Requests That Dc Sources - Operating Surveillance Requirements Be Reviewed & Issued Independent of Tech Spec Upgrade Review Effort,Per 860929 License Amend Application. Requirements More Consistent W/Mfg Recommendations
ML17342B061
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 12/22/1987
From: Woody C
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
L-87-494, NUDOCS 8712290398
Download: ML17342B061 (23)


Text

REGUL RY INFORMATION DISTRIBUTI SYSTEM (RIDS)

ACCESSION NBR: 87122'70398 DOC. DATE: 87/12/22 NOTARIZED: YES DOCKET 0 FACIL: 50-250 Turkey Point Planti Unit 3I Florida Power and Light C 05000250 50-251 Turkey Point Planti Unit 4I Florida Poujer and Light C 05000251 AUTH. NAME AUTHOR AFFILlATION WOODYI C. O. Florida Poeer h Light Co.

RECIP. NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk>

SUBJECT:

Application %or amends to Licenses DPR-31 5 DPR-41 i revising Tech Spec 4. 8. 2. 1 re DC sources operating surveil)ance requirements.

I DISTRIBUTION CODE: AOOID COPIES RECEIVED:LTR t ENCL ( SIZE: i4 TITLE: OR Submittal: General Distribution NOTES:

REC IP IENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD2-2 LA 0 PD2-2 PD 5 5 McDONALDI D 1 1 INTERNAL: ARM/DAF/LFMB 1 0 NRR/DEST/ADS 1 1 NRR/DEST/CEB 1 1 NRR/DEST/MTB 1 1 NRR/DEST/RSB 1 NRR/DOEA/TSB 1 1 NRR/PMAS/ILRB 1 OGC/HDS2 1 0 01 1 1 RES/DE/EIB 1 EXTERNAL'PDR ~

1 1 NRC PDR 1 1 NSIC 1 1 TOTAL NUMBER OF COPIES REQUIRED: LTTR 20 ENCL 17

0 I

P. X 14000, JUNO BEACH, FL 33408-0420 I ~

is~~<<a~~

L-87-494 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Gentlemen:

Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Proposed License Amendment D. C. Sources Surveillance Re irements By letter dated September 29, 1986 (FPL letter L-86-393)

Florida Power & Light Company (FPL) submitted a request to amend Appendix A of Facility Operating Licenses DPR-31 and DPR-41 to upgrade the current plant Technical Specifications and include, within limitations, the guidance of NUREG-0452, Standard Technical Specifications for Westinghouse Pressurized Water Reactors. FPL supplemented that, request by letter dated November 28, 1986 (FPL letter L-86-475), which provided proposed specifications and supporting documentation for the Electrical Power Systems.

FPL requests that you review and issue the D. C. Sources-Operating Surveillance Requirements (T.S. 4.8.2.1) independent of the Technical Specification Upgrade review effort. This specification reflects certain surveillance requirements for the station batteries that are more consistent with the manufacturer's recommendations, and consequently FPL would like to implement them as soon as possible. Changes were made to Technical Specification 4.8.2.1.f.(4) and Table 4.8-2 to address comments made during a preliminary review of the upgrade submittal by the NRC.

TCG/001 8712290398

  • DOCK OS0002SO 871222'PDR p PDR an FPL Group company

~I

~ ~

JI

U. S. Nuclear Regulatory Commission L-87-494 Page two The proposed specification reflecting the NRC comments and supporting documentation, are attached.

lf there are any questions, please call us.

Very truly yours, C. 0. Woo Executi ice President COW/TCG/gp Attachments cc: Dr. J. Nelson Grace, Regional Administrator, Region II, USNRC Senior Resident Inspector, USNRC, Turkey Point Plant Mr. Jacob Nash, Florida Dept. of Health and Rehabilitative Services TCG/001

STATE OF FLORlDA )

) ss.

COUNTY OF PALM BEACH )

~C.O.W d d dd d,d d That he is Executive Vice President of Florida Power & Light Company, the Licensee herein; That he has executed the foregoing document; that the statements made in this document are true and correct to the best of his knowledge, information, and belief, and that he is authorized to execute the document on behalf of said Licensee.

C. O. Wood of ~8 Subscribed and sworn to before me this

~day d 19~8

.'HOTAR-, PUBLIC, in and for the County I ',

-,of Palm Beach, State of Florida fo J d'g

'~

I, NOTARY PUBLIC STATE OF FLORIOA NY CONNISSION EXP ~ OCTd30y1991

'"'My.Commission expires: BONOEO TURU GENERAL INS. UNO,

, )

L 1

'c

TURKEY POINT UNITS 3 AND 4 PRO OSED LICENSE AMENDMENT TITLE: STATION BATTERY SURVEILLANCE DESCRIPTION:

Florida Power & Light Company (FPL) has replaced. the original station batteries (with lead-antimony cells) with Gould-GNB batteries (with lead-calcium cells). A review of the vendor's recommendations and preventative maintenance manual indicate that the existing Technical Specifications (TS) require modification. In addition, FPL previously committed to upgrade to the standard Westinghouse (Draft 5) TS when changes are made to the existing TS. Therefore the following changes have been made:

Pacae v The Table of Contents has been revised to reflect the changes discussed below.

Pa e 4.8-3 The surveillance requirements for the station batteries have

.been deleted in this section.

Pa es 4.8- 4.8-5 & Table,-4.8-2 The revised surveillances for the station batteries have been placed in this section. The following items have been added or deleted.

1) Table 4.8-2 has been added which lists battery parameters that must be verified by SURVEILLANCE REQUIREMENTS.
2) A SURVEILLANCE REQUIREMENT for battery terminal voltage verification once per 7 days has been added.
3) A SURVEILLANCE REQUIREMENT following battery discharge/overcharge or at least. quarterly has been added.
4) An annual SURVEILLANCE REQUIREMENT for verification of battery capacity when subjected to battery service test has been added.
5) An annual SURVEILLANCE REQUIREMENT for battery charger capacity verification has been added.

TCG/001

6) The requirement for a battery equalizing charge has been relaxed from a monthly basis to that required by Table 4.8-2. This is in accordance with the manufacturer's recommendations.
7) The requirement for a visual inspection of .each battery has been relaxed from once a month to require a visual check for corrosion at terminals or connectors every 92 days or after battery discharge below 105 volts or overcharge above 143 volts.

B 4.8-1 The basis for the Station Battery surveillance has been deleted from this section.

B 4.8-2 A new basis section has been added to describe the bases for the revised Station Battery surveillances.

TCG/001

Basis for No Significant Hazards Consideration Determination The standards used to arrive at a proposed determination that the changes described above involve no significant hazards consideration are included in 10 CFR 50.92. The regulations state that if operation of the facility in accordance with the proposed amendment would not: (1) involve a significant increase int he probability or consequences of an accident previously evaluated, or (2) create the possibility of a new or different kind of accident from any accident previously evaluated, or (3) involve a significant reduction in a margin of safety, then a no significant hazards determination can be made.

The Commission has provided guidance concerning the application of the standards for determining whether a significant hazards consideration exists by providing certain examples (48 FR 14870) of amendments that are considered not likely to involve a significant hazards consideration.

Example (i) relates to a purely administrative change to Technical Specifications: for example, a change to achieve consistency throughout the Technical Specifications, correction of an error, or a change in nomenclature. Example (ii) relates to a change that constitutes an additional limitation, restriction, or control not presently included in the Technical Specifications: for example, a more stringent surveillance requirement.

1) The proposed change as described in Item 4.8-2 is similar to example (i) of 48 FR 14870 in that an administrative change which consolidates current it is surveillance requirement into a technical specification format. consistent with the Standard Technical Specifications and does not involve technical or plant modifications.
2) The proposed changes as described in Items 4.8.2.1.b.a, 4.8.2.l.b.2, 4.8.2.1.c.1, 4.8.2.1.c.2, 4.8.2.1.d.1, 4.8.2.1.d.2, 4.8.2.1.d.3, 4.8.2.1.e, 4.8.2.1. f. 1i 4.8.2.1. f.2i 4.8.2 1. f.3i 4.8.2.1. f.4,

~

and 4.8.2.1.g. are similar to example (ii) of 48 FR 14870 in that they provide additional controls by:

Specifying the battery parameters and limits in added Table 4.8-2 that are verified by SURVEILLANCE'EQUIREMENTS.

Requiring a weekly terminal voltage surveillance.

Requiring special surveillance checks at least quarterly or after an unusual discharge or overcharge.

Requiring annual battery service and charger capacity tests.

TCG/001

3) The proposed change to relax the SURVEILLANCE REQUIREMENT for a monthly equalizing charge for each battery does not involve a significant hazards consideration because this change would not:

a) Involve a significant increase in the probability of 'or consequences of an accident previously evaluated.

The requirement for a monthly equalizing charge was for the original batteries which have been replaced by new lead calcium batteries. In accordance with the manufacturer's recommendations, the requirement for an equalizing charge has been changed from monthly to that required by Table 4.8-2 of the. revised technical specification which relates to measured battery parameters. This change in definition of a surveillance frequency would not increase the probability of an accident previously evaluated because the design and operation of the D. C. Systems are. otherwise unchanged.

b) Create the possibility of a new or different kind of accident from any previously analyzed because the proposed change introduces no new mode of plant operation nor involves a change in the design function of the batteries.

c) Involve a signif icant reduction in a margin of safety because the need for an equalizing charge in the battery is now related to the measured parameters of the battery in accordance with manufacturer's recommendations rather than calendar time.

4) The proposed change to relax the SURVEILLANCE REQUIREMENT for a monthly visual inspection does not involve a significant hazards consideration because the change would not:

a) Involve a significant, increase in the probability of or consequences of an accident previously evaluated. The current technical specifications did not provide a specific definition of what the monthly visual inspection was to include. The revised technical specifications require visual check for corrosion at terminals or connectors every 92 days or after battery discharge below 105 volts or overcharge TCG/001

h

<PE>>!e

above 140 volts. In addition the revised technical specification requires annual inspection to verify the cells, and battery racks show no visual indication of physical damage or abnormal deterioration. Any gross deterioration or malfunction could also be noted during daily and weekly surveillances required *by the revised technical specification.

inspections required 'y The visual the revised technical specification are consistent with industry practice in that these visual inspections are those required by the Standard Technical Specifications. Since the operation of the D. C. systems. are otherwise unchanged the change in visual

  • operation of the D. C. systems are otherwise unchanged the change in visual surveillance requirements as described would not involve a significant increase in the probability or consequences of an accident previously evaluated.

b) Create the possibility of a new or different kind of accident from any previously analyzed because the proposed change introduces no new mode of plant operation nor involve a change in the'lant design.

c) Involve a significant reduction in a margin of safety because the current, visual inspection without specific criteria is replaced by specific surveillance requirements, as described above, which are consistent with industry practice. In addition, the change in surveillance frequency or surveillance criteria does not impact the design function of the batteries during a postulated accident..

Based on the above considerations the changes included in the development of proposed Technical Specification 4.8.2.1 are considered not to involve a significant hazards consideration as defined in 10 CFR 50.92. Further, there is reasonable assurance that the health and safety of the public will not be endangered by the proposed changes.

TCG/001

ATTACHMENT TO: LICENSE AMENDMENT AMENDMENT NO. FACILITY-OPERATING LICENSE NO; DPR-31 AMENDMENT NO. FACILITY OPERATING LICENSE NO. DPR-41 DOCKET NO; 50-250 AND 50-251 Revise Appendix A as follows:

Remove Pa es Insert Pa es

4. 8-3 4.8-3 4.8-4 4.8-5 Table 4.8-2 B4. 8-1 B4. 8-1 B4.8-2

LIST OF TABLES Table Title Operational Modes 3.5-1 Instrument Operating Conditions for Reactor Trip 305-2 Engineering Safety Features Actuation 3.5-3 Instrument Operating Conditions for Isolation Functions 3.5-0 Engineered Safety Feature Set Points 3.5-5 Accident Monitoring Instrumentation 3.9-1 Radioactive Liquid Waste Sampling and Analysis Program 3.9-2 Radioactive Liquid Effluent Monitoring Instrumentation 3.9-3 Radioactive Gaseous Waste Sampling and Analysis Program 3.9-0 Radioactive Gaseous Effluent Monitoring Instrumentation 3.13-1 Deleted 3.10-1 Fire Detection System 3.10-2 Fire Hose Stations 3.16-1 Primary Coolant System Pressure Isolation Valves 3.17-1 Spent Fuel Burnup Requirements for Storage in Region II of the Spent Fuel Pit 3.18-1 Auxiliary Feedwater System Operability 0.1-1 Minimum Frequencies for Checks, Calibrations and Test of Instrument Channels 0.1-2 Minimum Frequencies for Equipment and Sampling Tests 0.1-3 Minimum Frequency for Surveillance of Radioactive Liquid Effluent Monitoring Instrumentation 0.1-0 Minimum Frequency for Surveillance of Radioactive Gaseous Effluent Monitoring Instrumentation 0.2-1 Deleted 0.2-2 Minimum Number of Steam Generators to be Inspected During Inservice Inspection 0.2-3 Steam Generator Tube Inspection 0.8-1 Diesel Generator Test Schedule 0.8-2 Battery Surveillance Requirements 0.12-1 Radiological Environmental Monitoring Program 0.12-2 Reporting Levels for Radioactivity Concentrations in Environmental Samples 0.12-3 Detection Capabilities for Environmental Sample Analysis 0.18-1 Minimum Frequencies for Safety Related Systems Flow Path Verification 6.2-1 Minimum Shift Crew Composition

-v- Amendment Nos. and

(a) Synchronize the diesel generator with offsite power while the generator is supplying emergency loads:

(b) Transfer the emergency load to offsite power; (c) Isolate the diesel generator; and (d) Return the diesel generator to standby status.

7. Verifying that auto-connected loads to each diesel generator do not exceed 2750 kw.

At least once per IO years or after any modification that could affect diesel generator independence, start both diesel generators simultaneously at a time when both reactors are shutdown and verify that both diesel generators provide 60 + 1.2 Hz frequency and 0160 + 620 volts in less than 15 seconds.

0.8-3 Amendment Nos.. and

'?I.8.2 STATION BATT S S.g.2.1 Each 125-volt battery bank and charger shall be demonstrated OPERABLE:

a. At least once per 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br /> read and record the pilot cell specific gravity. The specific gravity shall be within limits of Table 0.8-2 Category A.
b. At lease once per 7 days by verifying that:
1) The pilot cell parameters (except specific gravity) in Table 0.8-2 meet the Category A limits, and
2) The total battery terminal voltage is greater than or equal to 129 volts on float charge.
c. At least once per 31 days by performing the'ollowing:
1) Rotate the pilot cell, and
2) Check water level and restore as necessary recording amount of water added.

Amendment Nos. and

d. At least once per 92 days and within 7 days after a battery discharge with battery terminal voltage below 105 volts, or battery overcharge with battery terminal voltage above 143 volts, verify that:
1) The parameters in Table 4.8-2 meet the Category B limits,
2) There is no visible corrosion at either terminals or connectors,

,or the connection resistance of these items is less than 150 x 10-6 ohm, and

3) The average electrolyte temperature of every sixth cell is above 60 F.
e. At least once per 92 days perform a detailed visual inspection of the battery chargers.
f. At least once per 12 months by verifying that:
1) The cells, and battery racks show no visual indication of physical damage or abnormal deterioration,
2) The cell-to-cell and terminal connections are clean, tight, and coated=

with anticorrosion material.

3) The resistance of each cell-to-cell and terminal connection is less than or equal to 150 x 10-6 ohm, and
4) Each 50 kw battery charger will supply at least 390 2 10 amperes at 125 volts for at least 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> and each 37.5 kw battery charger will supply at least 290 k 10 amperes at 125 volts for at least 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.
g. At least once per 12 months by verifying that the battery capacity is adequate to supply and maintain in OPERABLE status all of the actual or simulated emergency loads for the design duty cycle when the battery is subjected to a battery service test.

4.8-5 Amendment Nos. and

TABLE 0.8-2 BATTERY SURVEILLANCE RE UIREMENTS CATEGORY A(1) CATEGORY B(2).

PARAMETER LIMITS FOR EACH LIMITS FOR EACH ALLOWABLE(3) designated pilot connected cell value for cell Connected Cell Electrolyte Greater than Greater than Above top of Level minimum level minimum level plates and no indication mark, indication mark, overflow and no overflow and no overflow Float Voltage Greater than Greater than Greater than or equal to or equal to or equal to 2.13 volts 2.13 volts (6) 2.07 volts Greater than Greater than Not more than or equal to or equal to 0.020 below the Specific 1.200<>> 1.195 average of all Gravity(<) connected cells Average of all Average of all connected cells connected cells greater than greater than or 1.205 equal tq 1.195(5>

TABLE NOTATIONS (1) For any Category A parameter(s) outside the limit(s) shown, the battery may be considered OPERABLE provided that within 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br /> all the Category B measurements are taken and found to be within their allowable values, and equalizing charge is started. All Category A and B parameter(s) must be restored to within limits within the next 6 days.

(2) For any Category B parameter(s) outside the limit(s) shown, the battery may be considered OPERABLE provided that the Category B parameters are within their allowable values, and equalizing charge is started. All Category B parameter(s) must be restored to within limits within 7 days.

(3) Any Category B parameter not within its allowable value indicates an inoperable battery.

(0) Corrected for electrolyte temperature and level.

(5) Or battery charging current is less than 2 amps when on charge.

(6) 'Corrected for average electrolyte temperature.

Amendment Nos. and

BO.S BASES FOR EME AGENCY POWER SYSTEM PERIODI TS The tests specified are designed to demonstrate that the diesel generators will provide power for operation of equipment. They also assure that the emergency generator system controls and the control systems for the safeguards equipment will function automatically in the event of a loss of normal power.

The testing frequency specified is often enough to identify and correct any

~

mechanical or electrical deficiency before it can result in a system failure. The fuel supply and starting circuits and controls are continuously monitored. Any faults are annunciated. An abnormal condition in these systems would be signaled without having to place the diesel generators themselves on test.

Each unit, as a backup to the normal standby AC power supply, is capable of sequentially starting and supplying the power requirement of the required safety feature equipment. Each will assume full load within 60 seconds after the initial starting signal.(1)(2)(3)

'he specified fuel supply will ensure power requirements for at least a week.

Reference:

(1) FSAR, Section 6.0.3 (2) FSAR, Section 8.2 (3) FSAR, Section 10.3.2 B0.8-1 Amendment Nos. and

80.8.2 BASES FOR SUR LLANCE RE UIREMENTS STATION BATTERIES Verifying average electrolyte temperature above the minimum for which the battery was sized, total battery terminal voltage on float charge, connection resistance values, and the performance of battery service discharge test ensures the effectiveness of the charging system, the ability to handle high discharge rates, and verifies the battery capability to supply its required load.

Table 0.8-2 specifies the normal limits for each designated pilot cell and each connected cell for electrolyte level, float voltage, and specific gravity. The limits for the designated pilot cells float voltage and specific gravity, greater than 2.13 volts and not more than 0.015 below the manufacturer's full charge specific gravity or a battery charger current that had stabilized at a low value, is characteristic of a charged cell with adequate capacity. The normal limits for each connected cell for float voltage and specific gravity, greater than 2.13 volts and not more than 0.020 below the manufacturer's full charge specific gravity with an average specific gravity of all the connected cells not more than 0.010 below the manufacturer's full charge specific gravity, ensures the OFERABILITYand capability of the battery.

Operation with a battery cells parameter outside the normal limit but within the allowable value specified in Table 0.8-2 is permitted for a period. During this period:

(1) the allowable values for electrolyte level ensures no physical damage to the plates with an adequate electron transfer capability; (2) the allowable value for the average specific gravity of all the cells, not more than 0.010 below the manufacturer's recommended full charge specific gravity, ensure that the decrease in rating will be less than the safety margin provided in sizing; (3) the allowable value-for an individual cells specific gravity, ensures that an individual cell's specific gravity will not be more than 0.030 below the manufacturer's full charge specific gravity and that the overall capability of the battery will be maintained within an acceptable limit; and (0) the allowable value for an individual cells float voltage, greater than 2.07 volts, ensures the battery's capability to perform its design function.

B0.8-2 Amendment Nos. and