01-22022 January 2021 Request for Additional Information - Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of Emergency Cooling Pond Supply Piping - Arkansas Nuclear One,Units 1 and 2 -Entergy Operations, Inc. NON-PROPRIETARY Redacted ML21019A5142021-01-14014 January 2021 March 2021 Emergency Preparedness Exercise Inspection - Request for Information ML20324A6412020-11-19019 November 2020 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-034 ML20316A0102020-11-0202 November 2020 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Concerning Relief Request EN-20-RR-01 ML20262H0752020-09-17017 September 2020 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20260H4762020-09-0909 September 2020 NRR E-mail Capture - ANO-1 Final RAI License Amendment Request to Revise Lov Relay Allowable Values ML20154K7622020-06-0101 June 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20119A0982020-04-28028 April 2020 Notification of Inspection (NRC Inspection Report 05000368/2020003 and Request for Information ML20106E8522020-04-13013 April 2020 Information Request, NRC Inspection Report 05000313/2020410 and 05000368/2020410 ML20065H7992020-03-0606 March 2020 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Revise Loss of Voltage Relay Allowable Values ML20055E9092020-02-24024 February 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Revise Control Element Assembly Drop Time ML20036D3092020-02-0505 February 2020 NRR E-mail Capture - ANO-2 - Final RAI Alternative Request VRR-ANO2-2019-1 ML20013C7472020-01-10010 January 2020 NRR E-mail Capture - ANO-1 and 2 -- Final RAI #2 LAR to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19316A0242019-11-0707 November 2019 NRR E-mail Capture - ANO-1 - - Final RAI Concerning Relief Request ANO1-ISI-033 (L-2019-LLR-0100) ML19280A0402019-10-0707 October 2019 NRR E-mail Capture - ANO-1 and 2 - Final RAI #1 License Amendment Request to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19339F5902019-09-23023 September 2019 Request for Information: Arkansas Nuclear One, IR 05000313/2019-004 Occupational Radiation Safety Inspection ML19281E0032019-08-0505 August 2019 ANO 2019 PIR Request for Information ML19203A0122019-07-16016 July 2019 Request for Information - Inservice Inspection Activities (NRC Inspection Report 05000313/2019004) ML19106A4322019-04-16016 April 2019 NRR E-mail Capture - ANO-2 Final RAI Re LAR to Add TS Actions to Address Inoperability of the Containment Building Sump ML19058A8332019-02-27027 February 2019 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-032 ML18324A8052018-11-19019 November 2018 Notification of an NRC Triennial Fire Protection Baseline Inspection Report 05000313/2019010 and 05000368/2019010) and Request for Information ML18263A3022018-09-19019 September 2018 NRR E-mail Capture - ANO-1 - Final RAI License Amendment Request to Adopt TSTF-425, Revision 3 ML18263A1482018-09-11011 September 2018 NRR E-mail Capture - ANO-2 - Final RAI #2 LAR to Update the RCS Pressure-Temperature Limits 2023-05-17
[Table view] |
See also: IR 05000313/2020410
Text
ML20106E852
PAPERWORK REDUCTION ACT STATEMENT
This letter contains mandatory information collections that are subject to the Paperwork
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)
approved these information collections (approval number 3150-0011). Send comments
regarding this information collection to the Information Services Branch, Office of the Chief
Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office
of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and
Budget, Washington, DC 20503.
Public Protection Notification
The NRC may not conduct nor sponsor, and a person is not required to respond to, a request
for information or an information collection requirement unless the requesting document
displays a currently valid OMB control number.
ML20106E852
Information Request
April 13, 2010
Arkansas Nuclear One
NRC Inspection Report
05000313 /2020410 AND 05000368 /2020410
Inspection Date: May 11-15, 2020
Please provide information to the inspector for in-office inspection and review by May 1, 2020.
It is preferable that Items be provided electronically, disc, email or IMS-Certrec. Please do not
send any SGI documents; they will be reviewed by the inspectors on site. If you find any
information that will be difficult to obtain due to COVID-19 CDC or site restrictions please
contact Michael Chambers by phone, 305.338.3038, or email to resolve. Thank you in advance
for your assistance. Please send any hard copy or discs to Michael Chambers at the work-at-
home address below. Again, please do not send any SGI documents to this address.
Send to: U.S. Nuclear Regulatory Commission
Attention: Michael Chambers
915 CR106
Buckholts, Texas 76518
Michael.Chambers@nrc.gov
To keep the requested information organized, please submit the information to us using the
same lettering system below. For example, all contacts and phone numbers for each of the first
inspection procedures should be in a file/folder titled 1- A, applicable organization charts in
file/folder 1- B, etc.
General: All Security Event Log entries since September 1, 2019, (the last .02 inspection).
Security Program Procedure index for all procedures, instructions, desk-top guides, standing
orders etc.
1. Access Control (71130.02) (Effective Date: January 1, 2019)
A. Condition report (CR) summaries related to access control from the last Access Control
inspection (September 1, 2019) to present. Include full reports/data on CRs:
CR-ANO-C-2020-00482, CR-ANO-C-2020-00509, CR ANO 2-2020-1439,
CR-ANO-C-2020-0567
B. Any Access Control policy, procedure, desk-top guide, or any other type of lower tier
instruction type document you may use, such as: access termination procedures, lock
and key control procedures, and access control and search procedures for personnel,
packages and vehicles
C. Lock and key control documentation.
D. A list of all personnel denied access to your facility for reasons of trustworthiness and
reliability that had access to protected area and/or vital area keys and cores from the last
inspection to present
2
E. Security personnel staffing records (shift manning)
F. Security Program Reviews, audits, or self-assessments which address Access Control
from the last inspection (September 1, 2019) to present.
LAST ITEM FOR SECTION 1 OF REQUEST
2. Security Plan Changes (71130.09) (Effective Date: January 1, 2020)
Please be prepared to provide the following items during the onsite inspection:
A. The latest version of the Physical Security Plan.
B. The security plan revision used during the last security plan changes inspection.
C. All security plan changes that have been submitted to the NRC since the last security
plan changes inspection.
D. Procedures associated with plan changes since the last security plan changes
inspection.
E. Training material (i.e., lesson plans, briefing materials, computer-based training)
developed to provide training to personnel responsible for implementing the plan
change(s) since last security plan changes inspection.
LAST ITEM FOR SECTION 2 OF REQUEST
3. Performance Indicator Verification (71151) (Effective Date: January 1, 2017)
Please be prepared to provide the PIV records during the onsite inspection.
LAST ITEM FOR SECTION 3 OF REQUEST
Following arrival on site the inspectors would like to discuss support for items that typically
impact normal operations:
TBD- Access Control/search equipment testing
TBD- Times and days for warehouse package search; vehicle search; personnel search
TBD All proposed interviews involving key personnel
TBD Actual exit meeting will be based upon IP sample completion
3