IR 05000298/2022010

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000298/2022010
ML22165A319
Person / Time
Site: Cooper Entergy icon.png
Issue date: 06/16/2022
From: Nick Taylor
NRC/RGN-IV/DORS
To: Dent J
Nebraska Public Power District (NPPD)
References
IR 2022010
Download: ML22165A319 (14)


Text

June 16, 2022

SUBJECT:

COOPER NUCLEAR STATION - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000298/2022010

Dear Mr. Dent:

On April 22, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Cooper Nuclear Station. On April 28, 2022, the NRC inspectors discussed the results of this inspection with Khalil Dia, General Manager of Plant Operations, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Nicholas H. Taylor, Chief Engineering Branch 2 Division of Operating Reactor Safety Docket No. 05000298 License No. DPR-46 Enclosure:

Inspection Report 05000298/2022010 Distribution via Listserv Signed by Taylor, Nicholas on 06/16/22

ML22165A319 X SUNSI Review By: GAP ADAMS:

X Yes No Sensitive X Non-Sensitive Non-Publicly Available X Publicly Available Keyword NRC-002 OFFICE RIV/EB2 DORS/EB2 DORS/EB2 EB2/BC PBC/BC EB2/BC NAME GPick NOkonkwo MChisolm NTaylor JJosey NTaylor SIGNATURE

/RA/

/RA/

/RA/

/RA/

/RA/

/RA/

DATE 6/14/2022 6/14/2022 6/15/2022 6/15/2022 6/15/2022 6/16/2022

Enclosure U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number:

05000298

License Number:

DPR-46

Report Number:

05000298/2022010

Enterprise Identifier:

I-2022-010-0008

Licensee:

Nebraska Public Power District

Facility:

Cooper Nuclear Station

Location:

Brownville, NE

Inspection Dates:

April 4 to 28, 2022

Inspectors:

G. Pick, Senior Reactor Inspector, Team Lead

M. Chisolm, Reactor Inspector

N. Okonkwo, Reactor Inspector

Approved By:

Nicholas H. Taylor, Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Cooper Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)

The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are in the safe shutdown analysis.

(1) Operator actions can be accomplished as assumed in the licensees fire probabilistic risk assessment analysis and safe shutdown analysis for Fire Area CB-D for a control room evacuation.
(2) Ensure that post maintenance tests and/or surveillance activities are performed as scheduled for the underground fire loop, fire pumps, and sprinkler system in the cable spreading room and halon gas system for the computer room.
(3) Walked down the sprinkler system and fire pumps to identify equipment alignment discrepancies. Inspect for deficient conditions such as corrosion, missing fasteners, cracks, and degraded insulation.
(4) Ensured that fire protection components are being managed for aging (e.g., loss of material, cracking, reduction of heat transfer) in accordance with appropriate aging management programs. Verify that the licensees aging management program activities associated with fire protection equipment are being implemented.

Fire Protection Program Administrative Controls (IP Section 03.02) (2 Samples)

The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees fire protection program contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.

(1) Hot work, fire impairment, and combustible control programs.
(2) Fire probabilistic safety assessment monitoring for classic fire protection activities.

Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)

The inspectors verified the following, as applicable:

a.

Changes to the approved fire protection program do not constitute an adverse effect on the ability to safely shutdown.

b.

The adequacy of the design modification.

c.

Assumptions and performance capability stated in the safe shutdown analysis have not been degraded through changes or modifications.

d.

The fire protection program documents, such as the Updated Final Safety Analysis Report, fire protection report, fire hazards analysis, and safe shutdown analysis were updated consistent with the fire protection program for design change.

e.

Post-fire safe shutdown operating procedures, such as abnormal operating procedures, affected by the modification were updated.

The inspectors reviewed the following as one sample:

Design Change 5229496, EOP PTM 97-100 Review - revises control logic for RHR MOVs 27A and spares

Engineering Change 6039780, Emergency Station Service Transformer (ESST)

Replacement

Engineering Evaluation 10-055, Fire Protection Evaluation of Conduit Internal Seals, Revision 1

Engineering Evaluation 01-009, Revise EE 01-009 to remove references to Kennedy FP, Revision 5

Engineering Evaluation 20-012, Evaluation of ClearView Shielding as Temporary Shielding Material

Engineering Evaluation 01-009, Revise EE 01-009 to replace Water Pressure and CO2 fire extinguishers with ABC fire extinguishers, Revision 6

Design Change 5357188, Replace Heat Activated Devices for Fire Protection Systems 9, 10, 12, & 13

Design Engineering Change 5246597, Relocates Hydrant #3 inside the protected area

Design Engineering Change 5343757, Replaces Computer Room Halon control and peripherals

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On April 28, 2022, the inspectors presented the triennial fire protection inspection results to Khalil Dia, General Manager of Plant Operations, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CNS-PSA-007

PRA Deterministic Calculation Notebook

NEDC 11-088

(Calc-17-031)

Fire Safety Analysis for Fire Area CB-0

NEDC 11-095

Fire Safety Analysis for Fire Area RB-DJ EPM Report RI-

1906-008-RBD-1

NEDC 14-056

Essential Control building Ventilation Desired Thermostat

Setpoints and Hydrogen Concentration Calculation

Calculations

NEDC-10-081

Task 8, Fire Risk Evaluation Area CB-A

Corrective Action

Documents

CR-CNS-

2008-01460, 2008-01576, 2008-02027, 2014-06146,

2016-03315, 2016-06698, 2016-07185, 2016-09062,

2017-04000, 2018-03118, 2019-00745, 2019-02049,

2019-02295, 2019-03165, 2019-05491, 2019-05576,

20-01859, 2020-04487, 2020-04670, 2020-05288,

20-05701, 2021-01477, 2021-01583, 2021-01787,

21-01858, 2021-02419, 2021-02467, 2021-03321,

21-03791, 2021-03793, 2021-04960, 2021-05266,

22-00362

Corrective Action

Documents

Resulting from

Inspection

CR-CNS-

22-01468, 2022-01470, 2022-01473, 2022-01474,

22-01492, 2022-01494, 2022-01497, 2022-01515,

22-01519, 2022-01770, 2022-01794

2016, Sheet 1B

Flow Diagram, Fire Protection, Cont., RW, ARDW Bldg

2016, Sheet 4

Halon and Cardox System Flow Diagram

2018

Flow Diagram Turbine Generator Bldg. & Control Bldg.

Heating & Ventilating

25

HVAC Control Bldg., Plan El 877-6 & El. 903-6 &

Section

3009 Sheet 1

Cooper Nuclear Station One Line Switching Diagram 12.5

kV Ring Bus System

3009 Sheet 4

Cooper Nuclear Station Fire Protection Pump "E"/Panel

DPTC1 Heat Trace Feeder Auxiliary One Line Diagram

71111.21N.05

Drawings

3036 Sheet 5

Control Elementary Diagrams

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

3101

Turbine Generator Bldg, Basement & Mezzanine

Grounding Plans

257 Sheet 65

Cooper Nuclear Station Alternate Shutdown HPCI Panel

Internal Connections

257 Sheet 66

Cooper Nuclear Station Alternate Shutdown HPCI Panel

Internal Connections

257 Sheet 67

Cooper Nuclear Station Alternate Shutdown HPCI Panel

External Connections

2242808

Fire Protection Pre-Fire-Plan, Reactor Building Southwest

Quadrant Elevation 881-9 and 859-9

2242809

Fire Protection Pre-Fire-Plan, Reactor Building First Floor

Elevation 903-6

2242819

Fire Protection Pre-Fire-Plan, Control Building Auxiliary

Relay Room, Elevation 903-6

2242823

Fire Protection Pre-Fire-Plan, Control Building Cable

Spreading Room Elevation 918-0

2242824

Fire Protection Pre-Fire-Plan, Con. Bldg Control Rm and

Comp Rm Elevation 932-6

2242828

Fire Protection Pre-Fire-Plan, Office Building Cable

Expansion Room Elevation 918-6

454003604

Flow Diagram, Fire Protection, Turbine Generator Building

454250005

Main Power Transformer Fire Protection, Fire Alarm

Control Panel Mechanical Outline

454250006

Main Power Transformer Fire Protection, Fire Alarm

Control Panel Interconnection Diagram

454250007

Main Power Transformer Fire Protection, Fire Alarm &

Detection System, Detection Layout & Valve Station

Layout

B

454250008

Main Power Transformer Fire Protection, Fire Alarm &

Detection System, Wiring Detail

D

64929D, Sheet 1

Fire Protection System Detection Layout Systems 9 & 10

Reactor Feed Pump 1A and 1B

C

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

64929M

Fire Protection System Mechanical Outline - ACI Model

A888-M1638

B

791E271,

Sheet 1A

Cooper Nuclear Station Elem Diagram HPCI System

CNS-FP-214

Fire Protection Pre-Fire Plan Reactor Building Southwest

Quadrant Elevations 881'-9" and 859'-9"

CNS-FP-215

Fire Protection Pre-Fire Plan Reactor Building First Floor

Elevation 903'-6"

CNS-FP-225

Fire Protection Pre-Fire Plan Control Building Auxiliary

Relay Room Elevation 903'-6"

CNS-FP-229

Fire Protection Pre-Fire Plan Control Building Cable

Spreading Room Elevation 918'-6"

CNS-FP-230

Fire Protection Pre-Fire Plan Control Building Control

Room and Computer Room Elevation 932'-6"

CNS-FP-234

Fire Protection Pre-Fire Plan Office Building Cable

Expansion Room Elevation 918'-6"

IN 08-1232

Equipment Layout Halon, 1301 System, NPPD Computer

Room

DC5229496

EOP PTM 97-100 Switches

DEC-5343757

Computer Room Halon System Control Upgrade

EC 6039780

Emergency Station Service Transformer Replacement

EE-01-006

Disposition of NFPA Code Compliance Deviations

(Systems in Fire Zones Requiring an IPEEE Phase 2

Screening)

EE-01-009

Review of NFPA 10, 14, & 24 Code Conformance for

Power Block Buildings

EE-01-009

Review of NFPA 10, 14, & 24 Code Conformance for

Power Block Buildings

Engineering

Changes

TCC 5396378

TCC repowers various electrical equipment that would

normally be de-energized during a 4160V Bus G outage.

EE 10-055

Fire Protection Evaluation of Conduit Internal Seals

EE 20-12

Evaluation of ClearView Shielding as Temporary Shielding

Material

Engineering

Evaluations

ER 2015-002

NFPA 805 Fire Protection Monitoring Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NEDC 10-041

Recovery Action Feasibility Assessment Report Review

EPM Report R1906-004-005

NEDC 11-088

Fire Safety Analysis for Fire Area CB-D

NEDC-10-085

Scientech Calculation 17712-018-04, Task 8 Fire Risk

Evaluation Area CB-D

2.3-FP-5

Fire Protection - Annunciator 5

3002018285

Results of Accelerated Aging for Sprinklers Used in

Nuclear Power Plants: Fire Sprinkler Head Testing

11/2020

ANSI/ANS-58.8

Time Response Design Criteria for Safety-related

Operator Action

1994

ANSIANS-59.2

Safety criteria for HVAC systems located outside Primary

Containment

1985

CED 6017100

Battery Room Heating Evaluation

2/19/05

CNS System

Health

FP System Health Report 21-10

10/2021

CNS System

Health

FP System Health Report 21-07

7/2021

Construction

Standard

U12S3C3 Dwg

NC34572

2KV-SW-Duct-3PH-Pad-SWGR 09/10/11/12

EE 01-006

Disposition of NFPA Code Compliance Deviations

(Systems in Fire Zones Requiring an IPEEE Phase 2

Screening)

FAQ (Frequently

Asked Question)

07-0030

Establishing Recovery Actions

FAQ 10-0059

NFPA (National Fire Protection Association) 805

Monitoring

FP-PNL-XFMR

Digital Evaluation of Fire Protection Panel for Transformer

Deluge Systems

2/04/2012

Miscellaneous

Information Notice 97-78

Crediting of Operator Actions in Place of Automatic

Actions and Modifications of Operator Actions, Including

Response Times

10/23/1997

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Instruction Sheet

2-505

Manual PMH Pad-Mounted Gear Outdoor Distribution

(14.4kV AND 25kV)

3/9/2020

NC33070

KV-SW-Duct-3PH-Pad, SWGR 03/04 Conn. Diag.

3/1/2020

NEDC 09-085

Section 7.44 Incipient Detection Excerpt from NEDC 09-

085 Rev. 4 Fire Risk Quantification

NEDC 09-085,

Sec.7.4.4

Incipient Detection Excerpt from Fire Risk Quantification

NFPA 12A

Halon 1301 Fire Extinguishing Systems

2/1980

NLS2012006

License Amendment Request to Revise the Fire

Protection Licensing Basis to NFPA 805 Per 10 CFR 50.48(c)

4/24/2012

Procedure 7.0.7

rev 12 screen

Scaffolding Construction and Control rev 12 screen

Procedure 7.0.7

rev 16 screen

Scaffolding Construction and Control rev 16 screen

Procedure 7.0.7

rev 25 screen

Scaffolding Construction and Control rev 25 screen

Purchase Order

5404944

AFFF Foam Chemical Analysis Summary

2/14/2022

RT 5368430

20 Scaffold Inspection

10/25/2020

TRM T3.11

Technical Requirements Manual - Fire Protection Systems

10/17/2016

TSP 5209096

2018 Scaffold Inspection

4/30/2018

U12S3C4B

S-Switch Underground

3/10/2020

NDE Reports

Condensate

Storage Tank -

Wall & Floor

4/11/2011

0-CNS-LI-102

Corrective Action Process

0.23

CNS Fire Protection Plan

0.39

Hot Work

0.39.1

Fire Watches and Fire Impairments

0.39.1

Fire Watches and Fire Impairments

0.39.2

Ignition Source Procedure

Procedures

0.7.1

Control of Combustibles

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

11.CS-Dedicated

Media

Dedicated Use of Media

15.FP.307

Halon 1301 Computer Room Fire Suppression

Surveillance Checks

15.FP.309

Fire Protection Manual Pull Station Functional Test.

15.FP.647

Non-TRM Required Fire Fighting Equipment Examination

15.FP.650

Fire Locker and Hazardous Material Response Inventory

2.0.4

Relief Personnel and Shift Turnover

2.2.18.3.DIV1

4160V DIV 1 Distribution Support

2.2.38

System Operating Procedure, HVAC Control Building

3-CNS-DC-357

NFPA 805 Monitoring Program

3-EN-DC-115

Engineering Change Process

5.3SBO

Station Blackout

5.4FIRE-S/D

Fire Induced Shutdown From Outside Control Room

5.4Post -Fire-

Reactor

Reactor Building Post-Fire Operational Information

5.4Post-Fire-

Control

Control Building Post-Fire Operational Information

5.4Post-Fire-

Turbine

Turbine Building/Outside Areas Post-Fire Operational

Information

6.1FP.301

Diesel Generator C02 Operability Test (DIV 1)

6.1FP.302

Fire Detection System Examination (DIV 1)

6.FP.101

Fire Pump Operability Test

6.FP.102

Station Fire Pump Surveillance Testing

6.FP.102

Station Fire Pump Surveillance Testing

6.FP.203

Fire Damper Assembly Examination (Fire Protection

System 24 Months Examination)

6.FP.204

Fire Door Examination

6.FP.314

Panel 9-32 and 9-33 Incipient Smoke Detector Testing

6.FP.601

Fire Protection System 31 Day Examination

6.FP.606

Fire Barrier/Penetration Seal Visual Examination

6.FP.610

Yard Hydrant Flow Check & Fire Protection System Flow

Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

7.0.7

Scaffolding Construction and Control

7.3.17.4

4160V Vacuum Bottle Breaker Maintenance

IP-ENG-001

Standard Design Process

Work Orders

4744842, 4880243, 5028698, 5067194, 5137136,

5181059, 5200420, 5201372, 5203385, 5205851,

205859, 5209006, 5209740, 5210849, 5211381,

211483, 5211484, 5211485, 5211486, 5303589,

5303593, 5303594, 5337669, 5344017, 5368430,

5395381, 5397980