Advises That Westinghouse Owners Group Generic Justification for Tripping Reactor Coolant Pumps During Transients & Accidents,Per Util 830422 Response to Generic Ltr 83-10d & NUREG-0737,Item II.K.3.5,will Be Delayed Until 840301
ML20083D678
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 12/22/1983
From: Clayton F
ALABAMA POWER CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.K.3.05, TASK-TM GL-83-10D, NUDOCS 8312280199
Download: ML20083D678 (2)


Text

-__

Malling Addrace Alabama Power Company 7 600 North 18th Street

\ Post Office Box 2641 Birmingham, Alabama 35291 Telephone 205 783-6081 F. L Clayton, Jr.

Senior Vice President Flintndge Building AlabamaPower December 22, 1983 * *t""*c"csrstem Docket Nos. 50-348 50-364 Mr. D. G. Eisenhut, Director Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Attention: Mr. D. G. Eisenhut Joseph M. Farley Nuclear Plant - Units 1 and 2 Generic Letter 83-10d and NUREG-0737 Item II.K.3.5

Dear fir. Eisenhut:

By letter of April 22, 1983 to the NRC, Alabama Power Company addressed the requirements of NRC Generic Letter No.83-10d dated February 8,1983. In this submittal, Alatama Power Company stated that, 90 days after receipt of the Westinghouse Owners Group (WOG) generic justification for tripping the reactor coolant pumps (RCPs) during transients and accidents) an evaluation for applicability to the Farley Nuclear Plant would be provided,.] At that time, receipt of the WOG generic response was scheduled for completion by the end of 1983. It is now anticipated that the WOG report justifying manual RCP trip will be submitted by March 1,1984. Alabama Power Company will submit an evaluation of the results of this generic' response to the NRC within 90 days of receipt of the WOG generic response.

A submittal has been transmitted to the NRC by WOG letter 0G-110 dated December 1,1983 which provided an evaluation of alternate RCP trip criteria. Alabama Power Company is evaluating this alternate criteria and will incorporate the appropriate value for manual RCP trip into the Farley Nuclear Plant Emergency Response Procedures (ERPs).

These procedures are scheduled to be revised in accordance with Alabama Power Company's schedule to implement the provisions of Supplement 1 to NUREG-0737.

P (p

t i

s l'

Mr. D. G. Eisenhut, Director December 22, 1983 Nuclear Regulatory Commission Page 2 If you have any questions, please advise.

Yours very truly, 41f F. L. Clayton, .

FLCJ r/ JAR:grs-D10 cc: Mr. R. A. Thomas Mr. G. F. Trowbridge

. Mr. J. P. O'Reilly Mr. S. A. Varga Mr. E. A. Reeves Mr. W. H. Bradford 1