Other: DCL-84-248, Notifies of Completion of Fixes for safety-related Masonry Walls,Per IE Bulletin 80-11.Existing as-built Condition Would Not Preclude Addl Mod.No Addl Fixes Necessary Based on Analysis for Line Break & Jet Impingement, DCL-86-083, Forwards Proprietary & Nonproprietary Verification of Diablo Canyon Energy Balance Technique Using San Onofre... Unit 1 Masonry Wall Tests. Proprietary Version Withheld (Ref 10CFR2.790).Affidavits Encl, ML16341D703, ML16341D707, ML16341D962, ML17083B468, ML20198G219, ML20209D910, ML20213E341
|
MONTHYEARML13310B3371984-04-12012 April 1984 Forwards Nonproprietary & Proprietary Results of Masonry Wall Test Program, Seismic Evaluation of Reinforced Concrete Masonry Walls, Results from Testing Walls 1A,1B & 1C.Application for Withholding & Affidavit Encl Project stage: Request DCL-84-248, Notifies of Completion of Fixes for safety-related Masonry Walls,Per IE Bulletin 80-11.Existing as-built Condition Would Not Preclude Addl Mod.No Addl Fixes Necessary Based on Analysis for Line Break & Jet Impingement1984-07-0202 July 1984 Notifies of Completion of Fixes for safety-related Masonry Walls,Per IE Bulletin 80-11.Existing as-built Condition Would Not Preclude Addl Mod.No Addl Fixes Necessary Based on Analysis for Line Break & Jet Impingement Project stage: Other ML20209D4161984-10-0202 October 1984 Discusses Review of Facility Masonry Wall Design,Per .Outstanding Issues Identified in Working Stress Approach & Nonlinear Analysis Method.Audit of Design Calculations Suggested Project stage: Approval ML17083B4681984-11-0101 November 1984 Trip Rept of 841001-05 Site Visit W/Bnl Re Identification of Engineering Matl Needed to Conduct Audit on Adequacy of Civil/Structural Design & Analyses.List of Addl Audit Items Encl Project stage: Other ML20209D9101985-02-11011 February 1985 Forwards Sser Input Re Masonry Wall Issue.License Condition Re Applicant Use of energy-balance Technique to Qualify 42 Masonry Walls Recommended Project stage: Other ML16341D5021985-10-29029 October 1985 Notification of 851105 Meeting W/Licensee in Bethesda,Md to Discuss Status of Util Masonry Wall Analysis Project stage: Meeting ML20198G2191985-11-15015 November 1985 Requests That Task of Reviewing Justification for Use of Energy Balance Technique to Qualify Masonry Walls Be Added to Assignment 6 to Contract NRC-03-81-130 Project stage: Other DCL-85-343, Forwards Proprietary & Nonproprietary Versions of Draft Verification of Diablo Canyon Energy Balance Technique Using San Onofre Nuclear Generating Station-1 Masonry Wall Tests. Proprietary Rept Withheld (Ref 10CFR2.790)1985-11-15015 November 1985 Forwards Proprietary & Nonproprietary Versions of Draft Verification of Diablo Canyon Energy Balance Technique Using San Onofre Nuclear Generating Station-1 Masonry Wall Tests. Proprietary Rept Withheld (Ref 10CFR2.790) Project stage: Draft Other ML16341D4961985-11-18018 November 1985 Summary of 851105 Meeting W/Util,Nrc Consultants & Bechtel Re Util Approach to Justify Use of energy-balance Technique to Qualify Masonry Walls.List of Attendees & Request for Addl Info Encl Project stage: RAI ML16341D5111985-11-30030 November 1985 Nonproprietary Draft Verification of Diablo Canyon Energy Balance Technique Using San Onofre Nuclear Generating Station-1 Masonry Wall Tests Project stage: Draft Other ML16341D5481985-12-0909 December 1985 Advises That Proprietary Version of Draft Diablo Canyon Power Plant,Units 1 & 2 - Verification of Diablo Canyon Energy Balance Technique Using SONGS-1 Masonry Wall Tests, Submitted by Will Be Withheld,Per 10CFR2.790 Project stage: Draft Other ML16341D5671985-12-20020 December 1985 Forwards,In Support of Masonry Wall Review,Pg&E & Proprietary & Nonproprietary Draft Verification of Diablo Canyon Energy Balance Technique Using SONGS-1 Masonry Wall Test. Proprietary Draft Withheld (Ref 10CFR2.790).W/o Encl Project stage: Draft Other DCL-86-083, Forwards Proprietary & Nonproprietary Verification of Diablo Canyon Energy Balance Technique Using San Onofre... Unit 1 Masonry Wall Tests. Proprietary Version Withheld (Ref 10CFR2.790).Affidavits Encl1986-03-27027 March 1986 Forwards Proprietary & Nonproprietary Verification of Diablo Canyon Energy Balance Technique Using San Onofre... Unit 1 Masonry Wall Tests. Proprietary Version Withheld (Ref 10CFR2.790).Affidavits Encl Project stage: Other ML16341D7071986-04-10010 April 1986 Forwards Nonproprietary & Proprietary Versions of Verification of Diablo Canyon Energy Balance... & to Assist in Evaluation of Masonry Walls.Proprietary Version Withheld (Ref 10CFR2.70(b)(6)).W/o Encls Project stage: Other ML16341D7031986-04-10010 April 1986 Responds to 860327 Application for Withholding Diablo Canyon Power Plant,Units 1 & 2 - Verification of Diablo Canyon Energy Balance Technique Using SONGS-1 Masonry Walls Tests .... Rept Will Be Withheld (Ref 10CFR2.790) Project stage: Other ML20213E3411986-11-0404 November 1986 Forwards Nonproprietary & Proprietary Version of TER-C5506-648, Masonry Wall Design,Diablo Canyon Units 1 & 2. Energy-balance Technique as Applied to Masonry Walls Acceptable.W/O Proprietary Version.Record Copy Project stage: Other ML16341D9621986-11-0404 November 1986 Forwards Nonproprietary & Proprietary Version of TER-C5506-648, Masonry Wall Design,Diablo Canyon Units 1 & 2. Energy-balance Technique as Applied to Masonry Walls Acceptable.W/O Proprietary Version Project stage: Other 1985-11-18
[Table View] |
Text
.
8
'o,,
UNITED STATES NUCLEAR REGULATORY COMMISSION o
E WASHINGTON, D. C. 20555
...../
FEB 111985 Docket No. 50-323 MEMORANDUM FOR:
Chief icensing No. 3 Division of Licensing THRU:
6 Robert Bosnak, Acting Assistant Director j iJ for Components and Structures Engineering Division of Engineering i
FROM:
George Lear, Chief Structural and Geotechnical Engineering Branch Division of Engineering
SUBJECT:
SSER INPUT FOR MASONRY WALL ISSUE - DIABLO CANYON UNIT 2 Plant Name: Diablo Canyon Unit No. 2 Docket No.: 50-323 Licensing Stage: OL Responsible Branch:
LB-3, H. Schierling, LPM Requested to Date: January 31, 1985 The information provided by the applicant on the subject issue has been reviewed and evaluated by the Structural and Geotechnical Engineering Branch. Our section of the safety evaluation report supplement is provided in the enclosure.
In summary, our evaluation indicates that the issue yet to be resolved between the staff and the applicant pertains to the applicant's use of the energy-balance technique to qualify 42 masonry walls. The existence of the same issue on Unit I resulted in a license condition for Unit 1.
Therefore, the same license condition is recommended for Unit 2.
0 yNW George Lear, Chief Structural and Geotechnical Engineering Branch Division of Engineering
Enclosure:
As stated cc:
D. Jeng P. Kuo E. Sullivan H. Polk
{
H. Schierling N. Chokshi
\\
h CONTACT:
N. Chokshi, x28967 J')(/
n\\\\
1
( TSB2 $ 309 S g 4
~
-