ML20154F395

From kanterella
Jump to navigation Jump to search
Safety Evaluation Supporting Request to Operate Facility at 25% Power Re Accident Evaluation
ML20154F395
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 09/14/1988
From:
NRC
To:
Shared Package
ML20154F388 List:
References
NUDOCS 8809190375
Download: ML20154F395 (93)


Text

.

  1. pa eso #o, UNITED STATES

! a NUCLEAR REGULATORY COMMISSION s wAsHWG TON, D. C. 20684 s . . . . . )1 ENCLOSURE 2 SAFETY EVALUATION OF THE REQUEST TO OPERATE THE SHOREHAM NUCLEAR POWER STATION AT 25% MWER ACCIDENT EVALUATION 1 INTRODUCTION t

The staff has completed a review of the PRA-based portion of LILCO's request to operate Shoreham Nuclear Power Station at 25 percent of full power (Reference 1).

The PRA which forms the basis of the request is an updated version of the original full power PRA, modified to account fer operation at 25 percent power.

i The staff has previously reviewed the original PRA (Reference 2); the results of that review are provided in Reference 3. The objective of the present review was to assess the validity of the major technical arguments upon which the utility's 25 percent power request is based. These arguments can be summariztd as follows:

1. Reduced Vulnerability to Core Damage Ac.cidents j With operation at 25 percent power, decay heat levels are reduced to the extent that (1) certain plant features, such as turbine bypass, are capable of mitigating accidents prior to core melt and (2) accidents will evolve more slowly allowing considerably greater time for recovery actions. These factors, in conjunction with a number of plant upgrades which have been implemented, will result in a reduced vulnerability to severe core melt accidents at shoreham.
2. Increased Time Interval Available for Emergency Response For accidents which are not arrester 1 prior to core melt, reduced decay heat levels associated with 25 percent power operation will result in a significant delay-in both core melt progression and onset of releases DbCkhhhhh$2 PDb

from containment. This delay represents an increase in the time avail-able for emergency response.

3. Reduced Offsite Consequences The magnitude of source term releases for accidents initiated from 25 percent power are less than predicted for similar accidents initiated at 100 percent power due to a proportionally smaller initial fission product inventory at the lower power level. The reduced source terms, in conjunction with the delayed times of release taentioned above, translate into reduced offsite consequences.

The staff review was divided into three main parts corresponding to the three utility arguments. These three parts and their objectives are described below:

Part 1 - Comparative Evaluation of Sequene.as with Potential Early Risk Impact The objective of this part of the review was to assess tne validity of the utility's assertion that the frequency of core melt accidents will be signifi-cantly reduced by (1) operation at 25 percent, and (2) a number of plant ,

upgrades which have been implemented. Emphasis of the review was on treatment

(

of: risk-important sequences (e.g., ATWS, station blackout, and interfacing l system LOCA), initiating frequencies, time for operator actions, and treatment f of external events. The review focused on the differences in these areas at l 25 percent and 100 percent power, and not on the estimates of core melt fre- l quency in an absolute, quantitative sense.

l l

Part 2 - Effect of Power Restriction on Timing of Severe Accidents The objective of this segment of the review was to assess the validity of the  ;

utility's calculated results for sequences identified as risk-important, with  !

special emphasis on characterization of the timing of events in the accident I progression, i.e., core uncovery, core melt, and vessel failure. -

i l

i 2

f i

i Part 3 - Effect of Power Restriction on Offsite Consequences The objective of this segment of the review was to assess the adequacy of the utility's treatment of source terms, including initial fission product inventory for reduced power levels, modelling assumptions and calculated results regarding  !

i fission product releases and deposition, and treatment of fission product reten-

, tion in the secondary containment building. A second objective was to assess  !

1 the reasonableness of the utility's offsite consequence analyses, and to perform  ;

independent consequence analyses, as needed. .

1 i The Part 1 evaluation allows an assessment of the first LILCO claim regardin] ,

] the impact of power restriction and plant upgrades on vulnerability to core  :

) damage accident like,11 hood at Shoreham Nuclear Power Station (SNPS). Similarly, 1

1 the second and third parts provide information necessary to assess the study

) claims regarding increased times for operator actions and emergency response, j and reduced offsite consequences at 25 percent power.

l l The organization of this report parallels the three major segments of the l staff's review described above. Section 2 provides the staff's evaluction of I sequences with pot.ential early risk impact. Sections 3 and 4 provide the staff's evaluati n of the effect of the power restriction on the timing and consequences of severe accidents, respectively. The summary and conclusions of the review are presented in sectio.1 5.

~

2 EFFECT OF POWER RESTRICTION ON CORE MELT FREQUENCY This section summarizes the major results of the staff review of the Shoreham 25 percent PRA evaluation of core melt frequency. The objective of the review was to assess the validity of the utility's assertion that the likelihood of incidents that can potentially result in core melt will be significantly reduced relative to full-power operation. The utility argument was based on a comparison of core melt frequency estimates for 25 percent power with those previously reported in the 1983 Shoreham Nuclear Power Station PRA for full-power operation of the plant. Thus, observed reductions were due to a combina-tion of operating at a reduced power level (25 percent of full power) and a number of plant upgrades which have bwen implemented at the plant since the publication of the 1983 full power PRA.

3

9 The following 4 types of sequences were identified as important by the staff, ,

on the basis of their contribution to core melt frequency and risk in the 25 percent PRA. These sequences were also found to be important in the staff's f

review of the original Shoreham PRA (for 100 percent power) and other PRAs.  ;

1. Anticipated Transient Without Scram (ATWS)
2. Loss of Cool" '-cidents (LOCAs) f
3. Los of Offs'
4. i - nsiv v of Injection i ATWS and .r .A sequences are of interest because of their rapid I nature arid , i. f early challenge to operators and offsite response. ,

t Loss of off;; w power and loss of injection sequences are of interest because they generally represent the major contributors to total core melt frequency for BWRs.

As part of the staff's review of core melt frequency, a focused evaluation was f performed of the modelling of several of these sequences in the PRA. The Sequences considered were: (1) AWS sequences. (2) LOCAs outside containment, and (3) station blackout sequences. The staff's assessment of the modelling of j these sequences as well as other factors affecting the reported estimates of  !

core melt frequency is sammarized In the discussion that follows. Further tech-  !

nical details and discussions of the review are included in Appendix A.

Anticipated Transients Without Scram (ATWS) sequences represent the cases where the plant is challenged by an off normal condition (accident initiator) that requires termination of the fission reaction, and the reactor protection system fails to function. The contribution of these sequences to core melt frequency was repoated by the utility to drop by approximately a factor of three for 25 percent operation as compared to the value reported in the 100 percent power PRA.

4

t

, i

)

i i

Restriction of the ormal power level to 25 percent creates a unique situation t

for the ATWS conditions in that the Turbine Bypass Value (TBV) can deliver 25 percent of rated steam flow to the main condenser. This represents a success i

path which is not available at full power operation. In general, the staff agrees with the analysis of ATWS sequences that shows a reduction in core melt i frequency contribution as compared to the estimates reported in the full power PRA. t Loss of Coolant Accidents outside of the reactor t.ontainment involve release f of primary coolant to the environment. This release is associated with failure i l

of the high pressure to low pressure boundary in systems interfacing the reac-  !

tors primary cooling piping. The 25 percent power PRA showed the contribution of these sequences to core melt frequency to be reduced by about a factor of three as compared to the Shoreham full power PRA. This decrease is primarily L i

due to changes in analysis of the pressure boundary failure and not to the i ef fect of power reduction.

}

m Station Blackout, which is complete loss of Alternating Current (AC) electrical 4

power in the plant (both offsite power and onsite emergency AC) represents an important challenge to plant safety. This is due to the dependence of systems

! required for reactor core cooling and containtrent heat removal on AC els.ctric

, power. Station blackout sequences are typically initiated by loss of offsite '

l

power. The likerihood of loss of offsite pewer depends on the reliability of I

the power griu and its susceptibility to severe weather. Loss of urfsite powar [

!l can also be induced by a seismic event. The centribution of loss of offsite 1

j power sequences to core damage frequency depends on the reliability of onsite j AC power sources, and on tne time period available to recover AC pcwor.

{

Redundant AC power sources exist in Shoreham; these include diesel generators  ;

' and a gas turbine. The utility study showed a significant reduction in core l melt frequency resulting from loss of offsite power relative to the 1983 PRA '

l (with the exception of seismically induced loss of offsite power). The staff  ;

I j 'sicludes that the results are reasonable and the credit given to the additional [

.aurcesofonsiteACpowerisjustified.

]  !

The staff review also assessed the adequacy of the treatment of external events  !

j in the FRA, since external events (such as earthquakes, fires and floods) carry  !

l  !

i 5 I l

i

! I

the potential for high risk significance due to their ability to induce condi- l tions that initiate accidents and their potential to fail systems that can l mitigate these accidents.

f 1 1

! The 100 percent power PRA identified flooding from sources inside the plant  :

j (internal flooding) as a leading contributor to the Shoreham estimate of core j j melt frequency. The dominant flood scenario occurred at elevation 8' of the i reactor building where all of the plant emergency core cooling system pumps are ,

l located. The 25 percent power PRA does not show a significant contribution j

( from internal flood scenarios. The primary reason is the credit given to the j l CRD pumps which is located above the reactor building flood elevation. The CR0 j pumos are capable of maintaining reactor vessel inventory for accident initia-l l tors occurring during 25 percent power operation. The credit taken for those j l pumps is judged by the staff to be reasonable and consistent with other sequences [

l in the PRA which took credit for this alternate high pressure injection source. f i The staff did not perform a detailed review of the seismic analysis for Shoreham.  !

l However, the staff had previously reviewed 'he seismic hazard calculations per- I i

{ formed for the nearty Millstone 3 site by the same subcontractor as used by i l LILCO. That review indicated that the seisaic hazarc coqld be increased by an (

{ order of magni'tude due to uncertainties. The staff he.s compared the seismic l hazard curvus from the Shoreham PRA to preliminary curves available for the l Shoreham site from the Seismic Hazard Characterization Project (SHCP). In con-l trast to Millstone, the Shoreham SHCP eurves are closer to those used in the' j

! utility PRA. Based on this comparison, it is our judgment that an increase in

! the utility estimates of seismic hazard by a factor of five would represent a (

) reasonable high estimate of uncertainty for regulatory purposes at Shoreham.  ;

l This is not to say that this high estimate represents the true upper limit of

! scientific uncertainty or that the true seismic hazard could not be less than l that proposed in the Shoreham study. Certainly there is no compelling evidence

) in the historic record that would indicate any likelihood of large earthquakes j

! in eastern Long Island. If the increase in seismic hazard where to translate I j into an muivalent increase in core melt frequency for seismic events at Shore' a. e. , a factor of five, the frequency of seismically induced core j melt seq _.;es would increase to approximately 1 x 10 8, which is about one-fifth that for internally initiated events. It should be pointed out, however, i that comparisons between seismic and nonseismic core melt frequency estimates  ;

} 6 l  !

1  !

are not completely valid since mean seismic hazard estimates directly reflect modelling uncertainties, whereas internal event estimates do so to a much lesser extent. As a result, comparisons of the means tend to overestimate the relative contribution of the sei;mic events to core damage and risk. Further, this effect ould Influence the results in both the 100 percent power PRA and the 25 percent power PRA.

The 25 percent PRA reported more than an order of magnitude reduction in the fire contribution to core melt frequency as compared to the full power PRA. As detailed in Appendix A, the staff has identified several areas relating to the fire analysis which should be addressed by the utility. However, our judgment is that they would not significantly alter the PRA results.

In summary, operation at the reduced power level results in a reduction in the j overall core damage frequency of about a factor of two. This reduction, how-ever, is well within the uncertainties associated with estimating core melt frequency, especially considering that the reported results are in the form of point estimates and that uncertainties can be much larger than a facter of two.

! Extarnel events (seismic and fires) and tstimates of human error data are the f patential anjor contributions to these large uncertainties.

l Basea upon the 1 .nited review performed a the systems analysis segment of 25 percent pcwer PRA submittal, the staff concludes that core melt frequency l at 25 oercent newer is not significantly different than at 100 percent power.

3 EFFECT OF POWER RESTRICTION ON TIMING OF GEVrRE ACCIDENTS This section provides the results of the staff's evaluation of the utility's claims regarding the effect of operation at 25 percent power on the time avail-able for operator actions and emergency response. The section is divided into two parts. The first part describes staff analyses performed for a limited number cf sequences to determine the effect of the power restriction on severe accident timing. The emphasis of these analyses was on establishing the timing-of key events in the core melt progression up to the time of reactor vessel failure. The second part describes the staff's assessment of the time of releases to the environment for broad classes of accidents at 25 percent power.

7

r As such, the information presented provides a basis for identifying which types of severe accident sequences will likely require prompt offsite emergency response, and the amount of time available prior to significant releases from the reactor :oolant system and containment.

3.1 Tiniina of Core Melt Progression The spectrum of core melt accidents in BWRs can be grouped into five generic accident classes or plant damage states on the basis of similar challenges to the core and containment functions, and similar possibilities for core melt progression. The plant daniage states define the boundary conditions for the subsequ' ant containment event tree (CET) analysis, the purpose of which is to systematically asscss and quantify the relative probability of successfully mitigating the challenges to core /containmer , or of obtaining a particular l

release. The product of the CET analysis is a number of quantified radio-nucitdo release end states; these **e typically grouped into a smaller set of release bins or categories on the basis of similar release characteristics.

Six release categories were defined by the utility to rerresent the 25 percent power accident spectrun, for Shoreham. The release characteristics for each of these categories are descritad in Table 2. Additional information is repre-

, sented in Table 3 for each of six release categories, specifically, the con-tribution of all sequences assigned to the release category to total core melt frequency, the time to core slump calculated by the Modular Accident Analysis Program (KAAP) code for the sequence chosen to represent the release category, and the time of releates to the environment for the release category estimated based on analyses performed using the MAAP. Statements made in Section II.C.4(c) of Reference 1 indicate that release categories 1 and 2 account for the bulk of the injury-threatening doses, i

To assess the effect of the power reduction on the nature and timing of accident progression, the staf f performed confirmatory calculations for seven :1 of the sequences used to represent release categories. The sequence types considered were: (1) anticipated transient without scram (ATWS), (2) large break LOCA, (3) station blackoui, and (4) transient with loss of injection. These 8

e i

calculations modeled only the thermal-hydraulic behavior of the reactor coolant system up to the time of reactor vessel failure.

A brief discussion of the calculations performed for each sequence type and the results is provided in the subsections below. A discussion is then provided of '

the applicability of the findings to other sequences.

3.1.1 ATWS Sequences An ATWS is an expected operational transient (such as loss of feedwater, loss ,

4 of condenser vacuum, or loss of offsite power) which is accompanied by a j failure of the reactor trip system to shut down the reactor. As part of the {

assessment of ATWS sequences at 25 percent powcr, the following two aspects of I

the accident were considered: (1) reactor response to sudden reactivity inser-

] tion under ATWS conditions, and (2) core melt progression for the ATWS sequence '

1 defined for release Category 1 of the utility submittal. Those are discussed l below.

3.1.1.1 Reactivity Insertion at 25 Percent Power- '

r Detailed studies have demonstrated that successful operator actuation of the  !

standby liquid control system (SLCS), will bring the ATWS sequence in BWRs under control. In the event of failure of the SLCS function, the operators are directed by procedure to lower the water level to the top of the core and to depressurize the reactor vestel. Recent preliminary work at Rensselaer f Polytechnic Institute (Refersnce 4) suggests that the Shoreham reactor would  ;

be subcritical in this configuration even without liquid poison injection, that t

is, with the control blades in their 25 percent power positions, the reactor  ;

vessel water levels at the top of the core, and the reactor vessel pressu"e at 200 psia (or below). Nevertheless, to account for the possibility that the [

j reactor does remain critical in this configuration, analyses were performed of r the power and pressure response during an ATVS event. i The transient analyses were performed by Oak Ridge National Laboratory (ORNL) using the BWR-Long Term Accident Simulation (BWR-LTAS) code developed at ORNL 9

O and described in Reference 5. The sequence considered was an ATWS initiated by transient-induced closure of the main steam isolation valves (MSIVs). The analyses assumed that the control blades remained stuck in their normal posi-tion and that no cperator actions were taken. Two cases were considered, one with the blades in the position corresponding to 25 percent power and the other with the blades in the full power position.

The calculated results for the two cases are shown in Figures 1 and ?. In the analyses, HPCI, RCIC, and CR0 injection maintain reactor vessel water level above the top of core until failure (by assumption) of the HPCI turbine at a suppression pool temperature of 210'.'. With HPCI system failure, reactor vessel water level decreases, leading to ADS actuation. As the vessel is depressurized into the regime in which the low pressure injection systems are able to pump cold water into the vessel, oscillations in injection flow, core power, and vessel pressure occur as a result of positive reactivity insertion associated with collapse of voids in the core by cold water. Similar trends are observed in both cases but the following key differences should be ncted:

1. The time to ADS actuation and core uncovery is significantly later for 25 percent power,
2. The frequency and magnitude of pressure and power oscillations is reduced for 25 percent power, and
3. Drywell pressure remains below the design value for 25 percent powar but exceeds it for 100 percent power.

Much of these differences in behavior can be attributed to the fact that the negative reactivity of the core voids relative to that of the control blades is less with the control blades in their 25 percent power configuration. It follows that perturbations that tend to collapse voids in the core region will insert less positive reactivity with the control blades in their 25 percent power positions chan with the control blades in their 100 percent power positio'1s.

Hence, the core response to positive reactivity inertions caused by uncon-trolled cold water injection by the low pressure ECC systems is more sluggish at 25 percent power.

10

On the easis of these calculations, the staff concludes that adequate mitiga-tion of an ATWS accident sequence, given failure of complete shutdown, is much 4 simpler for the control room operators if the control blades are in their con-figuration for 25 percent power operation as opposed to their configuration at 100 1ercent power. While we expect the likelihood of ATWS events to be extremely low at Shoreham due to hardware improvements and mitigative capabilities at 25 percent power, should an ATWS occur the safety concerns at 25 percent power would be substantially less than at full power.

3.1.1.2 Core Melt Progression for an ATWS Sequence The release Category 1 sequence, identified in LILCO's submittal as Case C90, is an ATVS initiated by MSIV closure at time.= 0. According to the sequence definition, reactor vessel water level is maintained at the top of the active fuel by various combinations of HPCI, RCIC, CRD, and LPCI, while the SRVs vent steam to the pressure suppression pool. The primary contain. ment is assumed to be vented from the wetwell airspace when the primary containment pressure reaches 60 psig in accordance with the Shoreham emergency operating procedures (EOPs). The vent line is assumed to fail at the flexible coupling which joins the vent line with the RBSVS ducting (reactor building elevation 101 ft), and the resulting harsh reactor building environmental conditions are assumed to l fail all reactor vessel inject;on systems. In the utility analysis, the l wetwell is vented at 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> into the event, at which time all injection is assumed to be lost. Core uncovery is predicted to occur at 1.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />, followed by onset of cladding relocation at 4.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. Core slump and eactor vessel failure is calculated to occur at 10.4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, at which time the drywell vent is opened to maintain primary containment pressure at or below 70 psig.

To confirm the sequence of core degradation and reactor vessel failure events that would occur after loss of all injection, an independent calculation was performed by ORNL for the latter period of the accident. This analysis was performed using the Boiling Water Reactor Severe Accident Response (BWRSAR) code developed by ORNL and documented in Reference 6. The calculation was initiated at time 90 minutes (the time at which venting and loss of injtetion occurred in the utility analysis) and was run until postulated reactor vessel 11

I I

failure. Core power was controlled by user input and the control blade posi-tions were established so as to approximate the actual 25 percent power con-figuration. The predicted timing of events is provided in Table 4, along with l

the results obtained by LILCO using the MAAP code.

Generally good agreement is noted between the BWRSAR and MAAP estimates of the time to start of cladding relocation and to slump of the first major portion of the core into the bottom head of the reactor vessel. However, the ORNL code ,

predicts a much longer time to reactor vessel failure (30.8 h) than does the MAAP code (10.4 h). This is due to different modelling approaches taken in the two cod 1s with regard to (1) the state of the debris which is assumed to slump into the bottom head, and (2) the extent of debris quenching which occurs in  !

the bottom head.

I The two different modelling approaches can be summarized as follows. In BWRSAR, radial columns or zones collapse when their average cladding temperature reaches 4250*F, at which time very little of the 002 mass in the region is molten (molten Zircaloy is relocated to the bottom head prior to that time). Falling mass is assumed to be quenched by the water in the lower plenum until the time of bottom head dryout. In MAAP, molten core materials are assumed to accumulate  ;

in the lower-most node of each radial zone until one of those rodes becomes compittely molten; at that time the material in the molten node and any molten material in adjacent nodes falls to the bottom head. The MAAP models provide for only minimal interactions between the molten material and the water in the lower plenum, and hence the debris does not quench. Subsequent heatup and attack of the reactor vessel lower head by the molten debris is calculated, and pro-duces vessel breach within tens of seconds to a few minutes. The MARCH code, discussed later, has the capability of modelling the heat transfer either way (i.e., with or without debris quenching) as a user option. The effect of the modelling differences on the estimated time to vessel failure is accentuated in the subject analyses due to the significant quantity of water in the bottom head of BWRs and the reduced decay heat levels in the core debris at 25 percent power.

The uncertainty in estimates of time to vessel failure, while significant, is reasonably well-bounded. The assumption of minimal debris quenching in the 12

~ - -

O

. o bottom head is considered by the staff to provide lower limit, conservative estimates of failure times, whereas, models which assume complete debris quench-ing and bottom head dryout prior to thermal attack of the bottom head may be somewhat optimistic and provide an upper limit. In reality, we would expect that the time to vessel failure would lie between the two extremes predicted by the models, but closer to the estimate obtained assuming debris quenching. This view is supported by the results of the TMI-2 core debris examinations performed to date (Reference 7). Hence, reactor vessel failure times for the ATWS sequence at 25 percent power would not occur until after nine hours following initiation of the transient, and may be delayed by as much as a day.

For comparison, results for an ATWS calculation at 100 percent power are presented in Table 5. The 100 percent power values are based on a MARCH 2 calculation performed previously for the Limorick plant which, like Shoreham, is a BWR/4 with a Mark II containment. Although the plant design characteristics, sequence definition, and computer codes are different for the two cases, they are judged to be sufficiently similar to illustrate the approximate effect of the power restriction on the timing of major events. The calculations indicate that the time to initial core slump and potential reactor vessel failure is extended from about two hours at full power to over nine hours at 25 percent power. It should be reogni.:ed that the ATWS event would proceed much differ-ently than modelled here if the sequence were more realistically d,$ined to include additional operator actions. However, in either case the 2d percent power restriction would substantially delay core melt progression and afford additional time for operator actions and protective measures.

i An additional difference identified in the ORNL analysis concerns the quantity of hydrogen produced in-vessel. The BWRSAR ATWS calculation for 25 percent power indicates that approximately 2400 lbm of hydrogen are generated, (For i the LOCA, station blackout, and loss of injection sequences discussed later the staff calculations indicate that about 1300, 1400, and 2100 lbm of hydrogen would be produced at 25 percent power.) The MAAP code consisten'.ly produces much less hydrogen than the staff calculations (typically a totti of about 250 lbm). The reasons for this are well established and due largely to assump-j tions in MAAP regarding the formation of blockages in t'e core and termination 13

Q

. . o J

of cladding oxidation (and hydrogen production) following cladding relocation; a more detailed discussion of this matter is presented in Appendix J.2 to Reference 8. Since hydrogen is produced as a result of an exothermic. reactior (cladding oxidation by steam), production of larger quantities cf hydrogen results in greater energy release during the core heatup precess, potentially accelerating the core melt progression. However, as evidenced by the generally good agreement between the staff and utility estimates presented in Table 4, the impact of increased hydrogen production on the timing of core melt progres-4 sion is not significant, i

, With regard to the effect of reactor power level on hydrogen production, staff j ralculations indicate that the difference in the total quantity of hydrogen produced at 25 percent and 100 percent power is within 300 lbm. This difference is not a critical consideration because a great deal of hydrogen is predicted

. to be generated regardless of the initial power level.

I i 3.1.2 Large Break LOCA Sequences

, Loss of coolant accidents involve the loss of reactor coolant via a breach in the reactor coolant system pressure boundary. LOCAs can occur either inside containment due to events such as pipe breaks, or outside containment as in the l case of a loss of coolant to an interfacing systen..' Large break LOCA sequences,

! in general, represent the most rapidly evolving severe accident sequence. As

) indicated in Tabis 3, two of the six release categories in the LILCO PRA for

] 25 percent power are represented by large break LOCA sequences. These are release Categories 2 and 5.

] The release Category 2 sequence, identified as Case CADRF, is a seismically-i initiated recirculation line LCCA, with a coincident drywell head failure of l 3 fta. All reactor vessel injection systems are lost. Only the refueling bay l is credited for fission product removal, and the Reactor Building Standby Ventilation System (RBSVS) is assumed to be unavailable.

l.

1 j The release Category 5 sequence, identified as Case C3C, is a large LOCA with j loss of all injection except that from the CR0 hydraulic system. One or more I

l l 14 1

I l- _

O E

drywell downconc > are ascumed to fail upon reactor vessel failure, allowing bypass of the pressure suppression pool and the wetwell air space is assumed to be vented when the primary containment pressure reaches 60 psig. In the utility l

analysis of this sequence the wetwell air space is vented at 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> into the accident to maintain primary containment pressure at or below 60 psig. l In the utility analyses for these two casos, the timing of core degradation and reactor vessel failure events is similar: i.e., the core uncovers within about 30 seconds, begins to melt at approximately an hour, and slumps at approximately four hours. As indicated in Table 3, howevar, the time of fission product release to the environment is distinctly different for the two sequences; this is because the containment is failed in the releaso Category 2 sequence and is l

intact in the release Category 5 sequence. .

To confirm the general nature of the timing of core melt progression and vessel failure, three large break LOCA calculations were performed by ORNL using the BWRSAR code. In the first calculation the drywell, was assumed to be failed, as modelled in the CADRF sequence (release Category 2), in the second calculation, the containment was assumed to be intact, as modelled in the C3C sequence (release Category 5). It should be noted that this calculation did not fully  !

simulate the C3C sequence in that the injectica flow from the CR0 hydraulic system was not modelled. This would have only a minimal effect on sequence '

progression since the injection flow would be expelled from the break without passing through the core. The third calculation was identical to the second except that the initial power level was changed from 25 percent to 100 percent.

The two BWRSAR calculations performed for 25 percent power yielded similac I results regarding the timing of core melt progression; this is not surprising since the only difference between the calculations was the containment back-Dressure. The calculated times for key events are presented in Table 4 along with the utility's values. The staff's values for the onset of cladding reloca-t r

tion and core slumping are consistent with the utility's, but indicate a some-what earlier (about one hour) time to slumping. The staff's estimates of the tima to vessel failure are considersbly longer for the reasons described in Section 3.1.1.

i 15

4 A comparison of the BWRSAR predicted core melt progression at 25 percent and a 100 percent power is presented in Table 5 for the large break LOCA with no injection and intact containment. These time estimates are considered by the staff to be representative for the sequences selected to represent release

, Categories 2 and 5. The results indicate that the delay in key events afforded i by the power reduction is significant: 1.e., it shifts the time of onset of cladding relocation from 0.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to I hour, and the time of core slumping from 0.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> to 3.3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />. This shift represents additional time for opera-

! tor actions and emergency response which would not be available if operating at 100 percent power.

)

3.1.3 Station Blackout Sequences

.i Station blackout is defined as a loss of all AC power (except vital AC supplied

, through DC inverters). This is caused by loss of offsite power and the sub-sequent failure of the diesel and gas turbine generators. The release Cate-

! gory 4 sequence, identified as Case CIA, is a station blackout sequence coupled with a stuck open relief valve and a failure to isolate the drywell equipment i

and floor drain lines. The RBSVS is not available. HPCI and RCIC (both turbine I

i driven) are initially available, but HPCI is lost due to low HPCI turbine steam flow at 8.5 minutes, followed by loss of RCIC at 45 minutes.

To confirm the timing of accident events at 25 percent power, MARCH 3 calcula-l tions were performed by Battelle Columbus Laboratories (BCL) fo?' the same 1 accident sequence. The MARCH 3 modelling assumptions used were in accord with i

j the methodology described in NUREG-0956. The effect of the treatment of debris l quenching on time of bottom head failure was investigated in these calculations by considering (1) no debris quenching in the vessel head, consistent with the

] MAAP models, and (2) debris fragmentation and quenching upon contact with water

) in the vessel head, consistent with the BWRSAR models.

1 l The predicted timing of key events is compared to the utility results in Table 4.

Although significant differences in time to core uncovery are observed (1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> i in MARCH 3 versus 4.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> in MAAP) estimates of the time to onset of cladding relocation and core slump are in good agreement with the MAAP results, as is the l

16 1

. . 1 o

time of vessel failure when no debris quench is assumed. When debris quench is assumed, the time to vessel failure is extended considerably (12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> with no quench versus 49 hours5.671296e-4 days <br />0.0136 hours <br />8.101852e-5 weeks <br />1.86445e-5 months <br /> with quench).

While the time to vessel failure predicted in the BCL calculation with debris quenching is somewhat higher than indicated in the ORNL calculations for conparable sequences (ATWS and Loss of Injection), the interpretation of the result is consistent with the ORNL results, i.e., delays on the order of a day are predicted when quenching is assumed and the initial water inventory in the bottom head is large. We conclude that the BCL calculation adequately confirms the timing of core melt progression events reported by the utility for this sequence at 25 percent power. ,

To show the effect of the 20 percent power restriction on severe accident event l timing for the station blackout sequence, a comparison with the results for a similar calculation at 100 percent power is presented in Table 6. The 100 per-cent power values are based on a MARCH 2 calculation performed previously for i the Limerick plant. The Limerick sequence is defined somewhat differently with j coolant boil off initially taking place at high pressure and depressurization l assumed af ter core uncovery, however, the differences in the timing of predicted accident progression illustrates the extent of the delays afforded by operation j at 25 percent power, l

3.1.4 Loss of Injection Sequences

(

Loss of injection sequences can be characterized as operational transients in

) which the reactor is successfully shut down, but reactor coolant injection systems fail to function. The releass Category 6 sequence, identified as Cao l

3 C6A1, is a transient with loss of all injection, i.e., a transient-induced l scram, followed by failure of all of the systems that would normally be relied (

i upon to deliver cooling water to the vessel as necessary to keep the core covered (normal feedwater, HPCI, RCIC, RHR core spray, and CR0 flow). In the utility analysis of this sequence, core melting begins at 5.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> with reactor vessel failure occurring at 11.3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />. The primary containment is not f l vented (pressure does not reach 60 psig), nor does it fail during the first  !

t I

I 17 l

50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> of the accident. Fission product releases are, therefore, limited to that associated with primary containment design Isakage (0.5 volume percent ,

per day). l I

A confirmatory calculation for the postulated total loss of reactor vessel injection at the Shoreham station was performed using the BWRSAR code. In this calculation it was assumed that the reactor had been operating at 25 percent  !

power at the time of scram and, in spite of the long times involved, no injec- i tion source is ever recovered. For conservatism in the analysis, there is no modelling of pressure suppression pool cooling or operation of the drywell  !

coolers. Also, the reactor vessel is assumed to remain at pressure. This l

sequence definition is consistent with that for the utility's C6Al sequence, f The calculated times for key events are pres 1nted in Table 4. Agreement with the MAAP results reported by the utility is good (with the exception of time to vessel failure and quantity of hydrogen produced, as discussed previously). l In order to clearly demonstrate the effects of operation at 25 percent power, the total loss of injection sequence was recalculated with all parameters the l

same except for the initial power, which was set at 100 percent of rated power.

l The difference in timing of the major events of the accident sequence are ,

indicated in Table 6. The results indicate that relative to full power opera- f tion, delays of about five hours in the onset of cladding relocation, nine hours in the start of core slump and nine to 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br /> in the time of vessel failure '

would be realized by restricting operation to 25 percent of rated power.

i 3.1.5 Applicability of Results to Other Sequences  ;

I A number of observations can be made concerning the results reported in the  !

previous four sections, ilrst, for tt;e sequences considered, the independent i

j staff analyses approximately confirm the timing of core melt progression k reported by the utility for operation at 25 percent power. Second, based on l the staff comparison of the core melt progression at 25 percent versus 100 per-cent power, the delay in key events afforded by the power restriction is significant, i.e., on the order of hours. Finally, a number of differences l remain in the modelling of the accident progression. Most notable are the  ;

I 18

r differences between the staff and utility estimates of the time to vessel failure and the quantity of hydrogen produced in-vessel.

While only a limited number of sequences have been evaluated as part of the staff's review of the utility submittal, we believe that the same observations would hold true for the range of accident sequences that are expected to domi-

nate core melt frequency at Shoreham. The underlying reason is that the observed delays in timing are directly attributable to the reduced decay heat level associated with operation at 25 percent power and that this reduced decay heat level will affect all sequences in a manner similar to observed here.

Specifically, the time of core melt for sequences in which the reactor coolant j system remains intact is characterized by the time required to boiloff the coolant inventory and subsequently heat the core to oxidation temperatures.

Sequences of this type will, in the limiting case of loss of all injection, exhibit the same general behavior as observed for the station blackout and loss of injection sequences. If the reactor does not scram, the coolant boiloff is -

more rapid (due to decay heat plus some fraction of core power) but subsequent f' core heatup case with scram; core melt progression for such sequences could be l approximated by the ATVS sequence considered previously. For sequences in which l a

the coolant inventory is lost due to breach of the reactor coolant system, the ,

1

delay in core-melt afforded by coolant boiloff will be reduced (by an amount (

! depending on break size and available injection flow), but at 25 percent power  ;

j a considerable amount of time will still be required to heat the core to oxida- I l tion temperatures. The limiting case is represented by the large break LOCA sequence described previously. If the break size is smaller or coolant injec-

] l tion is available, core melt would be considerably delayed or averted. (

l furthermore, the reasonably good agreement obtained between the staff and ,

utility estimates of the timing of key core melt events suggests that the principal thermal-hydraulic and core heat transfer models which govern reactor coolant blowdown /bolloff, core heatup, and the early stages of core degradation f

are not fundamentally different in the utility and staff codes; thus, addi- l tional comparisons with MAAP results (for timing) would likely result in the I Same level of agreement as observed here. Similarly, in those areas in which (

i 19 1

i 1

differences between MAAP and the staff's results have been identified, these same differences would be expected to exist for other sequences as well.

3.2 Timing of Releases to the Environment Estimatus of the time of releases to the environment for the spectrum of core melt accidents have been developed by considering the estimated frequency of each of the plant damage states and release categories in the Shoreham 25 per-cent power PRA, the types of sequences which comprise the various damage states and release categories, and the time progression of these accidents at 25 per-cent power. Table 7, extracted from Reference 9, provides a description of the types of sequences which comprise each of the plant damage states, as well as the frequency of occurrence of each damage state at 25 percent power. The utility, in Reference 10, has estimated the time from the initiating event to i the in%ial release of radiation to the environment for each release category wi+h'.) each plant damage state. The utility time estimates are reproduced as Table 8. Based on this assessment, the utility claims that approximately 74 percent of the core melt sequence (represented by release Categories 5 and

6) require 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> or more to proceed to an offsite release, while an addi-tional 22.7 percent of the sequences (represented by parts of release Categories 1, 2, 3, and 4) require between seven and 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> to produce offsite releases. The remaining 3.3 percent of all c' ore melt accidents would produce a release in about one hour.

3 t

The staff has performed a limited review of the utility analysis. This review focused on the timing of releases rather than on the fraction of cors melt j frequency allocated to each plant damage state and release category. An initial l observation is that for several of the release catagories, the estimated times of release reported in Table 8 are different than those used in the utility off-site consequence analysis (see Table 3). It is our understanding that the Table 8 values were developed by reviewing the fission product release histories calculated by MAAP for the representative sequence for each of the six release l

l categories, and identifying the time at which the releases exceeded some assumed threshold. In contrast, the times used in the offsite consequence calculations are chosen to best represent the release history as a single "puff" release, and 1,

20

{

r i are not linked to a threshold. This difference in approach for estimating the f j times to release would appear to account for the differences between the time

! estimates in Table 3 and Table 8. f 5 [

f Using an approach similar to the applicant's, the staff has developed a char- f acterization of the time of release for a spectrum of accidents at both 25 per-f j cent and 100 percent power. This assessment was performed at the plant damage  !

I state level rather than at the release category level. This avoids having to  !

deal with complu issues and assumptions related to the CET analysis, the bin-  !

t ning of CET and states into release categories, and the selection of repre- i j sentative sequences for the various release categories. l

[ The approach taken by the staff was to conservatively estimate the time of l l release for a typical sequence for each damage state, and to couple these esti- l mates with the utility's estimate of the fraction of core melt frequency for (

j the damage state to obtain a distribution of release times. The major limita-l tions of this approach are that (1) the sequence selected to represent a plant damage state may not be the limiting sequence (for timing) within the damage f

state and (2) the potential for early containment failure may not be adequately i

reflected in the release time estimates. However, these limitations should not l l

f significantly affect the results of the assessment for the following reasons.

l Foremost, release times are conservatively estimated by assuming reactor vessel j failure at core slump and containment pressurization rates based on participa-l tion of the entire core in subsequent core concrete interactions. For all plant f damage states, the estimated time to release is significantly less than a more realistic estimate of the time of vessel failure. Hence, early containment challenges associated with reactor vessel failure (e.g., in-vessel and ex-vessel steam explosions, direct containment heating, and containment liner melt-through) would realistically occur later than the estimated times of release. Also,

]

while certain sequences within a given plant damage state may have release l

j times thorter than the sequence selected to represent that damage state, it is  !

l the staff's judgement that the fraction of the core melt frequency associated (

with those sequences is not large enough to significantly alter the distribution of release times for the spectrum of accidents, j i

21 ,

4

_-- I

The results of the staff's assessment of the time of release to the environment for Shoreham is presented in Table 9 for 25 percent and 100 percent power opera-tion. In both cases the frequency of each plant damage state is bas 6d on values reported by the ut,ility. (These values are reported in Reference 1 for 25 per-cent power and References 2 and 11 for 100 percent power.) The estimated time of release for the various damage states is based on either staff estimates or utility estimates as described below. For operation at 25 percent power, the staff estimate of 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> for the Class I damage state is based un a loss of injection sequence, such as the station blackout or loss of injection sequences described in Section 3.1 and Table 6. Reactor vessel failure is assumed to occur coincident with slumping of the first radial zone of the core, or approx-imately 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br />. Containment failure by venting is assumed to occur three hours later due to releases from core concrete interactions in which the entire core participates. No consideration is given to the more likely situation in which core debris would enter the pool and be quenched, resulting in much later or perhaps no containment failure. The release time of six hours for the Class III damage state was based on the large break LOCA sequence subject to the same assumptions regarding vessel and containment failure. A similar process was followed to estimate the time to release for Class I and !!! damage states at 100 percent power.

The time of release for the Class II plant damage state is based on analyses performed for a transient sequence with loss of decay heat removal. This sequence is a dominant contributor to the Class II plant damage state frequency at Shoreham. In this sequence, denoted TW, the reactor shuts down and emer-gency core cooling systems operatt, but the suppression pool heat removal system fails. This leads to pool heatup and eventual centainment overpre:sure failure prior to core melt. Because the core is at decay heat power level the time to containment failure is substantial. Calculations performed for a TV sequence in Peach Bottom (Reference 12) indicate that containment failure does not occur (for Peach Bottom at full power) until about 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> after sequence initiation, with subsequent core melt at approximately two days. Similarly, the time of release used in the Shoreham full power PRA for release categories associated with the Class II damage state was 38 hours4.398148e-4 days <br />0.0106 hours <br />6.283069e-5 weeks <br />1.4459e-5 months <br />. The time of release would be even longer for operation at 25 percent power. Accordingly, the staff has estimated 22

the time of release for the Class II plant damage state to be greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> for operation at both 25 percent and 700 percent power.

The release times for the Class IV damage state are taken from the utility analysis since the staff did not have independent containment analyses for these cases. For 25 percent power, the time of release (7.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />) is based on the utility analysis of the ATWS sequence selected to represent release Category 3.

For 100 percent power, the time of release (2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />) is based on time esti-mates for the Class III damage state reported in the original 100 percent power PRA (Reference 2).

The time of release to the environment for the Class V and the seismically-induced reactor pressure vessel failure (SRPV). damage states at 25 percent and 1

100 percent power is taken to be the time to the beginning of cladding reloca-tion for a large break LOCA with no injection. The rationale for this assump-tion is that (1) a significant amount of the noble gases and volatile fission products would have been released from the core by the time the core reaches i

the temperatures associated with cladding relocation, (2) the dominant sequences

! associated with these plant damage states involve large LOCAs or rupture of the reactor pressure vessel; hence, the reactor coolant system (RCS) provides little delay in the release of fission products from the core to the containment, and (3) the containment building is bypassed or ruptured by definition of these plant damage states, minimizing its effectiveness in preventing or delaying the release of fission products to the environment. It should be noted that a more realistic analysis which accounts for the actual release history from the core, and delays afforded by the RCS and containment would result in estimated times of release more on the order of one to three hours for 100 percent and 25 per-l cent power operation.

4 A summary comparison of the utility and staff estimates of the distribution of the time of release for core melt accidents at Shoreham is presented in Table 10. '

The staff and utility estimates for 25 percent power are not significantly different for the release time windows considered. These results indicate that approximately 80 percent of all core melt sequences require 12 or more hours to i

i 23 4

O O

proceed to an offsite release and approximately 95 percent of all accidents require six or more hours to produce a release.

Comparison of the time estimates for 25 percent power with those developed by the staff for 100 percent power illustrates the frequency weighted shift in time of release afforded by operation at 25 percent power. Under conservative (

assumptions regarding reactor vessel failure times and containment performance, the bulk of the releases at full power (approximately 75 percent) occur between two and six hours following accident initiation. The Class I damage state, with release at f(ve hours, is the major contributor; Classes III and IV also contribute, with releases at just over two hours. For the same assumptions at 1 35 percent power, releases for the Class I damage state are delayed until 12 or more hours following accidant initiation, and releases for Classes III and IV  :

) are delayed until between six and 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

J ,

j A small fraction (three percent) of core melt accidents at Shoreham still result  ;

]

in releases on the order of an hour. These early releases are due almost exclu- ,

sively to seismic events which induce simultaneous reactor pressure vessel and

) containment failure. The difference in the fraction of core melt frequency for l

] this contributor at 25 percent and 100 percent power is attributed by the staff 1 to differences'in total core melt frequency estimates and rounding error rather than to some artifact of operation at 25 percent versus 100 percent power.

i 4 EFFECT OF POWER RESTRICTION ON OFFSITE CONSEQUENCES j This section provides the results of the staff's review of the utility's claim l l regarding reduced offsite consequences at 25 percent power. The factors which  ;

I contribute to reduced offsite consequences ace a smaller source term release at l the lower power level, in conjunction with the delayed times of release dis-i cussed in Section 3. The staff's evaluation of the fission product inventory I at 25 percent power is provided in Section 4.1. Important fission product 1

release and retention mechanisms for Shoreham (namely, core concrete interac- '

tions and the Shoreham reactor building) are also discussed. The impact of the power reduction on offsite consequences is assessed in Section 4.2.

1 1

I '

24 1 ,

4

4.1 Source Terms at 25 Percent Power The magnitude of radionuclide releases for accidents initiated from 25 percent l power can be expected to be less than for similar accidents initiated at 100 per-cent power for two reasons. First, the initial fission product inventory would l be smaller at the lower power level. Second, the evolution of certain fission '

products would be inhibited by the lower heatup rates and temperatures associated I with the decay heat level at 25 percent powar. An assessment of each of these  !

aspects of the source term reduction is provided below.

4.1.1 Fission Product Inventories In order to verify the expected lower radionuclide inventories for operation at reduced power, ORIGEN2 csiculations were performed by BCL for the Shoreham core. Radionuclide inventories were calculated at the end of two, four, and six years of operation at 25 percent power. A comparison of the results is presented in Table 11. These results indicate that significant increases in the radioisotope inventory do not occur after the second year. Although the quantity of certain radioisotopes continues to increase with time, this increase is considered insignificant relative to its impact on core melt pro-gression and offsite consequences.

The BCL results at the end of two years of operation at 25 percent power are compared in Table 12 with the inventories used in the LILCO analyses for 25 per-cent power operation. The latter were obtained by adjusting the WASH-1400 PWR inventories to account for differences in power and core size. It can be seen that the two sets of results are in reasonable agreement, with the BCL ORIGEN2 results being slightly higher. This is understandable when it is recognized that the WASH-1400 results were derived for the middle of an equilibrium cycle and thus correspond to slightly lower average exposure than the BCL calculation.

The current analysis uses a later version of the ORIGEN code than that applied in WASH-1400. The differences between the values used in the LILCO analysis and the BCL ORIGENT. values is not considered to be significant.

25

i Also shown in Table 12 are the results for the end of equilibrium cycle for the Shoreham core at full power. Comparison of the values for 25 percent  ;

power with those for 100 percent power confirms that the power restriction I indeed results in an approximate factor of four reduction in fission product ,

inventory.

L 4.1.2 Fission Product Releases The source terms used in the Shoreham 25 percent power PRA were obtained directly from MAAP analyses. The staff has reviewed these source terms for reasonableness and consistency with source terms that would be predicted using the staff methodology, i.e., the Source Term Code Package (STCP).

The emphasis of the review was on the source terms for release Categories 1 and 2, as these release categories account for the bulk of the injury-threatening doses.

Two major concerns regarding source terms were identified by the staff. The first was that little or no core-concrete attack in the drywell was considered to occur in the MAAP analyses for Shoreham, and that the utility source terms therefore underestimate the contributions from several important fission pro-duct groups, e.g., tellurium and strontium. The second was that the credit for fission product retention in the secondary containment building appeared to be overstated in the utility source term estimates for certain release cate-gories. The staf f's assessment of core-concrete interactions and secondary containment building performance is provided separately in the two sections which follow. The development of source terms which account for staff concerns in these areas is discussed in Section 4.2.2.

4.1.2.1 Releases from Core-Concrete Interactions The MAAP analyses for Shoreham assume that debris leaves the reactor vessel in a molten state and immediately flows through the pedestal downcomers into the suppression pool where it is pe-manently cooled. Although 10 percent of the core debris is assumed to remain in the drywell, the MAAP models do not predict significant core-concrete interactions. In contrast to the treatment in MAAP, 26

both the BWRSAR and MARCH 3 codes predict that a major portion of the core debris will be solid within the bottom head at the time of vessel failurt. Thus,  ;

the staff calculations do not support the contention that all core debris would i exit the vessel in a molten state, and pass into the pressure suppression pool.

l The more likely situation in the staff's view is that a substantial fraction of i

the core debris, e.g., 20 to 50 percent, would rapidly exit the vessel following ,

bottom head failure and that the remaining debris would be released from the vessel over the next several hours. While the bulk of the core material may I flow toward and eventually pass through the four steel downcomer pipes located

, within the reactor pedestal region, some interaction of the debris with the con-j crete drywell floor would be expected prior to the debris reaching the downcomers.

The extent of this core-concrete interaction and associated fission product f i release is influenced by several factors including (1) the chemical composition ,

i (particularly the fraction of unreacted Zircaloy), discharge rate, and tempera-  :

j ture of debris exiting the vessel, (2) the state of the debris bed on the dry-

) well floor during subsequent core debris additions, and (3) the length of time I which debris remains on the floor before draining into the suppression pool. '

1 Given the right combination of the above parameters, interaction of considerably  ;

greater than the 10 percent of core debris assumed by the utility would appear

likely.

(

1 1

l i

i In order to assess the potential for concrete attack by some portion of the ,

core debris, a series of four calculations were performed by Battelle Columbus l Laboratories (BCL) using the CORCON portion of MARCH 3. The assumptions and l principal results of these calculations are described below:

Care 1 - In the first CORCON case the entire inventory of core and structural debris was assumed to remain on the floor of the pedestal. This is  ;

not to imply that the debris would all remain in the pedestal, but to provide a point of reference and comparison with the results of other  !

l analyses. The initial conditions of the debris were those predicted  !

! by MARCH 3 for the early head failure case i.e., a mixed mean debris

temperature at the predicted time of vessel failure of 3550'F. CORCON l

) partitioned the debris into a metal and an oxide layer, with the f l

l i

27 i

i

(

+

latter predicted to be on the bottom. The oxide layer was predicted i

] to remain solid over the 10 hour1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> time period considered, even though

}

] the oxide layer temperature was predicted to increase to a peak of i about 4040'F before declining. Concrete attack was predicted to be j l.

predominantly radial with an increase in cavity radius of 3.6 ft ano (

axial penetration of 0.59 ft.

(

I j Case 2 - Since the initial mixed mean debris temperature was below the melting l

1 points of the oxides but above that of the metals, the second case I l considered assumed that the molten metallic components were able to f flow down the downcomers but that the oxide phases remained on the i I l

pedestal floor. The initial debris temperature was again that from j
j. the MARCH 3 calculation. In this case the oxide debris remained j i solid and increased in temperature to a peak value of about 4090*F  ;

f before declining. In the absence of chemical reactions between f

l metals and the concrete there was relatively little concrete attack. l The total radial and axial concrete attack over the time period l

considered wat 0.46 and 0.49 ft, respectively.

Case 3 - The third case considered was similar to Case 2, except that only half of the total oxide inventory was assumed to remain on the j p6destal floor; this would imply that the other half of the oxides were able to flow into the suppression pool with the metal phase.

With the reduced mass of debris and the absence of chemical interac- l tions the temperature of the debris was predicted to decrease con-j tinuously. The predicted radial and axial concrete erosion was O.30 and 0.43 ft, respectively.

Case 4 - In the fourth case the debris were assumed to be at the effective i liquidus temperature of 4130*F used in the in-vessel analysis.  !

r l This corresponds to approximately the state of the debris exiting i the vessel in the MAAP analyses. One fourth of the core was assumed to remain on the floor of the pedestal. For this case CORCON partitioned the debris into two layers, with the denser oxide layer '

on the bottom. The oxide was again predicted to be solid and i

i l 28 1

remair.ed below the liquidus temperature through the 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> of attack considered. In this case the rate of concrete attack was initially rapid and decreased with time; the debris temperature decreased monotonically from its initial value. The predicted extent of concretc erosion for this case was 2.3 ft in the radial and 0.33 ft in the axial direction.

The above analyses indicate that some attack of the pedestal floor by debris released from the reactor vessel is quite likely under a variety of assumptions.

In this context BCL augmented the above analyses with VANESA code calculations to assess the potential fission product releases that could be associated with such core-concrete interactions.

The results of the VANESA analyses for fission product release for the several cases of corium-concrete interactions are summarized in Table 13. Also sho. ,

in this table are VANESA results for Limerick which had been obtained in earlier studies at BCL, The types of concrete in the two plants are comparable.

Comparison of the results for the Shoreham full core at reduced power (Case 1) with the Limerick results indicates relatively little difference. This is to be expected since in both cases there is substantial unreacted Zircaloy in the debris: the chemical reaction of this Zircaloy with concrete dominates the behavior once high debris temperatures are attained. The principal effect of the reduced power operation is delay in time of the start of vigorous interac-tions, The predicted lower releases of ruthenium, lanthanum, and cerium for Shoreham may be attributable to somewhat lower temperatures for the reduced power operation.

If only the oxide phase is available to attack concrete (Case 2 and 3), the predicted results are different from the interaction of the entire core.

Since the oxide phase is predicted to remain solid, heat transfer is conduc-tion limited and high debris temperatures are predicted. In the absence of the chemical reactions associated with the metallic phase, however, the pro-duction of some of the more volatile exides appears to be reduced and the predicted releases are simply due +.o the volatilization of certain elemental 29

l

\

.' . l

! t 8

species. Thus, the predicted release of tellurium is enhanced, and those of I i cesium, strontium, lanthanum, cerium, and barium are reduced relative to the

[

} full core case. The predicted releases of ruthenium appear to be sensitive  !

i to the specific temperature history in each case, but are low under all the I i

! conditions considered here.

J f

l If it is assumed that only a fraction of the core debris can interact with the

] drywell floor, but that this fraction is at a temperature comparable to that j j assumed in the MAAP analysis (Case 4), the predicted fractional releases of j radionuclides are only somewhat lower than those indicated for the entire core. [

l and the releases occur rather rapidly.

i The CORCON analyses described above indicate significant potential for concrete f j attack even if only a fraction of the core debris remains on the pedestal floor I and interacts with concrete. The extension of the CORCON calculations to the predictions of fission product release by VANESA indicates substantial sensi-

[

tivity to the assumptions regarding the nature and degree of debris interaction  !

l with concrete. For the cases considered, however, the potential for consider- f able ex-vessel fission product release is indicated. On the basis of these

} (

! results, the staff concludes that the utility source terms do not adequately l reflect the potential for core-concrete interactions. Indepen6ent staff calcul-ations which account for significant core concrete interactions are described  ;

] in Section 4.2.2.

4.1.2.2 Retention in the Secondary Containment Building

$ An assessment was performed by the staff's contractor, Oak Ridge National Laboratory (ORNL) of the decontamination factors (DFs) for the $horsham second- I ary containment building. The sequences of interest for this assessment were cases C90, CADRF, and CIA, which were used to represent release Categories 1,

{

2, and 4, respectively. For these sequences OFs of 10, lo, and 50 were claimed a by the utility, No secondary containment OFs were claimed for the other three

) release categories.

J I i 30 b

I  !

1  :

O O

l A preliminary assessment of the secondary building 0Fs was obtained by compar- l ing Shoreham's secondary containment characteristics to those of the Browns (

Ferry and Peach Bottom plants, which were previously analyzed in detail. This  !

comparison indicated the following:  !

1. a total secondary containment OF of 10 for Case C90 appears reasonable l based on the similarity between Shoreham's and Browns Ferry's volume, and i heat sink and sedimentation area t.haracteristics,
2. a refueling bay 0F of 10 for case CMRF appears to be higher than can be {

justified based on previous ORNL calculations for Browns Ferry and Peach Bottom, and  !

3. a total secondary containment 0F of 50 for CIA appears to be somewhat f high, albeit this OF is claimed for a sequence in whien high containment  ;

pressures are never achieved, the point of fission product release is .

into the reactor building basement, and the reactor building standby i ventilation system is not operational -- all factors which would tend  !

to increase DF.  !

It is important to note, however, that these judgments apoty only if hydrogen

{

burns do not occur in the secondary containment. While the utility analyses j indicate that deflagration limits were not reacned in any of the MAAP simula- l I

tions performed for the 25 percent power PRA, the absence of hydrogen burns appears to be a result of the low Zircaloy oxidation fractions typically calcu-lated by MAAP. If one considers the estimates of in-vessel hydrogin production obtained from the BWRSAR and MARCH 3 analyses, which are considerably greater f l than those calculated by KAAP, it is clear that hydrogen burns in the secondary l containment cannot be precluded. Hence, a more detailed assessment was made.

I l Secondary containment hydrogen burn analyses were performed by ORNL for cases C90 and CAORF. These analyses were performed by ORNL using the MELCOR code in conjunction with a 13 cell model of the Shoreham secondary building, and the hydrogen / steam release histories obtained from the BWRSAR analyses discussed in 31

a .

l

,e *

. .  ?

r i i

{ Section 3. The results of the analyses indicate that the use of the BWRSAR-j predicted hydrogen sources would result in hydrogen deflagrations in the f

( Shoreham secondary containment for both sequences analyzed. 8WRSAR/MELCOR pre-  !

) dictions for the C90 ATVS sequence indicate that a severe global burn would {

) occur at approximately 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> into the accident, producing a peak reactor I I building pressure of six psid. BWRSAR/MELCOR predictions for the CAORF seismic !

LOCA sequence indicate that refueling bay hydrogen deflagrations would occur at f

1.1 and 3.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> into the accident, with a peak induced pressure of 0.8 psid.  ;

The second burn approximately coincides with the time of postulated reactor  ;

vessel failure. I I

j A potentially important observation made as part of the staff's review of the f Shoreham secondary building performance is that operation of the Reactor Build- .

r ing Standby Ventilation System (RBSVS) can increase the severity of deflagra- l l

tions and reduce secondary containment OFs. Operation of the RBSYS can actually  !

increase the severity cf secondary containment hydrogen deflagrations by promot- I

] ing a well mixed secondary containment atmosphere, resulting in severe, global  !

{ hydrogen deflagrations for cases in which at least 800 lbs of hydrogen are (

available. Such burns would tend to flush fission products from the secondary l containment into the environment. RBSYS operation might also decrease the {

secondary containment OF for accidents in which the primary containment fails

(

into the lower region of the reactor building, by actively transporting fission l products from the lower regions of the building to the refueling bay (which

! would be the secondary containment failure location in most accidents). (

An additional observation is that Shoreham's low R85VS filter exhaust capacity readers the plant vulnerable to secondary building pressurization froa primary containment blowdown. Primary containment blowdown rates as low as 1200 cfm

! could initiate pressurization of the secondary containment and leakage of  ;

fission products to the environment. This is an important consideration, since I l the utility estimates that primary containment venting procwdure employed in i i most accidents will result in a 3000 cfm steam source to the reactor building. f i

i j In summary, while a variety of conservative and non-conservative modelling assumptions were made in the utility analyses, the dominant factors which j 1

}

i I 32 l

1 i

would affect the calculated 0Fs are: (1) the absence of hydrogen deflagra-tions in the utility analyses. (2) the use of a non-conservative aerosol sedimentation area for cases C90 and CIA, and (3) the use of an erroneous (hign) heat sink area for case CADRF. Correction of each of these deficien-cies would result in a reduction in DF. The extent of the reouction cannot be assessed in the absence of detailed confirmatory calculations, but the staff believes that secondary containment decontamination factors would more likely range from two to five for cases C90, CADRF, and CIA.

4.2 Offsite Consequences at 25 Percent Power l

J The approach taken by LILC0 to determine the offsite consequences for operation

at 25 percent power was to perform a MAAP analyses for each of the six repre-I sentative sequences (one sequence for each of the six release categories identi-fied in Table 3). The output from each MAAP run, specifically, the calculated fission product release fractions and release histories, was then used as the basis for defining the source term release characteristics for the respective j release category. The release characteristics (in terms of time to release, duration of release, and fractions of fission product inventory released) were then input directly to the CRAC2 and the CRACIT codes to determine the offsite consequences for each of the release categories. An overall picture of risk is obtained by multiplying the consequences predicted for each of the release cate-gories by the probability of the respective release category occurring given a

] core melt accident, (e.g., column 3 of Table 3) and summing over all release categories.

I The offsite consequences for Shoreham at 25 percent power have been reported by the utility in the form of dose-distance curves. These curves reflect the contribution from each of the six release curves, weighted by their respective probabilities. The Shoreham dose-distance curves compare quite favorably with those presented in NUREG-0396 (Reference 13), with the utility curves falling

, typically a decade or more below the NUREG curves.

A limited review of the utility offsite consequences analysis was performed by the staff as described in Section 4.2.1. In addition, the staff performed independent offsite calculations were performed to investigate impact of the l 33 i

r i

increased time for emergency response afforded by operation at 25 percent power. l l inis is described in Section 4.2.2. l l t 1

i l 4.2.1 Review of Utility Analysis l l

l l The following aspects of the utility offsite consequence analysis were reviewed by the staf f:

1. Adequacy of the meteorology data used in the analysis,
2. Consistency of reported source terms and release category probabilities with the reported dose-distance curves, and
3. Consistency of the utility CRACIT results with those predicted by the  !

CRAC2 code.

The meteorology data used in the L!LCO consequence calculations for Shoreham was reviewed by the Radiation Protection Branch of the Division of Radiation l'

  • rotection and Emergency Preparedness. Based on this review, the staff con-clude.; that the meteorology data should reflect expected conditions at the site, and therefore is acceptible for use in the Shoreham analysis.

To assure reproducibility of the dose distance curves reported by L!LCO, and consistency with the reported source terms and release category probabilities, ,

a confirmatory CRAC2 calculation was performed by INEL. The CRAC2 input data j used for the Shoreham analysis was supplied by t.!LC0 on floppy disk. This I input was compared to that listed in Table A 1 in Reference 14 and ne sub-stantive differences were identified. Several discrepancies between Table A-1 j in Reference 14 and Tables A.5 2 and 3 in the utility submittal (Reference 1) i were identified, but these were largely confined to release Category 6, and would not significantly affect offsite consequences.

A CRAC2 analysis was performed by Idaho National Engineering Laboratory (!NEL) using the version of CRAC2 installed on the INEL mainframe computer and the utility supplied code input. The calculated dose-distance probability dis- l tributions were compared to those reported by the utility and found to be in agreement. This indicates that the input and code version used by the utility I

34 e t

L----------_. - . _ . _ -- - -

t

was essentially the same as used by INEL, but does not address the validity of the source term input.

4.2.2 Independent Assessment of Offsite Consequences The staff has performed an independent assessment of the effect of tne power restriction of offsite consequences. The approach taken was to devWr:.p source i terms for a slowly evolving sequence which represents the bulk of tie core melt l frequency for Shoreham, as well as a rapidly evolving but less likely sequence, and to focus on the offsite consequences for these source terms. It is recog-nized that a complete picture of risk is not obtained by focussing on only two types of releases and their consequences. However, it is the staff's view that consideration of the offsite consequences for these sequences provides a perspective on the effect of the power reduction for the range if accidents that can reasonably be expected at Shoreham.

A set of calculations were performed for each source term by the staft's con-tractor, INEL, to address the effect of reduced seurce terms and delayed times of release on offsite consequences. The calculations involved modifying ths CRAC2 input, and recomputing the dose-versus-distance probability distributions.

The CRAC2 isotope subgroup data were modified by increasing the multiplier for the activities by a factor of four, representing an increase in power from 25 percent to 100 percent. The source term input was modified to include revised time of release, duration of release, and release fractions for both  !

25 percent and 100 percent power cases. The release fractions were further modified by assuming containment / reactor building 0Fs. One case assum1d that the DF was one, or no decontamination, while the other case assumed the con-tainment/ reactor building was effective in reducing the source term, except the noble gases, by a factor of five. Key input assumptions in the CRAC2 analyses were that the population: (1) does not evacuate until 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after the release, and (2) continues normal acti'ities until evacuation (i.e., shielding factors of 0.75 and 0.33 were used for cloudshine and groundshine, respectively).

To provide some perspective as to the additional time for protective actions afforded by operation at 25 percent power, dose-versus-time figures were also generated, Although time dependent output is not available with CRAC2, several CRAC2 calculations were linked together to illustrate the influence of ti s 35

upon the probability of a dose being exceeded. The CRAC2 evacuation input was modified to freezr. the v .-;e calculations at specific times after the release.

Tl' CRAC2 calculations were performed by instantaneo'isly evacuating all the m around the plant at specific times after the release of the radioactive 3y performir.g several different evacuation time calculations, a dose-

< .ime curve was obtained. It was verified that the time-dependent results d correctly satisfied the limiting cases at 0 and 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Instantaneous ation at 0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> resulted in no dose to the public, whereas, instantaneous evacuation at 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> produced the base case probability distributions.

4.2.2.1 Slowly Evolving Sequences The Class I plant damage state accounts for approximately 80 percent of the total core melt frequency in the Shoreham 25 percent power PRA. Accidents in this c13ss can be characterized as transients with reactor scram, coupled with a loss of reactor coolant injection. Such sequences may progress either at high reactor vessel pressure (e.g. , failure of high pressure injection and depressurization systems) or at low pressure (e.g, failure of both high and low pressure systems). In either case, mass and energy releases occur over an extended period as the reactor coolant is boiled off due to decay heat. As evidenceu by the calculations presented in Table 6, the timing of major events in the core melt progression, up to core slump, art not significantly different for high pressure and low pressure sequences.

Source terms were developed by the staf f to represent releases which might occur for typical Class I BWR transients at 25 percent and 100 percant power.

Core melt progrossion and reactur vessel failure timos for such transients would be similar to these for the loss of injection and station blackout sequences described in Section 3.1. For thes sequences at 25 percent power, reactor vessel failure is assumed to occur cc'.c Hent with slumping of the first racial zone of the core; thi: is estimated to occur at 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> based on the results presented in Table 6. For full power, the time of vessel failure was estimated to be 3.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. This is about midway between the times of core slump and bottom head failure reported in Table 6. The containment building is initially intact, but is pcstulated to fail at some time subsequent to reactor vessel failure as a result of ensuing core concrete interactions.

36

  • l Two source terms were used to address different modes of releases froc the l containment. The first source term, Table 14, is based on releases occurring as a result of deliberate venting of the containment wetwell at 75 psia, in accordance with the Shoreham Emergency Operating Procedures. The second source term, Table 15, is based on releases occurring as a result of containment ,

overpressure failure in the drywell at 135 psia. Each of these source terms I is discussed below.

The rate of containment pressurization for a Class I transient in Shoreham and, hence, the time of containment venting or containment overpressure failure is strongly dependent on assumptions regarding the transport of core debris to the suppression pool following reactor vessel failure. If, as assumed in the utility analysis, essentially all of the debris rapidly enters the suppression pool with minimal interaction with the concrete diaphragm floor, then the containment venting pressure would not be reached for tens of hours following vessel breach if at all. On the other hand, if a large fraction of the core debris remains on the drywell floor long enough to interact with the concrete, then the products of the core concrete interaction (heat and non-condensible gases) could result in containment pressurization suf#4cient to necessitate venting or to fail the containment within several hot. s following vessel breach.

The staff estimates that at 25 percent power, core concrete interactions in which the full core participates could result in the containment venting pres-sure of 75 psia being reached within three hours following vessel failure. At 100 percent power, this pressurization time would be reduced by approximately i half, due to the higher decay heat levels at 100 percent power, and correspond-ingly thorter times required to heat the ex-vessel debris bed to the tempera-tures at which unoxidized constituents in the debris (e.g. , Zircaloy) would begin to react. On the basis of these conservative assumptions regarding reactor vessel failure times and containment performance, the time to release for the wetwell venting case was set to 14 hour1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br />,s and five hours for 25 percent and 100 percent power operation respectively in the staff's consequence calcu-lations. A duration of releas9 of two hours was used as it represents the time required to depressurize the containment with the available vent area.

If the operators do not vent the containment, pressurization will continue until the containment failure pressure is reached. Under the previous 37

assumptions regarding core concrete interactions, containment pressure would increase from the venting pressure (75 psia) to the estimated ultimate pressure capacity of containment (135 psia) within about two hours, for both 25 percent and 100 percent power operation. Hence, in the staff's consequence calculations for the case with containment drywell failure, the time to release was set to 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> and seven hours for 25 percent and 100 percent power operation, respectively. A duration of release of two hours was used in these calculations.

4 The fission product release fractions used in the offsite consequence calcula-tions are based on Source Term Code Package (STCP) calculations performed by BCL. For the wetwell venting case, Table 14, the release fractions are based on analysis of a T8UX sequence for Peach Bottom, as documented in Reference 15.

. This sequence involves a transient initiating event, immediately followed by reactor scram and loss of all ac and de power. As a result, all injection to the reactor is lost, leading to eventual reactor vessel and containment failure.

In the BCL analysis, the containment is assumed to fail above the water level in the wetwell, at approximately six hours. Henco, releases from the drywell pass thru and are scrubbed by the suppression pool before release to the environment. This fission product transport path is the same as would result if the wetwell were deliberately vented.

For the case with drywell failure, Table 15, the release" fractions are based on analysis of a TQUV sequence for Limerick, as documented in Reference 16. This sequence involve; a transient with scram, accompanied by complete failure of low pressure and high pressure coolant makeup to the reactor. In the BCL anal-ysis, this sequence leads to containment failure in the drywell at approxi-mately seven hours.

In both of the referenced BCL calculations the suppression pool downcomers are considered to remain intact following reactor vessel failure. In contrast, the utility 25 percent power PRA assigns a 50 percent probability to the potential for downcomer melt-through and subsequent suppression pool Sypass. The staff has assessed the effect that downcomer melt-through woula have on the release fractions presented in Tables 14 and 15. The approach taken was to assume that the tellurium, strontium, ruthenium, and lanthanum calculated to be retained in the suppression pool in the BCL calculations was instead distributed among the 38

c .

O wetwell airspace, drywell, and environment in the same proportion as each fission product was calculated to be retained in these regions without down-comer failure. (Only these species were considered redistributed since they are largely released subsequent to postulated downcomer melt-through). For the wetwell venting case, downcomer melt-through results in an increase in the release fractions for these species of approximately a factor of two to three.

For the drywell failure case, melt-through would result in an increase in the release fractions on the order of 50 percent. This is considered to be within the uncertainty in estimating the fission product release fractions.

Figures 3 and 4 show the five rem and 200 rem whole-body dose-versus-distance results for the core melt scenario with wetwell venting. Similar results are shown in Figures 5 and 6 for the scenario with drywell overpressure failure.

Unlike the final results presented in the utility submittal (as well as the curves presented in NUREG-0396), the probabilities shown for each scenario are conditional upon that scenario occurring. In contrast, the LILCO leakage categories were weighted by the release category probability given a core melt and the results were summed over all release categories.

In interpreting the dose-versus-distance curves presented in this section, it should be recognized that while containment / reactor building decontamination factors of five or more may be expected for Shoreham, the effect of downcomer melt-through and other uncertainties in estimating fission product release fractions may offset this reduction. These uncertainties are applicable to full power operation as well. Since the mode of release is uncertain, i.e.,

venting versus containment overpressure, the conclusions presented below are based on the more limiting case.

Several important trends can be noted from the dose-versus-distance curves for the two scenarios. First, the offsite consequences for the drywell overpres-sure scenario are considerably more severe than the wetwell venting scenaric, even though the time to release is later in the former case. Second, reducing the reactor power from 100 percent to 25 percent represents a significant reduction in the probability of exceeding a given dose, particularly for larger doses. Third, the assumption of a containment / reactor building 0F of five also provides substantial reduction in the dose probabilities. For the 39

drywell overpressure fore-melt scenario the level of reduction is roughly comparable to that associated with restricting operation to 25 percent power; for the wetwell core-melt scenario a reduction.in power by a factor of four shows a more significant impact on the dose-versus-distance probabilities than increasing the containment / reactor building 07. This is due largely to the reduced fission product inventory combined with a delayed time of release at 25 percent power.

The dose-versus-distance curves provide insights regarding the distances from the reactor over which either the Protective Action Guides (PAGs) might be exceeded or injury-threatening doses might occur in the more likely core melt sequences. However, because of the limited nature of this assessment and the large uncertainties inherent in estimation of source terms and modelling of offsite consequences, these results should be interpreted in a qualitative manner, i.e., they should not be used to estimate reduced distances over which protective measures may need to be taken in the event of an accident. Suffice it to say that the distance over which a given dose is exceeded would be significantly reduced at 25 percent power (by a factor of about three relative to full power) but that estimation of the absolute distances at which major reductions occur in the probability of dose exceedance v.~ould require a further assessment of uncertainties.

An additional staff calculation was p.srformed to assess the sensitivity of offsite consequences to release height. The LILCO submittal dnd all sensitiv-ities to date were performed witt, a 10 m release height. A review of the Mark-II design indicated the mrre probable release height would be 50 m. To determine the effect on consequences, the late drywell overpressure transient at 100 percent power and c;ntainment OF of one was performed with the release height increased to 50 m. The results showed no noticeable change in the off-site dose probabilities with the increase in release height.

To provide some perspective as to the additional time for protective actions afforded by operation at 25 percent power, dose-versus-time probability figures were also generated. Figures 7 and 8 show the probability of five rem and 200 l rem whole-body doses being exceeded at two miles versus time for the wetwell venting scenario at 25 percent and 100 percent power. Results for the scenario 40 t

with drywell overpressure failure are shown in Figures 9 and 10. Several important trends can be observed. First, the probability of exceeding smaller doses (i.e. , five rem) two miles from the reactor approaches the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> value quite rapidly following the onset of release. Although the probabilities of exceedance of the smaller doses at 25 percent power are not significantly lower than those for 100 percent power, the time required to reach a given probabil-ity of exceedance at 25 percent power is about 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> longer than at 100 per-cent power. This represents additional time available to take protective measures at 25 percent power. The amount of time corresponds approximately to the difference between the time of release at 25 percent and 100 percent power.

The dose-versus-time results for 200 rem exposures indicate that at 23 percent power the dose accumulation rates at two miles are sufficiently small tnat the probability of exceeding a 200 rem dose is insensitive to time of exposure, and remains small even if protective measures are not taken promptly.

4.2.2.2. Rapidly Evolving Sequences A source term was developed by the staff to represent the type of release which might occur during a rapidly evolving severe accident in which the containment is initially intact but fails at the time of reactor vessel failure. The source term is considered to be a conservative representation of releases which would not likely be exceeded, but is not intended to represent the worst conceivable case. The staff source term is presented in Table 16,'along with the most severe source term considered in the utility PRA. The WASH-1400 source term for a BWR 3 release is also included for comparison. A brief discussion of the key differences between the utility and staff source terms is provided below.

The time to release is significantly shorter in the staff source term. The value of 3.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> is based on the time of core slump for the large break LOCA sequence. For the 100 percent power calculations, a time to release of 0.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> was assumed, consistent with the time to core slump predicted for a large break LOCA at 100 percent power. The ti.?e of core slump was used to characterize the time to release for two reasons. F1i:+. under the conserva-tive assumption that core debris does not quench in the reactta ves;*1 bottom 41

head, the vessel would be expected to fail at about that time, releasing core debris into the drywell and suppression pool. Containment failure coincident with vessel failure might also be conservatively postulated to occur as a result of steam explosions in the wetwell or some other mechanism. The 3.5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> time to release for 25 percent power reflects both these conservatisms.

Second, a significant amount of the noble gases and volatile fission products are released from the fuel by the time that core slump is predicted to occur.

The time to release is considered to be conservative in that two barriers to the release of fission products are postulated to fail much earlier than would be predicted by mechanistic analyses. It should be recognized, however, that if the containment is failed prior to reactor vessel failure, as it is in the seismic LOCA sequence for release Category 2, releases to the environment can occur earlier than assumed. For the large LOCA in a failed containment, releases (principally noble gases, cesium and iodine) would begin as early as about one hour at 25 percent power, and earlier at full power.

The duration of release is also significantly shorter in the staff scurce term. The value of one hour is based on the time to release a significant fraction of the non-volatilo fission products, e.g., tellurium and strontium, from the core-concrete interactions in the drywell. This value is consistent with the results of the CORCON/VANESA calculations described in Section 4.1.2.1 for Case 4, i.e., a high core debris tenperature. The value is believed to be conservative as somewhat lower initial core debris temperatures would actually be expected. Lower debris temperatures would result in a delay in the onset of vigorous core-concrete interactions and a more gradual release of non-volatiles, e.g., over a period of five to 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />.

The staff estimates of cesium and iodine release fractions are a factor of five higher than the utility source term. LILCO, however, assumes a secondary containment building decontamination factor (DF) of 10 for this case. If, for the reasons described in Section 4.1.2.2, less credit is taken for the second-ary building, such as a OF of two, the staff and utility estimates are equivalent.

The staff estimates of release fractions for non-volatiles, particularly tellurium and strontium, are significantly higher than the utility values.

42

The staff values are based on the CORCON/VANESA analyses described in Section 4.1.2.1, which indicate significant potential for concrete attack. The utility values are based on analyses which indicate only minimal core-concrete inter-actions occur.

Based on the staff-developed source tt;iw , offsite consequence calculations l were performed for operation at 25 percent and 100 percent power using the l CRAC2 code. Table 17 lists the release fractions used in these calculations.

Figures 11 and 12 show the five and 200 rem dose-versus-distance results for  !

the various cases. As expected, the staff's dose-versus-d? stance probabil-ities were higher than those reported by LILCO. Also, the same general trends j described in the previous section for slowly evolving transients can be observed  !

l here, specifically, that reducing the reactor power from 100 percent to 25 per-  !

cent represents a significant reduction in the probability of exceeding a given dose, or conversely, a significant reduction in the distance over which a given dose would be exceeded.

To provide some perspective as to the additional time for protective actions afforded by operation at 25 percent power, a set of dose-versus-time release conditional probability figures were generated following the procedure described in Section 4.2.2. Figures 13 and 14 show the probability of five and 200 rem whole-body doses being exceeded at two miles versus time for 25 percent and 100 percent power. The probability of exceeding the

five rem dose two miles from the reactor approaches the 24-hour value quite rapidly for both 25 percent and 100 percent power, and the difference in the l time required to reach a given probability of exceedance is comparable to the differences in the time to release for the 25 percent and 100 percent ,

power cases. For the 200 rem doses, the results for full power indicate  !

that following the time of release (0.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />) the probability of exceedance at two miles rapidly approaches its 24-hour value. For 25 percent power, CRAC2 indicates a much lower dose accumulation rate; specifically, 200 rem doses are not exceeded until about three hours after the time of release (3.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />) or six hours af ter transient initiation. Since there is a signi-ficantly shorter time to release for 100 percent power and a high probability that a 200 rem whole-body dose will be exceeded very shortly af ter the  ;

release, less dose savings could be realized for 100 percent power operation.

43 1

---.__,,m,, _____,__.y_ _ _ _ _ _ _ _ _ _ . . _ . . - _ _ , _ _ . . _ . _ . . - _ _ . - _ - - - . ~ . , . - _ . . _ _ _ _ . . . . . _ . ~ , _ _ - , _

5

SUMMARY

AND CONCLUSIONS l The staff has completed an expedited review of the PRA-based portion of the LILC0 request. This review was oriented towards assessing the validity of the major technical arguments upon which the utility submittal is based. These arguments can be summarized as follows:

1. Reduced vulnerability to Core Damage Accidents With operation at 25 percent power, decay heat levels are reduced to the extent that (1) certain plant features, such as turbine bypass flow, are capable of mitigating accidents prior to core melt and (2) accidents will evolve more slowly allowing considerably greater time for recovery actions.

These factors, in co7 junction with a number of plant upgrades which have or will be implemented, will result in a reduced vulnerability to severe core melt accidents at Shoreham.

2. Increased Time for Emergency Response -

For accidents which are not arrested prior to severe core melt, reduced decay heat levels derived from operating at 25 percent power will result in a significant delay in both core melt progression'and onset of releases from containment. This delay represents an increase in the time available for emergency response.

3. Reduced Offsite Consequences The magnitude of source term releases for accidants initiated from 25 percent power are less than predicted for similar accidents initiated at 100 percent power due to a proportionally smaller Initial fission product inventory at the lower power level. The reduced source terms, in conjunction with the delayed times of release mentioned above, trans-late into reduced offsite consequences.

On the basis of the staff's review of the utility submittal and supporting documentation we have reached the following conclusiens:

44

e - .

1. The 25 percent power restriction, in conjunction with the improvements in the plant design and operating procedures, effectively reduces the signifi-cance of several specific plant vulnerabilities to core melt. However, the overall core melt frequency is not significantly reduced because of the nurrerous sequences that are unaffected. Moreover, the seismic-induced contribution to core melt frequency has large uncertainties, and can contribute about one fifth of the internally initiated core melt frequency estimate for both full power and restricted power operation. Such con-sideration will make the difference between the estimates of core melt frequencies at 25 percent and full power even less significant.
2. The utility claim that operation at 25 percent power results in a significant increase in the time available for accident mitigation and emergency response is valid. Calculations performed by the staff for selected risk-important sequences confirm the estimates of timing provided by the utility for key events. These calculations indicate that the timing of key events in the core melt progression (e.g., start of core melt, core slump) are significantly delayed at 25 percent power. This delay is on the ordor of a factor of four. For the most rapidly evolving sequences, significant core damage will not occur until after one hour for operation at 25 percent power versus 10 minutes for operation at 100 percent power. For the most likely sequences, the time of significant core damage will be delayed from about two to three hours for 100 percent power to 10 or more hours at 25 percent power.

Furthermore, the time of release to the environment is significantly delayed at 25 percent power. Under conservative assumptions regarding reactor vessel failure times and containment performance, the bulk of the releases at full power (approximately 80 percent) occur between two and six hours following accident initiation. For the same assump-tions at 25 percent power, the majority of releases (approximately 80 percent) are delayed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or more.

Finally, as discussed below, reductions in dose accumulation rates at 25 percent power af ford additional time to take protective measures.

45 '

o . .

3. The utility claim that offsite consequences are reduced by operation at 25 percent power is valid. The staff has confirmed that the power reduction translates approximately into a factor of four reduction in initial fission product inventory, and that the time to release will be significantly delayed at the lower power level, again by approximately a factor of four. These two direct benefits of the power restriction, in conjunction, translate into significant dose savings for all sequences.

Recognizing that an assessment of the remaining uncertainties in source terms as well as relative frequencies for the various release categories was not practicable, the effect of the power restriction on offsite consequences was determined by considering the offsite consequences for two different accident sequences selected to characterize the range of core melt progression timing which could be expected at Shoreham. This involved the specification of source terms for 25 percent and 100 percent power (i.e., fission product inventory and release fractions in conjunc-tion with release time and duration) and a comparison of offsite conse-quences for each case.

On the basis of staff calculations, restricting operation to 25 percent of rated power reduces the distances over which injury-threatening deses (i.e., 200 rem) would occur. CRAC2 calculations indicate that distances are reduced by approximately a factor of three relative to full power operation, however, the' absolute distances at which major reductions occur in the probability of exceeding a particular dose are dependent on modelling and input assumptions and are an area of remaining uncertainty.

The probability of exceeding a five rem whole-body is also reduced by operating at 25 percent power, but significant reductions do not generally occur within the 10 mile EPZ.

CRAC2 calculations indicate that dose accumulation rates alone may yield significant additional time to avoid injury threatening doses at 25 per-cent power (in addition to the delay in time of release afforded by the power restriction). Dose-versus-time calculations performed for a rapidly evolving sequence using CRAC2 show that at 25 percent power a 200-rem whole-body dose could be averted at a two mile radius by evacuating within 46

three hours following start of the release (or within six hours after accident initiation).

6 REFERENCES

1. "Request for Authorization to Increase Power to 25% and Motion for Expedited Commission Consideration," Long Island Lighting Company, Docket No. 50-322, April 14, 1987.
2. Probabilistic Risk Assessment of the Shoreham Huclear Power Station, Docket 50-322, Long Island Lighting Company, June 1983.
3. NUREG/CR-4050, "A Review of the Shoreham Nuclear Power Station Probabi--

listic Risk Assessment", Brookhaven National Laboratory, November 1985.

4. Letter from R.T. Lahey, Rensselaer Polytechnic Institute, to C.N. Kelber, USNRC, May 6, 1987.
5. NUREG/CR-3764, "BWR-LTAS: A Boiling Water Reactor Long-Term Accident Simulation Code", February 1985.
6. Hyman, C.R. , and Ott, L.J. , "Effects c' Improved Modelling on Best-Estimate BWR Severe Accident Analysis", Proceedings of the USNRC 12th Water Reactor Safety Research Information Meeting, October 22-26, 1984, NUREG/CP-00S8, Vol. 3, January 1985.
7. Cronenborg, A.W., et al., "Assessment of Damage Potential to the THI-2 Lower Head Due to Thermal Attack by Core Debris", EGG-TMI-7222, June 198d.
8. NUREG-1150, "Reactor Risk Reference Document," February 1987.
9. SAIC Corp. , "Containment and Phenomenological Event Tree Evaluation at 25% Power Level for the Shoreham Emergency Planning Study, SAIC-87/1563, March 1987.

47

10. "LILCo's Brief on the "Substantive Relevance" of Remaining Emergency Planning Contentions to LILCo's Motion to Operate at 25% Power," Long Island Lighting Company, Docket No. 50-322, April 1, 1988.
11. NUS Corp. "Major Common-Cause Initiating Events Contribution to Shoreham Nuclear Power Station Source Term, Mature Plant Operation at 100% Power",

NUS-4841, January 1986.  !

12. Gieseke, J.A., et al., "Radionuclide Release Under Specific LWR Accident Conditions," Battelle Columbus Division, BMI-2104, Volume 2, July 1984,
13. NUREG-0396, "Planning Basis for the Development of State and Local

, Govern.ient Radiological Emergency Response Plans in Support of Light Water Reactor Nuclear Power Plants", December 1978,

14. Pickard, Lowe and Garrick, Inc. , "Core Melt Accident Oose-Versus-Distance Probability Distributions 25% Power Operation, Shoreham Nuclear Power Station", PLG-0542, March 1987.
15. NUREG/CR-5062," Supplemental Radionuclide Release Calculations for Selected Severe Accident Scenarios," Final Draft Report, Battelle Columbus Division, February 1988.
16. Gieseke, J.A., et al., "Radionuclide Release Under Specific LWR Accident -

Conditions," Battelle Columbus Division, BMI-2104, Volume 8. July 1986.

Principal Contributor: R. Palla r

, i r

i 48

Table 1 Reported core melt frequency results Initiator Full Power 25% of Full Power Frequency Percentage Frequency Percentage Internal Events 5.5 x 10 5 85 2.5 x 10 5 89 External Events Fire 7.3 x 10.s 11 4.6 x 10 7 1. 6 Seismic 2.5 x 10 8 4 2.7 x 10 8 9.6 Total 6.5 x 10.s 2.8 x 10.s 1

49

Table 2 Reiscs2 charactcristics fer Shoreham relOss2 cctegorics (2S% power)1 -

Release Categories Qualitative attributes Reprt sentative sequence Release sequence characteristics RCl No pool scrubbing ATWS Class IV plant damage state Early, short duration and high Large leakage size with with overpressere failure in the energy release. Noble gases and a driving force drywell or wetwell with downconer few percent of particulates are Low reactor building failure, bypassing the pool with released.

1 retention minimum reactor building reten-Short duration, early tion. Suppression pool is release saturated providing sustained gas flow rates.

) RC2 No poon scrubbing Seismic RPV breach Class IIID Early, moderate duration and low large leakage size but plant damage state with drywell energy release. Noble gases and without driving force failure bypassing the pool. tenths of a percent of particulates Low reactor building Other sequences include inter- are released.

retention facing LOCAs Class V Plant Damage Moderate duration, early State, ATWS Class IV with small

<n release containment leakage failures c'

bypassing the pool (e.g. - -ell with downconers failure)

RC3 Pool scrubbing ATWS Class IV plant damage state Early, short duration and high Large leakage size with failure in the wetwell and energy release. Noble gases and Low reactor building downconer vents intact. The a few hundredths of a percent retention Short duration, release pathway involves pool of particulates are released.

early release scrubbing.

RC4 No pool scrubbing Station Blackout plant damage Relatively early, long duration

, Small leakage size state Class IB. Slow developing release. Noble gases are slowly or accident where the releases released, and less than 10 3 Large leakage size without bypass the suppression pool, particulate fractions are i driving force but reactor building hold up released.

( Reactor building retention is significant.

Long duration with containment attenuation, early release j

I

Tabla 2 Reicise charactcristics fcr Shorchas rala se cctegorics (25% power) (Continued)1

  • Release .

Categories Qualitative attributes Representative sequence Release sequence characteristics RCS Late release with and Loss of coolant makeup Class IA Very slow developing with long without pool scrubbing plant damage state. Late con- times to release. Noble gases tainment failure due .o operator and less than 10 5 particulate venting af ter 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. Fission fractions are released.

product releases are therefore significantly reduced.

RC6 Design leakage (contained Loss of coolant makeup Class IA Contained released where design rr'. ease) Recovered ccre plant dae32e state. The con- leakage determines fission telt states tainment is not breached or the products released to the core melt sequence is recovered. environment.

8Taken from e3ference 1. Release characteristics presented are those reported by the utility.

. .c ,

Table 3 Release categories and their contribution to core melt and early releasest Timing for representative sequence (hours after scram)

Re'iease Risk dominant  % contribution Release to category contributors to core melt 2 Core slump 3 environment 4 1 ATWS with pool 2.3 10.4 10 bypass 2 Seismic LOCA 2.0 4.6 5 (Failed Containment) 3 ATWS with no pool 8.2 6.8 7 bypass 4 Station blackout 13.9 13.9 15 5 Large LOCA 47.9 4.3 48 (Intact Containment) 6 Transient with Loss 25.7 11.3 15 of Injection IValues presented are those reported by the utility.

2 Total core melt frequency is 2.8 E-5/ Reactor-Year.

31n the analyses performed using MAAP, vessel failure occurs within minutes following core slump.

4 Values presented are those used in the utility offsite consequence calculations.

52

.'l Table 4 Comparison of utility and staff estimates of core melt progression for 25% power '.

Time of Event (Hours after scram)

ATWS1 Large Break LOCAZ Station Blackout 3 Loss of Injection

  • Event Utility Staff Utility Staff . Utility Staff Utility Staff
1. 7 1.7 .007 .001 4.1. 1. 5 2.7 2.3 Uncover top of active fuel 4.1 4.9 .6 1.0 7.5 7.2 5.8 6.6 Begin cladding relocation 10.4 9.4 4.6 3.3 13.9 12.3 11.3 10.7 Slump first radial zone of core 10.4 30.8 4.6 7.8 13.9 49.2 11.3 24.6 Fail bottom bead 5

[12.4]

3 Sequence as defined for Release Category 1.

2 Sequence as defined for Release Category 5, except ficw from CRD hydraulic system not modelled.

3 Sequence as defined for Release Category 4.

$ 4 Sequence as defined for Release Category 6.

S Utility analyses assume debris does not quench in bottom head; staff analyses assume debris quenchs and reheats prior to failing bottom head. Number in brackets is MARCH 3 result obtained assuming no debris quench.

l

.y. o .-ym.. - - - - - --e, -

-m -

em - m, - - . __

Table 5 Effect of power restriction on core melt progression for less probable sequences Time of Event (Hours After Initiation)

Large break LOCA ATWS Large break LOCA1 E3%* 100%3 25% 100% Event

1. 7 .7 .001 .001 Uncover top of active fuel 4.9 1.1 LO .2 Begin cladding relocation 9.4 1.7 3.3 .7 Slump first radial zone of core 22.3 1.9 3.7 1. 0 Dry out bottom head 28.7 1.8 5.8 1. 0 Slump remainder of core 30.8 2.4 7.8 1. 2 Fail bottom head 2 Based on ORNL calculations for Shoreham using the BWRSAR code.

2 Based on BCL calculations for Limerick using the MARCH 2 code.

54

e

o. .

O Table 6 Effect of power restriction on core melt progression for more probable sequences '

Time of Event (Hours After Scram)

Station Blackout with SORV Loss of injection 3 I F- 100%z -25% 100% Event

1. 5 1.0 2. 3 .4 Uncover top of active fuel 7.2 2.2 6.6 1.1 Begin cladding relocation 12.3 2.7 8.1 1.2 Uncover core plate 12.3 2.7 10.7 1. 8 Slump first radial zone of core 27.6 3.0 19.7 3.9 Dry out bottom head 7

49.2 4.0 24.6 4.5 Fail bottom head 2 Based on BCL calculations for Shoreham using the MARCH 3 code.

2 Based on BCL calculations for Limerick using the MARCH 2 code.

3 Based on ORNL claculations for Shoreham using the BWRSAR code.

F l

i t

i h I i

i r i

I l

i

! l 55  !

1

._~ _ _ _ - . . _ . . - _ _ . _ _ . , . - _ _ . _ _ . ._

_ _ _ _ _ . _ _ _ . _ m.

.]

Table 7 Summary of the core-vulnerable accident plant damage states at 7.5% power .

Plant Frequency Damage per reactor States Definition Example year CLASS IA Accident sequences involving loss of inventory makeup TQUX 1.5E-5 where the reactor pressure remains high.

B Accident sequences involving a loss of offsite T EQUV 2.3E-6 power and loss of coolant inventory makeup.

1 l C Accident sequences involving a loss of coolant T""2 C C 0'U' 6.6E-10 l inventory induced by an ATWS situation.

D Accident sequences involving a loss of coolant inventory TQUV 4.6E-6 l makeup where reactor pressure has been reduced to 200 psi.

l CLASS II Transient accident sequences involving a loss of TW 1.5E-9 l containment heat removal.

l CLASS IIIA Accident sequences leading to core vulnerable conditions initiated R g by vessel rupture. (Containment integrity is not breached by the initiating event.)

8 Accident sequences initiated by or resulting in small LOCAs S iQUX 2.4E-8 for which the reactor cannot be depressurized.

C Accident sequences initiated by or resulting in medium or large AQUV 7.0E-7 LOCAs for which the reactor is at low prassure.

O Accident sequences which are initiated by a LOCA or RPV failure AD 1.1E-7 and for which the vapor suppression system is inadequate, challenging the containment integr!ty.

l CLASS IV Accident sequences involving failure to insert negative reactivity TCC

  • "2 3.9E-6 l 1eading to a containment vulnerable condition due to high l containment pressure.

1 l

CLASS V LOCAs outside containment Interfacing LOCA 1.2E-6 SRPV* Seismically-induced reactor pressure failure and subsequent Seismic AD 8.0E-7 containment failure.

  • SRPV represents a seismically-induced reactor pressure vessel breach with subsequent loss of containment integrity. This sequence was combined with plant damage state Class IIID since the core melt progression is similar to the internally-initiated large LOCA sequences with an initially failed containment prior to core melt.

Table 8 Shoreham Nuclear Power Station -- 25% power Plant damage state release category distribution (percent of core melt)* .

Release Plant Damage State Category IA IB IC 10 11 IIIS IIIC 1110 IV V RC1 1.9E-02 1.9E-02 5.0E-06 2.4E-05 1.8E-07 3.1E-05 3.7E-06 8.1E-03 2.3E+00 4.3E-04 (7.0) (7.0) (7.0) (7.0) (7.0) (7.0) (7.0) (0.5) (7.0) (1.0)

RC2 5.3E-02 8.2E-01 1.4E-05 7.3E-03 1.0E-07 8.4E-05 1.1E-03 3.7E-02 1.0E+00 3.4E-02 (7.0) (7.0) (7.0) (7.0) (7.0) (7.0) (7.0) (0.5) (7.0) (1.0)

RC3 2.8E-01 3.8E-02 7.2E-05 3.5E-04 8.2E-07 4.4E-04 5.3E-05 2.8E-02 7.9E+00 (7.0) ( t.9) (7.0) (7.0) (7.0) (7.0) (7.0) (0.5) (7.0)

RC4 2.4E-01 7.3E+00 6.3E-05 6.6E-02 4.7E-07 3.9E-04 1.0E-02 3.2E+00 3.0E+00 9.2E-03 (11.0) (14.0) (11.0) (11.0) (11.0) (11.0) (11.0) (1.0) (11.0) (1.0)

RCS 3.1E+01 2.0E-04 1.5E+01 7.8E-03 2.3E+00 (48.0) (48.0) (48.0) (48.0) (48.0)

O RC6 2.4E+01 2.0E-03 1.8E+00 7.9E-02 2.8E-01 (60.0) (60.0) (60.0) (60.0) (60.9)

TOTAL 5.5E+01 8.2E+00 2.4E-03 1.7E+01 1.6E-06 8.7E-02 2.5E+00 3.3E+00 1.4E+01 4.4E-02 NOTES.! The bracketed numbers below each value of percent of core melt represent the time (hrs) from the initiating event to the release of radiation to the environment for the representative severe accident sequence of that group.

, The summation of the percent contributions of each group total slightly higher than 100% because of round-off.

  • Taken from Reference 10. Values presented are those reported by the utility.

- , . , - . - - eywv, w,. -win mw +-w w-w- w --_ - - - - - . - _ - - - -

e - J, Table 9 Time of release to environment for Shoreham accident classes ,

Fraction of total core Time of release to Plant Damage melt frequency environment (h)

States Definition 25% power' 100K power2 255 power 100K power CLASS I Transients with SCRAM, loss of coolant .80 .52 14. 5.

makeup, core vulnerability prior.to containment challenge CLASS II Transients with SCRAM, inadequate <.001 .24 >24. >24.

containment heat removal, containment vulnerability before core melt CLASS III LOCAs with inadequate core cooling, .03 .02 6. 2.2 core vulnerability prior to containment challenge CLASS IV Transients with failure to SCRAM, .14 .21 7. 2.5

, inadequate containment heat rencval.

  • contatoment vulnerability before core melt CLASS V LOCAs with containment bypass prior to <.001 <.001 1. .2 core melt SRPV Seismically-induced reactor pressure .03 .01 1. . .2 vessel failure with subsequent containment failure 2 Total core melt frequency for 25*. power operation is 2.8E-5/ Reactor-Year.

2 Total core melt frequency for 1001 power operation is 6.SE-5/ Reactor-Year.

y ,__ , , , - , , - - ,-- -ry - 3 - , , . - ,

- , - - - - _. . , . . - _ ~ _ _

e- .. .

Table 10 Compacison of utility and staff estimates of time of releate for a spectrum of accidents Time of Release - t Utility Staff (h) 25% Power 25% Power 100% Power 01 t <2 .03 .03 .01 2 < t <6

- 0. O. .75 6 1 t <12 .16 .17 0, 12 s t .81 .80 .24 l

l l

1

(

59

i Table 11 Radioisotope inventories for 2 and 6 years of operation at 25% power (10s curies) 2 year: 1 6 years:

KR-85 .1473 .3380 KR-85M 5.255 4.264 KR-87 10.31 8.122 KR-88 14.57 11.45 RR-86 .0063 .01609 .

SR-89 19.37 15.13 [

SR-90 1.161 2.853 SR-91 23.99 19.37 I J t Y-90 1.173 2.883 Y-91 24.26 19.57 ZR-95 29.93 27.36 i 1

i ZR-97 28.84 27.57  !

N8-95 30.01 27.43

, M0-99 30.56 30.30 i TC-99M 26.75 26.53  !

c i RU-103 21.92 26.04 (

RU-105 12.59 17.71 I RU-106 5.069 11.38 l RH-105 12.38 17.41 j TE-127 1.520 1.828 -

TE-127M .1966 .2492 TE-129 4.784 5.385 j TE-129M .7094 .8072 TE-131N 2.259 2.459 2

! TE-132 23.15 23.55 i 58-127 1.533 1.839 l 58-129 4.867 5.473

'-131 13.13 16.68 l I-132 23.44 23.94 l I-133 34.23 33.67 1

l i

i 60

Table 11 Radioisotope inventories (Continued) 2 yearsi 6 years 2 I-134 37.78 36.73 I'135 31,61 31.38 XE-133 34.28 33.78 XE-135 19.74 19.93 CS-134 .4379 2.437 CS-136 .3755 .8608 CS-137 1.403 4.014 BH-140 30.11 28,77 LH-140 30.30 29.22 CE-141 28.67 27.43 i CE-143 27.41 25.23 CE-144 21.03 21.83 PR-143 27.37 25.20 NO-147 11.29 10.90 NP-239 399.6 396.0 PU-238 .003064 .05208 PU-239 .01631 .02729 PU-240 .00742 .02835 l PU-241 .9045 6.406 AM-241 .0007529 .01737 CM-242 .03965 1.616 i CM-244 -

.01099 I

  • Based on 2 years of operation at 254 power. I 28ased on 6 years of operation at 25% power without refueling. [

l t

I h 61

Table 12 Comparison of radioisotope inventories (108 curies)

Shoreham 8CL ORIGEN2 BCL ORIGEN2 25% power 1 25% powers Full power 3 CO-58 .1484 CO-60 .0552 l

KR-85 .1066 .1473 .5232 KR-85M 4.565 5.255 20.06 KR-87 8.942 10.31 38.78 KR-88 12.94 14.57 54.69 RB-86 .0049 .0063 .07791 SR-89 17.88 19.37 72.93 L SR-90 .7040 1.161 4.115 SR-91 20.93 23.99 91.40 .

Y-90 .7420 1.173 4.261 Y-91 22.83 24.26 91.63 ZR-95 28.52 29.93 118.8 ZR-97 2C 52 28.84 121.8 c N8-95 28.52 30.01 113.8 -

MO-99 30.45 30.56 132.0 ,

TC-99M 26.62 26.75 115.6 RU-103 "0.93 21.92 103.3 RU-105 13.70 12.59 67.75 RU-106 4.755 5.069 25.33 RH-105 9.322 12.38 63.50 TE-127 1.122 1.520 7.012 TE-127H .2093 .1966 .8283 l TE-129 5.898 4.784 21.83 TE-129M 1.008 .7094 3.237 i TE-131M 2.473 2.259 10.18 I TE-132 22.83 23.15 100.8 l 58-127 1.160 1.538 7.196 58 129 6.278 4.867 22.20 I-131 16.17 16.13 70.51 l f

62 r

. t Table 12 Comparison of radioisotope inventories (Continued)

Shoreham BCL ORIGEN2 BCL ORIGEN2 25% power 1 25% power Full powers I-132 22.83 23.44 102.4 I-133 32.35 34.23 146.2 I-134 36.15 37.78 160.7 I-135 28.52 31.61 136.4 '

XE-133 32.35 34.28 143.9 XE-135 6.468 19.74 39.76 CS-134 1.427 .4379 5.481 CS-136 .5708 .3755 2.413 CS-137 .8943 1.403 5.531 BA-140 30.45 30.11 127.2 '

f LA-140 30.45 30.30 131.2 CE-141 28.52 28.67 120.9 CE-143 24.73 27.41 112.8 -

CE-144 16.17 21.03 70.05 PR-143 24.73 27.37 110.2 NO-147 23.96 11.29 47.T' NP-239 312.0 399.6 1,471. ,

l PU-238 .001084 .003064 .0717 PU-239 .003995 .01631 .02556

PU-240 .003995 .00742 .02970 i

PU-241 .6468 .9045 6.534

AM-241 .000324 .0007529 I CM 242 .09512 .03965 CH-244 .004375 -

]

l 1LILCo May 8, 1987 Letter, Table 4C-1 values Divided by four. i 2 Based on 2 year operation at 25% power.

l 3End of equilibrium cycle with peak burnup of 27,000 MWD /MT.  ;

i 63

Table 13 Ex-vessel fission product releases (expressed as fractions of that available at start of concrete attack)

Shoreham 25% Power Case 4 Case 1 Case 2 Case 3 25% core, Limerick Species Full core Oxides only 50% oxides 4130' F TQUV Tf4 Iodine 1. 0 1. 0 .98 .91 1. 0 1.0 Cesium 1.0 .42 .45 .79 1.0 1.0 Tellurium .33 1. 0 .90 .15 .35 .35 Strontium .63 .C4 .01 .15 .49 .48 Ruthenium 2E-7 SE-6 3E-8 1E-7 1E-6 1E-6 Lanthanum .01 6E-4 4E-5 .002 .' .044 C6 tium .036 .001 1E-5 .007 Barium .43 .023 .01 .C79 64 w.

Table 14 Approximate source terms for a BWR transient with wetwell venting 0F = 1* OF = 5 25% 100% 25% 100%

Parameter Power Power Power Power

. .c_

Time to release (h) 14. 5. 14, 5.

Duration of release (h) 2. 2. 2. 2.

Release fractions Noble Gases 1. 1. 1. 1.

Cesium .005 .005 .001 .001 Iodine .005 .005 .001 .001 Tellurium .02 .02 .004 .004 Strontium .006 .006 .001 .001 Ruthenium SE-7 SE-7 ,IE-7 1E-7 Lanthanum SE-4 SE-4 IE-4 IE-4 n l Release fractions based on STCP analysis of Peach Bottom TBUX sequence (NUREG/CR-5062). Cesium and Iodine release fractions increased to .005 to ,

reflect uncertainties.

Table 15 Approximate source terms for a BWR transient with late overpressure in drywell 0F = la OF = 5 25% 100% 25% 100%

Parameter Power Power Power Power Time to release (h) 16, 7. 16, 7.

Duration of release (h) 2. 2. 2. 2.

] Release fractions I Noble Gases 1. 1. 1. 1.

! Cesium .005 .005 .001 .001 Iodine .005 .005 .001 .001  ;

Tellurium

.02 .02 .004 .004 Strontium .05 .05 .01 .01 Ruthenium 6E-8 6E-8 1E-8 1E-8 Lanthanum .004 .004 8E-4 8E-4 x

)' Release fractions based on STCP analysis of Limerick TQUV sequence (BMI-2104, Vol. 8). Cesium and Iodine release fractions increased to .005 to reflect

! uncertainties.

l 65 l

Table 16 Comparison of utility and staff source term for early release at 25% power Utility 1 Staff 2 Wash-1400 (BWR 3)

Time to release (h) 10 3.5 Ouration of release (h) 5 1.

Release fractions Noble Gases 1. L 1.

Cesium .016 .1 .1 Iodine .02 .1 .1 Tellurium 1E-5 .1 .3

~

Strontium 3E-4 .1 .01 Ruthenium 8E-5 0. .02 Lantha.~,um O. .003 .004 a

j Values shown are for Release Category 1 - ATWS with suppression pool bypass and wetwell venting.

2 Includes the following conservatisms:

Release initiated at core slump rather than vessel failure Full core. assumed to participate in concrete attack Minimal fission product retention in containment and reactor building I -

t l

I I

66 1

O oo .

e Table 17 Approximate source terms for a BWR sequence with early release OF = 1.0 0F = 5.0 25% 100% 25% 100% '

Parameter Power Power Power Power Time to release (h) 3.5 0.8 3.5 0.6 '

Duration of release (h) 1. 1. 1. 1.

Release fractions Noble Gases 1. 1, 1. 1.

i Cesium 0.1 0.1 0.02 0.02 Iodine 0.1 0.1 0.02 0.02 Tellurium 0.1 0.1 0.02 0.02 Strontium 0.1 0.1 0.02 0.02 Ruthenium 0.0 0.0 0.0 0.0

Lanthanum 0.003 0.03 0.0006 0.006 3All other parameta-* identicafTE the PLG-0542 CRAC2 calculations.

I

, l I

l i

i l t t t

t l

! l l t 67  :

i 4

. . . _ . _ _ _ _ _ ___-_ . _. _ . _ . . _ . - _ _ . _ - _ _ _ - _ _ _ _ _ . . ~ _ _ . _ . .

_s newan- i 1

i .

_. , 1 t 1 1 j, i I ,,, ,

l- -

i

(. - .

- = ' i i i st i i i i

.l N%bliMA,WULj ff

\

' .. . = * .

m. m

=s m

'irn (a) (b)

, u -

, u -

g u a

= '

. pu ,

I _..

I_ .e u . , <

l " '

hv l l u ,

o .

a

___a i _ fl ,

4 4 <<<d 44d4 W gj . . . . . . .

., j . . . .

(c) (d) 1 , A,,, g E . .

.- . g o , - ---

' ,,h

a. .

..lg o

j o ,g - - - - '

.g (e) (f)

Figure 1 Accident signatures for the MSIV-closure ATVS from 100%

power operation. first 45 minutu sith no operatet action 68

. e . _= -

e i

  • M MM NN\ . ..

g . . . , = =

1- .

l~ Lm- - - .

..I, WilillllWillli  ;

.g

. n MWMM ..

,j

., j . . .

(a) (b)

. u ,

, u ,

I,_ . .

I_ . .

n l -

lm_ .

j- l .. .,

I 3 1

3

]

. . ,j

. . . ' .- I gj . ' . (lLL .

(c) (d)

6. P s

{ * '. - -

._ -3 g - _;

I. e .

f.

.e

s. o . , *,,.', .

[o ,

o i.. ,

,. ' s* , ..

"4 . . . .

me m

. (e) (f)

Figure 2 Accident signatures for the HSIV-closure ATVS from 25%

power operation,-first 45 minutes without operator action -

69

I I

Probobility conditional on NRC '

we t we ll venting core melt scenario, 10' = , ......i . . . .....i ........ . .i... . . ...i.

=

.=

1/4 POWER CF=1.0

. + 1/ 4 30WER. CF =5.0 .

j

" - rett :0WER, OF=1.0 18 4=.:e. ,_ _ _ ,,,

x cu tt power.cr-s.o 1 v E N ,' . .

E o .

N ,

y

~

\ ~

l l

4 10 r i.. 1 3

m 5 k 3

. j -

m 10 r i i a E i 5 i . , .

, , , ,,,,2 , , , , , , ,i ,

',t , , , , , a.

1 , ,1,,,a , , , ,,,,1 1903, 10' 10' 1(.T 10~ 10' Distence (mi)

Figure 3 CRAC2 calculated dose-versus-distance probability distributions for whole body dose of 5 rem -- wetwell venting scenario- - --

70

Probcbility conditionel on NRC wetwell venting core melt scenario, 1d = , . . .. ... . . . . .i . .i....i . ......i . . ....

- ~

1/4 POWER, OF=1.0

. + i/4 20WER, CF= 5.0 -

j

" rVLt. POWER, OF=1.0 18 r. , , ' x rutt PowE9. cF=s.O 1 y 5 ....

y 4 10 r ' ..,\

, 1 3

s 5

\ 5 1

m 10 r k i

' E \

\. . -

3 ' 'a '

in0

'1

Ia_'h1'a='tlv'a 10' 1U 5'10'

'"t 10 l Distence (mi) l i

Figure 4 CRAC2 calculated dose-versus-distance probability distributions for whole body dose of 200 rom -- wetwell venting scenario l

71

Probability conditional on NRC late drywell overpressure core melt scenario.

10' . . . ..... . . ....., . . ... oi . . ....., , , , , . . , ,

~ ~

- 1/4 POWER. OF=1.0 '

- + 1/4 POWER. OF=5.0 -

" ,.p ..... ryLL POWER. OF=1.0 i W x FULL POWER. OF=5.0 1; IV }: "**.......,,,*....,\  :

W .

e - ., .

~

5

~

\

4 10 r '.- ,

i-x

.a i :4 -

i -

- l j 1 l 8 10 r I ,

a  : i: 5 1

i; -

' ' ' ' ' ' " " ' '"- A ' ' ' ' ' " " ' ' ' ' ' " ' I

' 'l ' a" "

10.'0 1U 10~ 17 10~  !

Distence (mi)

Figure 5 CRAC2 calculated dose-versus-distance probability ,

distributions for whole body dose of 5 rem -- drywell  ;

overpressure scenario I

i 12

l Probability conditional on NRC  ;

late drywell overpressu e core melt scenario, 1d 5 ........ . . . . ..... . . . . . . i ii . . . ..i . . .iiii

~ '

1/4 power, Cr=1.0

- + 1/4 POWER, OF=5.0 -

. FUtt POWER, CF=1.0 l 1Cf x rutt aOwER. cr=s.0 i g

o o

x gg....,..........,,..,.,,..

E '.

4 10 r i- .

x
,

t s -  : -

2 10 r I 1 a =  :  : i

i

~

i 3 . , , i i i , L1 i e i ,!.ia _ _ i 1 , i,,,a 1 , o u i,a ii,,,m 19 0 1U u -- 10-- 17 10 t Distence (mi) 1 l j Figure 6 CRAC2 calculated dose-versus-distance probability p distributions for whole body dose of 200 rem -- drywell

! overpressure scenario t

i 73

b I

Probobility conditional on NRC we t well venting core melt scenario and a contoinment OF = 1. I 1 i i i i i i i 0 1/4 POWER

+ rutt power 0.8

}g y / -

l 0.6 -

I _#

4 - - -

[ 0.4 - -

i f [

I cE 0.2 - -

0 -

O 5 10 15 20 25 30 35 40 Time of ter tronsient initiotion (hrs)  !

Figure 7 CRAC2 calculated probability of 5 rem whole body dose being ,

exceeded at 2 miles from the plant -- wetwell venting scenario [

i t

74 I

O o' .

O Probability conditional on NRC we t we ll venting core melt scenario and a conteinment OF = 1.

0.2 i i i i i i i a 1/4 POWER

+ ruLL POWER W

I e 0.1 - -

t a

0.0  : 6 ':  :

0 5 10 15 20 25 30 35 40 Time of ter tronsient initiation (hrs)

Figure 8 CRAC2 calculated probability of 200 rem whole body dose being exceeded at 2 miles from the plant -- wetwell venting scenario 75

L l

[

[

i I

Probobility conditional on NRC '

late drywell overpressure core melt scen'orlo I ond o containment OF = 1, 1 i i i i i i i f

O 1/4 POWER l

+ FULL DOWER j 0.8 - -

g g -

, l u

0e - -

l 4 (

f 0,4 - -

[

f$ '

0.2 - -

l 0

'n ' ' ' '

O 5 10 15 20 25 30 35 40 i Time of ter trcnsient ;nitiotion (hrs)

Figure 9 CRAC2 calculated probability of 5 rem whole body dose being [

exceeded at 2 miles from the plant -- drywell overpressure  :

scenario  !

t 76 l

, 1 I  ;

i  !

t

l 1

l f

, 1 Probobility conditional on NRC I late drywell overpressure core melt scenerlo ,

and a containment OF = 1. i 0,5 , , , , , , ,

c 1/4 POWER I

+ FULL POWER g 0.4 - -

g r W i 0.3 - -  ;

i 1 i l A  !

l g 0.2 -

l E 0.1 - -

l 0.0 0' ,

0 5 10 15 20 25 30 35 40 Time of ter transient initiation (hrs) l Figure 10 CRAC2 calculated probability of 200 rem whole body dose being [

exceeded at 2 miles from the plant -- drywell overpressure scenario. -  ;

I r

f 77

L I

l i

i I

i i

i i

1 Probability conditional on core melt 1d . . . . . ...., . . . . . . . . , . . . . . . . . , . . . . . . . . , . . . .....

t

- ~

' 1/4 POWER, OF=1.0

, + 1/4 POWER, OF=5.0 -

t  ;

..... FULL POWER, CF=1.0 j 1Cf j =

E A """

x rutt POWER. CF=5.0 1 l

3  :

~

O -

N \ i 3 10'i r- i. 1-

>.  : . -l

s 1

. - i

. 10'* r i I

' 1 ~ i E

- \.

i t

i 3 , , , i ,,.il , , , , ,...I I i ' l id

  • 1 i ' 1d ' ' ' ' ' ' ' '

ITO lu i

10' 10 ~10~ 10 l Distence (mi) [

Figure 11 CRAC2 calculated dose-versus-distance probability [

distributions for whole body dose of 5 rem -- early ,

release scenario I 4

P 78 l

t

t 4

1 1

f

r k

i j Probability conditional on core melt

1 m i i i i iiiii i e i iiiiii , i i i i iiii i i i i i iiii , i iii.,

t

~ ~

1/4 POWER, oF=to l

! - + 1/4 POWER, CF=5,0 - 4

' FULL POWER, OF=to  !

o 10 ,

m. ..

x rutt power, or=s.O i -

l u .

x - -

u - ., -

v -

o .

4 10', r i, i- l.

x t.

- - - r

4 -

i - .

-  : - t

. 10'. r i i  ;

' E 1 i 1

- - p l

y ,

i

...A__\g,,,,.a j

3L , , , i . .a , ,

g ,,a i i i i,,,i

)90 1U 10' iv , i 3,1 J 10 (

Distcnce (mi) .

f Figure 12 CRAC2 calculated dose-versus-distance probability  !

distributions for whole body dose of 200 rem -- early e

release scenario- --

l r

I 4

F 1

r k

l l

I i

i Probobility conditional on NRC core melt scencrio end o conteinment OF = 1.  ;

1 _ ,0 i i: ,

a 1/4 POWER o FULL POWER

~

k  :  :  !

W

~0 .6 - -

[

N '

l 4 l x

s 0.4 - -

i 1o I E 0.2 - l o t i

i 0 c: )

0 6 12 18 24 30 i Time of ter trcnsient initiction (hrs) [

- Figure 17 CRAC2 calculated probability of 5 rem whole body dose being exceeded at 2 miles from the plant -- early release scenario I

80 [

[

t t

I

l l

l Probcbility conditional on NRC core melt scenorio and a conteinment OF = 1, 1 i i i i

! c 1/4 POWER

, o FULL POWER

= 0.8 - -

$o  : o W 9 0.6 - -

N 4

y 0.4 -

g 1v E 0.2 - 2 - -

l ' ' ' '

0e-O 6 12 18 24 30 Time ofter trcnsient initiation (hrs)

Figure 14 CRAC2 calculated probability of 200 rem whole body dose being exceeded at 2 miles from the plant -- early release scenario 81

l l

APPENDIX A I

L EVALUATION 0F SNPS CORE MELT FREQUENCY ESTIMATE FOR 25 PERCENT POWER f i

l A.1 Introduction t i

LILCO claims that the frequency of core melt a:cidents at Shoreham will be '

I significantly reduced by (1) operation at 25 percent, and (2) a number of r i plant upgrades which have been implemented since the original PRA. The objec-

)

tive of the staff's review was to assess the validity of the utility's asser- l tion. Emphasis of the review was on treatment of risk-important sequences I t

(e.g. , ATWS, station blackout, and interfacing system LOCA), and treatment of (

, external events. The staff's review of the treatment of risk impo tant  !

sequences is discussed in Section A.2 below. The treatment of external events I in the PRA is discussed in Section A.3.  !

i F

A.2 Comparative Evaluation of Risk Important Seouences e Table 1 in the mair. report shows values reported by L!LC0 for core melt  !

frequency for 100 percent and 25 percent power operation at SNPS (References A.1 and A.2). The core melt frequency associated with restricting operation to f 25 percent of rated power is about a factor of two below that reported for full-  !

power operation. The staff judges this reduction to be well within the range f

of uncertainty in estimating core melt frequency, especially since the reported  !

results are in the form of point estimates and large uncertainties are usually [

associated with the contribution from external events. (

L An evaluation was performed for those sequences triggered by internal or external initiators that may potentially result in early releases. These are: g I

1. Station Blackout Sequences f

i L

2. ATVS Sequences A-1 f t

i

t

3. LOCAs Outside the Containment The review focused on the differences in these sequences at 25 percent and 100 percent power, and not on the estimates of core melt frequency in an absolute, quantitative sense.

A.2.1 Loss of Offsite Power Sequences The contribution of loss of offsite power sequences to core melt frequency dropped from 10 5 per reactor year in the 100 percent PRA to about 3.6 x 10 7 per reactor year in the 25 percent PRA. The seismic contribution to these sequences is reported by the applicant to be about 2.7 x 10 8 per reactor year, l and is relatively independent of power level, i

The reduction in the contribution of these (non-seismic) sequences to core damage frequency is mainly due to:

1. Existence of redundant means of additional onsite AC power sources, and not considered in the original PRA, and
2. An increased time interval available for recovery actions as a result of the reduced level of decay heat.

Shoreham uses a frequency of occurrence for the losslof offsite power initiat-ing event of 0.082 per reactor year based upon data from their grid. Evidence gathered by EPRI and NSAC and published in several EPRI and NSAC reports (Refer-ences A.3 through A.6) indicates that loss of offsite power frequency for com-parable plants in the Northwest Power Coordinating Council, which includes Shoreham, has a value of 0.13 per reactor year. Shoreham is in a unique geo-graphical situation on Long Island because of the limited number of system interties. For this reason, the staff feels that the treatment of Icas of off-site power initiating event frequency may be somewhat optimistic in the 25 per-cent power license submittal. However, it eutt be noted that if one use,s the latest information available in the NSAC reports, tNa likelihood of recov6ry of offsite power is significantly bettar tF rn th9 Ifkeiihood calculated in the

Shoreham analysis, which was based upon an earlier report (Reference A.6).

Considering both issues together, the effect on total core melt frequency will be minimal if the loss of offrite power analysis is modified.

The 25 percent power PRA reported the unavailability of the black-start gas turbine to be 4 x 10 2 per demand based upon analysis of plant cata. This value appears reasonable to the staff based upon review of other data sources.

Credit is given for the remote start of this device in the event of a sustained loss of offsite power. No operator error is cited, however, given the time available, operator error would not be a significant contributor to failure of this backup source of power.

The study assigned a value of 0.3 per demand for unavailability of the three  !

) colt Industry diesels, and assumed no credit for this source prior to four i hours 6fter a sustained loss of AC power. The relatively high unavailability  :

is based primarily upon the method that must be used to connect this source to j

the in plant distribution system, which is dominated by operator errors. The value assigned appears reasonable given the procedures that must be followed I and the time available.

The on-site mobile power units are assigned a frequency of failure of 3 x 10 2 1 per demand for the common cause failure of three of four diesels (due primarily to operator errors). This value appears conservative given the time and th0 procedurts that are available.  !

{ lt is our conclusion that the credit given for the additional sources of AC power in loss of offsite power sequences is justified. I

?

A.2.2 ATWS Sequences [

I The contribution of ATWS sequences to core melt frequency dropped from about 1.1 x 10 5 per reactor year in the full power PRA to about 4 x 10 8 per reactor [

year in the 25 percent power PRA. This reduction is credited to casign changes 1 l as well as scme procedural changes, The most important of these are: i l

A-3  !

l

1. Improvement in the standby liquid control system (SLCS) to include sodium pentaborate with a high enrichment in boron 10 isotopic content. This improvement is claimed to extend the time available for the operator to initiate the SLCS operations, and
2. Addition of a manual inhibit switch to the automatic depressurization system (405) to prevent automatic depressurization during an ATWS event and to avoid low pressure injection.

Restriction of the normal power level to 25 percent creates a unique situation for the PRA under ATVS conditions, in that the turbine bypass valve (TBV) can deliver 25 percent of rated steam flow to the main condenser. If this mode of heat transfer remains available, the operator is not under pressure to initiate shutdown by Loron injection within a specific time, and for those event sequences the 25 percent power PRA claims that the core melt frequency is determined by hardware only. This claim ignores the possibility of operator errors of j commission which could, for example, interrupt the 25 percent power absorption capability of the TBV and condenser. Nevertheless, the Staff agrees that the 25 percent power bypass capability provides an additional success path that is not available at full power. ,

I The event sequences in the 25 percent power PRA cover many cases where heat transfer to the main condenser would not be available and where operator sctions would be required for attaining shutdown and decay heat removal. The study uses a period of 43 minutes as being available for SLCS initiation. In I addition, for certain event sequences, operator manipulation of the reactor water level is assumed in the PRA, either to prortote boron mixing by raising ,

the water level or to reduce the reactor power level by lowering the water level. The dependence of the PRA upon oparator reliability in these event sequences involves two considerations. First, the human error probability (HEP) values are derived frem the HEP model or correlation of Reference A.7. ,

The applicability of this generic correlation to the very specific unique actions involved in these event sequences is a source of uncertainty. Second, the PRA credits procedures and training, especially simulator based training, l I

for limiting the HEP values and for preventing the inducement of operator [

4 ,

I A-4 l

I

O

l stress that could increase the HEP values or increase the variability of opera-tor behavior and consequently the uncertainties in these values.

The degree of implicit credit in the PRA for operator actions du.aing the ATWS requires validation of the procedures and training for these actions and, also, some empirical confirmation of the HEP values for specific events. The credit given to timely operator action in case of the ATWS sequences remains to be a source of uncertainty in PRA studies in general. However, it is the staff's view that the ATWS sequence frequency and concerns

  • elated to credit for opera-tor actions are reduced at 25 percent power due to the greater time available for operator actions relative to operation at full power.

A.2.3 LOCAs Outside the Containment Large LOCAs outside of containment were estimated in the Shoreham full power PRA to contribute 3.6 x 10.s per reactor year to core melt frequency. In the 25 percent power PRA, the frequency of occurrence of these events has decreased to about 1.2 x 10 8 per reactor year. This decrease is primarily due to changes in the analysis of the high pressure / low pressure boundary failures and not to the effect of the power restriction. The staff considers this result to be reasonable.

A3 Treatment of External Events The original SNPS PRA (Reference A.2) scope included analysis of internal floods. This study was followed by the February 1985 Major Common-Cause Initiating (MCCI) Events Study (Reference 4.8), which coverec the remainder of external events. As part of the 25 percent power license submittal, the MCCI study was modified (Reference A.9) to reflect the current status of SNPS design and procedures, as well as relevant plant characteristics associated with the 25 percent power operation. The following subsections describe the results of the staff's review of the external events segment of the PRA studies.

A-5

O A.3.1 Internal Flood Imiv In the 100 percent PRA nt.vrt.:o flooding was identified as a leading contributor to the core damage frequency calculated for Shoreham. The Brookhaven review (Reference A.10) prepared an alternative analysis that indicated the frequency of core damage calculated in the Shoreham PRA for the internal flood initiators may be low by an order of magnitude. The dominant flood scenarios in both analyses were those that occurred at elevation 8' of the reactor building. All of the plant emergency core cooling system pumps are located at this elevation.

In the 25 percent power PRA, the internal flooding scenarios do not contribute significantly to either core damage or risk to the public. The pri.fiary reason for this is that credit is given to the operation of the CR0 pumps in the 25 percent power PRA. These pumps are located above the reactor building flood elevation and are expected to be unaf fected by floods in the reactor buildir.g.

The CR0 pumps are capable of maintaining reactor vessel inventory for initiat-ing events which occur from 25 percent power. Based upon the review of the information provided in the license submittal, the use of the CR0 pumps in the internal flooding scenarios appears reasonable and is consistent with the other I sequences in the PRA which took credit for this alternate high pressure injection source.

A.3.2 Analysis of Seismic Events The analysis of seismic events at Shoreham was performed for LILC0 by Oames and Moore corporation (D&M). Within the same approximate time period, D&M also performed the seismic analyses for Millstone 3 (which is located within 30 miles from Shoreham) and Seabroog.

The staff did not perform a detailed review of the seismic analysis for Shoreham. However, References A.11 and A.12 describe a detailed review of the seismic issues for Millstone 3. A key issue identified in that review is that the seismic hazard assumed for the Millstone site may be an order of magnitude too low. The staff has compared the seismic hazard curves from the Shoreham PRA to preliminary curves available for the Shoreham site from the Seismic Hazard Characterization Project ($HCP). In contrast to Millstone, the A6

.o .

e Shoreham SHCP curves are closer to those used in the utility PRA. Based on this comparison, it is our judgment that an increase in the utility estimates of seismic hazard by a factor of five would represent a reasonable high esti-mate of uncertainty for regulatory purposes at Shoreham. This is not to say that this high estimate represdrats the true upper limit of scientific uncer-tainty or that the true seismic hazard could not be less than that proposed in the Shoreham study. Certainly there is no compelling evidence in the historic record that would indicate any likelihood of large earthquakes in eastern Long I s l a r.d. If the increase in seismic hazard were to translate into an equivalent increase in core melt frequency for seismic events at Shoreham, i.e., a factor of five, the frequency of seismically-induced core melt sequences would increase to approximately 1 x 10 5, which is about one fif th that for internally-initiated events. It should be poirted out, however, that comparisons between seismic and non-seismic coce melt frequency estimates are not completely valid since mean seismic hazard estimates directly reflect modelling uncertainties, whereas internal event estimates do so to a much lesser extent. As a result, comparisons of the means tend to overestimate the relative contribution of the seismic events to core dan ge and risk, furthermore, this ef fect would influ-ence the results in both the 100 percent power PRA and the 25 percent power PRA.

Additional seismic concerns include:

  • The effects of a seismic event on non-safety related equipment, other than offsite power and reactor recirculation pumps, was not evaluated in the seismic analysis. Other reviews of seismic analysis have indicated that this omission may have significant effects on the results of the seismic analysis (especially the effects of seismically induced fires oue to failures in non-safety equipment). This effect should be evaluated for the Shoreham pRA including the 25 percent power PRA. i
  • Relay chatter was identified in the Structural Mechanics Associates study (performed for LILCO) as a seismic failure mode. However, this failure mode was assumed not to cause system failure. Without investigating the likelihood of successful operator action after relay chatter has occurred, this assumption appears optimistic.

A-7

o . .

A.3.3 Fire Analysis The MCCI studies performed for Shoreham include a fire analysis of selected areas. The 100 percent power MCCI study (Reference A.8) concluded that fires contributed 7.3 x 10 8 to total core damage frequency (approximately 10 percent).

The MCCI study for 25 percent power (Reference A.9) indica *.es that core damage frequency contribution from fires is 4.ti x 10 7 (approximately two percent).

The original fire study performed bounding calculations for fire areas in the plant and refined the bounding analysis for the fires considered to be risk important. Three fire zones were analyzed in detail as the major contributors to fire damage potential.

The 25 percent power MCCI study only reanalyzed the three dominant fire zones from the original analysis. All other fire zone damage frequencies are less than that calculated for the 25 percent power analysis.

We have identified several areas relating to the fire analysis which should be addressed by the applicant, however, our judgment is that they would not significantly affect the PRA results. These are as follows:

  • Operator recovery of fires: The values quoted for operator recovery (Event Q) in Table 3-2 of the 25 percent power MCCI study is 1 x 10 2 for operator actions within 30 minutes. The original analysis used a value of 0.7 for the same event for actions within 10 minutes. The change in timing is reasonable based upon the plants limited power level but the value assigned for recovery appears optimistic when one considers the confusion inherent in the fire scenarios analyzed in the 25 perceat power HCCI study. The effect of changing this operator recovery value has not been evaluated for this review. However, changing this operator recovery value to its original value would not significantly change the core damsge frequency from that calculated in the 25 percent power MCCI study.
  • Fires inside the containment: The original MCCI fire analysis screened out a majority of the fire initiating events in the data base that occurred in the containment building of PWRs on the basis that the BWR containment A-8

.. o  !

is nitrogen inerted during power operation, The MCCI update reevaluated I fires in the containment because at power levels less than 15 percent, the [

containment need not be inerted. However, those fire events that were q screened out in the original MCCI study were not reintroduced into the

[

j data base. The fires that were screened out were caused by oil leakage from PWR reactor coolant pumps. The recirculation pumps at Shoreham are  !

l also oil lubricated, therefore, we feel that the events are indicative of events which could occur inside a BWR non inerted drywell. Including these events would increase the frequency of fires inside the non-inerted l

] drywell by a factor of six, which does not significantly affect the core f I damage frequency calculated for fires, i t j

  • Fires Involving the Fuel Oil Storage Tank: The effects of a fire involving ,

] the contents of the gas turbine fuel oil storage tank were included in the l 1

original MCCI study. However, only the ef fects on safety-related structures f

were shown. Several offsite power lines (135 and 69 kV) pass rear this l

4 storage tank. It is not clear whether the effects of a fuel oil storage l

) tank fire on offsite power distribution were evaluated. This tank is also (

) located on a small hill above th major site structures. It is also not j j clear whether the effect of a fire and a dike breech or excessive smoke in .

] the vicinity of the safety related structures (primarily diesel generator l l buildings and control room) was evaluated. l t >

1 >

]

  • Other fires: Several fires induced by welding were screened out of the  ;

j fire data base in the 100 percent powe,' MCCI study. Welding, per se, is l j not precluded during power operation at most operating reactors. Without l further justification of the reasons for excluding these fire events, we [

) feel that these events should remain in the data base. However, keeping l 2

these fire occurrences in the data base will not significantly change the results of the fire analysis performed for the 25 percent power PRA.

1 l

A.3.4 Other External Events Analysis f

The original MCCI report presented analysis of other external initiating events l

' such as high wind, external flood, turbine missile, and aircraft crash. The l 1 l

other external event initiators did not contribute significantly to either core 1  !-

1

A-9 I

]

_ __,_ _ _ _ _ _.c

  • .* . l 1

damage or the risk to the public. The 25 percent power MCCI study did not '

re-examine these other initiators but based upon the results obtained in the  ;

100 percent power PRA determined that the frequency of core damage due to  !

these events was significantly less than the seismic and fire events included I in the analysis, i

l i The original NCCI study of these other external initiating events was reviewed ,

l and compared with the results of other similar studies (Reference A.11). Based upon these reviews and comparisons, the conclusions stated in the binal MCCI study and the 25 percent power MCCI study are reasonable. ,

i I

A4 Summary [

t  ?

Comparison of reported core damage frequency results as shown in Table 1

indicat0d that SNPS operation at the reduced r .ee level results in a reduction J

in the overall core damage frequency of abou* factor of two. This is well }

) within the uncertainties associated with est N sing core melt frequency, I especially considering that the reported results are in the form of point j estimates and that uncertainties can be much larger than a factor of two.

External events (seismic and fires) and estimates of human error data are the potential major contributions to these large uncertainties,

! I i i A review of seismic hazard calculations for $horeham indicates that the ur.cer-  !

, tainty could increase tha hazard by a factoe of five. A similar increase in f core melt frequency for seismic events would place sei nically-induced core (

i melt at about one-fifth the frequency presented for the sum of the internal I initiating events. This effect, however, .ould influence the results in both the 100 percent power PRA and the 25 percent power PRA. Some additional 1 concerns were raised about the treatment of fires, however, they remain a minor i component of total core damage frequency fo- the 25 percent power PRA. Also, l

}

they siay have a greater effect an the 100 percent power PRA results than on the I 25 percent power PRA.  ;

l  !

{

j Based upon the limited review performed on the systems analysis segment of the l

l 25 percent power PRA submittal, the staff concludes that core melt frequency at

] 25 percent power is not significantly different than at 100 percent power.

t A-10 l

i

, 1 A.6 References A.1. "Request for Authorization to Increase Power to 25% and Motion for F n dited Commission Consideration," Long Island Lighting Company, Occket No. 50-322, April 14, 1987.

A.2. Probabilistic Risk Assessment of the Shoreham Nt. clear Power Station, Docket 50-322, Long Island Lighting Company, June 1983.

A.3. Losses of Offsite Power at U.S. Nuclect Power Plants - All Years Through 1983, NSAC 80, July 1984.

A. 4. Losses of Offsite Power at U.S. Nuclear Power olants - All Years Through 1984, NSAC 85, June 1985. ,

A.S. Losses of Offsite Power at U.S. Nuclear Power Plants - All Years Through 1985, NSAC 103, May 1986.

A.6. Loss of Offsite Power at Nuclear Power Plants: Data and Analysis, EPRI NP-2301, March 1982.

A.7. Delian Corp., "Probabilistic Risk Assessment of the Shoreh'am Nuclear Power Station: Initial Power Operation Limited to 25% of Full Power",

April 1987.

A.8. NUS Corp., "Major Common-Cause Initiating Events Study -- Shoreham Nuclear Power Station", NUS-4617, February 1985.

A 9. NUS Corp., "Major Common-Cause Initiating Events (MCCI) Contribution to Shoreham Nuclear Power Station Core Damage Frequency -- Early Plant Operation at 25% Rated Power", NUS-4842, March 1987.

A.10. NUREG/CR-4050, "A Review of the Shoreham Nuclear Power Station Probabilistic Risk Assessment", Brookhaven National Laboratory, November 1985.

A-11

o A.11. NUREG/CR-4142, "A Review of the Millstone 3 PRA, Lawrence Livermore National Laboratory, Anail 198E.

A.12. NUREG-1152, "Millstonc 3 Task Evaluation Report", June 1986.

,1

  • i i'

I I

i 4

e I

I r

i n

l I

l l

I i

i i

A-12 (

r I

_ . _ _ _ - . . _ - - - _ _ _ _ . . _ .- , _ _ _ .-___-_.- _--__. _ __--,_ _ _- -