MONTHYEARIR 05000298/20240032024-11-0505 November 2024 Integrated Inspection Report 05000298/2024003 ML24250A2052024-10-0808 October 2024 Issuance of Amendment No. 278 Regarding Revision to Technical Specification Table 3.3.2.1-1 and Transfer of Minimum Critical Power Ratio Values to Core Operating Limit Report ML24227A0822024-09-0303 September 2024 Summary of Regulatory Audit in Support of License Amendment Request to Modify the High Pressure Coolant Injection Low Flow Value IR 05000298/20240052024-08-22022 August 2024 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2024005) IR 05000298/20240022024-07-25025 July 2024 Integrated Inspection Report 05000298/2024002 ML24183A1722024-07-17017 July 2024 Issuance of Amendment No. 277 to Adopt TSTF-374, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil ML24197A1462024-07-15015 July 2024 NRC Region IV Ltr to Cooper Nuclear Station Re FEMA Level 1 Finding ML24134A1782024-07-0303 July 2024 Issuance of Amendment No. 276 Revision to Technical Specification 3.8.3, Diesel Fuel Oil, Lube Oil and Starting Air, to Allow for Cleaning, Inspection and Any Needed Repairs During Refuel Outage 33 ML24197A0682024-06-24024 June 2024 FEMA Ltr to Missouri State Emergency Management Agency - Level 1 Finding, 24 June 2024 ML24192A0112024-06-13013 June 2024 2024-06-Post Exam Comments 05000298/LER-2023-002-01, Secondary Containment Differential Pressure Perturbation Exceeds Technical Specifications2024-06-0606 June 2024 Secondary Containment Differential Pressure Perturbation Exceeds Technical Specifications IR 05000298/20244012024-06-0404 June 2024 Security Baseline Inspection Report 05000298/2024401 ML24151A1082024-05-30030 May 2024 NRC Initial Operator Licensing Examination Approval 05000298/2024301 ML24137A0942024-05-17017 May 2024 Regulatory Audit Plan in Support of License Amendment Request to Modify Allowable Value Regarding Technical Specification for High Pressure Coolant Injection Pump Discharge Low Flow 05000298/LER-2024-005, High Pressure Coolant Injection Pressure Switch Installation Causes Condition That Could Have Prevented Fulfillment of a Safety Function and a Condition Prohibited B Technical2024-05-13013 May 2024 High Pressure Coolant Injection Pressure Switch Installation Causes Condition That Could Have Prevented Fulfillment of a Safety Function and a Condition Prohibited B Technical. 05000298/LER-2024-004, Main Turbine Stop Valve Position Switches Do Not Meet Channel Independence Criteria Results in Two Channels Being Declared Inoperable and a Condition Prohibited by Technical Specifications2024-05-0909 May 2024 Main Turbine Stop Valve Position Switches Do Not Meet Channel Independence Criteria Results in Two Channels Being Declared Inoperable and a Condition Prohibited by Technical Specifications IR 05000298/20240012024-05-0303 May 2024 Integrated Inspection Report 05000298/2024001 ML24129A0952024-04-25025 April 2024 Preparation and Scheduling of Operator Licensing Examinations IR 05000298/20240102024-04-24024 April 2024 Comprehensive Engineering Team Inspection Report 05000298/2024010 05000298/LER-2024-003, High Pressure Coolant Injection Steam Leak Causes Condition That Could Have Prevented Fulfillment of a Safety Function and a Condition Prohibited by Technical Specifications2024-04-22022 April 2024 High Pressure Coolant Injection Steam Leak Causes Condition That Could Have Prevented Fulfillment of a Safety Function and a Condition Prohibited by Technical Specifications ML24096A1202024-04-0505 April 2024 Issuance of Amendment No. 275 Revision to Technical Specification 3.3.1.1 (Emergency Circumstances) ML24093A2282024-04-0202 April 2024 Notice of Enforcement Discretion for Cooper Nuclear Station IR 05000298/20240902024-04-0101 April 2024 – Notice of Violation, NRC Inspection Report 05000298/2024090 05000298/LER-2024-001, Inoperable Turbine Stop Valve Limit Switch Causes Condition Prohibited by Technical Specifications2024-03-0404 March 2024 Inoperable Turbine Stop Valve Limit Switch Causes Condition Prohibited by Technical Specifications 05000298/LER-2024-002, Technical Specifications Prohibited Condition for Inoperable Service Water Booster Pump2024-03-0404 March 2024 Technical Specifications Prohibited Condition for Inoperable Service Water Booster Pump IR 05000298/20230062024-02-28028 February 2024 Annual Assessment Letter for Cooper Nuclear Station - Report 05000298/2023006 IR 05000298/20230042024-02-12012 February 2024 Integrated Inspection Report 05000298/2023004 ML24033A3092024-02-12012 February 2024 Summary of Regulatory Audit Regarding the Relief Request RC3-02 Regarding Drywell Head Bolting IR 05000298/20230122024-02-12012 February 2024 NRC Inspection Report 05000298/2023012 ML23334A2012024-01-0303 January 2024 Issuance of Amendment No. 274 Revision to Technical Specifications to Adopt TSTF-551, Revision 3, Revise Secondary Containment Surveillance Requirements 05000298/LER-2023-002, Secondary Containment Differential Pressure Perturbation Exceeds Technical Specifications2023-12-20020 December 2023 Secondary Containment Differential Pressure Perturbation Exceeds Technical Specifications ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23311A1122023-11-0909 November 2023 Project Manager Assignment IR 05000298/20230032023-11-0202 November 2023 Integrated Inspection Report 05000298/2023003 IR 05000298/20234012023-11-0101 November 2023 Cyber Security Report 05000298/2023401 Public ML23264A8052023-10-11011 October 2023 Issuance of Amendment No. 273 Revision to Technical Specifications to Adopt TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23233A1882023-09-0505 September 2023 Regulatory Audit Plan in Support of Relief Request RC3-02 Regarding Drywell Head Bolting IR 05000298/20243012023-09-0101 September 2023 Notification of NRC Initial Operator Licensing Examination 05000298/2024301 IR 05000298/20230052023-08-21021 August 2023 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2023005)- Mid Cycle Letter IR 05000298/20230022023-08-0808 August 2023 Integrated Inspection Report 05000298/2023002 IR 05000298/20234022023-08-0303 August 2023 NRC Security Inspection Report 05000298/2023402 ML23214A2742023-08-0303 August 2023 Nuclear Station - Notification of Inspection (NRC Inspection Report 05000298/2023004) and Request for Information IR 05000298/20234202023-08-0101 August 2023 Security Baseline Inspection Report 05000298/2023420 05000298/LER-2022-002-01, Manual Core Spray Injection to Restore Skimmer Surge Tank Level2023-06-29029 June 2023 Manual Core Spray Injection to Restore Skimmer Surge Tank Level ML23173A0862023-06-26026 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000298/2023401 IR 05000298/20230102023-05-17017 May 2023 Biennial Problem Identification and Resolution Inspection Report 05000298/2023010 05000298/LER-2022-004-01, 1 for Cooper Nuclear Station, Manual Reactor Scram and Group I Isolation Due to Main Turbine Bypass Valve Failing Open2023-05-11011 May 2023 1 for Cooper Nuclear Station, Manual Reactor Scram and Group I Isolation Due to Main Turbine Bypass Valve Failing Open 05000298/LER-2023-001, Valve Test Failures Result in Condition Prohibited by Technical Specifications2023-05-0808 May 2023 Valve Test Failures Result in Condition Prohibited by Technical Specifications IR 05000298/20234032023-05-0404 May 2023 Security Baseline Inspection Report 05000298/2023403 ML23129A2822023-04-20020 April 2023 Submittal of Revision 31 to Updated Safety Analysis Report 2024-09-03
[Table view] Category:Notice of Violation
MONTHYEARIR 05000298/20240902024-04-0101 April 2024 – Notice of Violation, NRC Inspection Report 05000298/2024090 ML19224B5092019-08-12012 August 2019 Notice of Violation, NRC Investigation Report 4-2019-004 IR 05000298/20150072015-06-22022 June 2015 IR 05000298/2015007; on 04/06/2015 - 05/08/2015; Cooper Nuclear Station; Component Design Basis Inspection and Notice of Violation ML15173A4502015-06-22022 June 2015 IR 05000298/2015007; on 04/06/2015 - 05/08/2015; Cooper Nuclear Station; Component Design Basis Inspection and Notice of Violation IR 05000298/20130092013-05-0909 May 2013 IR 05000298-13-009; March 11-28, 2013; Cooper Nuclear Station, Biennial Baseline Inspection of the Identification and Resolution of Problems and Notice of Violation ML13130A0372013-05-0909 May 2013 IR 05000298-13-009; March 11-28, 2013; Cooper Nuclear Station, Biennial Baseline Inspection of the Identification and Resolution of Problems and Notice of Violation ML12314A3722012-11-0909 November 2012 IR 05000298-12-004; 06/27/2012 - 09/26/2012; Cooper Nuclear Station, Integrated Resident and Regional Report; Equipment Alignment, Licensed Operator Requalification Program and Licensed Operator Performance, Maintenance Risk Assessments and NLS2012020, Response to Integrated Inspection Report No. 05000298/2011005, Denial of Non-Cited Level IV Violation No. 05000298/2011005-07, Cooper Nuclear Station, Docket No. 50-298, DPR-0462012-03-0808 March 2012 Response to Integrated Inspection Report No. 05000298/2011005, Denial of Non-Cited Level IV Violation No. 05000298/2011005-07, Cooper Nuclear Station, Docket No. 50-298, DPR-046 IR 05000298/20110062011-08-0808 August 2011 IR 05000298-11-006; 6/6/2011 - 6/24/2011; Cooper Nuclear Station, Biennial Baseline Inspection of the Identification and Resolution of Problems ML1122014992011-08-0808 August 2011 IR 05000298-11-006; 6/6/2011 - 6/24/2011; Cooper Nuclear Station, Biennial Baseline Inspection of the Identification and Resolution of Problems IR 05000298/20110092011-06-10010 June 2011 EA-11-204, Cooper Nuclear Station, Final Significance Determination of White Finding and Notice of Violation, NRC Inspection Report 05000298/2011009 ML1112306532011-05-0303 May 2011 IR 05000298-11-002 and Notice of Violation, on 01/01/11 - 03/24/11, Cooper IR 05000298/20110022011-05-0303 May 2011 IR 05000298-11-002 and Notice of Violation, on 01/01/11 - 03/24/11, Cooper IR 05000298/20100052011-02-10010 February 2011 IR 05000298-10-005; 09/24/2010 - 12/31/2010; Cooper Nuclear Station; Integrated Resident and Regional Report; Fire Protection, Maintenance Risk Assessments and Emergent Work Control, and Exercise Evaluation ML0821405182008-08-0101 August 2008 2008-02 Final Significance Determination for a White Finding and Notice of Violation IR 05000298/20080082008-06-13013 June 2008 IR 05000298-08-008, on 03/19/2008 - 06/13/2008, for Cooper, Triennial Fire Protection Follow-up Inspection ML0816500902008-06-13013 June 2008 IR 05000298-08-008, on 03/19/2008 - 06/13/2008, for Cooper, Triennial Fire Protection Follow-up Inspection IR 05000298/20070072007-10-23023 October 2007 Acceptance of White Finding and Notice of Violation - NRC Special IR 05000298-07-007 - Cooper Nuclear Station ML0722901672007-08-17017 August 2007 Final Significance Determination for a White Finding and Notice of Violation - NRC Special Inspection Report 05000298/2007007 ML0208601742002-03-26026 March 2002 EA-01-298, Cooper Nuclear Station-Final Significance Determination for a White Finding and Notice of Violation (NRC Inspection Report No. 50-298/01-12) ML0206002702002-03-0101 March 2002 EA-01-231 Nebraska Public Power District, Final Significance Determination for Two White Findings and Notice of Violation (NRC Inspection Report 50-298/01-09) 2024-04-01
[Table view] |
Inspection Report - Cooper - 2007007 |
---|
|
|
|
Text
ber 23, 2007
SUBJECT:
ACCEPTANCE OF WHITE FINDING AND NOTICE OF VIOLATION - NRC SPECIAL INSPECTION REPORT 05000298/2007007 - COOPER NUCLEAR STATION
Dear Mr. Minahan:
Thank you for your letter dated October 15, 2007, in response to our August 17, 2007, letter and Notice of Violation concerning failing to promptly identify and correct, to preclude recurrence, of a significant condition adverse to quality regarding a defective voltage regulator circuit board used in Emergency Diesel Generator 2. The significance of this finding was determined to be White, a finding with low to moderate safety significance. We have reviewed your reply and find it responsive to the concerns raised in our Notice of Violation.
Based on the guidance in Inspection Manual Chapter (IMC) 0305, the NRC staff will perform a 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area. This inspection is scheduled for the week of December 3, 2007. We will review the implementation of your corrective actions during this inspection to determine that full compliance has been achieved and will be maintained.
Sincerely,
/RA/
Michael C. Hay, Chief, Reactor Projects Branch C Docket: 50-298 License: DPR-46
Nebraska Public Power District -2-cc w/Enclosures:
Gene Mace Director, Missouri State Emergency Nuclear Asset Manager Management Agency Nebraska Public Power District P.O. Box 116 P.O. Box 98 Jefferson City, MO 65102-0116 Brownville, NE 68321 Chief, Radiation and Asbestos John C. McClure, Vice President Control Section and General Counsel Kansas Department of Health Nebraska Public Power District and Environment P.O. Box 499 Bureau of Air and Radiation Columbus, NE 68602-0499 1000 SW Jackson, Suite 310 Topeka, KS 66612-1366 David Van Der Kamp Licensing Manager Melanie Rasmussen, State Liaison Nebraska Public Power District Officer/Radiation Control Program Director P.O. Box 98 Bureau of Radiological Health Brownville, NE 68321 Iowa Department of Public Health Lucas State Office Building, 5th Floor Michael J. Linder, Director 321 East 12th Street Nebraska Department of Des Moines, IA 50319 Environmental Quality P.O. Box 98922 John F. McCann, Director, Licensing Lincoln, NE 68509-8922 Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
Chairman 440 Hamilton Avenue Nemaha County Board of Commissioners White Plains, NY 10601-1813 Nemaha County Courthouse 1824 N Street Keith G. Henke, Planner Auburn, NE 68305 Division of Community and Public Health Office of Emergency Coordination Julia Schmitt, Manager 930 Wildwood, P.O. Box 570 Radiation Control Program Jefferson City, MO 65102 Nebraska Health & Human Services Dept. of Regulation & Licensing Paul V. Fleming, Director of Nuclear Division of Public Health Assurance Safety Assurance 301 Centennial Mall, South Nebraska Public Power District P.O. Box 95007 P.O. Box 98 Lincoln, NE 68509-5007 Brownville, NE 68321 H. Floyd Gilzow Deputy Director for Policy Missouri Department of Natural Resources P. O. Box 176 Jefferson City, MO 65102-0176
Nebraska Public Power District -3-Electronic distribution by RIV:
Regional Administrator (EEC)
Deputy Regional Administrator (TPG)
DRP Director (ATH)
DRP Deputy Director (AXV)
DRS Director (DDC)
DRS Deputy Director (RJC1)
Senior Resident Inspector (NHT)
Branch Chief, DRP/C (MCH2)
Senior Project Engineer, DRP/C (WCW)
Branch Chief, EB1, DRS (WBJ)
Team Leader, DRP/TSS (CJP)
RITS Coordinator (MSH3)
State Liaison Officer (WAM)
Public Affairs Officer (VLD)
K.S. Fuller, RC/ACES (KSF)
Enforcement Specialist (GMV)
C.A. Carpenter, D:OE (CAC)
OE EA File (RidsOeMailCenter)
SUNSI Review Completed: MCH ADAMS: : Yes G No Initials: MCH
- Publicly Available G Non-Publicly Available G Sensitive : Non-Sensitive R:\_REACTORS\CNS\2007\CNS 2007-07_ThankYouLtr.wpd SPE:DRP/C C:DRP/C WCWalker MCHay
/RA/ /RA/
10/23/07 10/23/07 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax