IR 05000298/2020003
| ML20304A778 | |
| Person / Time | |
|---|---|
| Site: | Cooper |
| Issue date: | 11/02/2020 |
| From: | Jason Kozal NRC/RGN-IV/DRP/RPB-C |
| To: | Dent J Nebraska Public Power District (NPPD) |
| References | |
| IR 2020001, IR 2020003 | |
| Download: ML20304A778 (20) | |
Text
November 2, 2020
SUBJECT:
COOPER NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000298/2020003 AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT 07200066/2020001
Dear Mr. Dent:
On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Cooper Nuclear Station. On October 15, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Jason W. Kozal, Chief Reactor Projects Branch C Division of Reactor Projects
Docket No. 05000298 License No. DPR-46
Enclosure:
As stated
Inspection Report
Docket Number:
05000298 and 07200066
License Number:
Report Number:
05000298/2020003 and 07200066/2020001
Enterprise Identifier: I-2020-003-0006 and I-2020-001-0097
Licensee:
Nebraska Public Power District
Facility:
Cooper Nuclear Station
Location:
Brownville, NE
Inspection Dates:
July 1, 2020 to September 30, 2020
Inspectors:
B. Baca, Health Physicist
B. Bergeon, Operations Engineer
L. Brookhart, Senior Spent Fuel Storage Inspector
J. O'Donnell, Senior Health Physicist
E. Simpson, Health Physicist
A. Siwy, Senior Resident Inspector
C. Smith, Health Physicist
M. Stafford, Resident Inspector
C. Young, Senior Project Engineer
Approved By:
Jason W. Kozal, Chief
Reactor Projects Branch C
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Cooper Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
Type Issue Number Title Report Section Status LER 05000298/2019-002-00 Secondary Containment Rise in Differential Pressure Results in Loss of Safety Function 71153 Closed
PLANT STATUS
Cooper Nuclear Station began the inspection period at rated thermal power. On July 24, 2020, power was lowered to approximately 70 percent for a control rod sequence exchange. The plant was returned to rated thermal power on July 25, 2020. On July 26, 2020, power was lowered to approximately 80 percent for a control rod sequence exchange. The plant was returned to rated thermal power on July 26, 2020. On August 8, 2020, the plant commenced power coastdown. On August 9, 2020, power was lowered to 95 percent due to a single control rod scram. On August 10, 2020, power was lowered to 75 percent for control rod recovery. The plant was returned to rated thermal power on August 10, 2020. On September 8, 2020, power was lowered from 89 percent power to 80 percent power when reactor feed pump A was removed from service due to an issue with its governor valve. The plant was returned to 89 percent power on September 10, 2020. On September 26, 2020, the licensee shut the plant down for a scheduled refueling outage. The unit remained shutdown for the remainder of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted.
As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities; and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Emergency diesel generator 2 starting air while emergency diesel generator 1 was inoperable on July 9, 2020
- (2) Residual heat removal system B on July 30, 2020
- (3) Reactor building sumps on August 27, 2020
Complete Walkdown Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated system configurations during a complete walkdown of the core spray B system on July 31, 2020.
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Cable spreading room on July 1, 2020
- (2) Reactor building southwest quad, Elevation 881 feet and 859 feet, on July 30, 2020
- (3) Walkdown fire drill area on August 28, 2020
- (4) Reactor building southeast quad, Elevation 859 feet, on September 1, 2020
- (5) Reactor building refuel floor, Elevation 1001 feet, on September 28, 2020
71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance
Requalification Examination Results (IP Section 03.03) (1 Sample)
- (1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from June 9, 2020, through July 17, 2020.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the control room during downpower and scram for Refueling Outage RE31 on September 26, 2020.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated the licensed operator requalification scenario on August 12, 2020.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (3 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
- (1) Emergency core cooling system sumps on August 7, 2020
- (2) Heat trace on the condensate storage tank on August 7, 2020
- (3) Reactor protection system scram solenoid valve failure on August 23, 2020
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Residual heat removal heat exchanger B unavailable during service water flow adjustment on July 16, 2020
- (2) Division 2, 4160 volt undervoltage relay surveillance on August 18, 2020
- (3) High pressure coolant injection auto isolation logic steam line low pressure functional on September 26, 2020
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (2 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Reactor equipment cooling increased outflow on July 13, 2020
- (2) FLEX haul path functionality during outage preps on September 4, 2020
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)
The inspectors evaluated the following temporary or permanent modifications:
- (1) Reactor equipment cooling leakage modification on September 8, 2020
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:
- (1) Standby liquid control A post work testing on July 28, 2020
- (2) Service water booster pump A post work testing on July 30, 2020
- (3) Intermediate-range monitor G post work testing on August 6, 2020
- (4) Main steam line process radiation monitor repairs on September 10, 2020
- (5) Reactor feed pump A speed demand deviation repairs on September 11, 2020
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage Sample (IP Section 03.01) (Partial Sample)
- (1) The inspectors evaluated Refueling Outage 31 activities from September 26, 2020, to September 30, 2020. The inspectors completed inspection procedure Sections 03.01a and 03.01b.
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Surveillance Tests (other) (IP Section 03.01)
- (1) Emergency diesel generator 1 operability test with isolation switches in isolate on September 2, 2020
Inservice Testing (IP Section 03.01) (2 Samples)
- (1) Service water check valves on the Division 2 diesel generator on July 18, 2020
- (2) High pressure coolant injection dripleg drain valve inservice test on August 5, 2020
Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)
- (1) Local leak rate testing for primary containment penetrations on September 21,
RADIATION SAFETY
71124.02 - Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls
Radiological Work Planning (IP Section 03.01) (5 Samples)
The inspectors evaluated the integration of as low as is reasonably achievable planning into the work activities for the following ALARA packages:
(1)2018-01, "Control Rod Drive Mechanisms (CRDMs)," Revision 0, which involved the replacement of 15 CRDMs including loading into shipping boxes, rod position instrumentation system (RPIS) probe removal and re-installation, and set up and shoot out steel removals and re-installation (2)2018-05, "Reactor Disassembly, Refuel, Reassembly and Miscellaneous Repairs,"
Revisions 0 - 2, which involved the removal and re-installation of the reactor pressure vessel head and associated reactor vessel components, defuel and refuel, and the performance of miscellaneous repairs and maintenance (3)2018-15, "General Valve Work for Refuel-30 (RE-30)," Revision 0, which involved maintenance and repairs for valves in the reactor building, drywell, steam tunnel and rad waste buildings (4)2018-20, "Radiation Protection Support for RE-30," Revisions 0 - 2, which included radiation protection activities in high radiation areas and locked high radiation areas (5)2018-34, "High Pressure Core Injection (HPCI) Motor Operated Valve (MOV) MO-15,"
Revision 0 - 2, which involved high radiation area maintenance work and repairs to the HPCI MOV MO-15
Verification of Dose Estimates and Exposure Tracking Systems (IP Section 03.02) (5 Samples)
The inspectors evaluated dose estimates and exposure tracking in the following ALARA packages:
(1)2018-01, "CRDMs," Revision 0, which involved the replacement of 15 CRDMs including loading into shipping boxes, rod position information system probe removal and re-installation, and set up and shoot out steel removals and re-installation (2)2018-05, "Reactor Disassembly, Refuel, Reassembly and Miscellaneous Repairs,"
Revisions 0 - 2, which involved the removal and re-installation of the reactor pressure vessel head and associated reactor vessel components, defuel and refuel, and perform miscellaneous repairs and maintenance (3)2018-15, "General Valve Work for RE-30," Revision 0, which involved maintenance and repairs for valves in the reactor building, drywell, steam tunnel and rad waste building (4)2018-20, "Radiation Protection Support for RE-30," Revisions 0 - 2, which included radiation protection activities in high radiation areas and lock high radiation areas (5)2018-34, "HPCI MOV MO-15," Revision 0 - 2, which involved high radiation area maintenance work and repairs to the HPCI MOV MO-15 valve
71124.04 - Occupational Dose Assessment
Source Term Characterization (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated licensee performance as it pertains to radioactive source term characterization.
External Dosimetry (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated licensee performance as it pertains to external dosimetry that is used to assign occupational dose.
Internal Dosimetry (IP Section 03.03) (2 Samples)
The inspectors evaluated the following internal dose assessments for actual internal exposures:
- (1) Two radiation protection technicians' potential airborne exposure evaluations, dated October 15, 2019: Evaluation Nos. 29430 and 30360
- (2) A radiation worker alarming a personnel contamination monitor exiting the radiologically controlled area on October 11, 2019: Evaluation No. 37397
Special Dosimetric Situations (IP Section 03.04) (3 Samples)
The inspectors evaluated the following special dosimetric situations:
- (1) Four dose assessments for three declared pregnant workers
- (2) Three personnel contamination events (PCEs) which had skin/shallow dose assessments performed: PCE No. 18-12, PCE No. 18-13, and PCE No. 18-19
- (3) Effective dose equivalent for external exposure (EDEX) evaluations in ALARA Package 2018-05, "Reactor Disassembly, Refuel, Reassembly, and Miscellaneous Repairs," Revisions 0 - 2, for work activities involving entries into the cavity: with the drywell head set and during removal, during and after the reactor vessel head removal, to install and detension/retension the reactor vessel head, and insulation package and associated piping removal
OTHER ACTIVITIES - BASELINE
71152 - Problem Identification and Resolution
Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) Packing leak on high pressure coolant injection system valve on September 18, 2020
- (2) Reactor core isolation cooling governor 10 CFR Part 21 follow-up on September 24, 2020
71153 - Follow-up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)
The inspectors evaluated the following licensee event reports (LERs):
- (1) LER 05000298/2019-002-00, Secondary Containment Rise in Differential Pressure Results in Loss of Safety Function (ADAMS Accession No. ML19295F428). The circumstances surrounding this LER and an associated minor violation are documented in the Inspection Results section of this report.
OTHER ACTIVITIES
- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
===60855 - Operation of an Independent Spent Fuel Storage Installation (ISFSI) The inspectors verified that the licensee's processes and procedures fulfill the requirements specified in the Updated Final Safety Analysis Report (UFSAR), Safety Evaluation Report (SER), Certificate of Compliance (CoC), 10 CFR Part 72, the site-specific license and technical specifications. Additionally, the inspectors verified, by the review of selected records, that the licensee identified each fuel assembly placed in the ISFSIs, recorded the parameters and characteristics of each fuel assembly, and maintained a record of each fuel assembly as a controlled document.
Operation of An ISFSI===
- (1) The licensee's most current 10 CFR 72.212 Evaluation Report, dated July 24, 2020, was reviewed to verify that site characteristics remained bounded by the design bases of the dry fuel storage systems in use at Cooper Nuclear Station (CNS).
Specifically, CNS utilizes two variations of Transnuclear, Inc. (TN) NUHOMS dry spent fuel storage systems:
- (1) the Horizontal Storage Module (HSM) Model 202 HSM system with the 61BT dry shielded canister (DSC), and
The CNS ISFSI has a total of 52 HSMs, 30 of which are loaded with spent fuel. In 2019, CNS added an additional 22 HSMs to the existing ISFSI. TN CoC 1004, Amendment 13, Revision 1, and TN UFSAR, Revision 15, are the current revisions used at CNS.
===60857 - Review of 10 CFR 72.48 Evaluations The inspectors reviewed 10 CFR 50.59 and 72.48 evaluations, and 10 CFR 72.212(b)evaluations for general licensed ISFSIs for changes made to the ISFSI programs and procedures since the last inspection to verify that changes made were consistent with the license or CoC and did not reduce the effectiveness of the program.
Review of 10 CFR 72.48 Evaluations===
- (1) The inspectors reviewed a list of 10 CFR 72.48 screenings performed by the licensee since July 2017. During this time period the licensee did not perform any 10 CFR 72.48 evaluations. The inspectors evaluated the following:
- Selected licensee 10 CFR 72.48 screenings for associated changes, tests, and experiments associated with ISFSI operations
- The process by which the licensee evaluates 10 CFR 72.48 screenings and evaluations performed by the CoC holder
- Changes made to the licensees 10 CFR 72.212 report since July 2017 (adding additional HSMs)
INSPECTION RESULTS
Minor Violation 71153 Minor Violation: On August 8, 2019, secondary containment vacuum was reduced below the limit of 0.25 inches of vacuum water gauge, which is required by Technical Specification (TS)
Surveillance Requirement (SR) 3.6.4.1.1. This condition existed for 7 minutes and was identified by operations personnel approximately 97 minutes after it had occurred through a review of control room panel indications. This condition was a result of changes in reactor building ventilation flow caused by operations personnel in the field having taken actions to advance the filter media for the reactor building ventilation supply filters. This activity was performed without pre-planning, without informing control room personnel of the activity, and without any documented work instructions, due to it being classified as a skill of the craft activity in accordance with the licensees maintenance program procedures. This issue was entered into the licensees corrective action program as Condition Report CR-CNS-2019-04194.
Technical Specification 5.4.1.a requires that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Section 9.a of Appendix A to Regulatory Guide 1.33 requires that maintenance that can affect the performance of safety-related equipment should be properly pre-planned and performed in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances.
Contrary to the above, on August 8, 2019, the licensee failed to properly pre-plan and performed maintenance that can affect the performance of safety-related equipment in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances. Specifically, operations personnel performed a maintenance activity without pre-planning or documented work instructions to advance the filter media for the reactor building ventilation supply filters, which resulted in a condition that caused secondary containment vacuum to fall below the limit required by technical specification surveillance requirements.
Screening: The inspectors determined the performance deficiency was minor. The performance deficiency associated with this violation was determined to be minor because:
it could not be reasonably viewed as a precursor to a significant event; if left uncorrected, it would not have the potential to lead to a more significant safety concern; and it did not adversely affect the Barrier Integrity cornerstone objective to provide reasonable assurance that physical design barriers (containment) protect the public from radionuclide releases caused by accidents or events. Specifically, the performance deficiency did not affect the integrity of the secondary containment structure, nor did it affect the ability of the safety-related standby gas treatment system to perform its required safety function.
Enforcement:
The licensee has taken actions to restore compliance. This failure to comply with Technical Specification 5.4 constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On July 23, 2020, the inspectors presented the 71124.02 and 71124.04 occupational radiation safety inspection results to Mr. J. Dent, Jr., Site Vice President, and other members of the licensee staff.
- On September 10, 2020, the inspectors presented the independent spent fuel storage installation inspection results to Mr. T. Barker, Director of Engineering, and other members of the licensee staff.
- On October 1, 2020, the inspectors presented the annual licensed operator requalification inspection results to Mr. J. Florence, Superintendent, Simulator & Training Support, and other members of the licensee staff.
- On October 15, 2020, the inspectors presented the integrated inspection results to Mr. J. Dent, Jr., Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
60855
Corrective Action
Documents
CR-CNS-
2017-04504, 2017-04793, 2017-05139, 2017-06746,
2018-01495, 2018-04248, 2018-05679, 2019-01072,
20-02869, 2020-02882
Corrective Action
Documents
Resulting from
Inspection
CR-CNS-
20-03772
09/10/2020
Miscellaneous
Cooper Nuclear Station Independent Spent Fuel Storage
Installation 10 CFR 72.212 Report
07/24/2020
C/06838/01.01/LTR1
91017-001
CNS Review and Acceptance of ORANO, TN Americas,
Certificate of Conformance, NUHOMS Horizontal Storage
Modules
09/17/2019
NCR 2019-005
Hot Concrete Temperature Oven Testing
01/22/2019
Procedures
0-CNS-LI-102
Corrective Action Process
03/18/2020
Radiation
Surveys
ISFSI Pad Radiation Survey
07/01/2020
Self-
Assessments
QA Audit 18-05
Radiological Controls
09/23/2018
QS-2018-CNS-002
ISFSI Campaign #3 QA Surveillance Report
01/04/2018
QS-2019-CNS-020
ISFSI HSM Construction QA Surveillance
08/21/2019
Work Orders
283574
Reactor Building Crane Hoist Maintenance
04/02/2020
60857
Engineering
Changes
EC 09-11
Addition of 22 Model HSM-H Modules within the CSN
ISFSI Area and 2018 Update to ISFSI Offsite Dose
Estimates
Engineering
Evaluations
PAD 121939
Lift of the ISFSI Transfer Cask (TC) Lid from Elevation
903 Train Bay to Elevation 1001 Spent Fuel Pool using
the TC Lift Yoke as a Strong Back
PAD 122165
Modify 72.212 report for renewal of CoC 1004, add
technical specification for aging management, add NPPD
compliance with neutron shield in transfer cask, revise
training program description
PAD 142221
Revise EE 09-011 and the CNS 72.212 Report for minor
corrections and for addition of 22 model HSM-H modules
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
within the existing CNS ISFSI area. In addition, the ISFSI
offsite dose estimates from "Evaluation of ISFSI
Radioactive Effluents and Radiation" in accordance with
CFR 72.104, tables are updated for calendar years
2016 through 2018.
Miscellaneous
LBDCR 2019-001
CFR 72.212 Update
10/29/2019
Procedures
0-CNS-LI-100
Process Applicability Determination
2/12/2020
0-CNS-LI-101
CFR 50.59 Evaluations
2/12/2020
0-CNS-LI-112
CFR 72.48 Evaluations
2/20/2019
Drawings
2077
Flow Diagram - Diesel Gen. Bldg. Service Water, Starting
Air, Fuel Oil, Sump System & Roof Drains
Procedures
2.2.27
Equipment, Floor, and Chemical Drain System
2.2.27A
Equipment, Floor, and Chemical Drain System
Component Checklist
2.2.66A
Reactor Water Cleanup Component Checklist
2.2A.CS.DIV2
Core Spray Component Checklist (DIV 2)
2.2A.DG.DIV2
Standby AC Power System (Diesel Generator)
Component Checklist (DIV 2)
2.2A.RHR.DIV2
Residual Heat Removal System Component Checklist
(DIV 2)
Corrective Action
Documents
CR-CNS-
20-02475, 2020-02630, 2020-03545, 2020-03546
Fire Plans
CNS-FP-212
Reactor Building Southeast Quadrant Elevation 991-9
and 859-9
CNS-FP-214
Reactor Building Southwest Quadrant Elevations 881-9
and 859-9
CNS-FP-218
Reactor Building - Second Floor Elevation 931-6
CNS-FP-219
Reactor Building - Third Floor Elevation 958-3
CNS-FP-223
Reactor Building - Refuel Floor Elevation 1001-0
CNS-FP-229
Control Building Cable Spreading Room
CNS-FP-236
Diesel Generator Building Diesel Generator #1 Elevations
917-6 and 903-6
CNS-FP-237
Diesel Generator Building Diesel Generator #2 Elevations
917-6 and 903-6
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
CNS-FP-251
Turbine Building Turbine Operating Floor Elevation 932-
CNS-FP-285,
Sheet 1
Fire Barrier Penetration Seal Details
CNS-FP-285,
Sheet 2
Fire Barrier Penetration Seal Details
CNS-FP-285,
Sheet 3
Fire Barrier Penetration Seal Details
CNS-FP-285,
Sheet 4
Fire Barrier Penetration Seal Details
CNS-FP-65
Fire Area Boundary Drawing Cable Spreading Room
South Wall
CNS-FP-69
Fire Area Boundary Drawing South Wall (Office Building
Side)
Miscellaneous
NEDC 10-041
Recovery Action Feasibility Assessment Report Review
EPM Report R1006-004-005
Procedures
0-BARRIER
Barrier Control Process
0-BARRIER-MAPS
Barrier Maps
15.EE.302
Emergency Lighting and SBO Lighting Functional Test
3.6.1
Fire Barrier Control
5.1INCIDENT
Site Emergency Incident
6.FP.606
Fire Barrier/Penetration Seal Visual Examination
7.3.12.1
BBESI Emergency Lighting Unit Examination and
Maintenance
CNS-EE-178
Safe Shutdown Component Locations & Emerg Route
Lighting 903-6: Reactor Building
CNS-EE-180
Safe Shutdown Component Locations & Emerg Route
Lighting 859-0 Reactor Building
71111.11Q Procedures
2.0.3
Conduct of Operations
104
2.1.10
Station Power Changes
119
2.1.4
Normal Shutdown
175
2.1.5
Reactor Scram
2.2.18.1
4160V Auxiliary Power Distribution System
2.2.77
21
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
CR-CNS-
2019-00129, 2019-02921, 2019-02931, 2019-03061,
2019-03256, 2019-04359, 2019-04905, 2019-05350,
2019-05903, 2019-06032, 2020-03256, 2020-03279,
20-03282, 2020-03340
Miscellaneous
Maintenance Rule Function RW-F03 Performance Criteria
Basis
Maintenance Rule Function CRD-F03A Performance
Criteria Basis
Maintenance Rule Function CRD-F03B Performance
Criteria Basis
Maintenance Rule Function CRD-F02B Performance
Criteria Basis
Procedures
3-EN-DC-204
Maintenance Rule Scope and Basis
4C0
3-EN-DC-205
Maintenance Rule Monitoring
7C0
Corrective Action
Documents
CR-CNS-
20-03992, 2020-03993
Work Orders
WO 282141, 5337256
Corrective Action
Documents
CR-CNS-
20-02917, 2020-03601
Procedures
0-CNS-62
Control of Temporary Facilities
5.10FLEX.10
ECST Makeup from North Well
5.10FLEX.20
Debris Removal in Support of FLEX Operations
5.3SBO
FLOWCHART
Station Blackout
Corrective Action
Documents
CR-CNS-
20-02891, 2020-02913, 2020-02917, 2020-02946,
20-03188
Corrective Action
Documents
CR-CNS-
20-02757, 2020-02770, 2020-02775, 2020-02862,
20-02881, 2020-03679, 2020-03736, 2020-03764
Procedures
2.2.74
Standby Liquid Control System
6.1IRM.304
IRM Channel Calibration (Mode Switch in Run)
6.1SWBP.101
RHR Service Water Booster Pump Flow Test and Valve
Operability Test
6.PRM.324
Main Steam Line Process Radiation Monitor Channel
Calibration, Source Test, and Setpoint Determination
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
6.SLC.101
SLC Pump Operability Test
7.0.9
Control of Lubricants
7.2.26.2
Bolted or Screwed Bonnet Check Valve Maintenance
7.2.4
SLC Pump Maintenance
Work Orders
WO 209175, 5209254, 5216093, 5312971, 5335029,
5355837, 5357100, 5363228, 5363300
Corrective Action
Documents
CR-CNS-
20-04025, 2020-04026, 2020-04030, 2020-04038,
20-04053
Procedures
2.1.10
Station Power Changes
119
2.1.4
Normal Shutdown
175
2.1.5
Reactor Scram
2.2.18.1
4160V Auxiliary Power Distribution System
2.2.77
21
6.RCS.601
Technical Specification Monitoring of RCS
Heatup/Cooldown Rate
7.4DISASSEMBLY
Reactor Vessel Disassembly
Corrective Action
Documents
CR-CNS-
20-03592
Procedures
6.1DG.104
Diesel Operability Test with Isolation Switches in Isolate
6.2SW.401
Diesel Generator Service Water Check Valve and Sump
Test (IST) (DIV 2)
6.HPCI.204
HPCI-SOV-SSV64 and HPCI-SOV-SSV87 IST Closure
Test
6.PC.502
Primary Containment Instrumentation Local Leak Rate
Tests
Work Orders
WO 5088032, 5100584, 5116747, 5129867, 5209525,
209750, 5259394
ALARA Plans
2018-07
Refueling Outage (RE) 30 Scaffolds
2/06/2018
2018-32
RWCU-AOV-13/14A & 13/14B Replacements
2/06/2018
2018-33
Refueling Outage (RE) 30 In Vessel Visual Inspection
(IVVI)
11/09/2018
2018-35
Refueling Outage (RE) 30 MSIV Repairs
10/07/2018
Corrective Action
CR-CNS-
2018-04073, 2018-05864, 2018-08076, 2018-08202,
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Documents
2018-08665, 2019-01411, 2019-04073, 2020-00661,
20-02536, 2020-02828
Miscellaneous
Radiation Protection Program Annual Report 2018
05/29/2019
Radiation Protection Program Annual Report 2019
05/27/2020
2018-05
QA Audit "Radiological Controls"
07/24/2018
LO 2019-0202
Occupational ALARA Planning and Controls" (IP-
71124.02) and "Occupational Dose Assessment" (IP-
01/24/2020
Procedures
9.ALARA.1
Dosimetry Administration
9.ALARA.4
Radiation Work Permits
Hot Spot Program
ALARA Program
9.EN-RP-110-04
Risk Assessment Process
9.EN-RP-110-05
ALARA Planning and Controls
9.EN-RP-110-06
Outage Dose Estimating and Tracking
Radiation
Surveys
Unit 1, Reactor Building 1001': Cavity with Reactor Head
09/30/2018
Unit 1, Reactor Building 1001': RE-30 Survey performed
after drywell head removed from the cavity
10/01/2018
Unit 1, Reactor Building 1001': Cavity Survey following
insulation package removal
10/01/2018
Unit 1, Reactor Building 1001': Survey of cavity following
removal of reactor pressure vessel (RPV) head
10/02/2018
Unit 1, Reactor Building 1001': Remote survey prior to
initial cavity survey following drain down
11/01/2018
Unit 1, Reactor Building 1001': Pre-decontamination RPV
head not installed during survey; Survey of cavity
following drain down
11/01/2018
Unit 1, Reactor Building 1001': Survey performed after
final pass on cavity decontamination
11/01/2018
Unit 1, Reactor Building 1001': RE-30 Performed dose
rate gradient survey after setting drywell head during
reassembly
11/06/2018
Calculations
21585
Dose Equivalent Calculation Worksheet
10/28/2018
34677
Dose Equivalent Calculation Worksheet
10/15/2018
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
37436
Dose Equivalent Calculation Worksheet
10/15/2018
Corrective Action
Documents
CR-CNS-
2018-00935, 2018-03373, 2018-03990, 2018-07086,
2019-00972, 2020-00506, 2020-00784, 2020-00900,
20-01075
Miscellaneous
2018-05
QA Audit "Radiological Controls"
07/24/2018
31937
CNS Personnel TLD Vs DRD Discrepancy Dose
Evaluation
2/18/2019
34830
CNS Personnel TLD Vs DRD Discrepancy Dose
Evaluation
2/18/2019
35936
CNS Personnel TLD Vs DRD Discrepancy Dose
Evaluation
2/18/2019
37440
CNS Personnel TLD Vs DRD Discrepancy Dose
Evaluation
2/18/2019
37474
CNS Personnel TLD Vs DRD Discrepancy Dose
Evaluation
2/18/2019
37616
CNS Personnel TLD Vs DRD Discrepancy Dose
Evaluation
2/18/2019
37626
CNS Personnel TLD Vs DRD Discrepancy Dose
Evaluation
2/18/2019
37637
CNS Personnel TLD Vs DRD Discrepancy Dose
Evaluation
2/18/2016
37964
CNS Personnel TLD Vs DRD Discrepancy Dose
Evaluation
2/18/2019
LO 2019-0202
Occupational ALARA Planning and Controls" (IP-
71124.02) and "Occupational Dose Assessment" (IP-
01/24/2020
Procedures
9.EN-RP-110-04
Risk Assessment Process
Alpha Monitoring
Dose Assessment
Prenatal Monitoring
Dosimeter of Legal Record Quality Assurance
Whole Body Counting and In-Vitro Bioassay
Area Monitoring Program
Radiological Control
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
9.RADOP.1
Radiation Protection at CNS
9.RADOP.5
Airborne Radioactivity Sampling
Corrective Action
Documents
CR-CNS-
2018-01346, 2019-03189, 2019-03478, 2019-03936,
2019-03940, 2019-04045, 2019-05331, 2019-05388,
2019-05870, 2019-05923
Procedures
0-CNS-LI-108
CFR 21 Evaluations and Reporting
6.RCIC.102
Work Orders
WO 263795, 5272231
Corrective Action
Documents
CR-CNS-
2019-04194, 2019-04215, 2019-04217, 2019-04816,
2019-04827, 2020-02088
Procedures
2.0.3
Conduct of Operations
2, 103
7.0.4
Conduct of Maintenance
41, 42