MONTHYEARIR 05000275/20240032024-10-30030 October 2024 Integrated Inspection Report 05000275/2024003 and 05000323/2024003 and Independent Spent Fuel Storage Installation Report 07200026/2024001 IR 05000275/20240132024-10-28028 October 2024 – License Renewal Report 05000275/2024013 and 05000323/2024013 IR 05000275/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000275/2024404 and 05000323/2024404 IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 IR 05000275/20240012024-04-23023 April 2024 Integrated Inspection Report 05000275/2024001 and 05000323/2024001 IR 05000275/20244032024-03-12012 March 2024 Cyber Security Inspection Report 05000275/2024403 and 05000323/2024403 (Cover Letter) IR 05000275/20230062024-02-28028 February 2024 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2023006 and 05000323/2023006) IR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 IR 05000275/20240152023-10-10010 October 2023 – Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) IR 05000275/20234042023-10-0606 October 2023 NRC Security Inspection Report Report 05000275/2023404, 05000323/2023404 (Full Report) IR 05000275/20243012023-08-24024 August 2023 Notification of NRC Initial Operator Licensing Examination 05000275/2024301; 05000323/2024301 IR 05000275/20230052023-08-22022 August 2023 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2023005 and 05000323/2023005) - Mid Cycle Letter IR 05000275/20230022023-08-14014 August 2023 Quarterly Integrated Inspection Report 05000275/2023002 and 05000323/2023002- August 7, 2023 IR 05000275/20213012023-08-0909 August 2023 Errata for Diablo Canyon Power Plant, Units 1 and 2 - NRC Examination Report 050002752021301 and 050003232021301 IR 05000275/20234022023-08-0303 August 2023 NRC Security Inspection Report 05000275/2023402, and 05000323/2023402 IR 05000275/20233012023-07-25025 July 2023 NRC Initial Operator Licensing Examination Approval 05000275/2023301, 05000323/2023301 IR 05000275/20230102023-05-11011 May 2023 NRC Inspection Report 05000275 2023010 and 05000323 2023010 IR 05000275/20230012023-05-0909 May 2023 Integrated Inspection Report 05000275/2023001 and 05000323/2023001 IR 05000275/20234032023-03-10010 March 2023 NRC Security Baseline Inspection Report 05000275/2023403, 05000323/2023403 (Full Report) IR 05000275/20220062023-03-0101 March 2023 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2022006 and 05000323/2022006) IR 05000275/20220042023-02-0202 February 2023 Integrated Inspection Report 05000275/2022004 and 05000323/2022004 IR 05000275/20220102023-01-27027 January 2023 Biennial Problem Identification and Resolution Inspection Report 05000275/2022010 and 05000323/2022010 IR 05000275/20224022022-10-26026 October 2022 Security Baseline Inspection Report 05000275/2022402 and 05000323/ 2022402 IR 05000275/20220032022-10-24024 October 2022 Integrated Inspection Report 05000275/2022003 and 05000323/2022003 and Exercise of Enforcement Discretion IR 05000275/20220052022-08-23023 August 2022 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2022005 and 05000323/2022005) IR 05000275/20220022022-08-10010 August 2022 Integrated Inspection Report 05000275/2022002 and 05000323/2022002 IR 05000275/20220112022-08-0909 August 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000275/2022011 and 05000323/2022011 IR 05000275/20224012022-08-0303 August 2022 NRC Security Inspection Report 05000275/2022401, 05000323/2022401 ML22143A8812022-05-26026 May 2022 Revised Integrated Inspection Report 05000275/2022001 and 05000323/2022001 IR 05000275/20220012022-05-0505 May 2022 Integrated Inspection Report 05000275/2022001 and 05000323/2022001 ML22118A9362022-05-0505 May 2022 Integrated Inspection Report 05000275/2022001 and 05000323/2022001 IR 05000323/20214202022-03-31031 March 2022 Security Inspection Report 05000275 and 05000323/2021420 IR 05000275/20210062022-03-0202 March 2022 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2021006 and 05000323/2021006) IR 05000275/20210042022-02-0303 February 2022 Integrated Inspection Report 05000275/2021004 and 05000323/2021004 IR 05000275/20214042022-01-13013 January 2022 Public - Security Baseline Inspection Report 05000275/2021404 and 05000323/2021404 IR 05000275/20210032021-11-0303 November 2021 Integrated Inspection Report 05000275/2021003 and 05000323/2021003 IR 05000275/20210112021-09-10010 September 2021 Design Basis Assurance Inspection (Programs) Report 05000275/2021011 and 05000323/2021011 IR 05000275/20214052021-08-0505 August 2021 Security Baseline Inspection Report 05000275/2021405 and 05000323/2021405 IR 07200026/20214012021-08-0303 August 2021 Diablo Canon Nuclear Power Plant, Security Baseline Inspection Report 07200026/2021401 IR 05000275/20210022021-08-0202 August 2021 Integrated Inspection Report 05000275/2021002 and 05000323/2021002 IR 05000275/20210122021-07-28028 July 2021 Temporary Instruction 2515/194 Report 05000275/2021012 and 05000323/2021012 IR 05000275/20214012021-07-0101 July 2021 Security Baseline Inspection Report 05000275/2021401 and 05000323/2021401 IR 05000275/20210012021-05-0707 May 2021 DC IR 2021-001-drk, Diablo Canyon Power Plant Units 1 & 2 - Integrated Inspection Report 05000275/2021001, 05000323/2021001, & Independent Spent Fuel Storage Installation Inspection Report 07200026/2021001 2024-08-06
[Table view] Category:Letter
MONTHYEARML24302A1952024-11-0101 November 2024 Ltr to M. Olivas Tucker Ytt Re DCPP Dseis ML24302A1972024-11-0101 November 2024 Letter to V. Sage Walker Northern Chumash Tribal Council Re DCPP Dseis ML24302A1962024-11-0101 November 2024 Ltr to SLO County Chumash Indians Re DCPP Dseis ML24302A2612024-11-0101 November 2024 Letter to Achp Re DCPP Dseis ML24302A1942024-11-0101 November 2024 Ltr to K. Kahn Santa Ynez Band of Chumash Indians Re DCPP Dseis ML24302A1912024-11-0101 November 2024 Ltr to C. Mcdarment Tule River Tribe Re DCPP Dseis ML24302A2622024-11-0101 November 2024 Letter to CA SHPO Regarding DCPP Dseis ML24302A1932024-11-0101 November 2024 Letter to G. Pierce Salinan Tribe of Monterey, SLO Re DCPP Dseis ML24302A1922024-11-0101 November 2024 Ltr to G. Frausto Coastal Band of Chumash Indians Re DCPP Dseis IR 05000275/20240032024-10-30030 October 2024 Integrated Inspection Report 05000275/2024003 and 05000323/2024003 and Independent Spent Fuel Storage Installation Report 07200026/2024001 ML24275A0622024-10-30030 October 2024 NRC to NMFS Request Initiate Formal Endangered Species Act Consultation and Abbreviated Essential Fish Habitat for Proposed License Renewal of DCP Plant Units 1, 2 ML24269A0122024-10-29029 October 2024 OEDO-24-00083 2.206 Petition Diablo Canyon Seismic CDF - Response to Petitioner Letter ML24284A3122024-10-28028 October 2024 Ltr to P Ting, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants ML24284A3112024-10-28028 October 2024 Ltr to a Peck, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants IR 05000275/20240132024-10-28028 October 2024 – License Renewal Report 05000275/2024013 and 05000323/2024013 DCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 ML24261B9492024-10-24024 October 2024 Issuance of Amendment Nos. 246 and 248 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) IR 05000275/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000275/2024404 and 05000323/2024404 ML24277A0292024-10-18018 October 2024 NRC to Fws Req. for Concurrence W. Endangered Species Act Determinations for Diablo Canyon Power Plant Units 1,2, ISFSI Proposed License Renewals in San Luis Obispo Co., CA DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 ML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application 2024-09-09
[Table view] |
See also: IR 05000275/2019010
Text
March 11, 2019
Mr. James M. Welsch
Vice President Nuclear Generation
and Chief Nuclear Officer
Pacific Gas and Electric Company
Diablo Canyon Power Plant
P.O. Box 56, Mail Code 104/6
Avila Beach, CA 93424
SUBJECT: DIABLO CANYON POWER PLANT - NOTIFICATION OF NRC DESIGN BASES
ASSURANCE INSPECTION (TEAMS) (05000275/2019010 AND
05000323/2019010) AND INITIAL REQUEST FOR INFORMATION
Dear Mr. Welsch:
On May 21, 2019, the Nuclear Regulatory Commission (NRC) will begin a triennial baseline
component design bases inspection at the Diablo Canyon Power Plant. A six-person team will
perform this inspection using NRC Inspection Procedure 71111, Attachment 21M Design
Bases Assurance Inspection (Teams).
The inspection focuses on the maintenance of component design bases and modifications
made to structures, systems, and components. The samples reviewed during this inspection
will be identified during an information gathering visit. In addition, a number of operating
experience issues will also be selected for review during the in-office preparation week.
The inspection will include an information gathering site visit by the team leader and 2 weeks of
onsite inspection by the team. The inspection will consist of three NRC inspectors and two NRC
contractors, who will focus on engineering, and one NRC inspector that will focus on operations.
The current inspection schedule is as follows:
Onsite Information Gathering Visit: May 22, 2019
Preparation Week: June 3, 2019
Onsite Week: June 10-14 and June 24-28, 2019
The purpose of the information gathering visit is to meet with members of your staff to identify
potential risk-significant components and operator actions. The lead inspector will also request
a tour of the plant with members of your operations staff and probabilistic safety assessment
staff. During the onsite weeks, several days will be needed on the plant-referenced simulator in
J. Welsch 2
order to facilitate the development of operator action-based scenarios. Additional information
and documentation needed to support the inspection will be identified during the inspection,
including interviews with engineering managers, engineers, and probabilistic safety assessment
staff.
Our experience with these inspections has shown that they are extremely resource intensive,
both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact
on the site and to ensure a productive inspection, we have enclosed a request for information
needed for the inspection. The request has been divided into two groups. The first group lists
information necessary for the information gathering visit and for general preparation. This
information should be available to the regional office no later than May 21, 2019, unless
otherwise stated. If possible, this information should be provided electronically to the lead
inspector. Since the inspection will be concentrated on high risk/low margin components and
modifications, calculations associated with your list of high risk components and modifications
should be available to review during the information gathering visit to assist in our selection of
components based on available design margin.
The second group of documents requested lists information necessary to aid the inspection
team in tracking issues identified as a result of the inspection. It is requested that this
information be provided to the lead inspector as the information is generated during the
inspection. An additional request will be made by the team during the preparation week once
the specific components and modifications have been selected. Additional requests by
inspectors will also be made throughout the onsite weeks for specific documents needed to
complete the review. It is important that all of these documents are up-to-date and complete in
order to minimize the number of additional document requests during the preparation and/or
onsite portions of the inspection. In order to facilitate the inspection, we request that a contact
individual be assigned to each inspector to ensure information requests, questions, and
concerns are addressed in a timely manner.
The lead inspector for this inspection is Gerond A. George, Senior Reactor Inspector. We
understand that our licensing engineer contact for this inspection is Ms. A. Sorenson. If there
are any questions about the inspection or the requested materials, please contact the lead
inspector by telephone at 817-200-1562 or by e-mail at Gerond.George@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, control
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
J. Welsch 3
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for
Withholding.
Sincerely,
/RA/
Vincent G. Gaddy, Chief
Engineering Branch 1
Division of Reactor Safety
Docket Nos. 50-275, 50-323
License Nos. DPR-80, DPR-82
Enclosure:
Initial Request for Information
Design Bases Assurance Inspection (Teams)
Initial Request for Information
Design Bases Assurance Inspection (Teams)
Diablo Canyon Power Plant
Inspection Report: 05000275/2019010; 05000323/2019010
EPID ID: I-2019-010-0039
Information Gathering Date: May 22, 2019
Inspection Dates: June 10-14 and June 24-28, 2019
Inspection Procedure: IP 71111, Attachment 21M, Design Bases Assurance
Inspection (Teams)
Lead Inspector: Gerond A. George, Senior Reactor Inspector
I. Information Requested Prior to Information Gathering Visit (May 15, 2019)
The following information (Section I of this enclosure) should be sent to the Region IV
office in hard copy or electronic format (electronic database preferred), to the attention of
Gerond A. George, by May 15, 2019. The specific items selected from the lists shall be
available and ready for review on the day indicated in this request. *Please provide
requested documentation electronically in pdf files, Excel, or other searchable formats,
if possible. The information should contain descriptive names and be indexed and
hyperlinked to facilitate ease of use. Information in lists should contain enough
information to be easily understood by someone who has knowledge of pressurized
water reactor technology. If requested documents are large and only hard copy formats
are available, please inform the inspector and provide subject documentation during the
first day of the onsite inspection.
1. An Excel spreadsheet of equipment basic events (with definitions), including
importance measures sorted by risk achievement worth and Birnbaum from your
internal events probabilistic risk assessment. Include basic events with risk
achievement worth value of 1.3 or greater.
2. A list of the top 50 cut-sets from your PRA.
3. Copies of probabilistic risk assessment system notebooks and the latest
probabilistic risk assessment summary document.
4. An Excel spreadsheet of probabilistic risk assessment human action basic events or
risk ranking of operator actions from your site-specific PSA sorted by risk
achievement worth and Birnbaum. Provide copies of your human reliability
worksheets for these items.
Enclosure
5. If you have an external events or fire PSA model, provide the information requested
in items 1-4 for external events and fire.
6. Lists of permanent and temporary modifications performed in the past 5 years to
structures, systems, and components sorted by component identified in Item 1.
7. A list of high large early release frequency impact events and associated
components.
8. Structures, systems, and components in the Maintenance Rule (a)(1) category.
9. A list of high risk maintenance rule systems/components and functions; based on
engineering or expert panel judgment.
10. A copy of the Top Ten Issues list, if available.
11. Any pre-existing list of components and associated calculations with low design
margins.
12. A List of root cause evaluations associated with component failures or design issues
initiated/completed in the last 5 years.
13. A list of any common-cause failures of components in the last 3 years.
14. A list of operating experience evaluations for the last 3 years.
15. A list of all time-critical operator actions in procedures.
16. A list of current operator work arounds/burdens.
17. Procedures, including emergency and abnormal, used to accomplish operator
actions associated with the basic events credited in your PRA.
18. Electronic copies of quality assurance program manual, corrective action program,
and engineering design change procedures.
19. A copy of any internal/external self-assessments and associated corrective action
documents generated in preparation for this inspection.
20. A copy of engineering/operations-related audits completed in the last 2 years.
21. Electronic copies of the Technical Specifications, Technical Specifications Bases,
Technical Requirements Manual, and the Final Safety Analysis Report, as updated.
22. A copy of the Individual Plant Examination of External Events, if available
electronically.
23. One-line drawings of emergency core cooling systems, ultimate heat sink,
emergency safety features, and safety-related electrical systems.
24. A copy of plant systems equipment identifier key or procedure.
2
25. A copy of condition reports associated with inspection findings from the previous
NRC Inspection Procedure 71111.21 (or 71111.21 Attachment M inspection).
26. A list of licensee contacts for the inspection team with phone numbers.
27. A copy of the current management and engineering organizational charts.
II. Information Requested to be provided throughout the inspection.
1. Electronic copies of the design bases documents for selected components and
modifications.
2. Electronic copies of the system health notebooks for selected components and
modifications.
3. A list of the design calculations that provide the design margin information for
selected components. (Calculations for selected components should be available
during the information gathering visit.)
4. Calculations and drawings associated with selected components.
5. Documentation associated with modifications selected from Item I.6, this includes:
a. Post-modification testing, including performance characteristics affected,
assumptions, and acceptance criteria associated with modifications selected.
b. Updated maintenance and surveillance procedures associated with
modifications.
c. Updated operation, emergency, and abnormal procedures associated with
the modifications.
d. 10 CFR 50.59 applicability determination, screening, and safety evaluation.
6. Copies of any corrective action documents generated as a result of the teams
questions or queries during this inspection.
7. Copies of the list of questions submitted by the team members and the
status/resolution of the information requested (provide daily during the inspection to
each team member).
Inspector Contact Information: Mailing Address:
Gerond A. George U.S. NRC, Region IV
Senior Reactor Inspector Attn: Gerond A. George
817-200-1562 1600 East Lamar Blvd.
Gerond.George@nrc.gov Arlington, TX 76011-4511
3
ML19071A157
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: GAG Yes No Publicly Available Sensitive NRC-002
OFFICE SRI:EB1 C:EB1
NAME GGeorge VGaddy
SIGNATURE /RA/ /RA/
DATE 03/08/2019 3/11/2019