ML15173A450

From kanterella
Jump to navigation Jump to search
IR 05000298/2015007; on 04/06/2015 - 05/08/2015; Cooper Nuclear Station; Component Design Basis Inspection and Notice of Violation
ML15173A450
Person / Time
Site: Cooper Entergy icon.png
Issue date: 06/22/2015
From: Anton Vegel
Division of Reactor Safety IV
To: Limpias O
Nebraska Public Power District (NPPD)
References
EA-15-089 IR 2015007
Download: ML15173A450 (46)


See also: IR 05000298/2015007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD

ARLINGTON, TX 76011-4511

June 22, 2015

EA-15-089

Mr. Oscar A. Limpias

Vice President-Nuclear and CNO

Nebraska Public Power District

Cooper Nuclear Station

72676 648A Avenue

P.O. Box 98

Brownville, NE 68321

SUBJECT: COOPER NUCLEAR STATION - NRC COMPONENT DESIGN BASIS

INSPECTION REPORT NO. 05000298/2015007 AND NOTICE OF VIOLATION

Dear Mr. Limpias:

On May 8, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

the Cooper Nuclear Station. The NRC inspectors discussed the results of this inspection with

you and other members of your staff. Inspectors documented the results of this inspection in

the enclosed inspection report.

During this inspection, the NRC staff examined activities conducted under your license as they

relate to public health and safety to confirm compliance with the Commission's rules and

regulations and with the conditions of your license. Within these areas, the inspection consisted

of selected examination of procedures and representative records, observations of activities,

and interviews with personnel.

Based on the results of this inspection, the NRC has determined that a cited violation is

associated with this inspection. The violation is being cited because Cooper Nuclear Station

failed to restore compliance with NRC requirements within a reasonable time after a previous

violation was identified in NRC Inspection Report 05000298/2010007 (issued December 3,

2010). This is consistent with the NRC Enforcement Policy; Section 2.3.2.a, which states, in

part, that a cited violation will be considered if the licensee fails to restore compliance within a

reasonable time after a violation is identified.

You are required to respond to this letter and should follow the instructions specified in the

enclosed Notice when preparing your response. If you have additional information that you

believe the NRC should consider, you may provide it in your response to the Notice. The NRCs

review of your response to the Notice will also determine whether further enforcement action is

necessary to ensure compliance with regulatory requirements.

O. Limpias -2-

In addition, the NRC has determined that a Severity Level IV violation of NRC requirements

occurred. The NRC also identified two additional issues that were evaluated under the risk

significance determination process as having very low safety significance (Green). The NRC

has also determined that violations are associated with these issues. These violations are

being treated as non-cited violations (NCVs), consistent with Section 2.3.2.a of the NRC

Enforcement Policy. These NCVs are described in the subject inspection report.

If you contest the violations or significance of these NCVs, you should provide a response within

30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with

copies to: (1) the Regional Administrator, Region IV; (2) the Director, Office of Enforcement,

U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and (3) the NRC Senior

Resident Inspector at the Cooper Nuclear Station.

If you disagree with a cross-cutting aspect assignment or a finding not associated with a

regulatory requirement in this report, you should provide a response within 30 days of the date

of this inspection report, with the basis for your disagreement, to the Regional Administrator,

Region IV; and the NRC Senior Resident Inspector at the Cooper Nuclear Station.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosures, and your response, will be made available electronically for public inspection in the

NRC Public Document Room or from the NRC's Agencywide Documents Access and

Management System (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not

include any personal privacy or proprietary information so that it can be made available to the

public without redaction.

Sincerely,

/RA/

Anton Vegel, Director

Division of Reactor Safety

Docket No. 50-298

License No. DPR-46

Enclosures:

1. Notice of Violation

2. Inspection Report No. 05000298/2015007

w/Attachment: Supplemental Information

cc: Electronic Distribution

ML15173A450

x SUNSI Review ADAMS x Publicly Available x Non-Sensitive Keyword:

By: WCS x Yes No Non-Publicly Available Sensitive NRC-002

OFFICE SRI:EB1 RI:EB2 TTC SRI:EB1 BC:EB1 BC:DRP/C ACES D:DRS

NAME WSifre NOkonkwo EEmrich RLatta TFarnholtz GWarnick MHay AVegel

SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/ RVA for JMR for /RA/

DATE 6/17/15 6/17/15 6/16/15 6/17/15 6/19/15 6/17/15 6/17/15 6/22/15

Letter to Oscar A. Limpias from Anton Vegel, dated June 22, 2015

SUBJECT: COOPER NUCLEAR STATION - NRC COMPONENT DESIGN BASIS

INSPECTION REPORT NO. 05000298/2015007 AND NOTICE OF VIOLATION

Electronic distribution by RIV:

Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Acting Senior Resident Inspector (James.Nance@nrc.gov)

Branch Chief, DRP/C (Greg.Warnick@nrc.gov)

Senior Project Engineer (Ray.Azua@nrc.gov)

Project Engineer (Paul.Nizov@nrc.gov)

Project Engineer (Michael.Stafford@nrc.gov)

Administrative Assistant (Amy.Elam@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Siva.Lingam@nrc.gov)

Team Leader, DRS/TSST (Don.Allen@nrc.gov

ACES (R4Enforcement.Resource@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Michael.Waters@nrc.gov)

ROPreports

NOTICE OF VIOLATION

Nebraska Public Power District Docket No. 50-298

Cooper Nuclear Station License No. DPR-46

EA-15-089

During an NRC inspection conducted April 6 through May 8, 2015, a violation of NRC

requirements was identified. In accordance with the NRC Enforcement Policy, the violation is

listed below:

Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in part, that

measures shall be established to assure that applicable regulatory requirements and the

design basis, as defined in 10 CFR 50.2 and as specified in the license application, for

those components to which this appendix applies, are correctly translated into

specifications, drawings, procedures, and instructions.

Contrary to the above, since July 2010 the licensee failed to assure that applicable

regulatory requirements and the design basis were correctly translated into

specifications, drawings, procedures, and instructions. Specifically, the licensee failed to

correctly translate regulatory and design basis requirements associated with tornado and

high wind-generated missiles into design information necessary to protect the

emergency diesel generator fuel oil storage tank vent line components.

This violation is associated with a Green Significance Determination Process finding.

Pursuant to the provisions of 10 CFR 2.201, Nebraska Public Power District is hereby required

to submit a written statement or explanation to the U.S. Nuclear Regulatory Commission,

ATTN: Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional

Administrator, Region IV, and a copy to the NRC Senior Resident Inspector at the facility that is

the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of

Violation (Notice). This reply should be clearly marked as a "Reply to a Notice of Violation;

EA-15-089" and should include for each violation: (1) the reason for the violation, or, if

contested, the basis for disputing the violation or severity level, (2) the corrective steps that

have been taken and the results achieved, (3) the corrective steps that will be taken, and (4) the

date when full compliance will be achieved. Your response may reference or include previous

docketed correspondence if the correspondence adequately addresses the required response.

If an adequate reply is not received within the time specified in this Notice, an order or a

Demand for Information may be issued as to why the license should not be modified,

suspended, or revoked, or why such other action as may be proper should not be taken. Where

good cause is shown, consideration will be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis for your denial, to the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-0001.

Because your response will be made available electronically for public inspection in the NRC

Public Document Room or from the NRCs ADAMS, accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not include any

Enclosure 1

personal privacy, proprietary, or safeguards information so that it can be made available to the

public without redaction. If personal privacy or proprietary information is necessary to provide

an acceptable response, then please provide a bracketed copy of your response that identifies

the information that should be protected and a redacted copy of your response that deletes such

information. If you request withholding of such material, you must specifically identify the

portions of your response that you seek to have withheld and provide in detail the bases for your

claim of withholding (e.g., explain why the disclosure of information will create an unwarranted

invasion of personal privacy or provide the information required by 10 CFR 2.390(b) to support a

request for withholding confidential commercial or financial information). If safeguards

information is necessary to provide an acceptable response, please provide the level of

protection described in 10 CFR 73.21.

Dated this 22nd day of June 2015

-2- Enclosure 1

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 05000298

License: DPR-46

Report No.: 05000298/2015007

Licensee: Nebraska Public Power District

Facility: Cooper Nuclear Station

Location: P.O. Box 98

Brownville, NE 68321-0098

Dates: April 6 - May 8, 2015

Team Leader: W. Sifre, Senior Reactor Inspector, Engineering Branch 1

Inspectors: R. Latta, Senior Reactor Inspector, Engineering Branch 1

N. Okonkwo, Reactor Inspector, Engineering Branch 2

M. Emrich, Senior Reactor Technology Instructor, Technical Training

Center

Accompanying C. Barron, Contractor, Beckman and Associates

Personnel: S. Kobylarz, Contractor, Beckman and Associates

Approved By: Thomas R. Farnholtz

Branch Chief, Engineering Branch 1

Division of Reactor Safety

Enclosure 2

SUMMARY

IR 05000298/2015007; 04/06/2015 - 05/08/2015; Cooper Nuclear Station; Component Design

Basis Inspection.

The inspection activities described in this report were performed between April 6, 2015, and

May 8, 2015, by three inspectors from the NRCs Region IV office, one instructor from the

NRCs Technical Training Center, and two contractors. Four findings of very low safety

significance (Green) are documented in this report. Three of these findings involved violations

of NRC requirements and one of these violations was determined to be Severity Level IV under

the traditional enforcement process. The significance of inspection findings is indicated by their

color (Green, White, Yellow, or Red), which is determined using Inspection Manual

Chapter 0609, Significance Determination Process. Their cross-cutting aspects are

determined using Inspection Manual Chapter 0310, Aspects Within the Cross-Cutting Areas.

Violations of NRC requirements are dispositioned in accordance with the NRCs Enforcement

Policy. The NRCs program for overseeing the safe operation of commercial nuclear power

reactors is described in NUREG-1649, Reactor Oversight Process.

Cornerstone: Initiating Events

Criterion V, Instructions, Procedures, and Drawings, which states, in part, Activities

affecting quality shall be prescribed by documented procedures of a type appropriate to the

circumstances and shall be accomplished in accordance with these procedures.

Specifically, prior to April 6, 2015, the licensee failed to follow Procedure .05.OPS,

Operations Review of Condition Reports/Operability Determination, to ensure that an

operability review was performed for Condition Report CR-CNS-2015-01268, which was

initiated during the self-audit for the Component Design Bases Inspection to document that

Cooper Nuclear Station has under-voltage relays that could be affected by harmonics. In

response to this issue, the licensee performed an operability review and an operability

evaluation for the under-voltage relays. This finding was entered into the licensees

corrective action program as Condition Report CR-CNS-2015-02337.

The team determined that failure to perform an operability review associated with Condition

Report CR-CNS-2015-01268 was a performance deficiency. This finding was more than

minor because it was associated with the human performance attribute of the Initiating

Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of

events that upset plant stability and challenge critical safety functions during shutdown, as

well as power operations. Specifically, the licensee failed to perform the required operability

review for the identified condition. In accordance with Inspection Manual Chapter 0609,

Appendix A, The Significance Determination Process (SDP) for Findings At-Power, dated

June 19, 2012, Exhibit 1, Initiating Event Screening Questions, the issue screened as

having very low safety significance (Green) because the finding did not cause a reactor trip

and it did not involve the loss of mitigation equipment. This finding had a cross-cutting

aspect in the area of human performance associated with teamwork because individuals

and work groups failed to communicate and coordinate their activities across organizational

boundaries to ensure nuclear safety is maintained [H.4]. (Section 1R21.2.7)

-2-

Cornerstone: Mitigating Systems

Criterion III, Design Control, which states, in part, that design control measures shall

provide for verifying or checking the adequacy of design, such as by the performance of

design reviews, by the use of alternate or simplified calculational methods, or by the

performance of a suitable testing program. Specifically, prior to April 6, 2015, the licensee

failed to maintain procedure changes to periodically monitor and add nitrogen to fire

protection system headers in the reactor building to mitigate the effects of water hammer. In

response to this issue, the licensee determined that the fire protection system remained

functional without nitrogen based on empirical evidence suggesting that the system was

capable of absorbing the shockwave from a water hammer event. This finding was entered

into the licensees corrective action program as Condition Report CR-CNS-2015-02085.

The team determined that the failure to adequately maintain control of the fire protection

system design to prevent water hammer events was a performance deficiency. This finding

was more than minor because it was associated with the design control attribute of the

Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure

the availability, reliability, and capability of systems that respond to events to prevent

undesirable consequences. Specifically, the licensee failed to maintain procedure changes

to periodically monitor and add nitrogen to fire protection system headers in the reactor

building. In accordance with Inspection Manual Chapter 0609, Appendix A, The

Significance Determination Process (SDP) for Findings At-Power, dated June 19, 2012,

Exhibit 2, Mitigating Systems Screening Questions, the issue screened as having very low

safety significance (Green) because it was a design or qualification deficiency that did not

represent a loss of operability or functionality; did not represent an actual loss of safety

function of the system or train; did not result in the loss of one or more trains of

non-technical specification equipment; and did not screen as potentially risk-significant due

to seismic, flooding, or severe weather. The team determined that this finding did not have

a cross-cutting aspect because the most significant contributor did not reflect current

licensee performance. (Section 1R21.3.1)

10 CFR 50.71, Maintenance of Records, Making of Reports, Section (e), which states,

in part, each person licensed to operate a nuclear power reactor under the provisions of

10 CFR 50.21 or 10 CFR 50.22 shall update periodically the final safety analysis report

(FSAR) originally submitted as part of the application for the license, to assure that the

information included in the report contains the latest information developed. This submittal

shall contain all the changes necessary to reflect information and analyses submitted to the

Commission by the licensee since the submittal of the original FSAR, or as appropriate, the

last update to the FSAR under this section. Specifically, in January 2012 and February

2015, the licensee failed to update the Updated Safety Analysis Report for changes made to

their Anticipated Transient Without Scram analyses and plant conduct of operations

procedures. This finding was entered into the licensees corrective action program as

Condition Reports CR-CNS-2015-02106, CR-CNS-2015-02090, and CR-CNS-2015-02393.

The team determined that the failure to update the Final Safety Analysis Report to assure

that the information included in the report contains the latest information developed was a

-3-

performance deficiency. This finding was evaluated using traditional enforcement because

it had the potential for impacting the NRCs ability to perform its regulatory function. This

finding was more than minor because each example potentially rendered portions of the

safety analyses for Anticipated Transient Without Scram events described in the Updated

Safety Analysis Report less conservative or contradicted previous information regarding the

licensees flooding analysis contained in the Updated Safety Analysis Report. The

traditional enforcement violation was determined to be a Severity Level IV violation

consistent with the example in paragraph 6.1.d(3) of the NRC Enforcement Policy. Since

this was a traditional enforcement violation, no cross-cutting aspects were assigned per the

guidance contained in Inspection Manual Chapter 0612, Section 07.03(c). (Section 1R21.4)

Criterion III, Design Control, which states, in part, Design control measures shall

provide for verifying or checking the adequacy of design, such as by the performance of

design reviews, by the use of alternate or simplified calculational methods, or by the

performance of a suitable testing program. Specifically, since July 2010 the licensee

failed to verify the adequacy of design of the vents for the emergency diesel generator 1

and 2 fuel oil storage tanks to withstand impact from a tornado driven missile hazard, or to

evaluate for exemption from missile protection requirements using an approved

methodology. This finding was entered into the licensees corrective action program as

Condition Report CR-CNS-2015-02366.

The team determined that the failure to evaluate the lack of missile protection on the

emergency diesel generator 1 and 2 fuel storage tank vents was a performance deficiency.

This finding was more than minor because it was associated with the design control attribute

of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to

ensure the availability, reliability, and capability of systems that respond to events to prevent

undesirable consequences. Specifically, the licensee failed to evaluate a design

nonconformance on the emergency diesel generator 1 and 2 fuel storage tanks for lack of

missile protection. In accordance with Inspection Manual Chapter 0609, Appendix A, The

Significance Determination Process (SDP) for Findings At-Power, dated June 19, 2012,

Exhibit 2, Mitigating Systems Screening Questions, this finding screened as having very

low safety significance (Green) because it was a design or qualification deficiency that did

not represent a loss of operability or functionality; did not represent an actual loss of safety

function of the system or train; did not result in the loss of one or more trains of non-

technical specification equipment; and did not screen as potentially risk-significant due to

seismic, flooding, or severe weather. This finding had a cross-cutting aspect in the area of

human performance associated with conservative bias because individuals failed to use

decision making practices that emphasize prudent choices over those that are simply

allowable [H.14]. (Section 4OA2)

-4-

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

This inspection of component design bases verifies that plant components are

maintained within their design basis. Additionally, this inspection provides monitoring of

the capability of the selected components and operator actions to perform their design

basis functions. As plants age, modifications may alter or disable important design

features making the design bases difficult to determine or obsolete. The plant risk

assessment model assumes the capability of safety systems and components to perform

their intended safety function successfully. This inspectable area verifies aspects of the

Initiating Events, Mitigating Systems, and Barrier Integrity cornerstones for which there

are no indicators to measure performance.

1R21 Component Design Basis Inspection (71111.21)

.1 Overall Scope

To assess the ability of the Cooper Nuclear Station, equipment and operators to

perform their required safety functions, the team inspected risk-significant components

and the licensees responses to industry operating experience. The team selected

risk-significant components for review using information contained in the Cooper Nuclear

Station, probabilistic risk assessments and the U.S. Nuclear Regulatory Commissions

(NRC) standardized plant analysis risk model. In general, the selection process focused

on components that had a risk achievement worth factor greater than 1.3 or a risk

reduction worth factor greater than 1.005. The items selected included components in

both safety-related and nonsafety-related systems including pumps, circuit breakers,

heat exchangers, transformers, and valves. The team selected the risk-significant

operating experience to be inspected based on its collective past experience.

To verify that the selected components would function as required, the team reviewed

design basis assumptions, calculations, and procedures. In some instances, the team

performed calculations to independently verify the licensees conclusions. The team

also verified that the condition of the components was consistent with the design basis

and that the tested capabilities met the required criteria.

The team reviewed maintenance work records, corrective action documents, and

industry operating experience records to verify that licensee personnel considered

degraded conditions and their impact on the components. For selected components, the

team observed operators during simulator scenarios, as well as during simulated actions

in the plant.

The team performed a margin assessment and detailed review of the selected risk-

significant components to verify that the design basis have been correctly implemented

and maintained. This design margin assessment considered original design issues,

margin reductions because of modifications, and margin reductions identified as a result

-5-

of material condition issues. Equipment reliability issues were also considered in the

selection of components for detailed review. These included items such as failed

performance test results; significant corrective actions; repeated maintenance;

Title 10 CFR 50.65(a)1 status; operable, but degraded conditions; NRC resident

inspector input of problem equipment; system health reports; industry operating

experience; and licensee problem equipment lists. Consideration was also given to

the uniqueness and complexity of the design, operating experience, and the available

defense in-depth margins.

The inspection procedure requires a review of 15 to 25 total samples that include

risk-significant and low design margin components, components that affect the large

early release frequency (LERF), and operating experience issues. The sample selection

for this inspection was 16 components, 2 components that affect LERF, and 4 operating

experience items. The selected components and associated operating experience items

supported risk-significant functions including the following:

a. Electrical power to mitigation systems: The team selected several components in the

electrical power distribution systems to verify operability to supply alternating current (ac)

and direct current (dc) power to risk-significant and safety-related loads in support of

safety system operation in response to initiating events, such as loss of offsite power,

station blackout, and a loss of coolant accident with offsite power available. As such, the

team selected:

  • 125 Vdc Battery 1A
  • 125 Vdc Charger 1A
  • 125 Vdc Bus 1A
  • 480 Vac Safety-Related Motor Control Center K
  • 4160 Vac Safety-Related Switchgear 1F
  • Startup Station Service Transformer

b. Components that affect LERF: The team reviewed components required to perform

functions that mitigate or prevent an unmonitored release of radiation. The team

selected the following components:

  • Suppression Chamber Spray A Inboard Throttle Valve RHR-MOV-MO38A

c. Mitigating systems needed to attain safe shutdown: The team reviewed components

required to perform the safe shutdown of the plant. As such, the team selected:

-6-

.2 Results of Detailed Reviews for Components

.2.1 125 Vdc Battery 1A

a. Inspection Scope

The team reviewed the updated safety analysis report, design basis documents, the

current system health report, selected drawings and calculations, maintenance and test

procedures, and condition reports associated with 125 Vdc Battery 1A. The team also

performed walkdowns and conducted interviews with system engineering personnel to

ensure the capability of this component to perform its desired design basis function.

Specifically, the team reviewed:

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Calculations for electrical system load flow/voltage drop to verify that system

voltages remained within minimum acceptable limits.

  • Calculations to verify design loading, input assumptions, and environmental

parameters are appropriate and that the battery cell is sized to perform the

battery design basis function in accordance with the technical specifications.

  • Procedures for preventive maintenance, inspection, and testing to compare

maintenance practices against industry and vendor guidance.

  • Results of completed surveillance testing in accordance with technical

specifications.

b. Findings

No findings were identified.

.2.2 125 Vdc Charger 1A

a. Inspection Scope

The team reviewed the updated safety analysis report, design basis documents, the

current system health report, selected drawings and calculations, maintenance and test

procedures, and condition reports associated with 125 Vdc Charger 1A. The team also

performed walkdowns and conducted interviews with system engineering personnel to

ensure the capability of this component to perform its desired design basis function.

Specifically, the team reviewed:

-7-

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Calculations for sizing to verify that charger capacity supported design basis

requirements in accordance with technical specifications.

  • Calculations for the electrical protection to verify the charger protective devices

satisfied design basis requirements.

  • Procedures for preventive maintenance, inspection, and testing to verify vendor

guidance and design requirements were adequately incorporated.

  • Results of completed preventative maintenance and surveillance testing in

accordance with technical specifications.

b. Findings

No findings were identified.

.2.3 125 Vdc Bus 1A

a. Inspection Scope

The team reviewed the updated safety analysis report, design basis documents, the

current system health report, selected drawings and calculations, maintenance and test

procedures, and condition reports associated with 125 Vdc Bus 1A. The team also

performed walkdowns and conducted interviews with system engineering personnel to

ensure the capability of this component to perform its desired design basis function.

Specifically, the team reviewed:

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Calculations for electrical distribution, system load flow/voltage drop, short-circuit,

and electrical protection to verify that bus capacity and voltages remained within

minimum acceptable limits.

  • The protective device ratings to ensure adequate selective protection

coordination of connected equipment during worst-case short circuit conditions.

  • Procedures for preventive maintenance, inspection, and testing to verify vendor

guidance and design requirements were adequately incorporated.

b. Findings

No findings were identified.

-8-

.2.4 Standby Liquid Control Pump Motor Protection

a. Inspection Scope

The team reviewed the updated safety analysis report, design basis documents, the

current system health report, selected drawings and calculations, maintenance and test

procedures, and condition reports associated with the standby liquid control pump motor.

The team also performed walkdowns and conducted interviews with system engineering

personnel to ensure the capability of this component to perform its desired design basis

function. Specifically, the team reviewed:

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • The protective device ratings to ensure adequate motor circuit protection and

selective protection coordination of connected equipment during worst-case short

circuit conditions.

b. Findings

No findings were identified.

.2.5 Core Spray Pump Motor Protection

a. Inspection Scope

The team reviewed the updated safety analysis report, design basis documents, the

current system health report, selected drawings and calculations, maintenance and test

procedures, and condition reports associated with the core spray pump motor. The

team also performed walkdowns and conducted interviews with system engineering

personnel to ensure the capability of this component to perform its desired design basis

function. Specifically, the team reviewed:

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Calculations for electrical protection to verify adequate overcurrent relay settings

for motor circuit design basis requirements.

  • Protective relay test and calibration results to verify motor overcurrent relays

performed in accordance with acceptable setting tolerances.

b. Findings

No findings were identified.

-9-

.2.6 480 Vac Safety-Related Motor Control Center K

a. Inspection Scope

The team reviewed the updated safety analysis report, system description, design basis

documents, the current system health report, selected drawings and calculations,

maintenance and test procedures, and condition reports associated with 480 Vac Safety-

Related Motor Control Center K. The team also performed walkdowns and conducted

interviews with system engineering personnel to ensure the capability of this component

to perform its desired design basis function. Specifically, the team reviewed:

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Calculations for electrical distribution, system load flow/voltage drop, short-circuit,

and electrical protection to verify that bus capacity and voltages remained within

minimum acceptable limits.

  • The protective device settings and circuit breaker ratings to ensure adequate

selective protection coordination of connected equipment during worst-case short

circuit conditions.

  • Procedures for preventive maintenance, inspection, and testing to compare

maintenance practices against industry and vendor guidance; including the cable

aging management program.

  • Results of completed preventative maintenance on switchgear and breakers,

including breaker tracking.

b. Findings

No findings were identified.

.2.7 4160 Vac Safety-Related Switchgear 1F

a. Inspection Scope

The team reviewed the updated safety analysis report, system description, design basis

documents, the current system health report, selected drawings and calculations,

maintenance and test procedures, and condition reports associated with 4160 Vac

safety-related switchgear 1F. The team also performed walkdowns and conducted

interviews with system engineering personnel to ensure the capability of this component

to perform its desired design basis function. Specifically, the team reviewed:

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

- 10 -

  • Calculations for electrical distribution, system load flow/voltage drop, short-circuit,

cables routing, and electrical protection to verify that bus capacity and voltages

remained within acceptable limits.

  • The protective device settings and circuit breaker ratings to ensure adequate

selective protection coordination of connected equipment during worst-case short

circuit conditions.

  • Procedures for preventive maintenance, inspection, and testing to compare

maintenance practices against industry and vendor guidance; including the cable

aging management program.

  • Results of completed preventative maintenance on switchgear and breakers,

including breaker tracking.

b. Findings

Failure to Perform an Operability Review of a Condition Report

Introduction. The team identified a Green, non-cited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the licensees

failure to accomplish an operability review in accordance with Procedure .05.OPS,

Operations Review of Condition Reports/Operability Determination. Specifically,

the licensee failed to ensure that an operability review was performed for Condition

Report CR-CNS-2015-01268, which was initiated to investigate how plant equipment

is effected due to harmonics on under-voltage relays.

Description. The team performed a review of corrective actions associated with

4160 Vac safety-related switchgear 1F. Under-voltage relays (27-XX) are used

to monitor voltage levels (degraded or loss of voltage) in 4160 Vac switchgear.

Relay 27-1F2 is the under-voltage relay for 4160 Vac Switchgear 1F. In January 2015

Cooper Nuclear Station personnel performed a Component Design Basis Inspection

focused self-assessment in advance of the April 2015 NRC Component Design Basis

Inspection. During this assessment, it was found that the impact of harmonics on

under-voltage relays had not been considered in Calculation NEDC 88-086B,

Setpoint Determination of Second Level Under-Voltage Relays. Condition

Report CR-CNS-2015-01268 was then initiated to evaluate the impact of harmonics on

under-voltage relays. Harmonics are available on medium voltage switchgear through

breaker functions and rotating machinery. It is stated in the condition report that

Harmonics may affect when the undervoltage relays trip, causing the essential buses to

be shed earlier or not at all when it is desired.

In reviewing the corrective action specified in Condition Report CR-CNS-2015-01268,

the team determined that, though an operability review was stated to be required, none

had been performed. The licensee also concluded that the harmonics condition does

not affect installed plant equipment. The team questioned the validity of this conclusion

when no operability review was performed and it is known that the type of under-voltage

- 11 -

relays installed at Cooper Nuclear Station are susceptible to harmonic effect. In

response, the licensee initiated Condition Report CR-CNS-2015-02337 to document

the deficiency and perform the operability review in accordance with Procedure .05.OPS,

Operations Review of Condition Reports/Operability Determination. The result of

the operability review was to perform an operability evaluation in accordance with

Procedure 0.5.OPS to support a prompt operability determination.

Analysis. The team determined that failure to perform an operability review associated

with Condition Report CR-CNS-2015-01268 was a performance deficiency. This finding

was more than minor because it was associated with the human performance attribute of

the Initiating Events cornerstone and adversely affected the cornerstone objective to limit

the likelihood of events that upset plant stability and challenge critical safety functions

during shutdown, as well as power operations. Specifically, the licensee failed to

perform the required operability review for the identified condition. In accordance with

Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process

(SDP) for Findings At-Power, dated June 19, 2012, Exhibit 1, Initiating Event Screening

Questions, the issue screened as having very low safety significance (Green) because

the finding did not cause a reactor trip and it did not involve the loss of mitigation

equipment. This finding had a cross-cutting aspect in the area of human performance

associated with teamwork because individuals and work groups failed to communicate

and coordinate their activities across organizational boundaries to ensure nuclear safety

is maintained [H.4].

Enforcement. The team identified a Green, non-cited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, which states, in part,

Activities affecting quality shall be prescribed by documented procedures of a type

appropriate to the circumstances and shall be accomplished in accordance with these

procedures. Contrary to the above, prior to April 6, 2015, the licensee failed to ensure

that activities affecting quality as prescribed by documented procedures of a type

appropriate to the circumstances were accomplished in accordance with those

procedures. Specifically, the licensee failed to follow Procedure .05.OPS, Operations

Review of Condition Reports/Operability Determination, to ensure that an operability

review was performed for Condition Report CR-CNS-2015-01268, which was initiated

during the self-audit for the Component Design Bases Inspection to document that

Cooper Nuclear Station has under-voltage relays that could be affected by harmonics.

In response to this issue, the licensee performed an operability review and an operability

evaluation for the under-voltage relays. This finding was entered into the licensees

corrective action program as Condition Report CR-CNS-2015-02337. Because this

finding was of very low safety significance and has been entered into the licensees

corrective action program, this violation is being treated as a non-cited violation,

consistent with Section 2.3.2.a of the NRC Enforcement Policy:

NCV 05000298/2015007-01, Failure to Perform an Operability Review of a Condition

Report.

- 12 -

.2.8 Startup Station Service Transformer

a. Inspection Scope

The team reviewed the updated safety analysis report, system description, design basis

documents, the current system health report, selected drawings and calculations,

maintenance and test procedures, and condition reports associated with startup station

service transformer. The team also performed walkdowns and conducted interviews

with system engineering personnel to ensure the capability of this component to perform

its desired design basis function. Specifically, the team reviewed:

  • The design bases document and updated safety analysis report to verify design

bases requirement for the transformers.

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Calculations for electrical distribution, system load flow/voltage drop, short-circuit,

and electrical and mechanical protection to verify transformer loading and voltage

capacity limits.

  • The transformer protective device settings and tap changer settings to ensure

adequate selective protection coordination of connected equipment during worst-

case short circuit conditions.

  • Procedures for preventive maintenance, inspection, and testing to compare

maintenance practices against industry and vendor guidance; including the cable

and segregated bus aging management program.

  • Transformer dissolved gas analysis test reports to evaluate the result and trend

to ensure the health of the transformer oil and insulations.

b. Findings

No findings were identified.

.2.9 Main Steam Isolation Valve MS-AOV-AO80C

a. Inspection Scope

The team reviewed the updated safety analysis report, system description, design basis

documents, the current system health report, selected drawings and calculations,

maintenance and test procedures, and condition reports associated with main steam

isolation valve MS-AOV-AO80C. The team also conducted interviews with system

engineering personnel to ensure the capability of this component to perform its desired

design basis function. Specifically, the team reviewed:

- 13 -

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Valve stroke time and leakage test procedures, acceptance criteria, and recent

test results.

  • Evaluation of the impact of instrument air pressure, steam flow, and building

pressure on the valve closing time.

maximum allowable closing times.

b. Findings

No findings were identified.

.2.10 Suppression Chamber Spray A Inboard Throttle Valve RHR-MOV-MO38A

a. Inspection Scope

The team reviewed the updated safety analysis report, system description, design basis

documents, the current system health report, selected drawings and calculations,

maintenance and test procedures, and condition reports associated with suppression

chamber spray A inboard throttle valve RHR-MOV-MO38A. The team also performed

walkdowns and conducted interviews with system engineering personnel to ensure the

capability of this component to perform its desired design basis function. Specifically,

the team reviewed:

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Calculations for the required thrust to operate the motor-operated valve under the

most limiting conditions.

  • Motor-operated valve test procedures, acceptance criteria, and recent test

results.

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Calculations for motor-operated valve design basis operating conditions to verify

acceptable methodology for the selection of motor thermal overload protection.

unacceptable deterioration for the relays not bypassed during design basis

conditions.

- 14 -

b. Findings

No findings were identified.

.2.11 Core Spray Pump CS-P-A

a. Inspection Scope

The team reviewed the updated safety analysis report, system description, design basis

documents, the current system health report, selected drawings and calculations,

maintenance and test procedures, and condition reports associated with core spray

pump CS-P-A. The team also performed walkdowns and conducted interviews with

system engineering personnel to ensure the capability of this component to perform its

desired design basis function. Specifically, the team reviewed:

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Calculations for the required pump flow, head, minimum flow, and net positive

suction head under the most limiting conditions, including under and over-

frequency conditions.

  • Pump test procedures, acceptance criteria, and recent test results.

b. Findings

No findings were identified.

.2.12 Standby Liquid Control Pump SLC-P-A

a. Inspection Scope

The team reviewed the updated safety analysis report, system description, design basis

documents, the current system health report, selected drawings and calculations,

maintenance and test procedures, and condition reports associated with standby liquid

control pump SLC-P-A. The team also performed walkdowns and conducted interviews

with system engineering personnel to ensure the capability of this component to perform

its desired design basis function. Specifically, the team reviewed:

  • Component maintenance history and corrective action program reports to verify

the monitoring of potential degradation.

  • Calculations for the required pump flow, head, minimum flow, and net positive

suction head under the most limiting conditions, including postulated Anticipated

Transient Without Scram events.

- 15 -

  • Pump test procedures, acceptance criteria, and recent test results.

b. Findings

No findings were identified.

.2.13 Residual Heat Removal Heat Exchanger B

a. Inspection Scope

The team reviewed the updated safety analysis report, system description, the current

system health report, selected drawings, maintenance and test procedures, and

condition reports associated with residual heat removal heat exchanger B. The team

also performed walkdowns and conducted interviews with system engineering personnel

to ensure the capability of this component to perform its desired design basis function.

Specifically, the team reviewed:

  • Work orders and corrective action program documents for the last three years.
  • System design criteria and system health reports.
  • Corrective action program reports to verify the monitoring and correction of

potential degradation, operability evaluations, and apparent cause evaluations.

  • Piping and instrumentation diagrams.

b. Findings

No findings were identified.

.2.14 Residual Heat Removal Service Water Booster Pump 1C

a. Inspection Scope

The team reviewed the updated safety analysis report, system description, the current

system health report, selected drawings, maintenance and test procedures, and

condition reports associated with residual heat removal service water booster pump 1C.

The team also performed walkdowns, and conducted interviews with system engineering

personnel to ensure the capability of this component to perform its desired design basis

function. Specifically the team reviewed:

  • Past maintenance records for the last three years.
  • Surveillance test results, procedures and preventive maintenance work orders.

- 16 -

  • Associated condition reports for the past three years.
  • System design basis documents and system modifications.
  • Preventive maintenance procedures and completed maintenance work orders.

b. Findings

No findings were identified.

.2.15 Residual Heat Removal Heat Exchanger B Bypass Valve

a. Inspection Scope

The team reviewed the updated safety analysis report, system description, the current

system health report, selected drawings, maintenance and test procedures, and

condition reports associated with residual heat removal heat exchanger B bypass valve.

The team also performed walkdowns and conducted interviews with system engineering

personnel to ensure the capability of this component to perform its desired design basis

function. Specifically the team reviewed:

  • Vendor installation instructions.
  • Past maintenance records for the last three years.
  • Surveillance procedures and surveillance results.
  • Leak rate testing for last three years.
  • Associated condition reports for the past three years.

exchanger B bypass valve.

b. Findings

No findings were identified.

.2.16 Residual Heat Removal Service Water Motor Operated Valve 89B

a. Inspection Scope

The team reviewed the updated safety analysis report, design bases documents,

selected drawings, maintenance and test procedures, and condition reports associated

with motor-operated valve 89B. The team also performed system walkdowns and

conducted interviews with the system engineering personnel to ensure the capability of

- 17 -

this component to perform its desired design basis function. Specifically, the team

reviewed:

  • Technical specifications and basis documents.
  • Motor sizing data.
  • System design criteria and operating instructions.
  • Corrective action program documents and system health reports for the last three

years.

  • Piping and instrumentation diagrams.
  • Component surveillance test results and trend reports.
  • Maintenance records and operational history.

b. Findings

No findings were identified.

.3 Results of Reviews for Operating Experience

.3.1 Inspection of NRC Information Notice 98-31, Fire Protection System Design

Deficiencies and Common-Mode Flooding of Emergency Core Cooling System Rooms

at Washington Nuclear Project Unit 2

a. Inspection Scope

The team reviewed the licensees evaluation of Information Notice 98-31, Fire

Protection System Design Deficiencies and Common-Mode Flooding of Emergency

Core Cooling System Rooms at Washington Nuclear Project Unit 2, to verify the

licensee performed an applicability review and took corrective actions, if appropriate, to

address the concerns described in the information notice. This information notice

addressed the rupture of a fire protection system valve at WNP-2 station in 1998,

resulting in the flooding of emergency core cooling system rooms in the reactor building.

b. Findings

Failure to Adequately Maintain Design Modifications to Prevent Fire Protection System

Water Hammer

Introduction. The team identified a Green, non-cited violation of 10 CFR Part 50,

Appendix B, Criterion III, Design Control, for the licensees failure to adequately

maintain design modifications that were implemented to prevent fire protection system

water hammer events. Specifically, the licensee failed to maintain procedure changes to

- 18 -

periodically monitor and add nitrogen to fire protection system headers in the reactor

building.

Description. The inspectors reviewed Cooper Nuclear Stations evaluation of

NRC Information Notice 98-31, Fire Protection System Design Deficiencies and

Common-Mode Flooding of Emergency Core Cooling System Rooms at Washington

Nuclear Project Unit 2. This information notice addressed the rupture of a fire

protection system valve at WNP-2 station in 1998. At WNP-2, a water hammer event

resulted in the failure of a fire protection system valve in the reactor building and in the

flooding of two emergency core cooling system equipment rooms. In response to the

information notice, Cooper Nuclear Station implemented design change CED 1998-0060

to introduce nitrogen bubbles into three of the five fire protection risers in the reactor

building. The design change included revisions to station procedures to periodically

monitor and add nitrogen to the fire protection system headers. This design change was

based on calculation NEDC 00-097, which determined the forces associated with a

water hammer event would be significantly reduced by the addition of nitrogen. The

modification included procedure changes to periodically monitor and add nitrogen to the

headers.

In response to the inspectors questions, Cooper Nuclear Station personnel determined

that the requirement to monitor and add nitrogen to these fire protection risers was no

longer included in the plant procedures. They also determined that the technical basis

for removing this requirement had not been documented and that no design change was

initiated to implement this procedure change. Cooper Nuclear Station personnel initiated

Condition Report CR-CNS-2015-02085 during the inspection to address the issue. The

condition report recommended that the station either introduce nitrogen into the fire

protection risers in accordance with the previous revision of the plant procedure or

develop a technical basis for the removal of the nitrogen. The licensee determined that

the fire protection system remained functional without the nitrogen based on technical

input from Cooper Nuclear Station engineering personnel. This technical input was

partially based on calculation NEDC 00-097, which determined the maximum peak riser

pressure in the northwest corner of the reactor building and determined the peak force in

the fire protection piping system. The technical input also included a discussion of a

similar transient that occurred at Cooper Nuclear Station in 1995; this transient did not

result in a catastrophic water hammer or piping system damage. The technical input

determined that empirical evidence suggested that the system was capable of absorbing

the shockwave from a water hammer event.

Analysis. The team determined that the failure to adequately maintain control of the fire

protection system design to prevent water hammer events was a performance

deficiency. This finding was more than minor because it was associated with the design

control attribute of the Mitigating Systems cornerstone and adversely affected the

cornerstone objective to ensure the availability, reliability, and capability of systems that

respond to events to prevent undesirable consequences. Specifically, the licensee failed

to maintain procedure changes to periodically monitor and add nitrogen to fire protection

system headers in the reactor building. In accordance with Inspection Manual

Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings

At-Power, dated June 19, 2012, Exhibit 2, Mitigating Systems Screening Questions,

- 19 -

the issue screened as having very low safety significance (Green) because it was a

design or qualification deficiency that did not represent a loss of operability or

functionality; did not represent an actual loss of safety function of the system or train; did

not result in the loss of one or more trains of non-technical specification equipment; and

did not screen as potentially risk-significant due to seismic, flooding, or severe weather.

The team determined that this finding did not have a cross-cutting aspect because the

most significant contributor did not reflect current licensee performance.

Enforcement. The team identified a Green, non-cited violation of 10 CFR Part 50,

Appendix B, Criterion III, Design Control, which states, in part, that design control

measures shall provide for verifying or checking the adequacy of design, such as by the

performance of design reviews, by the use of alternate or simplified calculational

methods, or by the performance of a suitable testing program. Contrary to the above,

prior to April 6, 2015, the licensee failed to verify or check the adequacy of the fire

protection system to remain functional in the event of a water hammer event through

calculational methods or through a suitable testing program. Specifically, the licensee

failed to maintain procedure changes to periodically monitor and add nitrogen to fire

protection system headers in the reactor building to mitigate the effects of water

hammer. In response to this issue, the licensee determined that the fire protection

system remained functional without nitrogen based on empirical evidence suggesting

that the system was capable of absorbing the shockwave from a water hammer event.

This finding was entered into the licensees corrective action program as Condition

Report CR-CNS-2015-02085. Because this finding was of very low safety significance

and has been entered into the licensees corrective action program, this violation is

being treated as a non-cited violation consistent with Section 2.3.2.a of the NRC

Enforcement Policy: NCV 05000298/2015007-02, Failure to Adequately Maintain

Design Modifications to Prevent Fire Protection System Water Hammer.

.3.2 Inspection of NRC Information Notice 2013-017, Significant Plant Transient Induced by

Safety-Related Direct Current Bus Maintenance at Plant

a. Inspection Scope

The team reviewed the licensees evaluation of NRC Information Notice 2013-017,

Significant Plant Transient Induced by Safety-Related Direct Current Bus Maintenance

at Plant, to verify the licensee performed an applicability review and took corrective

actions, if appropriate, to address the concerns described in the information notice. This

information notice discusses significant plant transients induced by safety-related direct

current bus maintenance at the plant. The licensee documented the evaluation under

LO 2013-0088-032. The team verified that the licensees review adequately addressed

the issues in the information notice.

b. Findings

No findings were identified.

- 20 -

.3.3 Part 21 No. 2015-0014: Defect Identified in ABB K-Line Breaker Secondary Close

Latches (Part Number 716610K01)

a. Inspection Scope

The team reviewed the licensees evaluation of Part 21 No. 2015-0014: Defect

Identified in ABB K-Line Breaker Secondary Close Latches (Part Number 716610K01)

to verify the licensee performed applicability and vulnerability review of the defect

identified in ABB K-Line Breaker Secondary Close Latches (Part Number 716610K01).

The Operating Experience reviews were evaluated and documented by the licensee in

LO 2013-0087-075, LO 2014-0082-009, and LO 2014-0082-048. It was documented

that Cooper Nuclear Station does not use the ABB K-line circuit breakers in plant

systems. The team verified that the licensees review adequately addressed the issues

in the Part 21 report.

b. Findings

No findings were identified.

.3.4 Inspection of NRC Information Notice 2012-11, Age-Related Capacitor Degradation

a. Inspection Scope

The team reviewed the licensees evaluation of Information Notice 2012-11, Age-

Related Capacitor Degradation, to verify the licensee performed an applicability review

and took corrective actions, if appropriate, to address the concerns described in the

information notice. This information notice discusses age-related degradation of

capacitors that results from epoxy insulation hardening and cracking over time that

allows for a high flow of current and excessive heating. The team verified that the

licensees review adequately addressed the issues in the information notice.

b. Findings

No findings were identified.

.4 Results of Reviews for Operator Actions

a. Inspection Scope

The team selected risk-significant components and operator actions for review using

information contained in the licensees probabilistic risk assessment. This included

components and operator actions that had a risk achievement worth factor greater than

two or Birnbaum value greater than 1E-6.

For the review of operator actions, the team observed operators during simulator

scenarios associated with the selected components as well as observing simulated

actions in the plant.

- 21 -

The selected operator actions were:

reactor scram. A hydraulic Anticipated Transient Without Scram prevented the

reactor from being shut down. The operating crews were expected to enter

Emergency Operating Procedures 6A and 7A to control reactor pressure vessel

pressure and shut down the reactor using boron injection from the Standby

Liquid Control system. The operating crews were also expected to insert control

rods into the reactor per Procedure 5.8.3, Alternate Rod Insertion Methods.

This portion of the scenario specifically evaluated the licensees ability to

successfully initiate boron injection within 2 minutes as referenced in Updated

Safety Analysis Report XIV, Section 5.9.3.4.4.1 and Procedure 2.0.1.3, Time

Critical Operator Action Control and Maintenance.

  • Scenario 1, Part 2: As a result of the Anticipated Transient Without Scram

conditions described above, the operators were expected to take actions per

Emergency Operating Procedure 3A to mitigate adverse primary containment

parameters. Specifically, this portion of the scenario evaluated the licensees

ability to successfully place both loops of the residual heat removal system in

suppression pool cooling mode of operation within 30 minutes as referenced in

Procedure 2.0.1.3, Time Critical Operator Action Control and Maintenance.

designed to evaluate the licensees ability to perform subsequent actions for

ensuring emergency ventilation to essential equipment during a station blackout

event. Specifically, the job performance measure evaluated the ability of an

operator to open control room panel doors and 125V/250V dc switchgear room

doors in accordance with Procedure 5.3SBO, Station Blackout within

30 minutes as specified by 5.3SBO and Procedure 2.0.1.3, Time Critical

Operator Action Control and Maintenance.

designed to evaluate the licensees ability to perform actions to inject boron into

the reactor pressure vessel using the reactor core isolation cooling system in

accordance with Procedure 5.8.8, Alternate Boron Injection and Preparation.

b. Findings

Failure to Update the Final Safety Analysis Report

Introduction. The team identified three examples of a Severity Level IV, non-cited

violation of 10 CFR 50.71, Maintenance of Records, Making of Reports, for the

licensees failure to update the Final Safety Analysis Report originally submitted as part

of the application for the license to assure that the information included in the report

contains the latest information developed. Specifically, in April 2008, January 2012, and

February 2015 the licensee made changes to their operating procedures, Anticipated

- 22 -

Transient Without Scram analyses, and plant conduct of operations procedures that

were not subsequently reflected in their Updated Safety Analysis Report.

Description. The first example was identified on April 9, 2015, during the teams

review of the licensees time critical operator actions associated with Anticipated

Transient Without Scram events. In August 2014 the licensee identified that contrary

to Cooper Nuclear Station Procedure 2.0.1.3, Time Critical Operator Action Control

and Maintenance, the control room operators could not successfully place the residual

heat removal system in suppression pool cooling mode of operation during a

100 percent Anticipated Transient Without Scram event with main steam isolation valves

closed within the required 11 minutes (per Cooper Nuclear Station Updated Safety

Analysis Report Chapter XIV, Section 5.9.3.3.2.c). The licensee generated Condition

Report CR-CNS-2014-4453 requesting an engineering review of the time critical

operator action. As a result of the engineering review (ER 15-003, Revision 0, dated

February 4, 2015), the time critical operator action time for placing residual heat removal

in suppression pool cooling mode was changed to 30 minutes. The licensee did not

subsequently change Updated Safety Analysis Report, Chapter XIV, Section 5.9.3.3.2.c,

to reflect the new time critical operator action time to reflect the updated Anticipated

Transient Without Scram analysis that resulted from the engineering review. The

inspection team identified that the most recent Updated Safety Analysis Report was

submitted for approval on April 24, 2015, and covered changes to the Updated Safety

Analysis Report through the 24-month period ending March 10, 2015. The licensee

documented this issue in the corrective action program as Condition Report CR-CNS-

2015-02090.

The second example was identified on April 22, 2015, during the teams review of

the licensees time critical operator actions associated with Anticipated Transient Without

Scram events. In January 2012 the NRC issued Amendment No. 240 to Renewed

Facility Operating License No. DPR-46 for Cooper Nuclear Station, concerning changes

to the Technical Specification 3.4.3, Safety/Relief Valves and Safety Valves. As part of

the analyses submitted with the proposed amendment, Cooper Nuclear Station used

bounding Anticipated Transient Without Scram analysis values for safety/relief valve lift

setpoints of +3 percent of nominal lifting setpoint pressure. Cooper Nuclear Station

Updated Safety Analysis Report, Chapter XIV, Table XIV-5-4, was not updated to reflect

the +3 percent safety/relief valve lift setpoint pressure (the table displays nominal lift

setpoint pressures). The licensee documented this issue in the corrective action

program as Condition Report CR-CNS-2015-02393.

The third example was identified on April 10, 2015, during the teams review of the

internal flooding analysis and related Updated Safety Analysis Report section. The

Updated Safety Analysis Report, Section X-8.2.8.1, Flooding, stated that Two 3" service

water system lines provide an emergency cooling water source for the control room air

conditioner. There is normally no flow in these lines since they have normally closed

manually operated valves in the lines below the 903'6" passageway elevation.

Therefore, these lines pose no problems. However, a corrective action associated

with Condition Report CR-CNS-2007-07623 changed normal valve positions in

Procedure 2.2.76A. As a result, the service water lines were pressurized and were a

potential source of flooding. This change did not invalidate the results of the flooding

- 23 -

analysis, but the statement in the Updated Safety Analysis Report was not correct.

The licensee documented this issue in the corrective action program as Condition

Report CR-CNS-2015-02106.

Analysis. The team determined that the failure to update the Final Safety Analysis

Report to assure that the information included in the report contains the latest

information developed was a performance deficiency. This finding was evaluated using

traditional enforcement because it had the potential for impacting the NRCs ability to

perform its regulatory function. This finding was more than minor because each

example potentially rendered portions of the safety analyses for Anticipated Transient

Without Scram events described in the Updated Safety Analysis Report less

conservative or contradicted previous information regarding the licensees flooding

analysis contained in the Updated Safety Analysis Report. The traditional enforcement

violation was determined to be a Severity Level IV violation consistent with the example

in paragraph 6.1.d(3) of the NRC Enforcement Policy. Since this was a traditional

enforcement violation, no cross-cutting aspects were assigned per the guidance

contained in Inspection Manual Chapter 0612, Section 07.03(c).

Enforcement. The team identified three examples of a Severity Level IV, Green,

non-cited violation, of 10 CFR 50.71, Maintenance of Records, Making of Reports,

Section (e), which states, in part, each person licensed to operate a nuclear power

reactor under the provisions of 10 CFR 50.21 or 10 CFR 50.22 shall update periodically

the final safety analysis report (FSAR) originally submitted as part of the application for

the license, to assure that the information included in the report contains the latest

information developed. This submittal shall contain all the changes necessary to

reflect information and analyses submitted to the Commission by the licensee since the

submittal of the original FSAR, or as appropriate, the last update to the FSAR under this

section. Contrary to the above, in January 2012 and February 2015, the licensee failed

to update periodically the Final Safety Analysis Report (FSAR) to contain all the changes

necessary to reflect information and analysis since the last update to the Final Safety

Analysis Report. Specifically, the licensee failed to update the Updated Safety Analysis

Report for changes made to their Anticipated Transient Without Scram analyses and

plant conduct of operations procedures. This finding was entered into the licensees

corrective action program as Condition Reports CR-CNS-2015-02106,

CR-CNS-2015-02090, and CR-CNS-2015-02393. Because this finding was not

repetitive or willful and has been entered into the licensees corrective action program,

this Severity Level IV violation is being treated as a non-cited violation, consistent with

Section 2.3.2.a of the NRC Enforcement Policy: NCV 05000298/2015007-03, Failure to

Update the Final Safety Analysis Report (FSAR).

- 24 -

4. OTHER ACTIVITIES

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity

4OA2 Problem Identification and Resolution (71152)

Component Design Basis Review

a. Inspection Scope

The team reviewed condition reports associated with the selected components, operator

actions, and operating experience notifications. The team also reviewed corrective

actions associated with items identified in previous inspections. Specifically, the team

reviewed the updated safety analysis report, system description, design basis

documents, selected drawings, maintenance and test procedures, and condition reports

associated with the emergency diesel generator day and storage tank vents. The team

also performed walkdowns and conducted interviews with system engineering personnel

to ensure the capability of this component to perform the desired design function.

Specifically, the team reviewed:

  • Component maintenance history and corrective action program reports to

verify the monitoring of potential degradation.

  • Design basis adverse weather protection requirements.
  • Normal and alternate diesel fuel oil fill procedures.
  • Detailed plant drawings and operating, preventive maintenance, and testing

procedures.

b. Findings

Failure to Evaluate the Lack of Missile Protection on the Emergency Diesel Generator 1

and 2, Fuel Oil Storage Tank Vents

Introduction. The team identified a Green, cited violation of 10 CFR Part 50,

Appendix B, Criterion III, Design Control, for the licensees failure to evaluate the lack

of missile protection on the emergency diesel generator 1 and 2 fuel storage tank vents.

Description. The Cooper Nuclear Station Safety Evaluation Report (SER) and Updated

Safety Analysis Report states the following with regard to General Design Criteria and

the emergency diesel generators:

  • Updated Safety Analysis Report, Appendix F, states that the licensee complies

with Draft General Design Criteria GDC-2, published July 11, 1967, and the Draft

General Design Criteria GDC-2 requires that the systems and components

- 25 -

needed for accident mitigation remain fully functional before, during, and after a

tornado event.

  • Updated Safety Analysis Report, Chapter I-5, Section 5.2, defines Class I

structures and equipment as, Structures and equipment whose failure could

cause significant release of radioactivity or which are vital to a safe shutdown of

the plant and removal of decay and sensible heat.

  • Safety Evaluation Report, Section 3.5, states that Class I structures were

designed to withstand the effects of a spectrum of tornado generated missiles of

low level origin, including a 35 foot long utility pole with a 14 inch butt, with an

impact velocity of 200 miles per hour.

  • Updated Safety Analysis Report, Chapter XII-2, Section 2.1.2.3, specifically

identifies the Standby Diesel Generator System and Auxiliaries as Class I

equipment.

  • Updated Safety Analysis Report, Chapter XII, Section 2.3.3.2.1, states that

Class I structures are designed to provide protection against tornado generated

missiles.

On December 3, 2010, NRC Component Design Basis Inspection (CDBI)

Report 05000298/2010007 (ML103370640), documented Non-cited

Violation 05000298/2010007-04, Inadequate Design Control, for the licensees

failure to establish design control measures, involving the performance of a design

review, or the use of alternate or simplified calculational methods, or the performance

of a suitable testing program to verify that the emergency diesel generator fuel oil

storage and day tank vent lines were adequately protected from tornado generated

missiles. The licensee entered this deficiency into their corrective action program

as Condition Report CR-CNS-2010-05211 and generated Engineering

Evaluation (EE)10-060, Evaluation of the Diesel Generator Fuel Oil Tanks.

Subsequently, on February 13, 2014, NRC Inspection Report 05000298/2013005

(ML14044A105) documented Non-cited Violation 05000298/2013005-01, Failure to

Promptly Identify and Correct a Condition Adverse to Quality, for the licensees failure

to promptly identify and correct Non-cited violation 05000298/2010007-04, Inadequate

Design Control. Specifically, inspectors determined that Engineering

Evaluation EE 10-060 did not evaluate the vent lines with regard to their ability to

withstand tornado generated missiles. Instead, it assumed that if impacted by a missile,

there would be no damage to the fuel oil storage tank and discussed manual actions that

could be implemented if the vent lines were to be damaged by a tornado generated

missile. The licensee entered this deficiency into their corrective action program as

Condition Report CR-CNS-2014-00146.

In response to Non-cited Violation 05000298/201305-01, the licensee provided a reply

contained in a letter from Mr. O. Limpias to the NRC, dated May 20, 2014, which

disputed the use of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, as

- 26 -

the basis for the non-cited violation. As stated in this letter, the licensee denied that a

violation of NRC requirements had occurred, in that, the licensee had previously

evaluated this condition as documented in Condition Report CR-CNS-2010-05211,

which was initiated in response to a nonconforming condition identified during the

2010 Component Design Basis Inspection. The licensee also indicated that they had

re-evaluated these results and concluded the original evaluation remained valid.

Specifically, Engineering Evaluation EE 10-060, Evaluation of the Diesel Generator Fuel

Oil Tank Vents After a Tornado Strike, Revision 0, was performed to establish the basis

for conformance with the pre-General Design Criteria 2, contained in Appendix F, of the

Updated Safety Analysis Report.

In conclusion, the licensees violation denial letter stated that the previous NRC

Component Design Basis question related to the diesel generator fuel oil storage tank

vents ability to withstand a tornado missile strike was adequately resolved under

Condition Report CR-CNS-2010-05211 and appropriately evaluated in a timely manner

commensurate with 10 CFR 50, Appendix B, Criterion XVI.

Violation Denial Review

Consistent with the guidance provided in Policy Guide 0560-3, Region IV Enforcement

Procedures, the NRC staff performed an independent review of the documentation

associated with this finding. Based on the results of this review it was determined that

the requirements of the draft General Design Criteria, Criterion 2, clearly establish the

design function of systems and components of reactor facilities which are essential to

the prevention of accidents which could affect public health and safety or mitigation of

their consequences. These systems and components are required to be designed,

fabricated, and erected to performance standards that will enable the facility to

withstand, without loss of the capability to protect the public, the additional forces that

might be imposed by natural phenomena such as tornados. Furthermore, the system

design basis requirements contained in the Cooper Nuclear Station Updated Safety

Analysis Report, Chapter XII, Section 2.3.3.2.2, Tornado Generated Missiles, specifies

that all Class I structures are designed to provide protection against tornado generated

missiles including:

  • A 35-foot long utility pole with a 14-inch butt with an impact velocity of 200 miles

per hour.

  • A one-ton missile such as a compact-type automobile with an impact velocity of

100 miles per hour and a contact area of 25 square feet.

  • A two-inch extra heavy pipe, 12 feet long.
  • Any other missile resulting from failure of a structure or component or one which

has potential of being lifted from storage or working areas at the site.

Additionally, the Cooper Nuclear Station Design Basis for the Diesel Generator Fuel Oil

system includes the following requirements:

- 27 -

  • The standby diesel generator system must be capable of withstanding the most

severe conditions anticipated at the location of the plant. The design basis

events are described in IEEE-308-1970, Table I. This table includes postulated

earthquake, wind, hurricane, and tornado effects as natural phenomena design

basis. Additionally, Table I of IEEE-308-1973, lists accident-generated missiles

as one of the events that the emergency diesel system must be designed to

withstand.

  • The fuel oil subsystem must provide sufficient fuel to operate the standby diesel

generator under all postulated conditions.

  • The safety classification of the essential emergency diesel system including the

diesel fuel oil tank vents is Seismic Class I.

The NRC concluded that the diesel generator fuel oil storage tank Seismic Class I vents

were not assured to be designed, fabricated, and erected to withstand the additional

forces imposed by natural phenomena such as tornados, as required by the licensing

basis stated above. Specifically, the licensees evaluation performed in accordance

with Condition Report CR-CNS-2010-05211 and the associated Engineering

Evaluation EE-10-060 did not adequately demonstrate that the diesel generator fuel oil

storage tank vent lines would maintain its ability to withstand a postulated tornado

missile impact without loss of function. Although the evaluation references the location

of the vents, the area of exposure of the vents to missile impact, and generally discusses

the material composition of the vents and the inferred minimal load transferred to the

diesel generator fuel oil storage tanks, no definitive analytical basis was identified for

concluding that the vent lines would not be damaged by the postulated tornado

generated missile and they would remain functional. While the licensees compensatory

actions dealt with the initial operability condition, the requisite corrective and preventive

measures failed to address the nonconforming design condition, concerning the diesel

generator fuel oil storage tank vents tornado missile protection, initially identified as a

performance deficiency in NRC Component Design Basis Inspection

Report 05000298/2010007.

Based on these reviews, it was concluded that the finding and non-cited violation for

failing to assure that an identified condition adverse to quality was promptly corrected to

meet the requirements in 10 CFR Part 50, Appendix B, Criterion XVI, as documented in

NRC Inspection Report 05000298/2013005, were valid. The failure to perform a proper

engineering evaluation of the diesel generator fuel oil storage tank vents to demonstrate

the ability to perform its specified safety function as required by the licensing bases in

the event of a tornado generated missile has not been documented.

Current Evaluation Results

During the performance of the 2015 Component Design Basis Inspection, the team met

with the licensees engineering and licensing staff to establish the current status of the

diesel generator fuel oil storage tank vents. As a result of these discussions, it was

determined that calculation NEDC 13-046, Diesel Generator Storage Tank Vent Line

- 28 -

Tornado Missile Durability, had been developed to demonstrate that the current design

was acceptable without further action. Specifically, this calculation evaluated the ability

of the diesel generator fuel oil storage tank vents to remain operable following an impact

from design basis tornado generated missiles. As described in NEDC 13-046, the diesel

generator fuel oil storage tank vent lines are part of the fuel oil subsystem of the

emergency diesel generator system. Each component of this system is classified as

Seismic Class 1S. As described in the Updated Safety Analysis Report, Class I

structures are designed to provide protection against tornado generated missiles. The

calculation determines the maximum deflection the vent line can experience without

permanent deformation, the amount of deflection the vent line can experience without

fracture and the amount of force that would be required to fracture the vent line. Forces

from the three Updated Safety Analysis Report specified tornado generated missiles

were determined for comparison to the maximum allowable force the vent line can

withstand. Specifically, using the worst case tornado generated missile, the calculation

concluded that Due to the overwhelming magnitude of the force and the very short

duration of the impact, the vent pipes will shear off or fracture rather than bend and

crimp.

Based on the review of NEDC 13-046, the team determined that the calculation did not

provide an adequate design analysis that would assure that the diesel generator fuel oil

vent lines could maintain an open vent path during a postulated tornado event under all

missile scenarios. Specifically, the calculation failed to provide a bounding analysis that

demonstrated the vent lines would not crimp subsequent to a tornado generated missile

strike from a range of objects which has potential of being lifted from storage or

working areas at the site.

Analysis. The team determined that the failure to evaluate the lack of missile protection

on the emergency diesel generator 1 and 2 fuel storage tank vents was a performance

deficiency. This finding was more than minor because it was associated with the design

control attribute of the Mitigating Systems cornerstone and adversely affected the

cornerstone objective to ensure the availability, reliability, and capability of systems that

respond to events to prevent undesirable consequences. Specifically, the licensee failed

to evaluate a design nonconformance on the emergency diesel generator 1 and 2 fuel

storage tanks for lack of missile protection. In accordance with Inspection Manual

Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings

At-Power, dated June 19, 2012, Exhibit 2, Mitigating Systems Screening Questions,

this finding screened as having very low safety significance (Green) because it was a

design or qualification deficiency that did not represent a loss of operability or

functionality; did not represent an actual loss of safety function of the system or train; did

not result in the loss of one or more trains of non-technical specification equipment; and

did not screen as potentially risk-significant due to seismic, flooding, or severe weather.

This finding had a cross-cutting aspect in the area of human performance associated

with conservative bias because individuals failed to use decision making practices that

emphasize prudent choices over those that are simply allowable [H.14].

Enforcement. The team identified a Green, cited violation of 10 CFR Part 50,

Appendix B, Criterion III, Design Control, which states, in part, Design control

measures shall provide for verifying or checking the adequacy of design, such as by the

- 29 -

performance of design reviews, by the use of alternate or simplified calculational

methods, or by the performance of a suitable testing program. Contrary to the above,

since July 2010, the licensee failed to verify the adequacy of the applicable design

control measures. Specifically, the licensee failed to verify the adequacy of design of the

vents for the emergency diesel generator 1 and 2 fuel oil storage tanks to withstand

impact from a tornado driven missile hazard, or to evaluate for exemption from missile

protection requirements using an approved methodology. This finding was entered into

the licensees corrective action program as Condition Report CR-CNS-2015-02366.

VIO 05000298/2015007-04, Failure to Evaluate the Lack of Missile Protection on the

Emergency Diesel Generator 1 and 2 Fuel Oil Storage Tank Vents.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On May 8, 2015, the inspectors presented the inspection results to Mr. O. Limpias,

Vice President-Nuclear and Chief Nuclear Officer, and other members of the licensee

staff. The licensee acknowledged the issues presented. The licensee confirmed that

any proprietary information reviewed by the inspectors had been returned or destroyed.

- 30 -

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

A. Able, Instrumentation and Controls Supervisor, Design Engineering

T. Barker, Manager, Engineering Programs and Components

M. Bergmeier, Operations

D. Buman, Director, Engineering

T. Chard, Manager, Quality Assurance

L. Dewhirst, Manager, Corrective Actions and Assessment

K. Dia, Manager, Systems Engineering

M. Dickerson, Electrical Engineer, Design Engineering

L. DuBois, Emergency Preparedness

J. Ehlers, Electrical/Instrumentation and Controls Supervisor, System Engineering

R. Estrada, Manager, Design Engineering

J. Flaherty, Senior Staff Engineer, Licensing

G. Gardener, Supervisor, NSSS

D. Goochman, Manager, Operations

K. Higginbotham, General Manager, Plant Operations

D. Kimball, Director, Nuclear Oversight

O. Limpias, Senior Vice President, Nuclear, and Chief Nuclear Officer

E. Nelson, Supervisor, Emergency Preparedness

T. Ocken, Supervisor, Design Engineering

C. Pelchat, Manager, Projects

R. Penfield, Director, Nuclear Safety Assurance

J. Shaw, Manager, Licensing

J. Stough, Manager, Information Technology

C. Sunderman, Manager, Radiation Protection

K. Tom, Assistant to the Director, Engineering

A. Walters, Manager, Chemistry

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000298/2015007-04 VIO Failure to Evaluate the Lack of Missile Protection on the

Emergency Diesel Generator 1 and 2 Fuel Oil Storage Tank

Vents (Section 1R21.4OA2)

Opened and Closed

Failure to Perform an Operability Review of a Condition Report

05000298/2015007-01 NCV

(Section 1R21.2.7)

Failure to Adequately Maintain Design Modifications to Prevent

05000298/2015007-02 NCV

Fire Protection System Water Hammer (Section 1R21.3.1)

Failure to Update the Final Safety Analysis Report (FSAR)05000298/2015007-03 NCV

(Section 1R21.4)

Attachment

LIST OF DOCUMENTS REVIEWED

Calculations

Number Title Revision

NEDC 84-050GH Cable Tray Fill Calculation, Tray C35A, Section 134 1

NEDC 84-050GJ Cable Tray Fill Calculation Tray C35A, Section 136 1

NEDC 87-047K Motor Control Center K Load Summary 3

NEDC-86-105B 4160 Volt Switchgear Critical Bus 1F 10

B&R Calculation Cable Sizing Main Motors & Feeders Cable 1

2.05.01

B&R Calculation Cable Sizing summary - 4160 V Motors & Feeders 1

2.05.02

NEDC 91-190 Cable Withstand Evaluation 3

NEDC 00-003 Cooper Nuclear Station Auxiliary Power System Load Flow 8

and Voltage Analysis

NEDC-08-044 Assessment of SSST with Loss of Fan Cooling for PRA 0

NEDC 87-153 SLC Capacity 0

NEDC 87-158 NPSH Calculation for SLC Pumps 0

NEDC 87-167 SLC Operating Pressure with Two Pumps 2

NEDC 88-190 Essential Pump Minimum Flow 0

NEDC 88-286 MSIV Accumulator Capacity Evaluation 0

NEDC 89-1886 CNS Station Blackout (SBO) Condensate Inventory 3

NEDC 91-185 MOV Thermal Overload Heater Sizing 6

NEDC 92-015 SLC Pump NPSH 1

NEDC 93-125 Stem Nut Wear Evaluation 0

NEDC 94-142 Core Spray Flows with Minimum Flow Bypass (MFB) Valve 5

Open

NEDC 94-190 Core Spray Pump Miniflow Analysis 0

NEDC 95-003 Determination of Allowable Operating Parameters for CNS 29

MOV Program MOVs

NEDC 96-030 SLC Vortex Limit 0

NEDC 97-044A NPSH Margins for the RHR and CS Pumps 4

NEDC 97-071 Design Report RAL-1030 Spherical Disk Piston-Flite flow 0

Main Steam Isolation Valve

A-2

Calculations

Number Title Revision

NEDC 00-041 Limiting Component Analysis for Containment Spray Motor- 2

Operated Valves

NEDC 00-042 AC MOV Program MOVs 2

NEDC 00-047 Determination of Allowable Operating Parameters for RHR- 0

MOV-MO38A and RHR-MOV-MO38B

NEDC 00-080 Flood Door Gap Analysis 1

NEDC 00-110 MOV Program Valve Margin Determination 8

NEDC 01-064 8-hour ECST Volume Requirements for an Isolated Reactor 2

NEDC 01-072 ECCS Pump NPSH/ Vortex Limit with Suction from CST 1

NEDC 09-102 Internal Flooding - HELB, MELB, and Feedwater Line Break 1

NEDC 10-053 EDG High/Low Frequency Effect on ECCS Pumps 2

NEDC 87-131C 125 VDC Division 1 Load and Voltage Study 15

NEDC 86-105C CNS DC Short Circuit Study 4

NEDC 89-2163 Control Building HVAC 5

NEDC 86-105D CNS Critical DC Bus Coordination Study 8

NEDC 87-131C Service Test Profile 15

NEDC 91-094 125 VDC/250 VDC Battery Charger Analysis 5

NEDC 91-185 MOV Thermal Overload Heater Sizing 6

NEDC 99-083 Proto Power Calculation 99-056 Service Water Booster Pump 1

System Hydraulic Analysis

NEDC 99-056 Evaluation of Residual Heat Removal Service Water Booster 0

Pump Needed Differential Pressure

NEDC 97-044A Net Positive Suction Head Margins Residual Heat Removal & 4

Core Spray Pumps

NEDC 94-190 Core Spray Pump Miniflow Analysis 0

NEDC 94-142 Core Spray Flows with Min Flow Bypass Valve Open 5

NEDC 93-184 Residual Heat Removal Heat Exchangers Thermal 3

Performance &Tube Plug Margin

NEDC 93-125 Stem Nut Thread Wear Evaluation, Generic Letter 89-10 0

MOVs

NEDC 00-47 Allowable Operating Parameters RHR-MOV38A & 38B 0

A-3

Condition Reports (CRs)

2009-03704 2015-02061 2010-03876 2015-01268 2011-06146

2013-0088-032 2013-08099 2014-08465 2014-01680 2014-08318

2012-09382 2012-06657 2012-01997 2015-02024 2012-01647

2014-05947 2008-00666 2007-00773 2010-06302 2012-04960

2014-06054 2010-05211 2014-00146

Condition Reports (CRs) Generated during the Inspection

2015-02366 2015-02007 2015-02407 2015-02337 2015-02384

2015-02747 2015-02736 2015-02752 2015-02330 2015-02034

2015-02441 2015-02085 2015-02650 2015-02089 2015-02106

2015-02115 2015-02358 2015-02366 2015-02384 2015-02395

2015-02408 2015-02409 2015-02440 2015-02090 2015-02393

2015-02085

Work Orders

4458028 4699196 4698778 4442920 4699195

4748604 4983674 5072695 11117931 MWR 99-3212

4951675 4999222 5023453 5023550 5025370

5023592 4951419 4801811 4740703

Drawings

Number Title Revision/Date

3001 Main One Line Diagram AC/24

3002, Sh. 1 Auxiliary One line Diagram MCC Z, SWGR Bus 1A, 1B, 1E, AC/51

and Critical Bus 1F 1G

3006, Sh. 5 Auxiliary One line Diagram Starter Racks LZ and TZ, MCCs K, AE/83

L, LX, RA, S, T, TX, X

3127, Sh. 6 Turbine Generator Building Cable tray loading schedule N11

2018 Flow Diagram Turbine Generator Bldg. & Control Bldg. AD/40

Heating and Ventilating Cooper Nuclear Station

932-71212PI, Control Building H & V Unit 1-HV-C-1A N06

Sh. 1C

3752, Sh. 1 Annunciator Loop Diagram ANN-MUX-02 N04

3750, Sh. 1 Annunciator Loop Diagram ANN-MUX-00 N05

A-4

Drawings

Number Title Revision/Date

3157 Reactor Building Elev. 931-6 conduit and Tray plan AG/27

3013 Generator Tripping Schedule 9

3012, Sh. 2 Main three Line Diagram N09

3253, Sh. K1 460V Motor Control Center K Connection Wiring Diagram N19

3253, Sh. DT4 460V Motor Control Centers Wiring Details, Connection N20

Wiring Diagram

E506 Turbine Generator Building Connection Wiring Diagram, N04

Sheet 64

3255, Sh. 38 Control Room-Control Panels Connection Wiring Diagram N11

3156, Sh. 1 Reactor Building, El 903-6 Conduit and Tray Plan AC/35

E501, Sh. 48A Integrated Control Circuit Diagram, SW-MOV-M089B, AC/04

RHR HX B Service Water outlet

3007, Sh. 6 Auxiliary One Line Diagram, Motor Control Centers, N83

E, O, R, RB & Y

INV-3C-70048, Schematic Diagram ARR 130K200F N02

Sh. 2 of 2

3058 DC One Line Diagram 64

152D009 250V & 125V DC Switchgear One Line & Schematic N03

48K7A.STK MCC-K Circuit 7A March 18,

1994

2040, Sh. 2 Flow Diagram Residual Heat Removal System Loop B AB/19

791E264, Sh. 3 Elementary Diagram RCIC System Cooper N21

791E264, Sh. 7 Elementary Diagram RCIC System Cooper N15

791E271, Sh. 3 Elementary Diagram HPCI System Cooper N23

791E271, Sh. 8 Elementary Diagram HPCI System Cooper N20

2049, Sh. 2 Flow Diagram Condensate Supply System AC/38

Procedures

Number Title Revision/Date

7.3.17 4160 Breaker Maintenance 36

7.3.17-1 4160 Breaker Examination 29

7.3.17.4 4160V Vacuum Bottle Breaker Maintenance 1

3.11 Vendor Manual Control and Use 26

A-5

Procedures

Number Title Revision/Date

0-EN-OE-100 Operating Experience Program 16CS

14.35.1 Electrical Equipment Instrument Calibration 10

7.3.41 Examination and High-pot testing of Non-Segregated 10

Buses and Associate Equipment

2.2.38 HVAC Control Building 40

7.3.2.1 Westinghouse DB-50 Breaker Maintenance and Testing 19

7.3.13 Motor Control Center Examination and Maintenance 22

2.1.11.1 Turbine Building Data 148

0.5.OPS Operations Review of Condition Reports/Operability 53

Determination

6.SWBP.201 Surveillance Procedure SW-MO-89A/B Full Stroke 6

Operability (IST)

3-EN-DC-126 Engineering Calculation Process 3C2

2.3-C-2 Operator Observation and Action Startup Transformer 45

Trouble Panel Window C-2/F-9

14.11.16 IAC Procedure Yokogawa Recorder DX Series Calibration 73

Check

MNT118-00-00 Lesson on Calibration Tool Issues 07

2.2.15 Startup Transformer 54

6.EE.610 Off-Site AC Power Alignment 37

0-CNS-LI-102 Corrective Action Process 0

7.0.2 Preventive Maintenance Program Implementation 53

7.3.2 DC DB-25 and DB-50 Fused Disconnect Testing and 22

Maintenance

7.3.39 Inspection of 125/250 VDC Buses and Switchgear A and B 4

7.3.27.1 125V Station Battery Equalizing Charge 13

7.3.31.3 125V/250V Battery Terminal Cleaning and Torqueing 14

2.2.25.1 125 VDC Electrical System (Div. 1) 19

7.3.1.6 125/250 VDC Station Battery Charger Protective Relays 18

Testing and Calibration

7.3.14 Thermal Examination of Plant Components 10

7.3.23.6 Battery Charger Clean and Inspect 1

2.0.1.3 Time Critical Operator Action Validation 4

A-6

Procedures

Number Title Revision/Date

2.1.20.3 RPV Refueling Preparation (Wet Lift of Dryer and Separator) 52

2.2.99 Supplemental Diesel Generator System 5

3-EN-DC-304 MOV Thrust/Torque Setpoint Calculations 1C0

5.8.6 RPV Flooding Systems (Table 6) 32

5.8.7 Primary Containment Flooding/Spray Systems 30

6.1CS.101 Core Spray Test Mode Surveillance Operation (IST) (DIV 1) 28

6.2CS.101 Core Spray Test Mode Surveillance Operation (IST) (DIV 2) 25

6.MS.201 Main Steam Isolation Valve Operability Test (lST) 17

6. PC.513 Main Steam Local Leak Rate Tests 24

6.SDG.101 SDG Test Mode Surveillance Operation 4

6.SLC.101 SLC Pump Operability Test 23

6.SLC.102 SLC Test Mode Surveillance Operation (IST) 27

7.2.24.2 MSIV Speed Adjustment 2

89-176 MSIV Closing Test with Instrument Air Valved Out May 25, 1989

O-BARRIER Barrier Control Process 16

O-BARRIER- Control Building 5

CONTROL

5.3SBO Station Blackout 34

5.8 Emergency Operating Procedures (EOPs) 36

5.8, 1A - RPV Control 16

Attachment 1

5.8, 6A - RPV Pressure (Failure to Scram) / Reactor Power 16

Attachment 1 (Failure to Scram)

5.8, 7A - RPV Level (Failure to Scram) 17

Attachment 1

5.8, 3A - Primary Containment Control 15

Attachment 1

5.8, EOP / SAG Graphs 15

Attachment 2

5.8.8 Alternate Boron Injection and Preparation 16

2.1.5 Reactor Scram 71

5.8, Stop and Prevent Hard Card 36

Attachment 4

A-7

Procedures

Number Title Revision/Date

5.8, Failure to Scram Actions Hard Card 36

Attachment 6

2.1.22 Recovering From A Group Isolation 59

0.29.1 License Basis Document Changes 34

0.29.2 USAR Control and Maintenance 19

0-EN-LI-103 Operating License Amendments 7C0

2.0.1.3, Time Critical Operator Action Validation May 1, 2015

Attachment 1

2.0.1.3, Time Critical Operator Action Validation July 21, 2014

Attachment 1

Vendor Documents

Number Title Revision/Date

VM-1188 Vendor Manual 125 & 250 Volt Batteries and Chargers 12

0109D4798 Bus Duct Arrangement 01

022-3-R-0558, Power and Control Circuits line-up 04 Unit-1 2

Sh. 22

IC1000-K240- Siemens System and Service Instruction Manual - Vacuum

A164-X-4AUS Circuit Breaker (vehicle) Type GEH 4.16KV-250MVA,

4.16KV-250MVA upgraded to 350MVA

E50001-F710- Siemens Instruction Manual Type 3AH3 and 3AHc-Vacuum

A251-V1-4A00 Circuit Breaker operator modules 4.16KV to 38KV

GEK-41905 GE Instruction and Recommended Parts for Maintenance

Magne-Blast Circuit Breaker Type AMH-4.76-250-2D 1200 &

2000 Amperes with ML-13 Mechanism

GEK-88771-D GE Instruction Magne-Blast Circuit Breaker Type AMH-4.76-

250-0D AMH-4.76-250-1D

F-1329-D-0460 Connection Diagram, LT IB/24/30MVA OA/FA/FA N01

791E262, Sh. 1 Standby Liquid Control, System N17

791E252, Sh. 1 Nuclear Boiler Process Inst. N12

TR-109641 Guidance on Routine Preventive Maintenance for Magne-Blast October 1998

Circuit Breaker, Supplement to N

VM-0986 Limitorque Valves Composite manual 33

CD 7.4.1.7-7 ABB High Accuracy Voltage Relays ITE-27N Undervoltage A

Relay; ITE-59N Overvoltage Relay

A-8

Vendor Documents

Number Title Revision/Date

IB 7.4.1.7-7 ABB Single Phase Voltage Relays Type 27N High Accuracy D

Undervoltage Relay; 59N High Accuracy Overvoltage Relay

IB 7.4.1.7-7 ABB Single Phase Voltage Relays Type 27N High Accuracy E

Undervoltage Relay; 59N High Accuracy Overvoltage Relay

VMCF 9 3-228 FPE Transformer Installation, Operations and Maintenance

Instructions IN-T-415

Design Basis Documents

Number Title Date

DCD-05 DC Electrical System Design Criteria Document EEDC1 February 2,

2009

DCD-04 AC Electrical System Design Criteria Document EEAC1 October 30,

2014

DCD-12 Core Spray System - Design Criteria Document October 30,

2014

DCD-19 Standby Liquid Control (SLC) System - Design Criteria January 22,

Document 2010

Miscellaneous

Number Title Revision/Date

13-004 Engineering Evaluation - Electrical Bus Outage Maintenance 1

Plans - 24 Month Refueling Cycle Review

EC-4899459 1200 A, 4160V Vacuum Bottle Circuit Breaker Replacement 0

10776733 Notification - Evaluate for Preventive maintenance December 8,

2010

2LE6SJ Project - Hitachi Overhaul AMH 4,76-250 1200 Amp Circuit 0

Breaker S/N:0224A6208-001

061-15288 NLI Overhaul AMH-4.76-250-1D 1200Amp Circuit Breaker August 16,

S/N:224A6204-008 2011

LO 2014-0130 CDBI Focused Self-Assessment Report January 16,

2015

800000042081 Operation 0050, Transformer General Maintenance

IEEE Std 279- IEEE Standard: Criteria for Protection Systems for Nuclear

1971 Power Generating Stations

CED 1998- Nitrogen Cushion Installation into Fire Protection System High 1

0060 Points

A-9

Miscellaneous

Number Title Revision/Date

CED 6029940 Supplemental Diesel Generator May 25, 2010

Core Spray System Health Report January, 2015

Main Steam System Health Report January, 2015

Standby Liquid Control System Health Report January, 2015

EE 01-030 Flood Door Gap Analysis 0

ER 2015-011 Sensitivity Analysis of Diesel Generator Storage Tank Vent 0

Function Following a Tornado Missile Strike

SIL No. 482 MSIV Closure Testing Requirement February 22,

1989

NUMARC 87- Guidelines and Technical Bases for NUMARC Initiatives 1

00

OPL-3A Input Parameters Verification For ATWS Analyses (Cycle 27) 0

TAC NO. Cooper Nuclear Station - Issuance of Amendment Re: January 31,

ME5287 Technical Specification 3.4.3 To Reduce The Number of Safety 2012

Relief Valves Required To Be Operable For Overpressure

Protection

SW06 Simulator Cause and Effect Malfunction - Service Water 01.00

Leakage in Control Building Basement

A-10