Forwards Rev 3 to LaSalle County Station Restart Plan, for Unit 2 Only.Unit 1 Has Been Successfully Restarted & Is at Full Power Operation.Highlights of Rev 3,listed
ML20151Y586
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 09/14/1998
From: Dacimo F
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20151Y591 List:
References
NUDOCS 9809180286
Download: ML20151Y586 (2)


Text

.

a..

. ~.. - - _

... - ~.

Commonweahh Edison Company

-[ o

' laSalle Gent rating Station 2601 North 2ist Road

~ Marseilles, II. 6I3 619757 Tet Mi5-3574i?6l l

l September 14,1998 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555

Subject:

LaSalle County Nucler Power Station Restart Plan, Revised LaSalle County Nuclear Power Station, Units 1 and 2 Facility Operating License NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374

References:

F. R. Dacimo letter to U.S. NRC transmitting Restart Plan Action Plan Revision 2, dated April 30,1998

_ The reference letter transmitted Revision 2 of the LaSalle County Restart Plan.' Revision 2 of the Plan was directed toward the restart of Unit 1. With Unit.1 successfully restarted and at full power operation, the Restart Plan has been revised to only address Unit 2 restart.

Highlights of Revision 3 include:

The Restart Strategy Action Plan activities associated with Unit 2 have been transferred to the Nuclear Tracking System (NTS). NTS will track implementation of necessary actions to support Unit 2.

The Unit 2 Restart issue Identification Criteria is the same as that used Unit 1 The Restart Issues Review Committee (RIRC) is retained to certify Unit 2 readiness for restart.

Restart and Operational Readiness Assessments include:

System Readiness Reviews

[

Departmental Readiness Assessments I

h-I l

9909190286 980914 PDR ADOCK 05000373 p

PM A unicum company

Restart Certification will be similar to Unit 1:

l RIRC j

Nuclear Oversight Corporate Nuclear Review Board Chief Nuclear Officer Restart Authorization We will review these changes during the scheduled September 15,1998, public performance review meeting. If there are any questions or comments

. concerning this letter, please refer them to Perry L. Barnes, Regulatory Assurance Manager, (815) 357-6761, extension 2383.

Respectfully, J

OO Fred R. Dacimo Site Vice President LaSalle County Station cc:

J. L. Caldwell, Acting NRC Region 111 Administrator M. P. Huber, NRC Senior Resident Inspector - LaSalle D. M. Skay, Project Manager - NRR - LaSalle F. Niziolek, Office of Nuclear Facility Safety - IDNS

!