Letter Sequence Other |
---|
|
|
MONTHYEARML20023B3571983-04-15015 April 1983 Forwards Response to Generic Ltr 82-33, Suppl 1 to NUREG-0737,Requirements for Emergency Response Capability. Safety Parameter Display Sys Will Operate from Emergency Response Facilities Computer Sys.W/One Oversize Drawing Project stage: Request ML20073M2231983-04-15015 April 1983 Forwards Response to 821217 Generic Ltr 82-33 Re Schedule for Addressing Each Element of Emergency Response Capability.Schedule Developed Following Guidelines Contained in Suppl 1 to NUREG-0737 Project stage: Other ML20154J3951983-05-0303 May 1983 Discusses Negotiations Re Util 830415 Response to Generic Ltr 82-33.Licensee Proposed Implementation Dates,Summarized in Encl,Acceptable.Record of 820806 Telcon Encl Project stage: Other ML20078D5831983-09-27027 September 1983 Forwards Program Plan for Implementation of Control Room Design Review of Beaver Valley Power Station, Following Guidelines in Suppl 1 to NUREG-0737,per Generic Ltr 82-33 Project stage: Other ML20084H5191984-04-30030 April 1984 Provides Approx Starting Dates & Summaries of Each Review Phase of Control Room Design Review,In Response to NRC .Summary Rept Expected to Be Submitted in Nov 1985 Project stage: Other 1983-05-03
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARL-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages ML20196A6601999-06-16016 June 1999 Forwards Master Decommissioning Trust Agreements Revised After 1990 for Ohio Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & Pennsylvania Power Co Re Bvnps,Units 1 & 2,DBNPS,Unit 1 & Perry Unit 1 ML20195H4651999-06-16016 June 1999 Forwards for Filing Answer of Firstenergy Corp in Opposition to Petition for Leave to Intervene of Local 29, Intl Brotherhood of Electrical Workers. Copies of Answer Have Been Served Upon Parties & Petitioner by e-mail ML20195J5221999-06-16016 June 1999 Forwards Answer of Duquesne Light Co to Petition to Intervene of Local 29,International Brotherhood of Electrical Workers in Listed Matter.With Certificate of Svc L-99-100, Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-1091999-06-15015 June 1999 Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-109 L-99-095, Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys1999-06-15015 June 1999 Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys L-99-099, Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr1999-06-14014 June 1999 Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr ML20195H3731999-06-0303 June 1999 Forwards Petition to Intervene of Local 29,Intl Brotherhood of Electrical Workers in Matter of Firstenergy Nuclear Operating Co,For Filing L-99-090, Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request1999-06-0202 June 1999 Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request L-99-086, Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 11999-05-28028 May 1999 Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 1 L-99-089, Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b)1999-05-28028 May 1999 Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b) L-99-084, Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon1999-05-27027 May 1999 Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon L-99-082, Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS1999-05-17017 May 1999 Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS L-99-071, Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS1999-05-12012 May 1999 Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS 1999-09-03
[Table view] Category:UTILITY TO NRC
MONTHYEARML20059L4271990-09-0707 September 1990 Requests Approval for Use of Steam Generator Tube Plugs for Both Mechanical & Welded Applications ML20059G0821990-09-0404 September 1990 Forwards Application for Amend to License DPR-66,consisting of License Change Request 180,changing Section 3.3.3.2 to Reduce Required Number of Operable Incore Detector Thimbles for Remainder of Cycle 8 ML20059F7551990-08-29029 August 1990 Responds to Unresolved Item 50-334/90-16-01 Noted in Insp Rept 50-334/90-16.Corrective Actions:Initial Training for Maint Group Personnel Responsible for Maintaining Supplied Air Respirators Will Be Supplemented W/Biennial Retraining ML20059F1501990-08-29029 August 1990 Advises That Permanent Replacement Chosen for Plant Independent Safety Evaluation Group.Position Will Be Staffed Effective 900829 ML20028G8731990-08-29029 August 1990 Forwards fitness-for-duty Program Performance Data for Jan-June 1990,per 10CFR26.71 ML20059D3761990-08-24024 August 1990 Describes Cycle 3 Reload Design,Documents Util Review Per 10CFR50.59 & Provides Determination That No Tech Spec Changes or Unreviewed Safety Questions Involved.Reload Core Design Will Not Adversely Affect Safety of Plant ML20028G8881990-08-24024 August 1990 Withdraws Operator License SOP-10731 (55-60749) Issued to K Gilbert,Who Resigned 05000412/LER-1990-007, Responds to NRC Re Deviation 50-412/90-12-01 Noted in Insp Rept 50-412/90-12.Corrective Actions:Procedure OM 2.20-4.I Revised to Require Removal of Flanges Following Drain Operations & LER 90-007-00 Issued1990-08-23023 August 1990 Responds to NRC Re Deviation 50-412/90-12-01 Noted in Insp Rept 50-412/90-12.Corrective Actions:Procedure OM 2.20-4.I Revised to Require Removal of Flanges Following Drain Operations & LER 90-007-00 Issued ML20058P7651990-08-14014 August 1990 Provides Info on Acceptability of Rescheduling Response to Reg Guide 1.97 Ser,Item 4b, Neutron Flux Monitoring Instrumentation. Rescheduling of Util Response Will Be Determined on or Shortly After Meeting W/Nrc ML20059E0571990-08-10010 August 1990 Forwards Suppl 3 to Nonproprietary WCAP-12094 & Proprietary WCAP-12093, Evaluation of Pressurizer Surge Line Transients Exceeding 320 F for Beaver Valley Unit 2, for Review by 900901.Proprietary Rept Withheld (Ref 10CFR2.790(b)(4)) ML20059E7631990-08-0101 August 1990 Provides Results of Util Evaluation of Licensed Operator Requalification Exam Conducted During Wks of 900709 & 16. Crew That Failed to Meet Expected Performance Level Has Been Successfully Upgraded & re-evaluated to Be Satisfactory ML20059B8141990-08-0101 August 1990 Requests Exemption from 10CFR26 Re Fitness for Duty Program & 10CFR73 Re Physical Protection of Plants & Matls Concerning Unescorted Access Requirements for Nuclear Generating Stations ML20056A3471990-07-31031 July 1990 Responds to NRC Bulletin 90-001.Items 1 Through 5 of Requested Actions for Operating Reactors Completed ML20056A1841990-07-27027 July 1990 Forwards Revised Methodology for Achieving Alternate Ac for Plant,Per 900720 Telcon ML20055H2581990-07-25025 July 1990 Forwards Decommissioning Rept, Per 10CFR50.33(K) & 50.75(b) ML20055F7061990-07-0909 July 1990 Responds to NRC Re Dcrdr Requirements as Specified in Suppl 1 to NUREG-0737.DCRDR Corrective Actions Implemented & Mods Determined to Be Operational Prior to Startup Following Seventh Plant Refueling Outage ML20055D3871990-07-0202 July 1990 Provides Info Re long-term Solution to Action Item 3 of NRC Bulletin 88-008,per 890714 & s.Util Will Continue to Monitor Temp in Affected Lines & Evaluate Results ML20058K5031990-06-29029 June 1990 Discusses Use of Emergency Diesel Generators as Alternate Ac Source at multi-unit Sites,Per Licensee .Emergency Diesel Generator Load Mgt Methodology Evaluated to Meet Listed Criteria ML20044A3661990-06-21021 June 1990 Forwards Application for Amend to License NPF-73,consisting of Tech Spec Change Request 44,changing Stroke Time to 60 for Inside Containment Letdown Isolation Valves.Change Determined Safe & Involves No Unreviewed Safety Issue ML20043G6811990-06-14014 June 1990 Forwards Application for Amends to Licenses DPR-66 & NPF-73, Revising Tech Specs Re Electrical Power Sys - Shutdown & Ac & Dc Distribution - Shutdown ML20043H9341990-06-14014 June 1990 Forwards Issue 1 to Rev 4 to Inservice Testing Program for Pumps & Valves. Issue 1 Removes Relief Requests Requiring Prior NRC Approval & Adds Certain Program Changes Permitted by ASME XI & Generic Ltr 89-04 ML20043G5981990-06-12012 June 1990 Forwards Monthly Operating Repts for May 1990 for Beaver Valley Units 1 & 2 & Revised Rept for Apr 1990 for Beaver Valley Unit 1 ML20043G6851990-06-12012 June 1990 Forwards Application for Amend to License DPR-66,consisting of Proposed OL Change Request 176,revising Tech Specs to Replace Current Single Overpressure Protection Setpoint W/ Curve Based on Temp ML20043G7941990-06-12012 June 1990 Responds to NRC 900524 Request for Addl Info Re Proposed Operating License Change Request 156.Clarification of Magnitude of Confidence Level of Westinghouse Setpoint Methodology,As Specified in WCAP-11419,encl ML20043G8001990-06-11011 June 1990 Forwards Application for Amend to License NPF-73,consisting of Proposed Operating License Change Request 41.Amend Deletes Surveillance Requirement 4.4.9.3.1.d ML20043H0291990-06-11011 June 1990 Forwards Application for Amend to License NPF-73,consisting of Proposed OL Change Request 40,modifying Heatup & Cooldown Curves Applicable to 10 EFPYs Per WCAP-12406 Re Analysis of Capsule U from Radiation Surveillance Program ML20043F5251990-06-0707 June 1990 Requests Temporary Waiver of Compliance from Tech Spec Limiting Condition for Operation Re Operability of Containment Isolation Valves During Quarterly Slave Relay Testing.Evaluation to Support Request Encl ML20043F1361990-06-0404 June 1990 Advises That Chemistry Manual Chapter 5P1, Enhanced Primary to Secondary Leakrate Monitoring Program for Unit 1,per 880328 Request to Recommit to Item C.1 of NRC Bulletin 88-002 ML20043B5971990-05-18018 May 1990 Advises of Delay in Hiring Independent Safety Evaluation Group Replacement to Maintain Five Permanent Personnel Onsite,Per Tech Spec 6.2.3.2.Replacement Will Be Provided within 30 Days of Retirement of Engineer on 900531 ML20043B0511990-05-15015 May 1990 Responds to Telcon Request for Addl Info Re Elimination of Snubbers on Primary Component Supports.Probability of Case B/G Event Extremely Small & Does Not Represent Realisitic Scenario ML20043B1921990-05-11011 May 1990 Forwards Cycle 8 & Cycle 2 Core Operating Limits Rept,Per Tech Spec 6.9.1.14 ML20042G9761990-05-0808 May 1990 Responds to NRC 900226 Ltr Re Violations Noted in Insp Repts 50-334/89-80 & 50-412/89-80.Corrective Action:Maint Work Request Program Being Upgraded to Include Responsibilities of Nuclear Const Dept & Will Be Issued by 900601 ML20042G8541990-05-0303 May 1990 Forwards Technical Review,Audit Summary & Operability Assessments Re Potentially Invalid Leak Detection Tests Used as Alternative for Amse Section XI Hydrostatic Tests ML20042G9071990-05-0101 May 1990 Forwards Annual Financial Repts for Duquense Light Co,Ohio Edison Co,Pennsylvania Power Co,Centerior Energy Corp & Toledo Edison Co,Per 10CFR50-71(b) ML20042F1381990-04-30030 April 1990 Advises That Final SER for Implementation of USI A-46 Will Be Delayed Until Late 1990 ML20042F0991990-04-20020 April 1990 Forwards Response to Request for Addl Info Re Second 10 Yr ISI Program ML20012F5951990-04-10010 April 1990 Forwards Monthly Operating Repts for Mar 1990 & Revised Operating Data Rept & Unit Shutdown & Power Reductions Sheets for Jan 1990 ML20042E1471990-04-0404 April 1990 Forwards Application for Amends to Licenses DPR-66 & NPF-73, Consisting of License Change Request 174/36,updating Staff Titles to Reflect Nuclear Group Organization ML20012F6021990-03-30030 March 1990 Submits Supplemental Response to Station Blackout Rule for Plant,Per NUMARC 900104 Ltr.Summary of Changes to Condensate Inventory of Dhr,Effects of Loss of Ventilation, Control Room HVAC & Reactor Coolant Inventory Listed ML20012E3091990-03-23023 March 1990 Forwards Response to 900308 Request for Addl Info on Reg Guide 1.97 Re Variable for Steam Generator wide-range Level Instrumentation ML20012E3451990-03-23023 March 1990 Submits Addl Info for Exemption from General Design Criteria GDC-57,including Background Info Describing Sys Operation & Addl Bases for Exemption Request.Simplified Recirculation Spray Sys Drawings Encl ML20012D6491990-03-19019 March 1990 Requests Retroactive NRC Approval of Temporary Waiver of Compliance Re Tech Spec Limiting Condition for Operation 3.8.2.1 on Ac Vital Bus Operability.Sts Will Be Followed When Inverters Not Providing Power to Vital Bus ML20012E4091990-03-16016 March 1990 Forwards Inservice Insp 90-Day Rept,Beaver Valley Power Station Unit 1,Outage 7, for 880227-891221,per Section XI of ASME Boiler & Pressure Vessel Code 1983 Edition Through Summer 1983 Addenda,Section XI ML20012D6181990-03-15015 March 1990 Responds to NRC 900215 Ltr Re Violations Noted in Insp Repts 50-334/89-23 & 50-412/89-22.Corrective Actions:Safety Injection Signal Reset & Plant Returned to Presafety Injection Conditions & Crew Members Counseled ML20042D7401990-03-14014 March 1990 Forwards Corrected Annual Rept of Number of Personnel Receiving Greater than 100 Mrem & Associated Exposure by Work Function at Plant for CY89. ML20012D5801990-03-13013 March 1990 Forwards Correction to First 10-yr Inservice Insp Program, Rev 2 to Relief Request BV2-C6.10-1 Re Recirculation Spray Pump - Pump Casing Welds & Relief Request Index ML20012D6221990-03-13013 March 1990 Forwards Response to Generic Ltr 89-19, Resolution to USI A-47. Recommends All Westinghouse Plant Designs Provide Automatic Steam Generator Overfill Protection to Mitigate Main Feedwater Overfeed Events ML20012C1791990-03-0909 March 1990 Responds to NRC 900207 Ltr Re Deviations Noted in Insp Repts 50-334/89-25 & 50-412/89-23.Corrective Actions:Written Request Initiated to Identify Unit 2 post-accident Monitoring Recorders in Control Room & Recorders Labeled ML20012E0911990-03-0505 March 1990 Lists Max Primary Property Damage Insurance Coverages for Plant,Per 10CFR50.54(w)(2) ML20012B7051990-03-0202 March 1990 Responds to NRC 900131 Ltr Re Violations Noted in Insp Repts 50-334/90-05 & 50-412/90-04.Requests Withdrawal of Violation Re Stated Transport Problem & Reclassification as Noncompliance,Per 10CFR2,App C,Section G 1990-09-07
[Table view] |
Text
^
yp Telephone (412) 393-6000 Nuclear Division P.O. Box 4 Shippingport, PA 15077-0004 April 15,1983 pirector of Nuclear Reactor Regulation ATnited States Nuclear Regulatory Commission At ta: Mr. Darrell G. Eisenhut, Director Division of Licensing Washington, DC 20555 Eeference: Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Generic Letter No. 82-33; Supplement 1 to NUREG-0737 Gentlemen:
In response to your letter of December 17, 1982, Generic Letter No. 82-33, attached is the Beaver Valley Unit 1 plant specific schedule for addressing each of the elements for emergency response capability.
This schedule has been developed following the guidelines contained in Supplement 1 to NUREG-0737. It is recognized that the elements of emergency response must be integrated in such a fashion to assure adequate support is given to the plant operating staff when called upon to respond to an emergency condition. In recognition of' this, Beaver Valley Unit I has participated with the INPO sponsored NUTAC on Emergency Response Capability (ERC) and has worked closely with other utilities in preparing an integrated implementation plan which addresses the elements of Supplement 1.
Our plan for integrating these elements will have its focus on utilizing manpower in the most efficient manner and as a result several of the elements will be performed concurrently. Included as Figure 1 is a preliminary integrated inplementation plan. This plan was developed by the NUTAC on ERC and must be converted into a plant specific plan. We will use the guide-lines developed by this NUTAC to assist us in developing our plant specific
^
integration implementation plan. Included with this submittal is Appendix A which is 'a summary description of the integration plan developed by this NUTAC. The integration scheme, as developed by this NUTAC, has not been .
finalized, however, it should be available this June at which time our '
integrated implementation plan will be draf ted.
The Duquesne Light Company welcomes this opportunity to work with the NRC in establishing realistic plant-specific schedules. As indicated in your letter, implementing generic deadlines does not permit a utility to make the most efficient use of its staff when trying to integrate many related tasks. This approach by the NRC is viewed as a positive step which permits both the NRC and the electric utility industry to maximize d
, L#
\
8304210450 830415 h d PDR ADOCK 05000334 F PDR , g3. p
, A
-- ,e--,r,-r-- -.--,,r-- .n , , - - --, ,..m--. , . a, . . . - - , . , - - , , - ,- -, - - - - - - - ~ '
Beaver Valley Power Station, Unit No.1.
. Docket No. 50-334, License No. DPR-66 Generic Letter No. 82-33, Supplement I to NUREG-0737 Page 2 their resources, be responsive to the issue of emergency response capability and improve our ability to get the job done.
The Duquesne Light Company expects to complete those tasks identified .
in Supplement 1 to NUREG-0737 in accordance with the following schedule:
, 1. SPDS Safety Analysis -
contingent upon NRC issuance of SER on Westinghouse designed SPDS
- 2. SPDS operable and operators -
following fifth refueling trained outage
- 3. CRDR Program Plan -
draft; September 1983 final; date to be pro-vided by September 1983 -
- 4. CRDR Summary Report -
to be provided with our final program plan submittal.
- 5. R.G. - 1.97 Report -
to be provided with our CRDR Summary Report
- 6. E0P Technical Guidelines -
previously submitted by the (Generic) Westinghouse Owner's Group
- 7. EOP. Procedures Generation -
June 1, 1984 Package
- 8. Implementing E0Ps -
following simulator valida-tion and operator training
- 9. ERF fully functional -
following fourth refueling outage (without SPDS)
If you have any questions regarding this submittal, please contact myself or members of my staf f.
Very trul yours, J. . Carey Vice President, Nuclear Attachment
Bravar Valley Power Station, Unit No.-l
- Docket No. 50-334, License No. DPR-66 Generic Letter No. 82-33, Supplement 1 to NUREG-0737 Page 3 cc: 'U. S. Nuclear Regulatory Commission Office of Inspection & Enforcement Attn: R. C. Haynes, Regional Administrator Region I 631 Park Avenue King of Prussia, PA 19406 Mr. W. M. Troskoski, Resident Inspector U. S. Nuclear Regulatory Commissf.on Beaver Valley Power Station Shippingport , PA 15077 U. S. Nuclear Regulatory Commission c/o Docuoent Management Branch Washington, DC 20555
l l
COMMONWEALTH OF PENNSYLVANIA)
) SS:
COUNTY OF BEAVER )
On this _/[f/[ day of ( M ,
me,( Ih/a; ///,Jg7/2v.a Notary fublic in and for said Commonwealth
/ 9 [8 , before and-Cou6ty, personally a'ppeared J. J. Carey, who being duly sworn, deposed, and said that (1) he is Vice President of Duquesne Light, (2) he is duly authorized to execute and file the foregoing Submittal on behalf of said Company, and (3) the s+atements set forth in the Submittal are true and correct to the best of his knowledge, information and belief.
ON D
/
sNERA W.FAntti,sNAst regut semnspostsono, muses comm NY ConstSSIGR EIMGES SEPT. M,195 mae ramm == e asessena e amens l
4 ATTACRMENT i
Response to Generic Letter 82-33 Program Plan 4
. Duquesne Light Company, Beaver Valley Unit No. 1, will be utilizing Guidelines for an Integrated Implementation Plan which has been developed
, by the NUTAC on ERC. Included as Appendix A to this attachment is a summarized version of this guideline. This summarized guideline, when used with Figure 1 presents a method of ideal integration for the plan-ning of the elements of Supplement 1 which are:
Emergency Operating Procedures Regulatory Guide 1.97 Safety Parameter Display System Emergency Response Facilities Control Room Design Review When these guidelines are finalized, we will develop our plant-specific integratica plan of these elements. The guidelines are scheduled to be available in June of this year.
Proposed Schedules Much of the work discussed in the following sections will be performed in parallel so that effective integration of these elements can be
- accomplished. There are many documents providing guidelines being prepared to assist utilities in completing each of these elements. We will utilize these guidelines where appropriate, when evaluating our method of addressing each of the Supplement 1 elements.
- Safety Parameter Display System (SPDS)
The SPDS selected for Beaver Valley Unit No. 1 is a Westinghouse Electric Corporation design. This SPDS has been purchased and i installation of this system has started. It will require two refueling outages to complete all terminations in the plant which serve as inputs to the SPDS.. Completion of this work is scheduled to occur during *our fourth refueling outage in February 1985. After terminating all inputs, and completing loop calibration following the fourth refueling outage, a complete check-out of the SPDS will be accomplished. Between this outage and the fif th refueling outage, our plant operating staff will become familiar with this system, receive training on the system, and learn how to most ef fectively make use of this operating aid for responding to emergency conditions, t
i
,.-a- ,---- ,-. - --s. , ----~.-,..--------.---g-. - , - - - -- -,----.v v , - - p - , -
4 Attachment
-Page 2 1
Procedures that are to be developed or revised will be in place by the end of our fif th refueling outage. Although the SPDS is not expected to be installed in time to be thoroughly reviewed as part of the CRDR, it's location and parameters will be a consideration when performing the Control. Room Design Review.
j It is our understanding, that the NRC has reviewed the Westinghouse t design basis of the SPDS, which includes the basis for parameter
- selection. Our SPDS will be implemented using the Westinghouse I design basis and functional analysis requirements upon which this SPDS.has been designed. Upon issuance of a favorabic Safety Evalua-
!- tion Report by the staff, this document will be used as our design
- basis for parameter selection.
- Control Room Design Review (CRDR)
Beaver Valley, Unit 1, is presently developing a program plan for a control room design review. We plan to follow guidance being developed by the INPO sponsored NUTAC on CRDR. As inputs to this -
ef fort, we have developed a questionnaire which has been distributed i to the plant operating staff and will serve in part as the operating experience input for the review. Parallel with this task, we will
, ausess past operating events and the operations enforcement history
- which will als_o serve as operating experience input and together l these will assist in the identification of Human Engineering Discrep-ancies (HEDs). Our program plan will contain details of these tasks and explain our methodology for assessing this information and cate-gorizing HEDs for resolution. Final guidance in performing a CRDR.
is expected to. be published in May,1983, and as such, committing to
, . a date for submitting our program plan is not possible at this time.
4 We will, however, commit to providing a draf t plan by September of 1983. Our completed program plan will aid us in determining the l length of time needed to accomplish each task and provide the methodology for HED resolution which is an input for determining
! the final resolution of HEDs, Upon completion of these elements of I
our program plan, we will be able to provide a date for submitting the CRDR summary report.
, It is our intent to utilize our first draf t of the new E0Ps when per-
- forming our CRDR. Utilizing these plant-specific documents will
! most accurately assess the man-machine interface in our control room,
! and a sound basis for operator actions will exist. We believe this
- approach to be the most effective use of our resources and will fully
( satisfy the staff's concerns for integrating the EOPs with the CRDR.
Regulatory Guide - 1.97 l
Review of specific Regulatory Guide 1.97 instruments have been in
} progress since the issuance of revision 2, and positions have been i docketed on some generic, instrument related issues. ' Instrumentation needed to implement emergency operating procedures is being tabulated 1
i-t
At tachment P ge 3 and will be compared with the Regulatory Guide. This Regula-tory Guide has also been used as a design input to the parameters that will be available in the ERF, therefore, the majority of these parameters will be available to TSC and EOF personnel although we anticipate some exception to the Regulatory Guide. The NUTAC on ERC is developing Guidelines for evaluating Reg. Guide 1.97 instruments. These guidelines are scheduled to be issued in June of 1983 and will serve as an input document in assisting its when performing this evaluation. This task will be performed in parallel with the CROR effort to assure effective integration of the review of accident monitoring instrumentation with the CRDR and E0Ps. We will provide a final report on our evaluation of Regulatory Guide 1.97 instrumentation with the CRDR summary report.
Our report will satisfy the staf f concerns as documented in Sup-plement 1.
- Emergency Operating Procedures (EOPs)
Initial draf ts of new E0Ps are currently being developed based on the Westinghouse Emergency Respense Guidelines (ERGS) . These guide-lines have been previously submitted to the NRC via the Westinghouse Owner's Group, and as such, this submittal satisfies the Supplement I request for submitting technical guidelines for NRC review. Work has begun in developing initial draf ts for in-house reviews in advance of obtaining the staff's approval of the generic ERGS. The E0Ps will not be completed until the NRC staff has issued its SER on these procedures. It is our understanding that the Westinghouse Owner's Group plans to issue a revision to the ERGS in June of 1983.
Any revision, and subsequent staff review of these ERGS will be a consideration in the final development of our plant-specific E0Ps.
It is our intent to utilize the new E0P drafts when performing our CRDR. We will follow the guidelines contained in Supplement 1 to assure ef fective development of the E0Ps and the integration with the other elements. Our preliminary schedule at this time includes utilizing the new E0P draf ts for our CRDR in 1984 and completing a validation of our new E0Ps on our Unit 1 plant simulator scheduled for operation in 1985. Operator training on the new E0Ps will be performed in stages. The operators will become familiar with the new E0Ps during requalification training and then receive simulator training using the new E0Ps. We will submit the procedures genera-tion package by June 1,1984 for NRC review. The E0Ps will be imple-mented upon the completion of the simulator validation and training of the operators.
- Emergency Response Facilities Since the NRC first issued guidance related to establishing a Technical Support Center in NUREG-0578, we have actively pursued the necessary engineering studies to determine the design and optium location of such a facility. In November of 1979, we stated that our goal was to complete the installation of the permanent center, complete with necessary instrumentation and data transmission facilities by January 1, 1981. In early March,1980, a conceptual design of our TSC was pres-
Attachmznt
_ Pags 4 ented to the NRC while at the same time ground boring and sub-surface soil. analysis was complete and engineering was finalyzing details which would permit construction to begin.- In August of 1980, the staff issued for comment NUREG-0696 which defined the functional ariteria for -ERFs. Comments were provided on September 26, 1980 and several days later, a revised design concept was sub-mitted which reflected our understanding of the direction the NRC was going with respect to ERF design criteria. From the time the NRC identified the need for an ERF, we' endorsed both the- desir-ability and need for these . facilities and immediately began the necessary design and construction to support the desired implemen-tation date. We believe this early effort demonstrates our respon-siveness and also demonstrates a good faith effort at having an emergency response facility which was being built in close accordance with the then established criteria.
The current schedule for a fully functional ERF 13 following our fourth refueling outage. The TSC and EOF are located within the site structure .
referred to as the Emergency Response Facility (ERF) . Fully functional means all actions concerning structure, instrumentation, procedures and trained staff to be completed. The following is presented for your review:
Technical Support Center The permanent TSC is' located. in the ERF on the site property and is staffed by predesignated technical, engineering, senior management and other personnel as required by our Emergency Preparedness Plan.
The design is such that during periods of activation, it will operate
. uninterrupted to provide plant management and technical support -
to plant operations personnel. -
The TSC has not been located within the protected area. It is our position that the necessary interaction with control room, OSC, EOF and other personnel involved with the emergency can be adequately facilitated with the selected location of the TSC. The interim TSC also is not located within the site protected area and we have adequately demonstrated our ability to provide the necessary inter-action of emergency response personnel during a recent full scale drill which was conducted in accordance with 10 CFR 50, Appendix E and found
- satisfactory during reviews by FEMA and the NRC.
The basis, as per NRC guidance, for establishing a TSC within the site protected area is documented as being as close as possible to the control room because recent events at nuclear power plants demonstrated ineffective methods for providing all of the necessary management interaction and technical information exchange. The interim TSC has been equipped'with dedicated communications circuits i
to permit interfacing of TSC personnel with control room personnel and for retrieval of specific plant data. This is used in conjunction t
i f
, Attachment Page 5 with closed circuit televisions which provide for an independent method of obtaining specific plant data. As previously stated, we have demonstrated our ability to provide the necessary management interaction between control room personnel and TSC personnel during full scale emergency drills. It has never been necessary for any individual within the TSC to go to the control room for any manage-ment interaction, technical information exchange or to obtain data which wne unavailable in the TSC.
During the period of time the NRC guidance documents were being reviewed for their impact on our ERF design, we had committed to providing an alternate TSC in the existing conference room located in the Service Building. A description of this alternate TSC was provided in our December 12, 1980 submittal. Our commitment was based on the rigid guidance that the TSC be located within two minutes walking distance of the control room. Upon our further consideration of this commitment, we believe that the establish-ment of an alternate TSC in the service building will not enhance our capability to perform emergency operations. Therefore, we retract that commitment based upon following:
our demonstrated proficiency for adequately responding to emergency conditions during full scale emergency drills our present Emergency Preparedness Plan requires the TSC to be manned with sufficient personnel to permit overall plant management and technical assistance to the control room per-sonnel, not the alternate TSC.
the alternate TSC does not have adequate space to permit establishing the appropriate functions necessary to permit overall plant management and technical assistance to the control room personnel.
attempting to set-up this alternate TSC in conjunction with the permanent TSC would weaken our emergency response posture since key supervisory personnel would be in two separate loca-tions and effective coordination of activities would be jeop-ardized.
the alternate TSC does not have a radiologically filtered ventila-tion system or any shielding to permit an individual to remain in the event that plant conditions deteriorated beyond the plant design basis. Any evacuation from the alternate TSC would there-fore weaken our emergency response capability, subsequently, this alternate TSC would not be able to operate uninterrupted as requested in Supplement 1.
the permanent TSC is being equipped with data collection equip-ment (SPDS and computer displays of appropriate Regulatory Guide 1.97, Rev. 2 parameters) which will significantly enhance our existing capabilities for obtaining information from control room instrument channels which are the recognized accident moni-toring instruments, thereby improving an already adequate method of obtaining plant info rma tion. (Note: the SPDS is not considered necessary for a fully functional TSC).
, Attachment P:ga 6 the habitability, ventilation and shielding, of the perm-anent TSC is such that evacuation due to acy design basis accident would not be necessary, therefore, it will operate uninterrupted for the duration of the emergency. >
the alternate TSC does not have adequate floor space to permit storage of or access to accurate, complete and current plant records essential for evaluation of the plant under accident conditions; however, this is a dasign feature of the permanent TSC.
approximately 58 million dollars has been budgeted for the completion of the ERF. This represents a significant capital investment above which we cannot justify additional costs for an alternate facility to meet guidance documents.
in the event that at some time it would be desirable to go to the control room, the permanent TSC is three minutes driving time and within a short walking distance from the control room. The route between the TSC and Control Room iu on company cwned roadways, all within the property boundary.
The time required to travel from our TSC to the Control Room is reasonable and should not be considered an unacceptable dif-ference trom the guidance document.
As previously stated, the permanent TSC will not be fully functional until af ter the fourth refueling outage. In our submittal of June 8, 1982, response to Generic Letter 82-10, we indicated it would require two refueling outages to complete all construction work associated with providing a reliable data collection system. This schedule is necessary since the tie in and testing of the majority of the circuits between the plant and the ERF can only be performed during an extended outage. Our present schedule is to have available, at the conclusion of the third refueling outage, sufficient information in the ISC to enable emergency support personnel to assist the control room oper-ating staff in evaluating the status of the plant under emergency conditions. Included as TABLE 1 is a list of plant variables which we have determined to be the higher priority inputs to the new data aquisition system. All plant parameters serving as inputs to this new system will be completed during the fourth refueling outage.
Completion of this task will result in a fully functional TSC which will have addressed the guidance provided in Supplement 1. In the interim, we will maintain the existing interim TSC located in the Administration Building until the third refueling outage at which time the TSC functions will be relocated to the permanent ERF facility.
With respect to provisions for security at the permanent TSC, the same level of security will be maintained for controlling access, during TSC activation as our EPP currently provides for the interim TSC.
, Attachment Pegs 7 In addition to the data acquisition system discussed above, we have also procured another system to be used to monitor the meteorological variables for the site vicinity. This has been previously discussed in correspondence to the NRC staff, specifically, response to Generic Letter 82-10, dated June 8,1982, whereby we stated our schedule for completing this effort as being December 1983. Completion of this work will permit collection of meteorological data for use in evaluating the offsite consequences of a radiological emergency condition. This computerized meteorogical assessment system will be operable from the TSC, EOF and the Control Room. In the interim, we will continue to access these of fsite consequences through the use of our dose projection implementing procedures contained in our Emergency Preparedne.ss Plan.
Operational Support Center Our present OSC is defined in our Emergency Preparedness Plan and will remain the permanent OSC within the new emergency response framework.
Emergency Operations Facility The permanent EOF is located in the EFF on the site property and is staffed by predesignated emergency personnel as identified in the EPP to provide overall emergency response, coordination of radiological and environmental assessment, development of recom-mendations for public protective actions, and coordination of emergency response activities with Federal, State and local agencies.
During periods of activation, the EOF will operate uninterrupted to permit continuous dose assessment, communications and decision making. This portion of the ERF has been designed with a protection factor greater than 50 and includes HEPA and charcoal filters in the design of the ventilation system which is capable of operating in a recirculation mode.
Our schedule for having a fully functional EOF is following our fourth refueling outage. This schedule is necessary to permit com-pletion of the work associated with the data acquisition system as discussed in the above section on the TSC. Plant variables which serve as inputs to the data acquisition system will be phased into the system during the third and fourth refueling outages. In addition to this system, we are also installing an interactive graphics terminal and graphics printer connected to the meteorological com-puter system, as discussed in the above section on the TSC. In the interim, we will maintain the existing interim EOF located in the Administration Building until the third refueling outage at which time the EOF functions will be relocated to the permanent ERF facility. With respect to provisions for security at the perm-anent EOF, the same level of security will be maintained for control-ling access, during EOF activation as our EPP currently provides for the interim EOF.
Attachment Page 8 Upon consideration of the design of the permanent EOF, it is our position that maintaining a back-up EOF for potential activation is not necessary for the following reasons:
There is no accident condition within our design basis whereby an evacuation of the permanent EOF would necessi-tate the relocation of personnel.
There are no activities which would be performed at the back-up EOF which could not be performed in the permanent EOF.
It is undesirable to provide staffing or equipment to a back-up EOF which cannot contribute to the overall management of an erergency situation.
Staff guidance in the April 25, 1980 letter stated arrange-ments should be made to activate an alternate EOF in the event that the nearsite EOF becomes uninhabitable. There is no design basis accident for whicia our permanent EOF would become uninhabitable.
Staff guidance has also stated that the location of the EOF, and whether a back-up facility is required, should consider:
- a. whether the location provides optimum functional and availability characteristics for carrying out the functions specified for the EOF and,
- b. whether EOF functions would be interrupted during radiation releases for which it was necessary to recommend protective actions for the public to off-sita of ficials.
Based on the design of the permanent EOF and our procedures for directing emergency activities, it is concluded that all EOF functions will continue uninterrupted throughout an emergency condition.
Based on dose calculations for our site, access to the permanent EOF will be available during all design basis accident conditions.
This is possible due to the fact that af ter the first hour of a design basis accident, any release from containment will have stopped due to the return of our subatmospheric containment to a negative pressure. An individual standing outside the ERF for the first hour would not receive a radiation dose in excess of 10 CFR 100 limits. Any time af ter the first hour of a DBA, the source term will decrease due to the rapid radioactive decay of fission products and depletion of the plume due to normal meteoro-logical processes. This results in postulated doses to individuals outside the ERF becoming less. In the event the emergency organi-
, Attechment
.Pege 9 zation would decide to restrict access to the ERF for a short period of time, our emergency procedures will identify alternate steps to be taken. (i.e., a temporary holding loca-tion on route to the ERF)
Due.to the unique location of BVPS with respect to having three states within the Emergency Planning Zone, a single back-up EOF'beyond the EPZ would significantly delay-the staf fing of a back-up facility .by state and local emergency personnel.
In consideration of the above, we do not consider a back-up EOF as being necessary for the task of emergency management and offsite interfcce under design accident conditions, and therefore retract our previous commitment to having a back-up EOF after our permanent facility is mcde operational following our third refueling outage.
i 4
i
TABLE 1 PLANT VARIABLES DISPLAYED IN THE ERF FOLLOWING THE THIRD REFUELING OUTAGE Steam Generator LA Blowdown Isolation Valve Position Steam Generator IB Blowdown Isolation Valve Position Steam Generator-lC Elowdown Isolation Valve Position Charging Flow Reactor Coolant Pump 1A Seal Water Flow Reactor Coolant Pump 1B Seal Water Flow Reactor Coolant Pump 1C Seal Water Flow Non-Regenerative Heat Exchanger Letdown Flow Reactor Coolant Pump 1A Seal Injection Flow Reactor Coolant Pump 1B Seal Injection Flow Reactor Coolant Pump 1C Seal Injection Flow Blender Primary Grade Water Flow (Make-up Flow)
Volume Control Tank Level Volume Control Tank Pressure Charging Pumps Discharge Header Pressure Containment Sump Water Level Steam Generator lA Auxiliary Feedwater Flow Steam Generator 1B Auxiliary Feedwater Flow Steam Generator 1C Auxiliary Feedwater Flow Steam Generator LA Narrow Range Level Steam Generator 1B Narrow Range Level Steam Generator 1C Narrow Range Level Steam Generator lA Wide Range Level
. Steam Generator 1B Wide Range Level Steam Generator 1C Wide Range Level Waste Gas Surge Tank Pressure Waste Gas Decay Tank 1A Pressure Waste Gas Decay Tank 1B Pressure Waste Gas Decay Tank 1C Pressure Containment Hydrogen Concentration Containment Narrow Range Pressure Containment Atmosphere Temperature l Steam Generator lA Steam Pressure l Steam Generator 1B Steam Pressure
! Steam Generator 1C Steam Pressure l
Main Steam Header Pressure Main Steam Loop 1A Atmospheric Dump Valve Position
! Main Steam Loop 1B Atmospheric Dump Valve Position l
Main Steam Loop 1C Atmospheric Dump Valve Position
! Main Steam Loop 1A Isolation Valve Position Main Steam Loop 1B Isolation Valve Position Main Steam Loop 1C Isolation Valve Position l
i L
- TLANT VARIABLES DISPLAYED IN THE ERF FOLLCWING THE THIRD REFUELING OUTAGE PAGE 2 Neutron Flux Source Range Neutron Flux Intermediate Range Refueling Water Storage Tank Level Chemical Addition Tank Level Quench Spray Pump 1A Discharge Pressure Quench Spray Pump 1B Discharge Pressure Quench Spray Pump 1A Discharge Flow Quench Spray Pump 1B Discharge Flow Reactor Coolant Loop 1A Flow Reactor Coolant Loop 1B Flow Reactor Coolant Loop 1C Flow Pressurizer Level Pressurizer Wide Range Level (Cold Calibration)
Pressurizer Relief Tank Level Reactor Coolant Pressure (Wide and Narrow Range)
Pressurizer Relief Tank Pressure Pressurizer Liquid Temperature Pressurizer Vapor Temperature Reactor Coolant Auctioneered T e
Temperature Reactor Coolant T Temperature ref Reactor Coolant Loop 1A Cold Leg Temperature Reactor Coolant Loop 1B Cold Leg Temperature Reactor Coolant Loop 1C Cold Leg Temperature Reactor Coolant Loop 1A Hot Leg Tenperature Reactor Ccolant Loop 1B Hot Leg Temperature Reactor Coolant Loop 1C Hot Leg Temperature Reactor Coolant Loop 1A Delta T Reactor Coolant Loop 13 Delta T Reactor Coolant Loop 1C Delta T Reactor Coolant Loop 1A T ave Reactor Coolant Loop 1B T ##*
Reactor Coolant Loop 1C T Pressurizer PORV Common Dis 0harge Line Temperature Pressurizer Code Safety Valve A Discharge Line Temperature Pressurizer Code Safety Valve B Discharge Line Temperature Pressurizer Code Safety Valve C Discharge Line Temperature Pressurizer Relief Tank Temperature Pressurizer Code Safety Valve A Position Pressurizer Code Safety Valve B Position Pressurizer Code Safety Valve C Position Reactor Coolant Pump 1A Current Reactor Coolant Pump 1B Current Reactor Coolant Pump IC Current Degree of Subcooling Pressurizer Heater Currents Outside Recirculation Spray Pump 1A Discharge Pressure Outside Recirculation Spray Pump 1B Discharge Pressure Inside Recirculation Spray Containment Sump 1A Temperature Inside Recirculation Spray Containment Sump 1B Temperature
. PLANT VARIABLES DISPLAYED IN THE ' ERF FOLLCWING THE THIRD REFUELING OUTAGE PACE 3 Inside Recirculation Spray Pump 1A Discharge Temperature Inside Recirculation Spray Pump 1B Discharge Temperature Outisde Recirculation Spray Pump IC Discharge Temperature Outside Recirculation Spray Pump 1D Discharge Temperature Inside Recirculation Spray Containment Sump 1A Level Inside Recirculation Spray Containment Sump 1B Level Reactor Coolant Loop 1A Cold Leg High Head Safety Injection Flow Reactor Coolant Loop 1B Cold Leg High Head Safety Injection Flow Reactor Coolant Loop 1C Cold Leg High Head Safety Injection Flow Reactor Coolant Loop LA Hot Leg High Head Safety Injection Flow Reactor Coolant Loop 1B Hot Leg High Head Safety Injection Flow Reactor coolant Loop 1C ' Hot- Leg High Head Safety Injection Flow High Head Safety Injection ~ Flow to BIT Low Head Safety Injection Pump 1A Discharge Flow Low Head Safety Injection Pump 1B Discharge Flow River Water Pump 1A Discharge Flow to Recirculation Spray Heat Exchangers River Water Pump 1B Discharge Flow to Recirculation Spray Heat Exchangers Condenser Air Ejector Discharge to Containment Trip Valve Position Primary Plant Demineralized Water Storage Tank Level 480V-Emergency Bus LN Volts 480V Emergency Bus 1N1 Volts 480V Emergency Bus IP Volts 480V Emergency Bus IP1 Volts 120 VAC Vital Bus 1 Volts 120 VAC Vital Bus 2. Volts 120 VAC Vital Bus 3 Volts 120 VAC Vital Bus 4 Volts Incore Thermocouples Incore T/C Cold Reference Junction Temperatures s
L
. Cwgsa a w I.*
L ~ l" i"iL'. i 11 ,.'.
gs=
s>_ ,f,f, s=
t, T o > _i s lf ,,
o-n_ > ,o, i D" i t g,, ~
-i ,w lI p
e.
wc m,, a l
a ar s i* ;mmee i
- c. u r
ma 7n 1
m>w o
, w
.t w ap ta,e 4
' ev u,
e n s w t rwa w ew u
g
),
>< rt l
,o i si u. i n
3,f 7 uM ,T tCf it V r
- m. ?,, "
+w," s e
r , "' gw ni l i
l, l
1a t s
rf- p,i a
l1
, a n
itI S
L s
9, e 2'"
_w 0,w* f, w,* p,ia E
' Tf ,u ..! Y;e;;'a ,r . t 3
3
,* y*
4 V t-l,. ' l'
>1 m eb.1 t9 l
t_i .n l I.
i.u1.s I .
4 t_
- %I i 1yw.1
- v. .
id v ),
L >va.
s 1,* Yv 4 L' T.
< S t Q t ial
> I 1.l .
G
_ws i 2 . t
., ) ,. .
T w.,. - I
~
a, gl>i a pI**
I1
\T ,
e
t
a.
I "r "'
i>~$ >
wu > ' '
i
w ="
b, ,1 ;. .
.s
,w 2 aw 1i i.
i
,. .. ?.e<o n "m T1.e.a 1
d' i
p v" ,
- a. ""
a ' r. m o e
f u i t o~ . I1 )a p
.* a g i n w o d
f s, n. I m! t m g, w o
,,, . M v &
3' J . a' p )
L g
" y no ?" i 2
g
, (v n t o
t 3, ,, ' '
" swt,
,v
,e s F'*
1 " ,
w ' e ,,,
y g1 s
V o
f 2 1 I , ',i," ,-
,> 3 J, Q d
w
,u g..
J,,.
3 pj'
, [,
s1
>t ty
,n
,u s
n'
,3 m ,,,,,
31 ft 4
3 E
lvpp f 5 u l,'
1 s d' rg g r,
s t J'*m r,
( t4 6
n Ll , - , !, i,, i '. ,!!l
-- L---. -u-_- a, 4 --- - - + - , -- - , <
0 0
APPENDIX A CENEkIC INTEGRATION SCHEME i
i t
{ A-1 l
l 3
INTRODUCTION A subcommittee of the NUTAC on emergency response capabilities was formed to provide industry guidance to individual utilities for the development of an integrated implementation plan that addresses the provisions of Supplement 1 to NUREG-0737. The method developed to integrate these provisions is shown in Figure 1.
Figure 1 is divided into basis steps that may be considered in the development of en integrated, plant-specific implementation plan.
Each step and its relation to previous and succeeding steps is dis-cussed in the following plan descriptions.
E0P PLAN The E0P plan consists of those tasks that will provide a documented method for developing, utilizing, revising, and controlling emergency operating procedures.
Initial plant-specific E0Ps are developed by utilities for the purpose of mitigating the consequences of a broad range of initiating events and subsequent multiple failures or operator errors, without the need to diagnose a specific event. These procedures are function-oriented and written with human factors considerations to improve human relia-bility. These initial E0Ps are based upon a writer's guide and NSSS generic technical guidelines.
Determination of procedure adequacy is dependent upon the trained operator's needs. E0Ps should be checked for completeness, under-standability, technical correctness, usability, and compatability with the control room. A walk-through of the initial E0Ps provides a method of evaluating these criteria. A utility may choose to perform an E0P walk-through in the control room, in a simulator, using a mock-up of their control room, or any combination of the three. Although Figure 1 indicates only one E0P walk-through, this process should be repeated following any major modifications to the E0Ps.
Plant-specific E0Ps should be incorporated in an iterative process l
with control room HEDs, specific utility application of RG-1.97 reco-l mmendations, SPDS design bases, and emergency response facility criteria.
This interactive process should be used to determine what changes can be made easily to the E0Ps to accommodate deficiencies in other areas l without impacting the effectiveness of the E0Ps. For this iterative l process to be most effective, all of the elements that impact E0Ps should be available at the same time.
CRDR PLAN i
The CRDR program plan is the first step toward performing a CRDR and provides a method for performing the entire review.
l l A-2 l
l
The operating experience review is performed to identify any opera-tional problems resulting from design discrepancies or to identify any improvements to the control room that would improve the ability of an operator to respond to an emergency condition.
In performing the CRDR, accepted human factors guidelines should be used. Good human engineering practices should be incorporated in any control room design since the operator must interface with this equip-ment under stressful, as well as normal, conditions.
The control room survey should utilize results from the E0P walk-through, operating experience data, and human engineering criteria, to uncover any control room human engineering discrepancies. This survey should include, among other things, an assessment of control room layout, the control room environment, the usefulness of audible and visual alarms, the readability of displays, the adequacy of instrumentation, and the information recording and recall capabilities.
The results of the E0P walk-through, with consideration given to the oper-ators tasks, must be compared with the available control room instruments and controls during the survey process to determine the adequacy of exist-ing displays or controls.
The operators tasks and informational requirements are validated by the E0P valk-through and provide input criteria to the control room survey procees.
Enhancements to the control room should be coordinated with other Supple-ment 1 elements such as E0Ps, RG-1.97, SPDS, and ERF.
RG-1.97 ELEMENT The EG-1.97 plan provides administrative guidance required to assess and document all aspects of RG-1.97 consideration. A complete set of design criteria is developed from the plan to form a basis for plant-specific instrument selection. Utilizing the design criteria, as well as the post-accident instrumentation requirements identified from the CRDR task analysis, a plant-specific list of accident monitoring instru-mentation, qualification criteria and locations is developed. The plant list also provides feedback to the control room survey and SPDS design basis. ERF design criteria provide additional input to the plant list.
Once the list is finalized in design, an iterative process occurs to consider changes associated with E0Ps, enhancements to the control room, SPDS design, and ERF design.
SPDS PLAN The SPDS plan describes the tasks that will provide a method for devel-oping, revising, assessing, and implementing the safety parameter display
- system decign bases and a method for documenting these ef forts. This plan is plant-specific, though it is developed with cognizance of current NRC and industry guidelines.
A-3
A plant-specific list of human factors criteria pertaining to the SPDS should be developed as a basis for developing and assessing plant-specific SPDS designs. This list of criteria may be developed in conjunction .with the human factors criteria required as input for the performance of a control room survey.
The E0Ps, as a result of the efforts performed by the NSSS owners groups and plant-specific considerations, specify the critical safety functions for a plant. The SPDS design bases should incorporate this information to allow the operator to use the SPDS.
The CRDR/SPDS design basis interface may be classified as one-way or two-way, depending upon the intended use of the SPDS: 1.e., the inter-
. face becomes two-way. if a utility intends to resolve control board HEDs by taking credit for the information displayed by the SPDS or incorpora-ting . additional information on the SPDS.
The ERF criteria /SPDS design bases interface is classified as one-way, i.e. , the SPDS design bases may be used as input in the ERF design criteria; however, the ERF design should have no direct effect on the SPDS.
The iteration interface is an ongoing process, as long as HEDs exist or design changes that could impact the SPDS are made to any of the other basic Supplement 1 to NUREG-0737 elements. A great deal of coordination is essential to determine modifications to the SPDS effectively, without creating additional discrepancies.
ERF PLAN The ERF plan consists of those tasks that describe a method for designing, implementing, and utilizing the emergency response facilities.
j The plan should be plant-specific and developed in cognizance of current NRC and industry guidelines. The following items should be considered in the development of an ERF plan:
- purpose of the TSC, EOF, and OSC
' - description of tasks
- source document availability
+
project personnel requirements and materials needed manpower requirements and restrictions
- description of the design documentation required
- desired date of completion and milestones
- schedule controlling factors t - interfaces with other Supplement 1 to NUREG-0737 elements A set of criteria that provides a basis for the design or upgrade of the technical support center (TSC), emergency operating facility (EOF) and operaticnal support center (OSC) need to be determined. The bases for this criteria should include 10 CFR 50.47,10 CFR 50, Appendix E, utility emergency plans, and guidance provided by nuclear industry organ-izations. Plant-specific criteria should include, but not be limited to, the following information:
A-4
r purpose loca tion required instrumentation (not required for OSC) habitability (not required for OSC) communications needs
- structural considerations (not required for OSC) size staffing needs Guidance produced by the ERC NUTAC should provide assistance in the dev-clopment of this criteria.
A set of criteria that provides a basis for identifying non-utility or utility of f-site interactions that have an impact on the emergency response facilities should be developed to provide the following:
interactions with state and local government communications required between plant and utility headquarters resources required from utility headquarters emergency capabilities supported by NSSS vendors, A/Es, and medical facilities non-utility personnel located in the ERF during emergency conditions.
A set of criteria that provides a basis for ensuring the integration of the TSC, OSC, EOF, and of f-site facilities should be developed.
The ERF criteria should be included in an iterative process with other elements of Supplement 1 to NUREG-0737. These include enhancements to the control room, plant-specific E0Ps, specific RG-1.97 application and SPDS design. This iterative process should continue until all of the elements associated with ERF criteria have been completed. A final set of criteria used to build or upgrade emergency response facilities should be developed, based on the proceeding considerations.
l l
l I
l l
l l
l t
l A-5 l
l t