MONTHYEARML23269A0232023-09-22022 September 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - TSTF-505 Audit Questions ML23240A3412023-08-28028 August 2023 NRR E-mail Capture - ANO-2, Grand Gulf, and River Bend - Acceptance Review of LAR Revising TSs to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23194A1752023-07-13013 July 2023 NRR E-mail Capture - ANO-1 - Acceptance Review of Alternative Request ANO1-ISI-037 ML23187A0432023-07-0303 July 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 1 - TSTF-505 Audit Agenda ML23166A0132023-06-14014 June 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 1 - TSTF-505 Audit Questions ML23130A2752023-05-10010 May 2023 NRR E-mail Capture - ANO Unit 2- Acceptance of Requested Licensing Action LAR to Adopt TSTF-505 Revision 2 ML23118A0692023-04-28028 April 2023 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Modify ANO-1 TS 3.3.1, Reactor Protection System Instrumentation (L-2023-LLA-0048) ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23039A0872023-02-0808 February 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - Acceptance Review of Relief Request ANO2-RR-23-001, Half-Nozzle Repair of RVCH Penetration 46 (L-2023-LLR-0000) ML23026A1322023-01-26026 January 2023 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Adopt TSTF-505 Revision 2 ML22354A0122022-12-19019 December 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Acceptance Review of Request for Alternative ANO-CISI-002 Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (L-2022-LLR-0080) ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22341A1202022-12-0707 December 2022 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation (L-2022-LLA-0161) ML22273A0982022-09-30030 September 2022 NRR E-mail Capture - ANO Units 1 and 2 - Acceptance of Requested Licensing Action Emergency Plan Staffing Requirements ML22265A2012022-09-22022 September 2022 NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Request ANO1-ISI-036 ML22188A1782022-07-0707 July 2022 NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Request ANO1-ISI-035 ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22081A3902022-03-22022 March 2022 NRR E-mail Capture - ANO-2 - Acceptance Review of Relief Requests ANO2-ISI-023, -024, -025, -026, -027, and -028 (Epids: L-2022-LLR-022, -023, -024, -025, -026, and -027) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML22020A0742022-01-13013 January 2022 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action Alternative ANO2-PT-003 ML21314A1212021-11-0909 November 2021 Verbal Authorization of Relief Request ANO2-RR-21-002 ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21287A1692021-10-13013 October 2021 Record of 10-13-21 Verbal Authorization of ANO2-R&R-012 (L-2021-LLR-0082) ML21298A1562021-10-11011 October 2021 NRR E-mail Capture - ANO-2 Final RAI Relief Request ANO2-R&R-012 Concerning Rv Closure Head Penetration 46 ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21238A3742021-08-23023 August 2021 RFI Email - Cyber PI&R Inspection (ANO) ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21202A1662021-07-20020 July 2021 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action Alternative ANO2-PT-003 ML21201A0062021-07-19019 July 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 ML21179A0052021-06-25025 June 2021 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21179A0042021-06-25025 June 2021 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping ML21105A0122021-04-0909 April 2021 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Adopt a Safety Function Determination Program ML21074A2552021-03-15015 March 2021 NRR E-mail Capture - ANO-1 and ANO-2 - Acceptance of Requested Licensing Action LAR for One-Time Change to Support Upgrade of the ECP Supply Piping ML21071A2172021-03-10010 March 2021 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Proposed Change to Quality Assurance Program Manual ML21022A1692021-01-22022 January 2021 NRR E-mail Capture - Entergy Fleet (ANO, Grand Gulf, River Bend, and Waterford) - Acceptance Review for RR EN-20-RR-003, Proposed Alternative to Use ASME Code Case N-711-2 ML21019A5142021-01-14014 January 2021 March 2021 Emergency Preparedness Exercise Inspection - Request for Information ML20356A1142020-12-17017 December 2020 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action LAR Concerning LCO 3.0.6 and Proposed Adoption of SFDP ML20350B7602020-12-14014 December 2020 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - Acceptance Review of Request to Use Alternative Examination Requirements - ANO2-ISI-022 2023-09-22
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23019A0672023-01-19019 January 2023 Inservice Inspection Request for Information ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22213A1662022-08-0101 August 2022 Information Request, Security IR 2022401 ML22208A0542022-07-26026 July 2022 Request for Information ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22159A3242022-06-0909 June 2022 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000313/2022003 and 05000368/2022003) and Request for Information ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22122A2952022-05-0404 May 2022 Notification of Inspection NRC Inspection Report 05000368/2022003 and Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21286A7132021-10-15015 October 2021 ANO2022010 Tfp RFI Stg, Arkansas Nuclear One, Units 1 and 2 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000313/2022010 and 05000368/2022010) and Request for Information ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21236A3222021-09-19019 September 2021 Request for Information ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21204A0842021-07-28028 July 2021 ANO Phase 4 2021013 RFI Gap ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 0CAN042105, Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operation'S Quality Assurance Program Manual Description2021-04-30030 April 2021 Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operation'S Quality Assurance Program Manual Description ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping ML21105A0122021-04-0909 April 2021 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Adopt a Safety Function Determination Program ML21071A2172021-03-10010 March 2021 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Proposed Change to Quality Assurance Program Manual ML21026A2682021-01-26026 January 2021 Request for Information ML21022A0842021-01-22022 January 2021 Request for Additional Information - Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of Emergency Cooling Pond Supply Piping - Arkansas Nuclear One,Units 1 and 2 -Entergy Operations, Inc. NON-PROPRIETARY Redacted ML21019A5142021-01-14014 January 2021 March 2021 Emergency Preparedness Exercise Inspection - Request for Information ML20324A6412020-11-19019 November 2020 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-034 ML20316A0102020-11-0202 November 2020 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Concerning Relief Request EN-20-RR-01 ML20262H0752020-09-17017 September 2020 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20260H4762020-09-0909 September 2020 NRR E-mail Capture - ANO-1 Final RAI License Amendment Request to Revise Lov Relay Allowable Values ML20154K7622020-06-0101 June 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20119A0982020-04-28028 April 2020 Notification of Inspection (NRC Inspection Report 05000368/2020003 and Request for Information ML20106E8522020-04-13013 April 2020 Information Request, NRC Inspection Report 05000313/2020410 and 05000368/2020410 ML20065H7992020-03-0606 March 2020 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Revise Loss of Voltage Relay Allowable Values ML20055E9092020-02-24024 February 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Revise Control Element Assembly Drop Time ML20036D3092020-02-0505 February 2020 NRR E-mail Capture - ANO-2 - Final RAI Alternative Request VRR-ANO2-2019-1 ML20013C7472020-01-10010 January 2020 NRR E-mail Capture - ANO-1 and 2 -- Final RAI #2 LAR to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19316A0242019-11-0707 November 2019 NRR E-mail Capture - ANO-1 - - Final RAI Concerning Relief Request ANO1-ISI-033 (L-2019-LLR-0100) ML19280A0402019-10-0707 October 2019 NRR E-mail Capture - ANO-1 and 2 - Final RAI #1 License Amendment Request to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19339F5902019-09-23023 September 2019 Request for Information: Arkansas Nuclear One, IR 05000313/2019-004 Occupational Radiation Safety Inspection ML19281E0032019-08-0505 August 2019 ANO 2019 PIR Request for Information ML19203A0122019-07-16016 July 2019 Request for Information - Inservice Inspection Activities (NRC Inspection Report 05000313/2019004) ML19106A4322019-04-16016 April 2019 NRR E-mail Capture - ANO-2 Final RAI Re LAR to Add TS Actions to Address Inoperability of the Containment Building Sump ML19058A8332019-02-27027 February 2019 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-032 ML18324A8052018-11-19019 November 2018 Notification of an NRC Triennial Fire Protection Baseline Inspection Report 05000313/2019010 and 05000368/2019010) and Request for Information ML18263A3022018-09-19019 September 2018 NRR E-mail Capture - ANO-1 - Final RAI License Amendment Request to Adopt TSTF-425, Revision 3 ML18263A1482018-09-11011 September 2018 NRR E-mail Capture - ANO-2 - Final RAI #2 LAR to Update the RCS Pressure-Temperature Limits 2023-05-17
[Table view] |
Text
From: Hedger, Sean To: Toben, Joshua Cc: MOSHER, NATALIE B
Subject:
RFI for Arkansas Nuclear One EP Exercise Inspection (August 2022)
Date: Tuesday, May 31, 2022 3:12:00 PM Attachments: ANO EP Exercise Inspection RFI 2022.pdf Mr. Toben, Ms. Mosher:
This e-mail serves to transmit a request for information to support and prepare for the Emergency Preparedness (EP) Exercise inspection at Arkansas Nuclear One, scheduled to occur the week of August 8, 2022.
By design, the biennial EP Exercise inspection includes the use of Inspection Procedures (IP) 71114.01, 71114.04, 71114.08, and 71151, to assess the overall health and maintenance of the stations EP program during the inspection year when the biennial EP Program inspection is not conducted. Details of the requested materials are included in the attachment to this e-mail. As noted in the attached, due to the ongoing Public Health Emergency, if possible, please make the requested materials available to me in electronic format using the online document portal of the stations choice, by the dates stated within the attachment. If you are unable to complete the request by this date, please contact me at the phone number listed below to discuss alternative options.
This letter/e-mail does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget under control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
This email and its enclosures will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sean Hedger Senior Emergency Preparedness Inspector NRC, Region IV 817-200-1556
Request for Information for EP Exercise and Performance Indicator Verification Inspection Dockets 05000313, 05000368 (Arkansas Nuclear One) Inspection Report 2022003 Inspection Procedures 71114.08, 71114.01, 71114.04, and 71151 Draft Scenario In-Office Review: June 9 - July 8, 2022 Onsite/Inspection Week: August 8 - 12, 2022 Please provide the following to support the inspection consistent with the methods and timeframes listed for each.
- 1) IP 71114.08: Exercise Evaluation - Scenario Review a) The licensee will be submitting the draft exercise scenario package to the NRC, with the 60-day submission due date of 06/09/2022. The inspectors will conduct a review of the scenario over the coming weeks in accordance with IP 71114.08.
The NRC Lead Inspector will schedule a teleconference to communicate the inspectors comments and observations associated with the review of the scenario no later than 30 days prior to the exercise. Since 07/09/2022 is on a weekend, a plan is being developed to conduct a teleconference providing comments July 6 or 7, 2022.
b) Consistent with the new NRC Temporary Staff Guidance (NSIR/TSG 2020-02, Temporary Staff Guidance - Additional Guidance for EP Inspections During the PHE),
the NRC inspectors are expected to obtain and review Extent of Play agreements for both the onsite and ORO performance prior to the conduct of the exercise, depending on the applicable regulatory requirements the licensee chooses to demonstrate (e.g., 10 CFR Part 50, Appendix E, Section IV.F.2.b and/or 2.c). Specific guidance in Section 3.9 and Attachments 1 and 2 of the TSG describe the bases and scope of the review. As such, please provide a copy of all Extent of Play agreements associated with the August 9, 2022 plume phase exercise once they are available.
- 2) IP 71114.01: Exercise Evaluation a) First day of Onsite Inspection (08/08/2022) - Please provide hard/paper copies of the final, full Exercise Manual, one copy per inspector (4 total).
b) First day of Inspection (08/08/2022) - Provide a single hard copy document of the current site Emergency Plan and complete set of Emergency Plan Implementing Procedures. These will be used/referenced by the inspection team and returned at the conclusion of the exercise inspection week.
c) No later than 8:00 AM on Wednesday, 08/10/2022 (morning after the exercise) - Provide copies of all documents generated by participants (players, controllers, and evaluators) in the conduct of the exercise on 08/09/2022, separated by Emergency Response Facility (preferred).
Items 2.d - 2.f may be provided prior to the onsite inspection via the electronic portal of the stations choosing, in hard copy for review starting on the first day of inspection, or combination thereof (whichever is more readily available and convenient for the station):
d) Copies of all Drill and Exercise reports since CY2020, including standalone drills, team drills, dress-rehearsals, etc.
e) In addition, a copy of the 2018 and 2022 Biennial EP Exercise Reports (if not provided as part of Item 2.d).
f) Listing of all EP-related Corrective Action Documents/CRs generated since CY2020, in a sortable/searchable format. (Specific full CR documents may be subsequently requested based on sampling and review by the inspectors.)
- 3) IP 71114.04: EAL and Emergency Plan Changes Items 3.a - 3.c are requested to be provided approximately two weeks prior to the onsite inspection (07/25/2022) via the electronic portal of the stations choosing:
a) Copy of the 50.54(q) procedure (current revision) b) Listing of all of 50.54(q) reviews and screens performed since March 2021.
c) Copy of all 50.54(q) evaluations completed since March 2021.
- i. Including copies of all evaluations completed [per 50.54(q) or other corrective action program process] to implement compensatory measures/contingency plans to ensure E-Plan requirements continued to be met during COVID-19 Public Health Emergency (PHE).
- 4) IP 71151: PI Verification (ERO Participation, DEP, and ANS) - ANNUAL review a) Please provide the applicable EP-related Performance Indicator data for:
1st Quarter 2021 through 2nd Quarter 2022 (6 quarters)
The bulleted items below include materials and data that licensees may maintain in support of the collection and reporting of the EP-related Performance Indicators. The list is illustrative and may not be all inclusive. In general, the inspectors are requesting access to the specific materials and data that Arkansas Nuclear One used to report the EP indicators.
Any information provided may be done so prior to the onsite inspection via the electronic portal of the stations choosing, in hard copy for review starting on the first day of inspection, or combination thereof (whichever is more readily available and convenient for the station):
- Station procedure for Alert & Notification System (ANS) Siren Testing.
- ANS Siren Test reports for the 6 quarters.
- Station procedure(s) for EP Performance Indicator data collection and submission.
- List of the DEP opportunities used in developing the PI values for the 6 quarters.
- All supporting documentation used to assess the DEP opportunities in the 6 quarters, which may include: (a) Drill/Exercise/LORT session reports, (b) actual declared emergency reports/assessments (if any), and (c) copies of notification forms associated with each of the DEP opportunities.
- Quarterly qualification rosters (or similar) for the key ERO members who were included in the ERO Participation data for the 6 quarters.
- Qualification records for the key ERO members who were included in the ERO Participation date for the 6 quarters.
- If not included in the supporting documentation for DEP opportunities (5th bullet above), drill/exercise attendance records and any other supporting documentation used to develop the reported ERO participation PI data for 6 quarters.
Items 4.b - 4.d are requested to be provided approximately two weeks prior to the onsite inspection (07/25//2022) via the electronic portal of the stations choosing:
b) Listing of all CRs related to ANS Siren failures and/or corrective maintenance during the 6 quarters, in a sortable/searchable format.
c) Listing of all CRs related to DEP opportunity failures during the 6 quarters, in a sortable/searchable format.
d) Listing of all CRs related to ERO qualification issues/deficiencies during the 6 quarters, in a sortable/searchable format.
If there are any challenges or questions related to providing the requested materials, please contact the lead inspector (Sean Hedger, phone: 817-200-1556), at the stations earliest convenience.
This request does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget under control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
This e-mail and its enclosures will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.