IR 05000298/2023003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000298/2023003
ML23305A144
Person / Time
Site: Cooper Entergy icon.png
Issue date: 11/02/2023
From: William Schaup
NRC/RGN-IV/DORS/PBC
To: Dia K
Nebraska Public Power District (NPPD)
References
IR 2023003
Download: ML23305A144 (24)


Text

November 02, 2023

SUBJECT:

COOPER NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000298/2023003

Dear Khalil Dia:

On September 30, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Cooper Nuclear Station. On October 5, 2023, the NRC inspectors discussed the results of this inspection with John Dent, Executive Vice President and CNO, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, William T. Schaup, Jr., Acting Branch Chief Reactor Projects Branch C Division of Operating Reactor Safety Docket No. 05000298 License No. DPR-46

Enclosure:

As stated

Inspection Report

Docket Number:

05000298

License Number:

DPR-46

Report Number:

05000298/2023003

Enterprise Identifier:

I-2023-003-0010

Licensee:

Nebraska Public Power District

Facility:

Cooper Nuclear Station

Location:

Brownville, NE

Inspection Dates:

July 1, 2023, to September 30, 2023

Inspectors:

G. Birkemeier, Resident Inspector

K. Chambliss, Senior Resident Inspector

R. Kopriva, Senior Project Engineer

J. O'Donnell, Senior Health Physicist

W. Schaup, Acting Branch Chief

S. Veunephachan, Health Physicist

Approved By:

William T. Schaup, Jr., Acting Branch Chief

Reactor Projects Branch C

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Cooper Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000298/2022-002-01 Manual Core Spray Injection to Restore Skimmer Surge Tank Level 71153 Closed

PLANT STATUS

Cooper Nuclear Station began the inspection period at rated thermal power. On August 18, 2023, power was lowered to approximately 65 percent for a planned rod pattern adjustment. The plant returned to rated thermal power on August 19, 2023. On September 30, 2023, power was lowered to approximately 80 percent for flexible power operations. The plant returned to rated thermal power on October 1,

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal hot temperatures for the following systems:
  • heating, ventilation, and air conditioning on July 24, 2023

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)reactor core isolation cooling system on July 14, 2023 (2)emergency diesel generator division 2 on July 24, 2023 (3)125 Vdc battery system division 1 on August 15, 2023 (4)core spray subsystem B on August 15, 2023 (5)core spray subsystem A on September 27, 2023

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the high pressure coolant injection system on August 18, 2023.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)reactor building standby liquid control area, 976-foot 0-inch elevation, on July 12, 2023 (2)reactor building northeast quadrant, 881-foot 0-inch and 859-foot 0-inch elevations, on July 14, 2023 (3)reactor building southeast quadrant, 881-foot 0-inch and 859-foot 0-inch elevations, on July 14, 2023 (4)reactor building northwest quadrant, 881-foot 0-inches and 859 foot 0-inches, on July 25, 2023 (5)control building battery and switchgear rooms, 903-foot 6-inch elevation, on July 25, 2023 (6)reactor building southwest quadrant, 881-foot 0-inch and 859-foot 0-inch elevations, on July 27, 2023 (7)control building critical switchgear rooms, elevation 932-foot 6-inch elevation, on July 27, 2023

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an announced fire drill on August 16, 2023.

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) emergency diesel generator 2 lube oil and jacket water heat exchanger on August 14, 2023

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during quarterly downpower for rod sequence exchange on August 21, 2023.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated simulator licensed operator training on July 12, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)radiation monitoring function RMP-F03 near (a)(1) on August 24, 2023 (2)core spray function CS-PF01A potentially at (a)(1) due to relay failing to fully drop out on August 24, 2023 (3)failure to properly scope in several components within the fuel pool cooling system into function FPC-F01 on September 29, 2023

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)control of quality parts and verification of quality control process for relay replacement and maintenance in various safety-related systems on September 29, 2023

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)planned Yellow online risk during residual heat removal service water booster division 1 maintenance window on July 12, 2023 (2)planned Yellow online risk during high pressure coolant injection relay maintenance on July 31, 2023 (3)emergent assessment of risk due to through wall piping leakage near discharge flange of residual heat removal service water booster pump C on August 31, 2023 (4)planned Yellow online risk during reactor core isolation cooling maintenance window on September 6, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)reactor core isolation cooling lube oil cooler auxiliary cooling water supply relief valve experiencing degradation of seat leakage on July 14, 2023 (2)service water check valve to emergency diesel generator inservice test missed due to operator misinterpreting test setting value on July 24, 2023 (3)potential loss of secondary containment due to path from secondary containment to atmosphere not being identified prior to maintenance activities on August 31, 2023

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1)reactor core isolation cooling system temporary modification of trip and throttle valve closing time and sequence on September 8, 2023

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (7 Samples)

(1)high pressure coolant injection relay replacement operational testing on July 31, 2023 (2)division 1 residual heat removal service water booster maintenance window post work testing on August 1, 2023 (3)standby liquid control pump post work testing for pump and metering on August 25, 2023 (4)service water pump B maintenance window post maintenance testing on August 25, 2023 (5)service water booster pump C post work testing after through wall piping leak repairs on August 31, 2023 (6)system operability testing of core spray subsystem B following maintenance window activities on September 7, 2023 (7)reactor core isolation cooling maintenance window post maintenance and modification testing on September 29, 2023

Surveillance Testing (IP Section 03.01) (4 Samples)

(1)division 1 high pressure coolant injection steam line high flow channel functional test on July 13, 2023 (2)division 2 main steam isolation valve logic system functional test on July 31, 2023 (3)biennial residual heat removal division 2 pumps comprehensive testing on August 25, 2023 (4)high pressure coolant injection overspeed hydraulic reset timing functional test on September 20, 2023

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) full scale emergency preparedness drill on August 31,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (9 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1)portable survey instruments "ready for use" at the exit to the radiologically controlled area (2)portable survey instruments in storage, but "available for use" in the instrument lab (3)personnel contamination monitors at the exit to the radiologically controlled area (4)portal monitors at the exit to the protected area (5)chemistry count room instruments (gamma spectroscopy and liquid scintillation)

(6)process radiation monitors in the reactor building (7)area radiation monitors in the reactor building (8)elevated release point gaseous effluent monitor in the augmented radwaste building (9)turbine building gaseous effluent monitor

Calibration and Testing Program (IP Section 03.02) (14 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Ludlum Model 177, RP-11281, frisker
(2) Ludlum Model 3, RP-11330, count rate meter - alpha
(3) Ludlum Model 2401P, RP-11292, dose rate meter
(4) Mirion Wide Range TelePole II, RP-11967, dose rate meter
(5) Mirion TelePole, RP-11246, dose rate meter
(6) Eberline RO-20, RP-10749, dose rate meter
(7) HPI REM-500, RP-100516, neutron survey meter
(8) Thermo Eberline SAM, RP-11152, contamination (small article) monitor
(9) Canberra GEM-5, RP-11996, gamma exit monitor
(10) Canberra ARGOS -5AB, RP-11983, personnel contamination monitor
(11) Eberline E-140, RP-10063, dose rate meter
(12) Victoreen Model 875, RMA-RM-40A/B, containment high range radiation monitors
(13) Canberra High Purity Germanium Detector 01, gamma spectroscopy system
(14) General Electric RMA-RM-1 through RMS-RM-30, area radiation monitors Effluent Monitoring Calibration and Testing Program Sample (IP Section 03.03) (3 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1)liquid radwaste effluent monitor RMP-RM-354 (2)reactor building vent monitor RMV-RM-40 (3)turbine building vent monitor RMV-RM20A

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, and

Transportation

Radioactive Material Storage (IP Section 03.01)

The inspectors evaluated the licensees performance in controlling, labeling and securing the following radioactive materials:

(1) Part 37 radioactive materials and selected sealed sources (2)radioactive material storage containers stored within the radiological controlled boundary and storage site

Radioactive Waste System Walkdown (IP Section 03.02) (2 Samples)

The inspectors walked down the following accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality:

(1)radioactive liquid processing system (2)solid radioactive processing system

Waste Characterization and Classification (IP Section 03.03) (2 Samples)

The inspectors evaluated the following characterization and classification of radioactive waste:

(1)2022 Part 61 spent bead resin waste stream analysis and characterization (2)2022 Part 61 dry active waste stream analysis and characterization

Shipping Records (IP Section 03.05) (4 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1) Shipment number 23-06, UN 3321, LSA II, Class AU dewatered bead resin
(2) Shipment number 22-05, UN2916, Yellow-III, Type B(U), Class AU mixed bead resin
(3) Shipment number 22-11, UN 2912, LSA I, Class AU dry active waste
(4) Shipment number 23-03, UN3321, LSA II, Class AU mixed bead resin

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) July 1, 2022, through June 30, 2023 IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)
(1) July 1, 2022, through June 30, 2023

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (1 Sample)

(1) July 1, 2022, through June 30, 2023

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)review of follow-up actions regarding relays subject to 10 CFR Part 21 notification on September 29, 2023

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1)human performance trend resulting in configuration management, configuration control, and in-service testing issues on September 1, 2023

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000298/2022-002-01, Manual Core Spray Injection to Restore Skimmer Surge Tank Level (ADAMS Accession No. ML23180A170). The circumstances surrounding this LER and a Green, non-cited violation are documented in the Cooper Nuclear Station - Biennial Problem Identification and Resolution Inspection Report 05000298/2023010 (ML23135A107). This LER is closed.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 24, 2023, the inspectors presented the public radiation safety inspection results to Bill Chapin, General Manager of Plant Operations, and other members of the licensee staff.
  • On October 5, 2023, the inspectors presented the integrated inspection results to John Dent, Executive Vice President and CNO, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

CR-CNS-

22-01568, 2022-01692, 2022-02600, 2022-03646, 2023-

01821, 2023-01825, 2023-02721, 2023-03807, 2023-03882

0-CNS_FAP-WM-

016

Seasonal Reliability

2.1.12

Control Room Data

144

2.2.38

HVAC Control Building

2.2.39

HVAC Diesel Generator Building

2.2.47

HVAC Reactor Building

2.2.84

HVAC Main Control Room and Cable Spreading Room

Procedures

2.2.93

Sewage Lagoon

71111.01

Work Orders

WO 5393272, 5444141, 5444142, 5444177, 5444227, 5450139

Corrective Action

Documents

CR-CNS-

2018-08353, 2018-08576, 2021-04964, 2021-05277, 2022-

00698, 2022-01774, 2022-03120, 2022-04401, 2022-04507,

22-04797, 2022-04925, 2022-05599, 2022-05695, 2022-

06035, 2022-06037, 2022-06070, 2022-06072, 2022-06316,

23-00400, 2023-00423, 2023-00665, 2023-00975, 2023-

01149, 2023-01828, 2023-01977, 2023-01978, 2023-02401,

23-02881, 2023-02896, 2023-03347, 2023-03558, 2023-

06139, 2022-06143

DWG 2043

Reactor Core Isolation Coolant and Reactor Feed Systems

DWG 2044

High Pressure Coolant Injection and Reactor Feed Systems

DWG 2045,

Sheet 1

Flow Diagram Core Spray System

DWG 2077

Flow Diagram - Diesel Generator Building Service Water,

Starting Air, Fuel Oil, Sump System & Roof Drains

DWG 3058

DC One Line Diagram

Drawings

DWG 69-4

Valve Needle Model 500F

Clearance Order

ASB-1-2023

Summer ASB Work

Miscellaneous

Clearance Order

HPCI-1

Replace Relay K10 And K36

71111.04

Procedures

0.36.8

Electrical Safety Rule Book, Revision 230.36.8, Electrical

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Safety Rule Book

2.2.20

Standby AC Power System (Diesel Generator)

116

2.2.20.1

Diesel Generator Operations

2.2.20.2

Operation of Diesel Generators from Diesel Generator Rooms

2.2.33.1

High Pressure Coolant Injection System Operations

2.2.33A

High Pressure Coolant Injection System Component Checklist

2.2.33B

High Pressure Coolant Injection System Instrument Valve

Checklist

2.2.67A

Reactor Core Isolation Cooling System Component Checklist

2.2.9

CS Subsystem A Standby Status

2.2A.CS.DIV2

Core Spray Component Checklist (DIV 2)

2.2A.DG.DIV2

Standby AC Power System (Diesel Generator) Component

Checklist (DIV 2)

2.2A.DGDO.DIV1

Diesel Fuel Oil Transfer System Component Checklist (DIV 2)

2.2A_125DC.DIV1

25 VDC Power Checklist (DIV 1)

2.2B.DG.DIV2

Standby AC Power System (Diesel Generator) Instrument

Valve Checklist (DIV 2)

2.2B.DGDO.DIV2

Diesel Fuel Oil Transfer System Instrument Valve Checklist

(DIV 2)

2.3_DG2

Panel DG-2 - Annunciator DG-2

6.HPCI.311

HPCI Turbine Trip and Initiation

6.HPCI.311

HPCI Turbine Trip and Initiation Logic Functional Test

6.HPCI.313

HPCI (</= 165 PSIG) Beginning of Cycle Test

6.HPCI.318

HPCI Simulated Actuation Test (IST)

Corrective Action

Documents

CR-CNS-

2018-02084, 2018-02385, 2018-06275, 2019-00903, 2019-

01368, 2019-02575, 2019-06278, 2020-00766, 2020-00874,

20-05971, 2021-00495, 2021-02855, 2021-03030, 2021-

03150, 2021-03189, 2021-03981, 2022-00209, 2022-04525,

22-05579, 2023-00550, 2023-01031, 2023-01108, 2023-

01109, 2023-01725, 2023-03496

CNS-FP-211

Reactor Building Northeast Quadrant Elevations 881-9" and

859-9

71111.05

Fire Plans

CNS-FP-212

Reactor Building Southeast Quadrant Elevations 881-9" and

859-9

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CNS-FP-213

Reactor Building Northwest Quadrant Elevations 881-9 and

859-9

CNS-FP-214

Reactor Building Southwest Quadrant Elevations 881-9 and

859-9

CNS-FP-216

Reactor Building Critical Switchgear Room 1F Elevation 932-

CNS-FP-217

Reactor Building Critical Switchgear Room 1G Elevation 932-

CNS-FP-220

Reactor Building SBLC Area Elevation 976-0

CNS-FP-227

Control Building Corridor Battery/Switchgear/RPS Rooms 1A

Elevation 903-6

CNS-FP-228

Control Building Corridor Battery/Switchgear/RPS Rooms 1B

Elevation 903-6

CNS-FP-245

Turbine Generator Building North - Condensate Pump Area

Elevation 882-6

0-BARRIER

Barrier Control Process

0-BARRIER-

CONTROL

Control Building

0-BARRIER-

MAPS

Barrier Maps

0-BARRIER-MISC

Miscellaneous Buildings

0-BARRIER-

REACTOR

Reactor Building

0-BARRIER-

TURBINE

Turbine Building

0.23

CNS Fire Protection Plan

0.7.1

Control of Combustibles

2.2.30

Fire Protection System

5.1INCIDENT

Site Emergency Incident

5.4POST-FIRE-

TURBINE

Turbine Building/Outside Areas Post-Fire Operational

Information

Procedures

EPIPEALHOT

CNS EAL Wall Chart Hot

71111.07A

Corrective Action

Documents

CR-CNS-

23-01843, 2023-01849, 2023-01965, 2023-01976, 2023-

01977, 2023-02019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Drawings

DWG KSV-47-9-

NP

Jacket Water Schematic

Miscellaneous

VM-1778

ITT/American Heat Exchangers Composite Manual

Work Orders

WO 5441278

Corrective Action

Documents

CR-CNS-

21-01581, 2021-01938, 2022-03751, 2023-03791, 2023-

03792, 2023-03793, 2023-03794

10.13

Control Rod Sequence and Movement Control

10.14

Reactivity Maneuver Plan

15.TG.301

Main Turbine Lube Oil Pumps Functional Test

2.0.3

Conduct of Operations

106

2.1.10

Station Power Changes

23

2.3_C-2

Panel C - Annunciator C-2

2.4EX-STM

Extraction Steam Abnormal

2.4PC

Primary Containment Control

2.4RR

Reactor Recirculation Abnormal

EOP-1A

RPV Control (1-3)

EOP-3A

Primary Containment Control (1-3)

71111.11Q

Procedures

EPIPEALHOT

CNS EAL Wall Chart Hot

Corrective Action

Documents

CR-CNS-

2019-01609, 2019-01613, 2019-01672, 2019-01673, 2019-

01674, 2019-01675, 2019-01676, 2020-01995, 2020-02930,

20-04733, 2020-05244, 2021-03316, 2021-05792, 2022-

201, 2022-00225, 2022-00452, 2022-04449, 2022-05293,

22-05296, 2022-05574, 2023-01010, 2023-01055, 2023-

252, 2023-02263, 2023-02274, 2023-02298, 2023-02545,

23-03260, 2023-03421

DWG 3752,

Sheet 3

Annunciator Loop Diagram ANN-MUX-2

DWG 791E265,

Sheet 2

Elementary Diagram Core Spray System

DWG 791E265,

Sheet 3

Elementary Diagram Core Spray System

Drawings

DWG 791E269,

Sheet 1

Elementary Drawing Fuel Pool Cooling and Cleanup System

71111.12

Miscellaneous

Maintenance Rule Function FPC-F01 Performance Criteria

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Basis Document

Maintenance Rule Function RMP-F03 Performance Criteria

Basis Document

Maintenance Rule Function CS-PF01A Performance Criteria

Basis Document

Maintenance Rule (a)(1) Evaluation, CR 2023-02298

07/25/2003

VM-0469

Rad Monitoring

VM-1025

Operations & Maintenance Instructions

0-CNS-FAP-QV-

400

Quality Control Hold Point Independent Review

0.50.5

Outage Shutdown Safety

2.1

CNS QC Program Description

2.5

CNS QC Functions

2.4FPC

Fuel Pool Cooling Trouble

3-CNS-DC-112

Engineering Change Request and Project Initiation Process

3-CNS-DC-213

Engineering Quality Review

4.15

Elevated Release Point and Building Kaman Radiation

Monitoring Systems

5.8.17

Primary Containment Venting

5.8.18

Primary Containment Venting for PCPL, PSP, Primary

Containment Flooding, or Early Containment Venting

5.8.21

PC Venting and Hydrogen Control (Less Than Combustible

Limits)

5.8.21

PC Venting and Hydrogen Control (Greater Than Combustible

Limits)

5.8.23

Decay Heat Removal Methods

EOP-3A

Primary Containment Control (1-3)

EOP-8A

RPV Control (4)

Procedures

EOP-8B

Decay Heat Removal (5,D)

Work Orders

WO 5300313, 5386055, 5430830, 5463574, 5503728, 5504618,

5504641

71111.13

Corrective Action

Documents

CR-CNS-

20-00907, 2023-01453, 2023-03091, 2023-03136, 2023-

03909, 2023-03911, 2023-03947

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Protected Equipment Tagout RHWA-1-SW-P-BPA WEEK

27

Protected Equipment Tagout RHWA-1-SW-P-BPCLEAK

Protected Equipment Tagout RCIC-1-RCIC TCC WEEK 2336

Miscellaneous

Protected Equipment Tagout HPCI-1-HPCI WK 2330

0-CNS-FAP-OM-

031

Emergent Issue Response, Risk Classification, and Oversight

Determination

0-CNS-WM-104

On-Line Risk Assessment

0-PROTECT-EQP

Protected Equipment Program

2, 63

2.0.2

Operation Logs and Reports

23

Procedures

7.0.8.1

System Leakage Testing

Work Orders

WO 5512675

Corrective Action

Documents

CR-CNS-

23-01325, 2023-03253, 2023-03296, 2023-03561, 2023-

03580

DWG 2012,

Sheet 1

Flow Diagram Building Heating and Auxiliary Steam Systems

DWG 2012,

Sheet 2

Flow Diagram Building Heating and Auxiliary Steam Systems

DWG 2012,

Sheet 3

Flow Diagram Building Heating and Auxiliary Steam Systems

DWG 2012,

Sheet 4

Flow Diagram Building Heating and Auxiliary Steam Systems

DWG 2012,

Sheet 5

Flow Diagram Building Heating and Auxiliary Steam Systems

Drawings

DWG 2041

Flow Diagram Reactor Building Main Steam System

VM-0005

Consolidated Safety & Relief Valve Composite Manual

NEDC 07-082

Radiological Dose Analysis for a Loss of Coolant Accident

(LOCA) at Cooper Nuclear Station

Miscellaneous

VM-0227

Cast Steel Valves

0-CNS-31

CNS Clearance Order and Lockout Standards

13.1

ECCS Leakage Evaluation

71111.15

Procedures

6.1SW.401

Diesel Generator Service Water Check Valve and Sump Test

(IST)(DIV 1)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

6.MISC.501

ECCS Leakage Walkdown

6.SC.501

Secondary Containment Leak Test

6.SC.502

Secondary Containment Penetration Examination

Work Orders

WO 5401965, 5453354

NEDC 31322

BWR Owners Group Report on the Operational Design Basis

of Safety-Related Motor Operated Valves

NEDC 87-131C

25 VDC Division 1 Load and Voltage Study

CCN 19C8

NEDC 91-079

System Level Design Basis Review for Reactor Core Isolation

Cooling System MOVs

Calculations

NEDC 96-039

RC-Powered Motor Operated Valve Stroke Time and

Capability Calculation

Corrective Action

Documents

CR-CNS-

23-02885

Drawings

DWG

29E517BC,

Sheet 3

Reactor Core Isolation Cooling System Functional Control

Drawing

Temporary Configuration TCC-5503748, RCIC Jumpers For

RCIC Turbine Trip on High Water Level

Miscellaneous

VM-0075

RCIC Pump Drive

0.31MOV

Motor Operated Valves

0.4LSFT

Logic System Functional Test (LSFT) Guidelines

2.2.67

Reactor Core Isolation Cooling System

2.2.67.1

Reactor Core Isolation Cooling System Operations

3-CNS-DC-354

Risk Assessment of Surveillance Test Interval Changes

4.6.1

Reactor Vessel Water Level Indication

Procedures

6.RCIC.102

RCIC IST And 92 Day Test

71111.18

Work Orders

WO 287229

Corrective Action

Documents

CR-CNS-

20-00181, 2020-00677, 2020-01524, 2020-01990, 2020-

2944, 2021-03591, 2023-02252, 2023-03381, 2023-03436,

23-03909, 2023-03911, 2023-03947

DWG 2006,

Sheet 1

Flow Diagram Circulating, Screen Wash, & Service Water

Systems

71111.24

Drawings

DWG 2006,

Sheet 4

Flow Diagram Control Building Service Water System

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DWG 2026,

Sheet 1

Flow Diagram Reactor Vessel Instrumentation

DWG 2040,

Sheet 2

Flow Diagram Residual Heat Removal System Loop B

DWG 2045,

Sheet 1

Flow Diagram Core Spray System

DWG 2045,

Sheet 1

Flow Diagram Core Spray System

DWG 2C4747

28KXL1STGVCT Service Water Pump

DWG-2044

Flow Diagram - High Pressure Coolant Injection and Reactor

Feed Systems

DWG-791E271,

Sheet 4

Elementary Diagram HPCI System

Protected Equipment Tagout RHWA-1-SW-BPA WEEK 2327

Miscellaneous

VM-1824

Allen Bradley Composite Manual

6.1HPCI.701

HPCI Steam Line High Flow Channel Functional Test (DIV 1)

6.1SWBP.101

RHR Service Water Booster Pump Flow Test and Valve

Operability Test (DIV 1)

6.2RHR.101

RHR Test Mode Surveillance Operation (IST) (DIV2)

6.2RPS.305

MSIV Channel Logic Test (DIV 2)

6.2SC.101

Core Spray Test Mode Surveillance Operation (IST) (DIV 2)

6.2SC.501

ASME Section XI Periodic Pressure Test of Class 2 Core

Spray System Loop B

6.2SW.101

Service Water Surveillance Operation (DIV 2) (IST)

6.HPCI.312

HPCI Pump Low Discharge Flow Channel Calibration

6.HPCI.317

HPCI Overspeed Hydraulic Reset Timing Calibration and

Functional Test

6.HPCI.709

HPCI Gland Seal Condenser Hotwell Level Channel

Functional Test

6.RCIC.102

RCIC IST and 92 Day Test

6.RCIC.201

RCIC Power Operated Valve Operability Test (IST)

6.SLC.101

SLC Pump Operability Test

Procedures

7.0.14.2.2

Oil Sampling

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

7.0.8.1

System Leakage Testing

Work Orders

WO 5356822, 5389891, 5399151, 5405058, 5405064, 5407274,

5407315, 5407316, 5407322, 5412210, 5412228, 5414706,

5455461, 5455551, 5455622, 5455635, 5503746, 5504618,

5504641, 5512675,

Corrective Action

Documents

CR-CNS-

23-03934, 2023-03936, 2023-03943, 2023-03944, 2023-

03946, 2023-03954

2.1.5

Reactor Scram

2.4FPC

Fuel Pool Cooling Trouble

2.4PC

Primary Containment Control

2.4TURB

Main Turbine Abnormal

5.1QUAKE

Earthquake

5.3ALT-

STRATEGY

Alternate Core Cooling Mitigating Strategies

5.3DC125

Loss of 125 VDC

5.3EMPWR

Emergency Power During Modes 1,2, or 3

5.3SBO

Station Blackout

5.7.2

Emergency Director EPIP

5.7.6

Notification

5.8.1

RPV Pressure Control Systems

EOP-1A

RPV Control (1-3)

EOP-1B

Alternate Level/Pressure Control

EOP-3A

Primary Containment Control (1-3)

71114.06

Procedures

EPIPEALHOT

CNS Wall Chart Hot

5166228 /

5166232 /

5398873

14.8.16 KAMAN System Flow Indication Calibration

2/17/2021

and

03/03/2021

and

06/02/2021

5166232

6.PRM.315 Turbine Building KAMAN Channel Calibration

03/05/2021

5166732

6.PRM.329 Containment High Range Monitors A/R/H

Determination

10/03/2018

71124.05

Calibration

Records

238323 /

248168

15.ARM.302 Area Radiation Monitors Calibration and

Functional Test - 2020

03/06/2020

and

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

06/01/2020

282475

6.PRM.323 High Range Containment Monitor Victoreen

Model 875 Source Calibration Check

10/04/2020

5315880 /

5413628 /

5340429

15.ARM.302 Area Radiation Monitors Calibration and

Functional Test - 2021

10/14/2021

and

2/30/2021

5358399

6.PRM.313 Reactor Building KAMAN Monitor Channel

Calibration

08/17/2022

5362794

6.PRM.308 Liquid Radwaste Effluent System Channel

Calibration

08/31/2022

5384952

6.PRM.322 Containment High Range Area Monitor Channel

Calibration

10/27/2022

5399148

6.PRM.322 SW Radiation Monitor B Calibration Check and

Instrument Channel Test

05/16/2023

Detector 1 - 2

Liter Marinelli

Efficiency Confirmation Check Report

07/25/2022

Detector 1 -

Charcoal Canister

Efficiency Confirmation Check Report

08/12/2022

Detector 1 -

Particulate Filter

Efficiency Confirmation Check Report

05/20/2023

RP-100516

Certificate of Calibration

HPI REM-500

06/08/2022

RP-10063

Instrument Calibration Data Sheet

Eberline E-140

08/08/2022

RP-10749

Instrument Calibration Data Sheet

Eberline RO-20

03/14/2023

RP-11152

Instrument Calibration Sheet

Thermo Eberline SAM

05/01/2023

RP-11246

Instrument Calibration Data Sheet

Mirion WR TelePole

03/20/2023

RP-11281

Instrument Calibration Data Sheet

Ludlum Model 177

2/02/2023

RP-11292

Instrument Calibration Data Sheet

Ludlum Model 2401P

06/06/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

RP-11330

Instrument Calibration Data Sheet

Ludlum Model 3

05/10/2023

RP-11967

Instrument Calibration Data Sheet

Mirion Wide Range TelePole II

03/15/2023

RP-11983

Instrument Calibration Data Sheet

Canberra ARGOS-5AB

08/29/2022

RP-11996

Instrument Calibration Sheet

Canberra GEM-5

08/22/2022

Corrective Action

Documents

CR-CNS-

21-04133, 2021-04226, 2021-04298, 2021-04381, 2021-

04793, 2021-05062, 2022-02044, 2022-02050, 2022-02334,

22-03074, 2022-03078, 2022-04111, 2022-04318, 2022-

04646, 2022-05514, 2023-00188, 2023-01040, 2023-01967,

23-02439, 2023-02606, 2023-02725, 2023-02908, 2023-

2909, 2023-02946

Corrective Action

Documents

Resulting from

Inspection

CR-CNS-

23-03848

Miscellaneous

2Q2023

System Health Report:

Radiation Monitors

07/19/2023

3.26

Instrument Setpoint Control

07/25/2018

6.PRM.308

Liquid Radwaste Effluent System Channel Calibration

2/19/2020

6.PRM.313

Reactor Building KAMAN Monitor Channel Calibration

03/17/2021

6.PRM.315

Turbine Building KAMAN Channel Calibration

03/08/2023

6.PRM.322

Containment High Range Area Monitor Channel Calibration

2/21/2022

6.PRM.323

High Range Containment Monitor Victoreen Model 875

Source Calibration Check

2/08/2023

9.INST.50

Geiger-Mueller (GM) Survey Meters

01/12/02022

9.INST.53

Ion Chamber Survey Instrument - Eberline Model RO-20

09/08/2021

9.INST.68

WR TelePole GM Survey Instrument

07/19/2023

9.INST.70

TelePole II Telescopic Meter

10/23/2019

9.INST.71

CRONOS Gamma Object/Tool Monitor

06/15/2022

Procedures

ODAM

Offsite Dose Assessment Manual

04/01/2020

Self-Assessments

LO-2022-0100

Radiological Monitoring Instrumentation and Radioactive Solid

01/19/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Waste Processing and Radioactive Material Handling,

Storage, and Transport

577786003

Spent Bead Resin Waste Stream Analysis

2/03/2022

Miscellaneous

8-J Cond-WST

23 condensate waste storage tank waste stream analysis

2/27/2023

Self-Assessments

8-C 2022

71124.05-08 Pre-NRC Assessment Report

2/16/2022

2-02

Shipping record 22-02 UN 2912, LSA-I Class 7 AU

04/15/2022

71124.08

Shipping Records

23-04

Shipping record UN2912 LSA-I, Dry active waste, AU

03/27/2023

Miscellaneous

Performance Indicator Documentation and Data Review

Package

0-EN-LI-114

Regulatory Performance Indicator Process

6.1SW.401

Diesel Generator Service Water Check Valve and Sump Test

(IST)(DIV 1)

71151

Procedures

6.HPCI.314

HPCI Pump Discharge Flow Indication Calibration

DWG 3071

Control Elementary Diagram

DWG 3257,

Sheet 66

Alternate Shutdown HPCI Panel Internal Connections

DWG 791E261,

Sheet 18

Elementary Drawing Residual Heat Removal System

DWG 791E261,

Sheet 21

Elementary Drawing Residual Heat Removal System

DWG 791E261,

Sheet 22

Elementary Drawing Residual Heat Removal System

DWG 791E261,

Sheet 3

Elementary Drawing Residual Heat Removal System

DWG 791E261,

Sheet 7

Elementary Drawing Residual Heat Removal System

DWG 791E271,

Sheet 6

HPCI System Elementary Diagram

DWG 791E562,

Sheet 2

Panel 9-3 Connection Diagram

DWG 791E562,

Sheet 6

Panel 9-3 Connection Diagram

Drawings

DWG CNSEE89

HPCI Flow Control and Indication Loop Diagram DC 86-21

71152A

Miscellaneous

Clearance Orders

SDG-1-5451827 SDG-VI-PSYNC 02

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0.31.1

Configuration Control During Maintenance Activities

0.9

Tagout

113

2.2.99

Supplemental Diesel Generator System

Procedures

7.3.24.2

HFA DC and AC Relay Pick-Up Test

Corrective Action

Documents

CR-CNS-

20-05244, 2022-02778, 2022-04176, 2022-06139, 2022-

06878, 2023-00085, 2023-00400, 2023-00454, 2023-00487,

23-00492, 2023-00528, 2023-00960, 2023-01170, 2023-

01171, 2023-01317, 2023-01340, 2023-01385, 2023-01415,

23-01421, 2023-01423, 2023-01453, 2023-01956, 2023-

252, 2023-02274, 2023-02322, 2023-02357, 2023-02468,

23-02823, 2023-03026, 2023-03091, 2023-03238, 2023-

296

71152S

Work Orders

WO 5075843, 5401965, 5451827, 5503746

Corrective Action

Documents

CR-CNS-

22-05293, 2022-05296, 2023-01743, 2023-01750, 2023-

01757, 2023-01786, 2023-01842, 2023-01868

2.5FPC.F/DA

Fuel Pool Cooling Filter Demineralizer A

71153

Procedures

2.5FPC.F/DB

Fuel Pool Cooling Filter Demineralizer A

3