LER 88-024-00:on 880812,maint Surveillance Tests Verifying Nuclear Instrumentation Source Range Monitor Operability Not Performed Prior to Mode 6 Entry.Caused by Deficient Planning & Scheduling.Surveillance Tests scheduled.W/880913 Ltr
ML18005A592
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 09/13/1988
From: Corey Jeffries, Watson R
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
HO-880187-(O), LER-88-024, LER-88-24, NUDOCS 8809200147
Download: ML18005A592 (5)


Text

ACCESSION NBR:8809200147 DOC.DATE: 88/09/13 NOTARIZED: NO DOCKET FACXL:50-400 Shearon Harris Nuclear Power Plant, Unit 1, Carolina 05000400 AUTH. NAME AUTHOR AFFILIATION JEFFRIESPC. Carolina Power & Light Co.

WATONiR.A. Carolina Power & Light Co.

RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

LER 88-024-00:on 880812,entry into Mode 6 w/o performing TS surveillance requirements on source range detectors.

W/8 ltr.

DISTRIBUTION CODE: IE22D COPIES RECEIVED:LTR i ENCL TITLE: 50.73 Licensee Event Report (LER), Incident Rpt, etc.

J SIZE:

NOTES:Application for permit renewal filed. 05000400 RECIPIENT COPIES RECIPIENT COPIES XD CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD2-1 LA 1 1 PD2-1 PD 1 1 BUCKLEY,B 1 1 INTERNAL: ACRS MICHELSON 1 1 ACRS MOELLER 2 2 ACRS WYLIE 1 1 AEOD/DOA 1 1 AEOD/DSP/NAS 1 1 AEOD/DSP/ROAB 2 2 AEOD/DSP/TPAB 1 1 ARM/DCTS/DAB 1 1 DEDRO 1 1 NRR/DEST/ADS 7E 1 0 NRR/DEST/CEB 8H 1 1 NRR/DEST/ESB 8D 1 1 NRR/DEST/ICSB 7 1 1 NRR/DEST/MEB 9H 1 1 NRR/DEST/MTB 9H 1 1 NRR/DEST/PSB 8D 1 1 NRR/DEST/RSB 8E 1 1 NRR/DEST/SGB 8D 1 1 NRR/DLPQ/HFB 10 1 1 NRR/DLPQ/QAB 10 1 1 NRR/DOEA/EAB 11 1 1 NRR/DREP/RAB 10 1 1 NRR/DREP/RPB 10 2 2 R~/ SXB 9A 1 1 NUDOCS-ABSTRACT 1 1 WEG FILE 02 1 1 RES TELFORD,J 1 1 RES DSIR DEPY 1 1 RES/DSIR/EXB 1 1 RGN2 FILE 01 1 1 EXTERNAL: EG&G WILLIAMSPS 4 4 FORD BLDG HOYPA 1 1 H.ST LOBBY WARD 1 1 LPDR 1 1 NRC PDR 1 1 NSIC HARRISgJ 1 1 NSIC MAYS,G 1 1 TOTAL NUMBER OF COPIES REQUIRED: LTTR 46 ENCL 45

NRC Fevve 355 U.S. NUCLEAR REGULATORY COMMISSION (D4)31

'1 APPROVED 0MB NO, 31500104 LICENSEE EVENT REPORT ILER) EXPIRES: 5/31/SS FACILITY NAME (I) DOCKET NUMBER I2) PAGE 3 Shearon Harris Nuclear Power Plant Unit One 0 5 0 0 0 1 OF TITLE (4)

Entry Into Mode 6 Without Performing Technical Specification Surveillance Re u ements On Source Ran e Detectors EVENT'ATE (5) LER NUMBER (Sl REPOAT DATE (7) OTHER FACILITIES INVOLVED IS)

MONTH DAY YEAR YEAR SEOVENTIAL .Pyri REVISION MONTH OAY YEAR FAOLITY NAMES DOCKET NUMBER(5)

?Pm NUMBER NUMBER 0 5 0 0 0 0 8 1 2 8 8 8 8 024 0 0 1 3 8 8 THIS REPOAT IS SUBMITTED PURSUANT T0 THE REDUIREMENTs oF 10 cFR II: (check one otmtNr 0 5 0 0 0 OPERATING of thr follovflnfl (11)

MODE (D) 20.402(b) 20.405 (e) 50.734) 0) I iv) 73.71(h)

POWE R 20A05(e) (1)(ll 50M(e) (Il 50.73(el(2)(v) 73.71(e)

LEVEL (10) 0 20.405(e) (I I (5 I 50.35(el(2) 50.73(el(2)(vD) OTHER ISprclfy In Ahtttect P" hrlovventf In Trit, HRC Form

. Yg 20.405(e) (1)(ill) xvv~(Q'u 50.73(e) (2)(l) 50.73(e) 12) (vill)IA) 366AI 20.405(e) (I ) (hr) 50.73(el(2) (5) 50.73(el(2)(vlBI(B) oct 20.405(e) (1)(vl 50.73(e) l2)(ill) 50.73( ~ ) (2) (il LICENSEE CONTACT FOR THIS LER (12)

NAME TELEPHONE NUMBER AREA CODE Cathy Jeffries Specialist Regulatory Compliance 91 936 2- 2695 COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPOAT (13)

MANUFAC EPORTABLE MANUFAC EPORTABLE CAUSE SYSTEM COMPONENT TO NPRDS CAUSE SYSTEM COMPONENT TURER TURER TO NPAOS NMN SUPPLEMENTAL REPORT EXPECTED (14)

EXPECTED MONTH N&k OAY YEAR SUBMISSION DATE (15)

YES Ilfyrt, complete EXPECTED SUShtISSIOH OATEI NO ABsTRAcT ILlmlt to f400 tprcrt, I.r., rpptoilmrtrly fifteen tlnplrrpecr typrvvrfttrn Ilnrtf (ISI ABSTRACT The plant was at 0 percent power in Mode 5, Cold Shutdown, on August 12, 1988, with the Reactor Coolant System temperature at 100'F.

Technical Specification Surveillance Requirement (TS) 4.9.2.c requires an analog channel operational test be performed at least once peL seven days on each of two Source Range Neutron Flux Monitors (EIIS:IG) while in Mode 6. At 2259 hours0.0261 days <br />0.628 hours <br />0.00374 weeks <br />8.595495e-4 months <br />, the plant entered Mode 6, Refueling, when the reactor vessel head closure bolts were detensioned. Two Maintenance Surveillance Tests (MSTs) which verify operability of the Nuclear Instrumentation Source Range Monitors and are required to satisfy TS 4.9.2.c were not performed prior to entering O

O Mode 6, thereby, violating technical specification requirements. On August 15, 1988, the Maintenance Foreman and Operations Shift Foreman

~pL discussed the requirements for running these surveillance tests and agreed t OO N((3 they should have been performed prior to entry into Mode 6. By 1645 hours0.019 days <br />0.457 hours <br />0.00272 weeks <br />6.259225e-4 months <br />, mO both MSTs had been performed satisfactorily.

mQ The cause of the event was deficient planning and scheduling. These two Oa surveillance tests had been unscheduled while the plant was operating due to O4 the tests being Mode 6 requirements.

Ol o(x

~A Corrective action includes automatically scheduling all surveillance tests, 6)0 N regardless of mode requirement or frequency, and printing schedule dates for routine reports to ensure the requirements are visible to all personnel responsible for performing surveillance tests.

NAC Fotm 355 (DS3)

NRC Form 388A U.S. NUCLEAR AEOULATOAY COMMISSION 18831 LICENSEE EVENT REPORT ILER) TEXT CONTINUATION APPAOYEO OMB NO. 3150&l04 EXPIRES: 8/31/88 FACILITY NAME ljII DOCKET NUMBER 121 LEA NUMBER (8) PACE LS) aevrsloN Shearon Harris Nuclear Power Plant YEAR',o're r>

SEQUENT/AL NUMeea rrUMeea Unit One TEXT///~ AM' ~ UM ~//RC r 3/ISAB/IITI 0 5 0 0 0 OF DESCRIPTION The plant was at 0 percent power in Mode 5, Cold Shutdown, on August 12, 1988, with the Reactor Coolant System temperature at 100'F.

Technical Specification Surveillance Requirement (TS) 4.9.2.c requires an analog channel operational test be performed at least once per seven days on each of two Source Range Neutron Flux Monitors (EIIS:IG) while in Mode 6, Refueling. TS 4.0.4 prohibits entry into an operational mode unless the surveillance requirements associated with the Limiting Condition of Operation have been performed within the specified interval. or unless otherwise specified. Maintenance Surveillance Test (MST) -I0169, Nuclear Instrumentation Source Range N31 Operability Test, and MST-I0170, Nuclear Instrumentation Source Range N32 Operability Test, satisfy TS 4.9.2.c.

At 2259 hours0.0261 days <br />0.628 hours <br />0.00374 weeks <br />8.595495e-4 months <br />, the plant entered Mode 6, when the reactor vessel head closure bolts were detensioned. Surveillance tests, MST-I0169 and MST-I0170 had not been performed as required prior to entering Mode 6, violating TS 4.0;4. At 0730 hours0.00845 days <br />0.203 hours <br />0.00121 weeks <br />2.77765e-4 months <br /> on August 15, 1988, Regulatory Compliance personnel were conducting a review of Mode 6 surveillance requirements. It was then discovered that these weekly tests had not been performed and the Maintenance Foreman responsible for performing the test was notified. At 1330 hours0.0154 days <br />0.369 hours <br />0.0022 weeks <br />5.06065e-4 months <br />, the Maintenance Foreman and Operations Shift Foreman discussed the requirements for running these surveillance tests and agreed they should have been performed prior to entry into Mode 6. At 1600 hours0.0185 days <br />0.444 hours <br />0.00265 weeks <br />6.088e-4 months <br />, MST-I0169 was completed satisfactorily and at 1645 hours0.019 days <br />0.457 hours <br />0.00272 weeks <br />6.259225e-4 months <br />, MST-I0170 was completed satisfactorily.

CAUSE Surveillance tests with a frequency of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or .greater are automatically scheduled on the Surveillance Test Scheduling System. The surveillance procedure schedule is pr'nted for a routine report based on the frequency of the 'test, i.e., if the frequency is weekly, the test will print on the schedule every week. MST-I0169 and MST-I0170 did not schedule automatically because Regulatory Compliance had previously removed 'them from the schedule.

This was due to the tests being a Mode 6 requirement andrit was undesirable to have those tests print on schedule for the long term the plant was not in Mode

6. Since they did not print out automatically, it was not readily apparent that the tests needed to be performed.

ANALYSIS MST-I0050, Calibration of Nuclear Instrumentation System Source Range N31, had been performed satisfactorily in its entirety on August 7, 1988. This test satisfies the requirements of MST-I0169, therefore, source range monitor N31 was in compliance with the seven day requi.rement of TS 4.9.2.c when the plant entered Mode 6 on August 12, 1988. Source Range Monitor N32 had been tested r

NRC FORM See* o U.S OPO.1088 082e 538/e55 IB 831

NRC Form SSSA U.S. NUCLEAR REOULATORY COMMISSION (883(

LICENSEE EVENT REPORT ILER) TEXT CONTINUATION APPROVED OMS NO, 3(50&104 EXPIRES; 8/31/88 FACILITY NAME l(l DOCKET NUMSER (2) LER NUMBER (Sl PACE (3I yE*R,'; SEQI/SNTIAL pl'8 rlEVISION Shearon Harris Nuclear Power Plant NVMSS/I r'rr NI/Mefrl Unit One TEXT (// more Afeoe ie eerreirer/. ore ~ /YRC form 38SA'5/ (ul o s o o o 4 0 0 8 8 024 0 03oF 0 3 ANALYSIS (continued) on August 2, 1988, which is greater than seven days prior to entering Mode 6, thereby, making that monitor inoperable and putting the plant in TS Action Requirement 3.9.2.a. This action statement requires that all operations involving core alterations or positive reactivity changes be immediately suspended when one of the source ~ange monitors is inoperable. The plant was in compliance with this requirement as there were no core alterations or positive reactivity changes in process. No safety consequences resulted'rom this event. This event is reportable in accordance with 10 CFR 50.73(a)(2)(i)(B) as a noncompliance with TS 3.9.2.a and 4.0.4.

CORRECTIVE ACTION Surveillance tests with a frequency of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or greater, regardless of mode requirement, have been automatically scheduled on STSS and schedules will be printed for routine repoits to ensure the requirements are visible to Operations personnel, Regulatory Compliance personnel, Ma'intenance personnel, and others responsibLe for performing surv'eillance tests.

NRC FORM SSSA e U S GPO.(085 O.d24 538/455 (883 I

C~L Carolina Power & Light Company HARRIS NUCLEAR PROJECT P.O. Box 165 New Hill, NC 27562 SEpt s 889 File Number'SHF/10-13510C Letter Number'HO-880187 (0)

U.S. Nuclear Regulatory Commission ATTN: NRC Document Control Desk Washington, DC 20555 SHEARON HARRIS NUCLEAR POWER PLANT UNIT 1 DOCKET NO. 50-400 LICENSE NO. NPF-63 LICENSEE EVENT REPORT 88-024"00 Gentlemen'.

In accordance with Title 10 to the Code of Federal Regulations, the enclosed Licensee Event Report is submitted. This report fulfills the requirement for a written report within thirty (30) days of a reportable occurrence and is in accordance with the format set forth in NUREG-1022, September 1983.

Very truly yours, R. A. Watson Vice President Harris Nuclear Project RAW:tbb Enclosure cc.'Dr. J. Nelson Grace (NRC - RII)

Mr. B. Buckley (NRR)

Mr. W. H. Bradford (NRC SHNPP)

MEM/LER-88-024/1/Osl