Advises of Need to Evaluate NRC SER Impact Re Westinghouse Owners Group ATWS Mitigating Sys Actuation Circuitry Generic Design Program to Determine Best Logic.Implementation Schedule Will Be Submitted 90 Days After SER Issuance
ML17342A228
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 10/14/1985
From: Williams J
FLORIDA POWER & LIGHT CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
L-85-393, NUDOCS 8510180023
Download: ML17342A228 (4)


Text

REGULATO INFORMATION DISTRIBUTION ~TEM (RIDS)

ACCESSION NBR:8510180023 DOC ~ DATE: 85/10/14 NOTARIZED NO DOCKET FACIL:50 250 Turkey Point Plant'i Unit 3i Florida Power and Light C 05000250 50-251 Turkey Point Planti Unit 0i Florida Power and Light BYNAME C 05000251 AUTH AUTHOR AFFILIATION I'(ll LIAMSiJ+W. Florida Power 8 Light Co, RECIP ~ NAME RECIPIENT AFFILIATION DENTON<H.R. Office of Nuclear Reactor Regulationi Director

SUBJECT:

Advises of need to evaluate NRC SER impact re Nestinghouse Owners Group ATNS mitigating sys actuation circuitry generic design program to determine best logic ~ Implementation schedule will be submitted 90 days after SER issuance, DISTRIBUTION CODE: A055D COPIES RECEIVED:LTR 'NCL SIZE ~

TITLE: OR/Licensing Submittal: Salem AT}'IS Events GL~83-28 NOTES: 05000250 OL: 07/19/72 05000251 OL+ 04/14/73 RECIPIENT COPIES RECIPIENT COPIES ID'ODE/NAME LTTR ENCL ID CODE/NAME LTTR: ENCL NRR ORB1 I3C 01 INTERNAL: ACRS 6 ADM/LFMB ELD/HDSO 1 IE/DI IE/DQAVT 1 NRR/DE/FQB NRR/DE/MEB 1 NRR/DHFS/HFEB NRR/DHFS/LQB 1- NRR/DL DIR 1 NRR/DL/ORAB 1 1 NRR/DL/SSPB 1 NRR/DL/TAPMG 1 1 NRR/DS I/ASB 1 NRR/DSI/ICSB 2 PSB NRR/DSI/RSB 1 i REG F IL 04 1 RGN2 1 EXTERNAL: 24X i LPDR 03 NRC PDR 02' 1 NSIC 05 TOTAL NUMBER OF COPIES REQUIRED: LTTR 32 ENCL 0

ll II l

P.o. BOX 029100 MIAMI, F L 33102 yQIib~

J Ikv4<4%

FLORIDA POWER 8( LIGHT COMPANY tN' 4 1ees L-85-393 Office of Nuclear Reactor Regulation Attention: Mr. Harold R. Denton, Director Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Mr. Denton:

Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-25 I ATWS Im lementation Schedule On August 20, l 985 (L-85-308), FPL notified the NRC that a preliminary schedule had been developed for implementation of the modifications required under IO CFR 50.62 and that based on the schedules it would not be possible to implement the modifications by the Winter of I 986 for Turkey Point Unit 3, nor by the Winter of l987 for Turkey Point 'Unit 4 in accordance with IO CFR 50.62(d) requirements.

~ I FPL is a member of the Westinghouse Owners Group (WOG) and participating in the WOG AMSAC Generic Design Program.

The results of the WOG Program (WCAP-l0858 AMSAC Generic Design Package) were transmitted to the NRC for review and approval on July 25, I 985. WOG has recently indicated to FPL that the NRC Safety Evaluation Report (SER) is not planned to be issued until Mid-November.

FPL needs to evaluate the impact of the SER on each of the designs described in WCAP-l0858 in order to determine which logic is best suited for the Turkey Point Units and when it can be installed.

FPL will provide NRC the Turkey Point schedule to comply with the ATWS rule 90 days after the SER on WCAP-10858 is issued.

Very truly yours, J. W. Williams, Jr.

Group Vice President Nuclear Energy JWW/GRM/cab cc: Dr. J. Nelson Grace, Region II, USNRC 'to Harold F. Reis, Esquire GRMI /005/I ~

8510180023 8 PDR p ~ .'DR ADQCK 05000250 PEOPLE... SERVING PEOPLE