ML18117A221
ML18117A221 | |
Person / Time | |
---|---|
Site: | Catawba |
Issue date: | 04/27/2018 |
From: | Matthew Toth Division Reactor Projects II |
To: | Frank Ehrhardt Division Reactor Projects II |
References | |
Download: ML18117A221 (12) | |
Similar Documents at Catawba | |
---|---|
Category:Meeting Summary
MONTHYEARML24242A3242024-08-30030 August 2024
[Table view]Duke Energy Carolinas - Catawba 2A EDG Regulatory Conference Meeting Summary - August 7, 2024 ML24124A0342024-05-0101 May 2024 Summary of Public Meeting Concerning Annual Assessment of Catawba Nuclear Station Units 1 and 2, McGuire Nuclear Station Units 1 and 2, Oconee Nuclear Station Units 1, 2, and 3, Brunswick Steam Electric Plant Units 1 and 2, Shearon Harris ML23118A2852023-05-0202 May 2023 Public Meeting Summary - 2022 Annual Assessment Meeting Regarding Catawba Nuclear Station, McGuire Nuclear and Oconee Nuclear Station ML22335A4012022-12-15015 December 2022 Summary of December 8, 2022, Public Meeting with Duke Energy Carolinas, LLC, Regarding Pre-Application Meeting to Discuss Proposed License Amendment Request to Revise TS 3.7.11 Control Room Area Chilled Water System (Cracws) ML22129A0062022-05-10010 May 2022 Summary of April 20, 2022, Meeting with Duke Energy Progress, LLC, to Discuss Proposed License Amendment Request to Revise Reactor Coolant System Pressure Isolation Valve Operational Leakage Surveillance Requirement Frequency (L-2022-LRM 00 ML22094A1112022-04-0404 April 2022 Public Meeting Summary 2021 Annual Assessment Meeting Catawba Dockets Nos. 50-413 and 50-414; McGuire No. 50-369 and 50-370; Oconee. 50-269, 50-270, and 50-287 ML21341A5542021-12-29029 December 2021 Summary of November 29, 2021, Meeting with Duke Energy Progress, LLC and Duke Energy Carolinas, LLC to Discuss a Planned License Amendment Request to Relocate ML21342A0902021-12-14014 December 2021 Summary of December 7, 2021, Public Meeting with Duke Energy Carolinas, LLC, Regarding Pre-Application Meeting to Discuss Reactor Vessel Closure Head Nozzle Repair for Catawba Nuclear Station, Unit 2 ML21236A2832021-09-22022 September 2021 Summary of August 30, 2021, Public Meeting with Duke Energy Carolinas, LLC, Regarding Pre-Application Meeting to Discuss Moderator Temperature Coefficient Methodology Revision ML21133A0042021-05-26026 May 2021 Summary of Conference Call Regarding the Spring 2021 Steam Generator Tube Inspections (Epid: L-2021-Nfo-0004) ML21116A0662021-04-22022 April 2021 C2R24 Relief Request Pre-Submittal Slides Call 2 ML21099A0932021-04-0909 April 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Catawba, McGuire, and Oconee Nuclear Stations ML20141L4172020-05-20020 May 2020 EOC Public Meeting Summary ML19220A6702019-08-26026 August 2019 Summary of August 7, 2019, Meeting with Duke Energy Progress, LLC and Duke Energy Carolinas, LLC to Discuss a Proposed License Amendment Request for a Common Emergency Plan ML19087A0622019-04-11011 April 2019 Summary of March 25, 2019, Public Teleconference with Duke Energy to Discuss the Request for Additional Information Response Regarding the Proposed Alternative to the Depth Sizing Qualification Requirement (Duke Energy Fleet Relief Request ML18183A4502018-07-16016 July 2018 Summary of June 11, 2018, Licensing Meeting with Duke Energy to Discuss a Planned License Amendment Request to Remove Containment Valve Injection Water from Specified Containment Isolation Valves ML17293A0232018-05-0404 May 2018 Summary of 9/20/17, Meeting with Duke Energy to Discuss LAR to Extend Completion Time for an Inoperable Emergency Diesel Generator and Electrical Alignments for Shared Systems for Catawba and McGuire (CAC Nos. MF9667-74; Epids L-2017-LLA-02 ML18117A2212018-04-27027 April 2018 Summary of Public Meeting with Catawba Nuclear Station Concerning Annual Assessment of Units 1 and 2 for Period of January 01, 2017 - December 21, 2017 ML17107A0642017-04-17017 April 2017 Summary of Public Meeting with Catawba, Units 1 and 2 ML17089A2042017-04-0707 April 2017 Summary of January 25, 2017, Pre-Licensing Meeting with Duke Energy to Discuss Proposed License Amendment Request to Create a New Condition for Nuclear Service Water System TS 3.7.8 - Catawba Nuclear Station, Unit Nos. 1 and 2 (CAC MF8944-5 ML16264A1232016-10-12012 October 2016 September 14, 2016, Summary of Category 2 Public Meeting with Duke Energy Carolinas to Discuss Seismic Probabilistic Risk Assessments Associated with Implementation of Japan Lessons-Learned Near-Term Task Force R2.1, Seismic, for Catawba Nu ML16264A1022016-10-0505 October 2016 Summary of Pre-Licensing Meeting with Duke Energy to Discuss Proposed License Amendment Request to Extend Completion Time for an Inoperable Diesel Generator for Catawba Nuclear Station & McGuire Nuclear Stations (Cac. Nos. MF8102-MF8105) ML16116A3712016-05-17017 May 2016 Summary of Meeting with Duke Energy Carolinas, LLC, to Discuss Proposed Changes to the Technical Specification Bases for the Catawba Nuclear Station, Units 1 and 2 ML16081A3352016-03-17017 March 2016 Summary of Meeting with Public Concerning Annual Assessment of Catawba Nuclear Station, Units 1 and 2 ML16035A4802016-02-12012 February 2016 Jsc Meeting Summary Attachment ML15117A5812015-05-0606 May 2015 April 14, 2015, Summary of Public Meeting on Calculation of Risk for NFPA-805 Fire Areas Crediting Control Room Abandonment ML15106A0302015-04-15015 April 2015 Meeting Summary with Public to Discuss the Annual Assessment of Catawba Nuclear Station, Units 1 and 2 ML14126A6792014-05-0606 May 2014 Summary of Public Meeting with Catawba, Units 1 & 2 to Discuss Annual Assessment ML13312A9882013-11-0808 November 2013 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Provide Opportunities to Discuss the Planned Fukushima-Related Modifications ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13127A0502013-05-20020 May 2013 Summary of April 18, 2013, Meeting with Duke Energy Concerning the National Fire Protection Association (NFPA) 805: Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants ML13127A1742013-05-0303 May 2013 4/29/2013 - Summary of Catawba 2012 EOC Meeting ML12261A2232012-09-17017 September 2012 September 11, 2012 - Summary of Category 1 Public Meeting Held in Atlanta, Ga ML12117A2512012-04-26026 April 2012 Meeting Summary with Catawba Nuclear Station to Discuss the Nrc'S Reactor Oversight Process (ROP) and the Nrc'S Annual Assessment of Plant Safety Performance for the Period of January 1, 2011, to December 31, 2011 ML1112308322011-05-0303 May 2011 End of Cycle Public Meeting Summary ML11097A0272011-04-14014 April 2011 Summary of Meeting with Duke Energy Carolinas, LLC, on Upcoming Submittal of License Amendments Regarding Implementation of National Fire Protection Association Standard 805, (TACs ME5767 & ME5768, Catawba 1 & 2 ME5769 & ME5770 Mcguire 1 & ML1034807072010-12-14014 December 2010 Public Meeting Summary - Duke Quality Assurance Program Discussion Meeting ML1030810242010-11-10010 November 2010 Summary of November 1, 2010, Meeting with Duke to Discuss Responses to Generic Letter (GL) 2004-02 (Tac Nos. MC4673, MC4674, MC4692, and MC4693) ML1023804682010-08-26026 August 2010 08/18/10 Summary of Meeting NRC Initial Exam Writer'S Workshop ML1020100072010-07-21021 July 2010 Summary of Telephone Conference Call Regarding the Fall 2007 Steam Generator (SG) Tube Inspections ML1019000622010-07-14014 July 2010 Summary of Telephone Conference Call with Duke Energy Carolinas, Llc., Regarding 2009 Steam Generator Tube Inspections Catawba, Unit 2 ML1011604522010-04-26026 April 2010 Summary of Public Meeting with Catawba Nuclear Station to Discuss Nrc'S Reactor Oversight Process and the Nrc'S Annual Assessment of Plant Safety Performance for the Period of January 1, 2009 - December 31, 2009 ML0926700202009-10-0707 October 2009 Summary of Conference Call with Duke Regarding Responses to Generic Letter (GL) 2004-02 ML0923803922009-08-26026 August 2009 08/11-12/2009-Summary of Meeting Re 2009 Us NRC Initial Exam Development Workshop ML0906404402009-01-28028 January 2009 Enclosure 6: Case Study 2: Catawba Emergency TS Change - Meeting Summary of the January 27 & 28 Meeting with Nrc/Tstf L-04-004, 11/24/2008 - Summary of Meeting to Discuss 11/21/2008 and 11/18/2008 Requests for Additional Information GL 2004-04, Potential Impact of Debris Blockage of Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors2008-12-0303 December 2008 11/24/2008 - Summary of Meeting to Discuss 11/21/2008 and 11/18/2008 Requests for Additional Information GL 2004-04, Potential Impact of Debris Blockage of Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML0833103972008-12-0303 December 2008 Summary of Meeting to Discuss 11/21/2008 and 11/18/2008 Requests for Additional Information GL 2004-04, Potential Impact of Debris Blockage of Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML0820604872008-08-0606 August 2008 Summary of Meeting to Discuss Transition from Duke'S Current Quality Assurance Program to American Society of Mechanical Engineers NQA-1-1994 ML0621305672006-08-0101 August 2006 Summary of 07/19 - 07/20/2006 Meeting - 2006 Initial Exam Development Workshop ML0601800062006-03-28028 March 2006 Meeting Summary, Reload Design and Safety Analysis Methodology 2024-08-30 Category:Memoranda MONTHYEARML24124A0342024-05-0101 May 2024
[Table view]Summary of Public Meeting Concerning Annual Assessment of Catawba Nuclear Station Units 1 and 2, McGuire Nuclear Station Units 1 and 2, Oconee Nuclear Station Units 1, 2, and 3, Brunswick Steam Electric Plant Units 1 and 2, Shearon Harris ML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion ML23118A2852023-05-0202 May 2023 Public Meeting Summary - 2022 Annual Assessment Meeting Regarding Catawba Nuclear Station, McGuire Nuclear and Oconee Nuclear Station ML22300A0742023-01-11011 January 2023 Final Environmental Assessment and Finding of No Significant Impact for the Duke Energys Updated Decommissioning Funding Plans Submitted in Accordance with 10 CFR 72.30(C) for Catawba Nuclear Station Independent Spent Fuel Storage Installat ML21099A0932021-04-0909 April 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Catawba, McGuire, and Oconee Nuclear Stations ML20141L4172020-05-20020 May 2020 EOC Public Meeting Summary ML19098B4482019-04-0808 April 2019 Public Meeting Summary ML18117A2212018-04-27027 April 2018 Summary of Public Meeting with Catawba Nuclear Station Concerning Annual Assessment of Units 1 and 2 for Period of January 01, 2017 - December 21, 2017 ML17107A0642017-04-17017 April 2017 Summary of Public Meeting with Catawba, Units 1 and 2 ML16111B2472016-04-28028 April 2016 Request for Additional Information Re. License Amendment Request to Revise TS 5.5.2 Containment Leakage Rate Testing Program ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16081A3352016-03-17017 March 2016 Summary of Meeting with Public Concerning Annual Assessment of Catawba Nuclear Station, Units 1 and 2 ML15253A4032016-03-11011 March 2016 Recommendation for Dispositioning Proposed Generic Issue on the Effects of Downstream Dam Failures on Nuclear Power Plants ML15244B2522015-08-31031 August 2015 Report on Trip to Catawba on August 26-27, 2015 ML15106A0302015-04-15015 April 2015 Meeting Summary with Public to Discuss the Annual Assessment of Catawba Nuclear Station, Units 1 and 2 ML14126A6792014-05-0606 May 2014 Summary of Public Meeting with Catawba, Units 1 & 2 to Discuss Annual Assessment ML14077A1312014-03-18018 March 2014 Special Inspection Charter to Evaluate the Abnormal Rotation of the Piston Crankshaft Bearings on the Catawba Unit 1 Diesel Generators ML13295A3062013-10-22022 October 2013 Meeting Notice with Duke Energy Carolinas, LLC Discuss the Planned Modifications Related to the Fukushima Flood Hazard Reevaluations for the Sites Operated by Duke Energy Carolinas, LLC ML13135A5962013-05-16016 May 2013 Cancelled 05/23/2013 Notice of Forthcoming Pre-Application Meeting with Duke Energy Carolinas, Llc. to Discuss a Proposed License Amendment Request Concerning Methodology Report DPC-NE-3001-P for Catawba and McGuire Nuclear Stations ML13127A4352013-05-0909 May 2013 Notice of Forthcoming Pre-Application Meeting with Duke Energy Carolinas, Llc. to Discuss a Proposed License Amendment Request Concerning Methodology Report DPC-NE-3001-P for Catawba and McGuire Nuclear Stations ML13072B2022013-03-19019 March 2013 Meeting Notice with Duke Energy Concerning NFPA-805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants License Amendment Request for Catawba, McGuire, and H. B. Robinson ML12300A4032012-10-26026 October 2012 11/8/2012 Meeting Notice with Duke Energy to Discuss NRC Order on Mitigation Strategies for Beyond-design-Basis External Events ML12284A4612012-10-12012 October 2012 Forthcoming Meeting Notice with Duke Energy to Discuss NRC Order on Mitigation Strategies for Beyond-Design-Basis External Events ML12103A3522012-04-10010 April 2012 Special Inspection Charter to Evaluate Catawba Loss of Offsite Power ML1106603302011-03-0707 March 2011 Notice of Meeting with Duke Energy to Present Status of Licensing Submittals Regarding Implementation of National Fire Protection Association Standard 805, Requirements at Catawba Nuclear Station, Units 1 and 2 and McGuire Nuclear Station ML1029306502010-10-20020 October 2010 Notice of Forthcoming Conference Call with Duke Energy Carolinas, LLC Regarding McGuire Nuclear Station, Units 1 and 2 and Catawba Nuclear Station, Units 1 and 2, ML1021400692010-08-0404 August 2010 Notice of Meeting with Duke Energy to Discuss Duke Energy'S Assessment of the Results of the Catawba Baseline Inspection Conducted by the NRC ML1015804072010-06-0808 June 2010 the Nuclear Regulatory Commission Staff Spot-Check Review of Duke Energy'S Ownership Interest of Catawba, Units 1 and 2, McGuire, Units 1 and 2, and Oconee, Units 1, 2 and 3 on May 20, 2010 - Finding of No Potential Issues in Bank Statement ML1015804682010-06-0808 June 2010 the Nuclear Regulatory Commission Staff Spot Check Review of North Carolina Electric Membership Corporation'S Ownership Interest of Catawba Nuclear Station Units 1 and 2 on May 20, 2010 - Finding of No Potential Issues in Bank Statements ML1015900402010-06-0808 June 2010 the Nuclear Regulatory Commission Staff Spot-Check Review of Piedmont Municipal Power Agency'S Ownership Interest of Catawba Nuclear Station Units 1 and 2 on May 19, 2010 - Finding of No Potential Issues in Bank Statements ML1012604632010-05-0707 May 2010 Notice of Forthcoming Conference Call with Duke Energy Carolinas, LLC (Duke) to Discuss Duke'S Responses to Generic Letter 2004-02 at Catawba 1 and 2 and McGuire 1 and 2 ML0926700202009-10-0707 October 2009 Summary of Conference Call with Duke Regarding Responses to Generic Letter (GL) 2004-02 ML0925404602009-09-10010 September 2009 Summary of Phone Call with Industry to Issues Related to Eccentricity of the Steam Generator Tube-to-Tubesheet Joints in the Finite Element Model Used for the Technical Basis of the Permanent Alternate Repair Criteria License Amendment Requ ML0922908922009-08-18018 August 2009 Notice of Conference Call with Duke Energy Carolinas, LLC (Duke), Regarding Catawba Nuclear Station, Units 1 and 2 (Catawba 1 and 2) and McGuire Nuclear Station Units 1 and 2 ML0831009482008-11-10010 November 2008 Notice of Meeting with Duke Energy Carolinas, LLC, (Duke), Catawba, Units 1 and 2, and McGuire, Units 1 and 2 ML0831107952008-11-0606 November 2008 Cancellation of Meeting with Duke Energy Carolinas, LLC, to Discuss the Request for Additional Information Generic Letter 2004-04, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents. ML0829701832008-10-30030 October 2008 Notice of Meeting with Duke Energy Carolinas, LLC, to Discuss the Request for Additional Information Generic Letter 2004-04, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents ... ML0818301542008-07-0101 July 2008 Notice of Meeting with Duke Energy Carolinas, LLC to Discuss Transition to ASME NQA-1-1994 ML0817903662008-06-27027 June 2008 Safety Evaluation by the Office of Nuclear Reactor Regulation Application for Direct Transfer of Facility Operating License Catawaba Nuclear Station, Unit 1 ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0800201632008-01-0303 January 2008 Cancelled - Meeting with Duke Power Company ML0800202162008-01-0303 January 2008 Forthcoming Meeting with Duke Power Company LLC Catawba Nuclear Station to Discuss the Relief Request Dated October 26, 2006 (Agencywide Documents Access and Management System Accession No. ML063120211) ML0733711662007-12-0303 December 2007 Notice of Meeting with Progress Energy & Duke Energy Regarding Fire Probabilistic Risk Assessment for the Pilot Plants Transitioning to the National Fire Protection Association Standard NFPA 805 ML0628401062006-10-18018 October 2006 Staff'S Review of CLIIP Amendment to Adopt TSTF-372 ML0614505462006-05-25025 May 2006 Revised Augmented Inspection Team Charter ML0614303612006-05-23023 May 2006 Augmented Inspection Team Charter for Catawba, Units 1 and 2 ML0533900722005-12-0707 December 2005 Notice of Forthcoming Meeting with Duke Energy Corporation, to Discuss Reload Design and Safety Analysis Methodology Report Submittals ML0524103052005-09-0606 September 2005 08/18/05 - Summary of Public Meeting on Mspi/Rop Topics for August 17/18, 2005 ML0524503412005-09-0202 September 2005 Notice of Meeting with Duke Energy Corp, Regarding RAIs on Nuclear Service Water System for Catawba, Units 1 and 2 2024-05-01 |
Contents
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 27, 2018 MEMORANDUM TO: Frank Ehrhardt, Chief Reactor Projects Branch 1 Division of Reactor Projects FROM: Matthew Toth, Project Engineer /RA/
Reactor Projects Branch 1 Division of Reactor Projects
SUBJECT:
PUBLIC MEETING
SUMMARY
- CATAWBA NUCLEAR STATION DOCKET NOS. 50-413 AND 50-414 On April 25, 2018, Nuclear Regulatory Commission (NRC) staff met with members of the public in Rock Hill, South Carolina concerning the annual assessment of Catawba Nuclear Station Units 1 and 2. The purpose of the meeting/open house session was to provide opportunities to discuss the annual assessment of Catawba Nuclear Station Units 1 and 2 for the period of January 1, 2017 - December 31, 2017, with the public. Enclosed are a list of attendees and presentation slides displayed at the meeting.
Docket Nos.: 50-413 and 50-414 License No.: NPF-35 and NPF-52
Enclosures:
- 1. List of Attendees
- 2. Presentation Slides CONTACT: Jannette Worosilo, RII/DRP/RPB1 404-997-4485
ML18117A221 OFFICE RII:DRP RII:DRP NAME MToth FEhrhardt DATE 4/27/2018 4/27/2018