Fourth Interim Rept Re Significant Const Deficiency 29, Concerning Inadequate Clearance Between Process Piping Sys & box-type Pipe Supports/Restraints.Initially Reported on 821015.Corrective Actions Completed.Final Rept by 830831
ML20072N257
Person / Time
Site: Waterford Entergy icon.png
Issue date: 07/11/1983
From: Drummond F
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
W3I83-0232, W3I83-232, NUDOCS 8307150261
Download: ML20072N257 (1)


Text

, --

LOUISIANA f 34a otanoNoe s1 ster POWE R & LiG HT/ P O BOX 6008 . NEW ORLEANS. LOUISIANA 70174 . l504) 366-2345

'$ EON dvs$i t

W3I83-0232 Q-3-A35.07.29 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 9 {'ci g a 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012 JUL I l 1983

SUBJECT:

Waterford SES Unit No. 3 ", '

Docket No. 50-382 J

Significant Construction Deficiency No. 29 u

" Inadequate Clearance Between Process Piping Systems and Box-Type Pipe Supports / Restraints" Fourth Interim Report

REFERENCE:

LP&L letter W3183-0073 dated October 15, 198

Dear Mr. Collins:

The above referenced letter indicated submittal of a Final Report no later than July 8, 1983. All corrective action has now been completed and LP&L review of the supporting documentation is underway.

A Final Report will therefore he submitted Ly August 31, 1983.

Vary trulf yours, F. J. Drummond Project Support Manager - Nuclear FJD/RWP/ DEB:keh cc: 1) Director 3) Mr. E. L. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555