IR 05000298/2021003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000298/2021003
ML21299A198
Person / Time
Site: Cooper Entergy icon.png
Issue date: 11/04/2021
From: Jason Kozal
NRC, NRC/RGN-IV/DRP
To: Dent J
Nebraska Public Power District (NPPD)
References
IR 2021003
Download: ML21299A198 (21)


Text

SUBJECT:

COOPER NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000298/2021003

Dear Mr. Dent:

On September 30, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Cooper Nuclear Station. On October 4, 2021, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Jason W. Kozal, Chief Reactor Projects Branch C Division of Reactor Projects Docket No. 05000298 License No. DPR-46

Enclosure:

As stated

Inspection Report

Docket Number:

05000298

License Number:

DPR-46

Report Number:

05000298/2021003

Enterprise Identifier:

I-2021-003-0131

Licensee:

Nebraska Public Power District

Facility:

Cooper Nuclear Station

Location:

Brownville, NE

Inspection Dates:

July 1, 2021, to September 30, 2021

Inspectors:

D. Antonangeli, Health Physicist

D. Bryen, Project Engineer

K. Chambliss, Resident Inspector

J. O'Donnell, Senior Health Physicist

G. Pick, Senior Reactor Inspector

A. Siwy, Senior Resident Inspector

M. Stafford, Nuclear Systems Engineer

Approved By:

Jason W. Kozal, Chief

Reactor Projects Branch C

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Cooper Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000298/2020-002-00 Secondary Containment Differential Pressure Perturbation Results in Potential Loss of Safety Function 71153 Closed LER 05000298/2021-001-00 Secondary Containment Differential Pressure Perturbation Exceeds Technical Specifications 71153 Closed LER 05000298/2020-004-00 Secondary Containment Differential Pressure Perturbation Could Have Prevented Fulfillment of a Safety Function 71153 Closed

PLANT STATUS

Cooper Nuclear Station began the inspection period at rated thermal power. On August 6, 2021, power was lowered to approximately 67 percent for a control rod sequence exchange. The plant was returned to rated thermal power on August 7, 2021. The unit remained at rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week, increasing the amount of time on-site as local COVID-19 conditions permitted.

As part of their on-site activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; conducted routine reviews using IP 71152, Problem Identification and Resolution; observed risk significant activities; and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Standby liquid control subsystem B on July 7, 2021
(2) Reactor core isolation cooling on July 26, 2021
(3) Core spray B on August 3, 2021
(4) Division 2 reactor equipment cooling on August 10, 2021
(5) Division 1 emergency diesel generator on August 18, 2021
(6) Division 2 emergency diesel generator on September 16, 2021
(7) High pressure coolant injection on September 22, 2021

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (9 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Reactor building, 976-foot elevation, on July 6, 2021
(2) Reactor building northeast quadrant, 881-foot 9-inch elevation and 859-foot 9-inch elevation, on July 28, 2021
(3) Reactor building southeast quadrant, 881-foot 9-inch elevation and 859-foot 9-inch elevation, on August 3, 2021
(4) Reactor building second floor, 931-foot 6-inch elevation, on August 10, 2021
(5) Division 2 emergency diesel generator room, 917-foot 6-inch elevation and 903-foot 6-inch elevation, on August 16, 2021
(6) Reactor building southwest quadrant, 881-foot 9-inch elevation and 859-foot 9-inch elevation, on August 24, 2021
(7) Reactor building third floor, 958-foot 3-inch elevation, on August 28, 2021
(8) Reactor building refuel floor, 1001-foot elevation, on September 2, 2021
(9) Turbine building basement north condensate pump area, 882-foot 6-inch elevation, on September 14, 2021

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during downpower and rod pattern adjustment on August 6, 2021.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the licensed operator requalification scenario on July 13, 2021.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (4 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1) FLEX equipment operating experience smart sample 2020/01 (ADAMS Accession No. ML20220A261) on July 9, 2021
(2) Open phase isolation system on September 1, 2021
(3) Reactor core isolation cooling on September 28, 2021
(4) Dry compressed air for instrument air near A(1) on September 29, 2021

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Yellow risk during standby liquid control subsystem A maintenance on July 7, 2021
(2) Yellow risk during high pressure coolant injection instrument repair on July 28, 2021
(3) Yellow risk during Division 1 4160 volt bus undervoltage/underfrequency testing on August 2, 2021
(4) Yellow risk during Division 2 4160 volt bus undervoltage testing on August 25, 2021

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Standby liquid control pump A motor results on July 8, 2021
(2) Limiting condition of operation not entered during maintenance on primary containment valves on July 23, 2021
(3) Secondary containment operability in relation to a steam leak on August 19, 2021
(4) Southeast quadrant heating, ventilation, and air conditioning flow rate on August 31, 2021
(5) Reactor equipment cooling pump D motor inductance imbalance on September 13, 2021
(6) Control rod drive mechanism high accumulator water level on September 14, 2021

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (3 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Emergency service station transformer motor operated disconnect switch on July 14, 2021
(2) Southeast quadrant fan coil unit replacement on August 26, 2021
(3) Open phase isolation modifications on September 20, 2021

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Primary containment valve torus isolation on July 19, 2021
(2) Division 2 emergency diesel generator starting air compressor operability test on July 23, 2021
(3) Core spray pump A test line recirculation valve on August 4, 2021
(4) Reactor equipment cooling pump B replaced on August 12, 2021
(5) Core spray check valve on August 19, 2021
(6) Fan coil unit FC-R-1E air flow test (newly installed fan coil) on August 19, 2021

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Division 1 emergency diesel generator monthly surveillance on July 12, 2021
(2) Reactor core isolation cooling pump low discharge flow calibration and steam supply pressure low channel functional test on July 16, 2021
(3) Service water pump B in-service test on July 26, 2021
(4) Reactor equipment cooling pumps C and D in-service tests on August 28, 2021
(5) High pressure coolant injection quarterly surveillance on September 15, 2021

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) Emergency preparedness drill on August 31,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (7 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Area radiation monitors and continuous air monitors in the reactor building, turbine building, and radwaste building
(2) High purity germanium detectors and liquid scintillation counter in the chemistry lab
(3) Friskers staged for use in the reactor building, radwaste building, and radiologically controlled area exits
(4) SAM-12s staged for use at the exit of the radiologically controlled areas (5)iPCM-12 located at the radiologically controlled area exits
(6) Telepoles and portable ion chambers staged for use within the radiological controlled area
(7) Tennelec XLB alpha/beta counters located within the radiation protection count room

Calibration and Testing Program (IP Section 03.02) (14 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) G17 ion chamber, RMA-RA-1, 03/04/2020
(2) G17 ion chamber, RMA-RA-2, 03/04/2020
(3) G12 ion chamber, RMP-RM-452C, 03/04/2021
(4) Victoreen Model 875 high range containment monitor, RMA-RM-40A, 04/14/2021
(5) Victoreen Model 875 high range containment monitor, RMA-RM-40B, 04/14/2021
(6) Eberline passive monitor (PM) -7, RP-10758, 11/09/2020
(7) Eberline personnel contamination monitor (PCM) -2, RP-10788, 02/27/2020
(8) Eberline small article contamination monitor (SAM) -12, RP-11152, 05/20/2020
(9) Eberline SAM-12, RP-11150, 05/20/2020
(10) Telepole II Geiger-Mueller survey meter, RP-11969, 10/10/2020
(11) Ludlum Model 3 count rate meter, RP-11363, 04/22/2021
(12) Frisker Model 177, RP-11276, 07/09/2020
(13) Eberline AMS-4, RP-10872, 07/07/2021
(14) Tennelec XLB alpha/beta counter, RP-10848, 03/02/2020 Effluent Monitoring Calibration and Testing Program Sample (IP Sample 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Elevated effluent release point monitor, RMP-RM-3A/3B
(2) Reactor building vent effluent monitor, RMV-RM-40

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Radioactive Material Storage (IP Section 03.01)

Inspectors evaluated the licensees performance in controlling, labeling and securing radioactive materials. The following areas were observed by the inspectors:

(1) Low level radioactive waste pad
(2) Radioactive material storage building
(3) East warehouse radioactive materials area

Radioactive Waste System Walkdown (IP Section 03.02) (2 Samples)

Inspectors walked down accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality.

(1) Condensate resin
(2) Equipment drain/floor drain filter demineralizer

Waste Characterization and Classification (IP Section 03.03) (3 Samples)

The inspectors evaluated the licensees characterization and classification of radioactive waste.

(1) Condensate and waste resin
(2) Spent bead resin
(3) Dry active waste

Shipment Preparation (IP Section 03.04) (1 Sample)

The inspectors observed that a shipment containing radioactive material is prepared according to requirements.

(1) Shipment No. 21-05, low specific activity, LSA-II, dry active waste (trash) in a 20-foot sea/land container (ESUU200542), 07/20/2021

Shipping Records (IP Section 03.05) (5 Samples)

The inspectors evaluated the following nonexcepted radioactive material shipments through a record review:

(1) Shipment No. 19-12, LSA-I, dry active waste (metal trash) in a 20-foot sea/land container (No. 209002), 09/16/2019
(2) Shipment No. 19-13, Type A, high integrity container (PO690656-10), activated metal and contaminated, noncompactible metal trash, 10/22/2019
(3) Shipment No. 20-02, LSA-II, condensate sludge and resin liner (PO690095-01),06/20/2020
(4) Shipment No. 21-02, LSA-II, steel liner (No. 680262-3) filters and bulk dry active waste, 05/11/2021
(5) Shipment No. 21-05, LSA-II, dry active waste (trash) in a 20-foot sea/land container (ESUU200542), 07/20/2021

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) January 1, 2020, through June 30, 2021 IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)
(1) January 1, 2020, through June 30, 2021

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (1 Sample)

(1) April 1, 2020, through June 30, 2021

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (1 Sample)

(1) April 1, 2020, through June 30, 2021

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (3 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Effectiveness of corrective actions related to the full implementation cyber security inspection findings as discussed in NRC Inspection Report 05000298/2019410 (ADAMS Accession No. ML19175A252)
(2) Limiting condition of operation not entered during maintenance on primary containment valves on August 30, 2021
(3) Failure to properly implement the fatigue management program on September 10, 2021

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000298/2020-002-00, Secondary Containment Differential Pressure Perturbation Results in Potential Loss of Safety Function (ADAMS Accession No. ML20304A209). The circumstances surrounding this LER and an associated minor performance deficiency are documented in the Inspection Results section of this report.
(2) LER 05000298/2020-004-00, Secondary Containment Differential Pressure Perturbation Could Have Prevented Fulfillment of a Safety Function (ADAMS Accession No. ML21022A042). The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER; therefore, no performance deficiency was identified. The inspectors did not identify a violation of NRC requirements.
(3) LER 05000298/2021-001-00, Secondary Containment Differential Pressure Perturbation Exceeds Technical Specifications (ADAMS Accession No. ML21102A278). The circumstances surrounding this LER and an associated minor performance deficiency are documented in the Inspection Results section of this report.

INSPECTION RESULTS

Minor Performance Deficiency 71153 Minor Performance Deficiency: On August 6, 2020, secondary containment vacuum was reduced below the limit of 0.25 inches of vacuum water gauge, which is required by Technical Specification Surveillance Requirement 3.6.4.1.1. This condition existed for 3 minutes and was identified by operations personnel after it had occurred due to a computer alarm in the control room. This condition was initially concluded to be a momentary transient due to gusty wind conditions, which is considered acceptable and not a cause for failure to meet the surveillance requirement. An engineering review completed on August 13, 2021, concluded it was the result of an equipment issue rather than gusty wind conditions. This condition was a result of an air-line leak between the valve positioner and the lower diaphragm of a vortex damper due to contact with a support brace that was installed on November 7, 2007. At the time the support brace was installed, Attachment 15 of Procedure 3.4, Configuration Change Control, Revision 59, required an administrative engineering change to install the support brace. The guidance at the time of the causal evaluation was in Attachment 6 of Procedure 3-CNS-DC-112, Engineering Change Request and Project Initiation Process, Revision 0, which required an engineering change request. Contrary to the above, from November 7, 2007, to January 27, 2021, the licensee failed to properly evaluate the support brace as an engineering change in accordance with their procedures.

Screening: The inspectors determined the performance deficiency was minor. The performance deficiency associated with this violation was determined to be minor because: it could not be reasonably viewed as a precursor to a significant event; if left uncorrected, it would not have the potential to lead to a more significant safety concern; and it did not adversely affect the Barrier Integrity cornerstone objective to provide reasonable assurance that physical design barriers (containment) protect the public from radionuclide releases caused by accidents or events. Specifically, the performance deficiency did not affect the integrity of the secondary containment structure, nor did it affect the ability of the safety-related standby gas treatment system to perform its required safety function.

Minor Performance Deficiency 71153 Minor Performance Deficiency: On February 9, 2021, secondary containment vacuum was reduced below the limit of 0.25 inches of vacuum water gauge, which is required by Technical Specification Surveillance Requirement 3.6.4.1.1. This condition existed for less than 30 seconds and was identified by operations personnel after it had occurred due to a computer alarm in the control room. This condition was concluded to be a momentary transient due to barometric pressure changes. A similar issue occurred on November 3, 2020 and is documented in LER 05000298/2020-004-00 (ADAMS Accession No. ML21022A042). It was determined in both occurrences that the tuning parameters of the reactor building differential pressure controllers were not optimized to maintain the required pressure during changing conditions. After the first occurrence, the licensee decided not to implement interim actions on the basis that the condition was unlikely to repeat prior to full action implementation. Procedure 0-CNS-LI-118, Cause Evaluation Process, Section 8.2, requires interim corrective actions to address short term vulnerabilities. Contrary to the above, from November 3, 2020, through February 9, 2021, the licensee failed to develop interim actions to address short term vulnerabilities.

Screening: The inspectors determined the performance deficiency was minor. The performance deficiency associated with this violation was determined to be minor because: it could not be reasonably viewed as a precursor to a significant event; if left uncorrected, it would not have the potential to lead to a more significant safety concern; and it did not adversely affect the Barrier Integrity cornerstone objective to provide reasonable assurance that physical design barriers (containment) protect the public from radionuclide releases caused by accidents or events. Specifically, the performance deficiency did not affect the integrity of the secondary containment structure, nor did it affect the ability of the safety-related standby gas treatment system to perform its required safety function.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On July 22, 2021, the inspectors presented the public radiation safety inspection results to Mr. K. Dia, General Manager of Plant Operations, and other members of the licensee staff.

On September 22, 2021, the inspectors presented the cyber security full implementation problem identification and resolution inspection results to Mr. J. Wissler, Nuclear Information Technology Manager, and other members of the licensee staff.

On October 4, 2021, the inspectors presented the integrated inspection results to Mr. J. Dent, Vice President and Chief Nuclear Officer, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2.2.20

Standby AC Power System (Diesel Generator)

2

2.2.20.1

Diesel Generator Operations

2.2.33A

High Pressure Coolant Injection System Component Checklist

2.2.33B

High Pressure Coolant Inject System Instrument Valve

Checklist

2.2.67A

Reactor Core Isolation Cooling System Instrument Valve

Checklist

2.2.74A

Standby Liquid Control System Component Checklist

2.2A

Reactor Equipment Cooling Water System Component

Checklist (Div 2)

2.2A.DG.DIV1

Standby AC Power System (Diesel Generator) Component

Checklist (Div 1)

2.2A.DG.DIV2

Standby AC Power System (Diesel Generator) Component

Checklist (Div 2)

71111.04

Procedures

2.2B

Core Spray System Instrument Valve Checklist

CNS-FP-211

Reactor Building Northeast Quadrant Elevations 881-9 and

859-9

5, 6

CNS-FP-214

Reactor Building Southwest Quadrant Elevations 881-9 and

859-9

CNS-FP-218

Reactor Building Second Floor Elevation 931-6

CNS-FP-219

Reactor Building - Third Floor Elevation 958-3

CNS-FP-220

Reactor Building SBLC Area Elevation 976-0

CNS-FP-221

Reactor Building MG Set Area Elevation 976-0

CNS-FP-223

Reactor Building - Refuel Floor Elevation 1001-0

CNS-FP-237

Diesel Generator Building Diesel Generator #2 Elevations

917-6 and 903-6

Fire Plans

CNS-FP-245

Turbine Building Basement North - Condensate Pump Area

Elevation 882-6

71111.05

Procedures

0-BARRIER-

MAPS

Barrier Maps

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

RMP 32-012

71111.11Q

Procedures

2.0.3

Conduct of Operations

104

Corrective Action

Documents

CR-CNS-

2019-02127, 2021-02941

Maintenance Rule Unavailability Reports

09/24/2021

FLEX, HCVS, and DAMS Program Document

REC (Reactor Equipment Cooler) Pump Vibration and

Spectral Data

08/28/2021

VM-0143

Instrument Air System

Miscellaneous

VM-2912

Open Phase Protection (OPP) System Operating and

Maintenance Manual

15.AIR.501

Plant Air System Examination

15.EE.701

Open Phase Active System Functional Test

Procedures

7.2.21

Air Dryer Desiccant Removal and Replacement

71111.12

Work Orders

WO 5305639, 5315637, 5349739, 5349740, 5361148, 5363543,

5363544, 5371520

Drawings

3019, Sheet 3

Miscellaneous

Clearance Order SLC-1-SLC-P-A Week 2127

6.1EE.302

4160V Bus 1F Undervoltage Relay and Relay Timer

Functional Test (Div 1)

6.2EE.302

4160V Bus 1F Undervoltage Relay and Relay Timer

Functional Test (Div 2)

Procedures

6.HPCI.312

HPCI Pump Low Discharge Flow Channel Calibration

71111.13

Work Orders

WO 5401691

Corrective Action

Documents

CR-CNS-

21-02285, 2021-03239, 2021-03644, 2021-03874, 2021-

04315

DEC-5347082

Replacement of HV-COIL-FC-R-1E, (FCR #2&3)

NEDC 90-388

HPCI Room and CS & RHR Quad Heat Load Tabulation for

REC

3C2

NEDC 97-087

Acceptance Criteria for HPCI Room Cooler and Reactor

Building Quad Coolers

4C3

71111.15

Miscellaneous

USAR, Section III-

Control Rod Drive Mechanism Design

03/08/2000

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

VM-1037

Control Rod Drive Model 7RDB144EG001

2.2.8

Control Rod Drive Hydraulic System

115

6.SC.502

Secondary Containment Penetration Examination

Procedures

7.3.20.3

Motor Analysis

Work Orders

WO 237983, 5339707, 5383218

EC 6038060

Installation of PSStech OPP System on SSST and ESST

Engineering

Changes

EC 6039780

Review of Zachary Calculation 16-101, ECN #1

Aerofin Calculation File, Aerofin Type W Coil, CA-529-2046-1

Aerofin Calculation File, Aerofin Type W Coil, CA-1811

DEC-5347082

Replacement of HV-COIL-FC-R-1E

Miscellaneous

NEDC 97-074

Thermal Performance of the HPCI Room Cooler and the CS &

RHR Quad Coolers

2C3

71111.18

Procedures

Cooper Nuclear Station Cyber Security Plan

6.1CS.101

Core Spray Test Mode Surveillance Operation (IST) (Div 1)

6.1PC.204

PC Purge and Vent Valve 24 Month Test (Div 1) (IST)

6.1REC.101

REC Surveillance Operation (IST) (Div 1),

6.2CS.101

Core Spray Test Mode Surveillance Operation (IST) (Div 2)

6.2DG.105

Diesel Generator Starting Air Compressor Operability

(IST)(Div 2)

6.2HV.601

Air Flow Test of Fan Coil Unit FC-R-1E (Div 2)

Procedures

6.PC.522

Standby Nitrogen Injection and PC Purge and Vent System

Local Leak Rate Tests

71111.19

Work Orders

WO 5304567, 5339707

Corrective Action

Documents

CR-CNS-

21-03381

6.1DG.101

Diesel Generator 31 Day Operability Test (IST) (Div 1)

6.1RCIC.703

RCIC Steam Supply Pressure Low Channel Functional Test

(Div 1)

6.1SW.101

Service Water Surveillance Operation (Div 2)(IST)

6.2REC.101

REC Surveillance Operation (IST) (Div 2)

6.HPCI.103

HPCI IST and 92 Day Test Mode

Procedures

6.RCIC.302

RCIC Pump Low Discharge Flow Channel Calibration

71111.22

Work Orders

WO 5363759, 5385905

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71114.06

Miscellaneous

EPIPEALHOT

CNS EAL Wall Chart Hot

Calibrator Verification Exposure Rate Table

01/05/2021

Eberline Passive Monitor (PM)- 7, RP-10758

11/03/2020

Eberline Personnel Contamination Monitor (PCM)- 2,

RP-10788

2/27/2020

Eberline Small Article Contamination Monitor (SAM)-12,

RP-11152

05/20/2020

Eberline SAM-12, RP-11150

05/20/2020

Telepole II Geiger-Mueller Survey Meter, RP-11969

10/10/2020

Ludlum Model 3 Count Rate Meter, RP-11363

04/22/20201

Eberline Air Monitoring Station (AMS)-4

07/07/2021

Tennelec XLB Alpha/Beta Counter, RP-10848

03/02/2020

Frisker Model 177, RP-11276

07/09/2020

WO 5205832

Reactor Building Ventilation Radiation Monitor, RMP-RM-452B

09/09/2019

WO 5238323

Control Room Area Radiation Monitor, RMA-RA-20

03/06/2020

WO 5282475

High Range Containment Monitor Victoreen Model 875,

RMA-RM-40A

10/04/2020

WO 5291902

Main Steam Line Radiation Monitors (MSLRM),

RMP-RM-251D

10/08/2020

WO 5337774

Containment High Range Monitor Victoreen Model 875,

RMA-RM-40B

03/02/2020

Calibration

Records

WO 5362219

Reactor Building Ventilation Radiation Monitor, RMP-RM-452A

09/20/2020

Corrective Action

Documents

CR-CNS-

2019-04420, 2019-04713, 2019-06406, 2020-00717, 2020-

01052, 2020-01067, 2020-01080, 2020-01508, 2020-02009,

20-03028, 2020-03308, 2021-01539, 2021-02180

CNS System Health for Radiation Monitor Systems

06/01/2020

Effluent Radiation Monitors Out of Service Longer Specified in

the Offsite Dose Assessment Manual (ODAM)

07/19/2021

Miscellaneous

The Past Three Annual Trends of the Vent/Stack Effluent Flow

Rates Via Chart

06/17/2021

6.PRM.308

Liquid Radwaste Effluent System Channel Calibration

6.PRM.310

ERP Kaman Monitor Channel Calibration

71124.05

Procedures

6.PRM.313

Reactor Building Kaman Monitor Channel Calibration

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

6.PRM.320

Radwaste Building Kaman Monitor Channel Calibration

6.PRM.322

Containment High Range Area Monitor Channel Calibration

6.PRM.323

High Range Containment Monitor Victoreen Model 875 Source

Calibration Check

6.PRM.328

Kaman Sample Flow System Channel Calibration

8-CNS-CY-102

Laboratory Analytical Quality Control

9.ALARA.3

Operation of the Canberra Fastscan Whole Body Counter with

Apex-Invivo

9.INST.14

Tennelec Eclipse LB Operation

9.INST.15

REM 500 Neutron Survey Meter

9.INST.53

Ion Chamber Survey Instrument Eberline Model RO-20

9.INST.57

Friskers

9.INST.64

Thermo Electron Corporation Small Articles Monitor SAM

9.INST.68

WR Telepole GM Survey Instrument

9.INST.70

Telepole II Telescopic Meter

Corrective Action

Documents

CR-CNS-

2019-05715, 2020-01085, 2020-02092, 2020-03042, 2020-

06381

CR-CNS-

21-03440, 2021-03464, 2021-03472

Corrective Action

Documents

Resulting from

Inspection

WT-

21-0001-249

Local Law Enforcement Agency Meeting Attendance

2/18/2020

Cooper Nuclear Station Part 37 Security Plan for the

Protection of Category 1 and Category 2 Quantities of

Radioactive Material

05/24/2016

Process Control Program (Uncontrolled)

11/10/2015

CNS RP-504

Radioactive Source Inventory and Leak Test Record

2/23/2020

RAD916-01-04

RP and Radioactive Transport Actions Regarding

CFR Part 37 "Protection of Category 1 and Category 2

Radioactive Material"

Sample No.

26708005

Waste Stream Analysis Review for Dry Active Waste

2/21/2020

71124.08

Miscellaneous

Sample No.

530399001

Waste Stream Analysis Review for Condensate/Waste Resins

01/20/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Sample No.

2677001

Waste Stream Analysis Review for Spent Bead Resin

06/08/2021

0.PCP.1

Process Control Program (PCP)

59.RW.10

Physical Protection of Category 1 Quantities of Radioactive

Material

9.RADOP.1

Radiation Protection at CNS

9.RW.1

Radioactive Shipments

9.RW.7

Waste Stream Sampling

9.RW.9

Filling Containers with Waste/Radioactive Material

Procedures

Security

Procedure 2.16

Radioactive Materials Security

CNS-2104-0024

Horizontal Storage Module Pad

2/21/2021

CNS-2105-0025

Radioactive Material Storage Building

05/19/2021

CNS-2106-0012

Underwater Survey of Spent Fuel Pool and Items Stored

Within

06/15/2021

Radiation Surveys

CNS-2107-0010

Low Level Radioactive Waste Building, Perimeter Fencing and

General Area

07/14/2021

2019

Radiation Protection Program Annual Report

05/27/2020

LO-2019-0039-

001

CFR Part 37 - At Facilities with a 10 CFR Part 73 Physical

Protection Program

2/27/2020

LO-2020-0127

Radiological Monitoring Instrumentation and Radioactive Solid

Waste Processing and Radioactive Material Handling,

Storage, and Transport

04/19/2021

LO-2020-066-001

CFR Part 37 - At Facilities with a 10 CFR Part 73 Physical

Protection Program

2/22/2021

Self-Assessments

QAD 2020-0019

Quality Assurance Audit 20-04, "Radiological Controls"

08/19/2020

Shipment No.

19-12

LSA-I, Dry Active Waste (Metal Trash) in a 20-foot Sea/Land

(#209002)

09/16/2019

Shipment No.

19-13

Type A, High Integrity Container (PO690656-10), Activated

Metal and Contaminated, Non-Compactible Metal Trash

10/22/2019

Shipment No.

20-02

LSA-II, Condensate Sludge and Resin Liner (PO690095-01)

06/20/2020

Shipping Records

Shipment No.

21-02

LSA-II, Steel Liner (#680262-3) Filters and Bulk Dry Active

Waste

05/11/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Shipment No.

21-05

LSA-II, Dry Active Waste (Trash) in a 20-foot Sea/Land

(ESUU200542)

07/20/2021

Corrective Action

Documents

CR-CNS-

2019-00860, 2019-01161, 2019-01166, 2019-01167, 2019-

2947, 2019-02948, 2021-02439, 2021-03013, 2021-03257,

21-03313, 2021-03346, 2021-03767

Corrective Action

Documents

Resulting from

Inspection

CR-CNS-

21-04378, 2021-04379, 2021-04385

Drawings

High Level Connectivity Diagram - Cyber Security Architecture

Fire Plans

Assessment-

RFC-003

Reactor Feedwater Control Critical Digital Assets in the

Turbine Building Corridor

Cooper Nuclear Station Cyber Security Plan

Assessment

CDA-CPE-001-

CPU2

Computer Room Control Network Firewall

10/19/2019

Assessment

CDA-PDN-002-

NS

Network Switches

01/20/2021

Assessment-

CDA-CPE-001

Computer Process Equipment

Miscellaneous

Assessment-

CDA-TGC-002

Turbine Generator Control Critical Digital Assets (Computer

Room)

11.CYBER-

SECURITY

Cyber Security

11.CYBER.01

Physical Security Guidance for Critical Digital Assets

11.CYBER.03

Cyber Security Scope

11.CYBER.07

Configuration Control of Critical Digital Assets

11.CYBER.08

Security Impact Analysis

11.CYBER.11

Cyber Security Vulnerability Management

11.CYBER.15

Cyber Security Access Control

11.CYBER.16

Audit and Accountability Procedure

11.CYBER.18

Identification and Authentication

71152

Procedures

11.CYBER.19

Systems and Communications Protection

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

11.CYBER.20

Supply Chain for Critical Digital Assets

11.CYBER.21

Cyber Security Defense-in-Depth

71153

Corrective Action

Documents

CR-CNS-

20-03402, 2020-03628, 2020-03728, 2020-05668, 2021-

00573