IR 05000298/2021402
| ML21278A725 | |
| Person / Time | |
|---|---|
| Site: | Cooper |
| Issue date: | 10/12/2021 |
| From: | Ray Kellar Plant Support Branch-1 |
| To: | Dent J Nebraska Public Power District (NPPD) |
| References | |
| IR 2021402 | |
| Download: ML21278A725 (8) | |
Text
October 12, 2021
SUBJECT:
COOPER NUCLEAR STATION - SECURITY BASELINE INSPECTION REPORT 05000298/2021402
Dear Mr. Dent:
On September 23, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Cooper Nuclear Station and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Ray L. Kellar, P.E., Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 05000298 License No. DPR-46
Enclosure:
As stated
Inspection Report
Docket Number:
05000298
License Number:
Report Number:
Enterprise Identifier:
I-2021-402-0005
Licensee:
Nebraska Public Power District
Facility:
Cooper Nuclear Station
Location:
Brownville, NE
Inspection Dates:
September 20, 2021 to September 23, 2021
Inspectors:
J. Buchanan, Physical Security Inspector
J. Rollins, Senior Physical Security Inspector
Approved By:
Ray L. Kellar, P.E., Chief
Plant Support Branch 1
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Cooper Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Unless otherwise noted, baseline security inspections were conducted in accordance with the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Publicly available IPs are located at:
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
SAFEGUARDS
71130.01 - Access Authorization
The inspectors evaluated the access authorization program through completion of the following
inspection elements: Access Authorization
- (1) Tier I: All Requirements
Tier II: All Requirements
Tier III: All Requirements except 01.02.10b
71130.02 - Access Control
The inspectors evaluated the access control program through completion of the following
inspection elements: Access Control
- (1) Tier I: All Requirements
Tier II: All Requirements
Tier III: All Requirements
71130.09 - Security Plan Changes
The inspectors evaluated the security plan changes through completion of the following inspection elements:
Review Security Plan Changes (IP Section 02.01) (1 Partial)
(1)
(Partial)
The opportunity to apply this procedure was not available in accordance with Inspection Manual Chapter 0306. This sample was not available because the licensee did not conduct the activity covered by this IP. Specially, the licensee has not initiated a physical security plan change in accordance with Title 10 of the Code of Federal Regulations, Part 50.54(p)(2) since the last performance of this IP, and the Physical Security Plan dated January 8, 2019, remains current.
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17)
=
- (1) September 1, 2020, through August 31,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On September 23, 2021, the inspectors presented the security baseline inspection results to Mr. John Dent, Jr. and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
CNS-2019-02883, CNS-2019-04442, CNS-2019-05330,
CNS-2020-03-938,
CNS-2020-04191, CNS-2021-01873, and CNS-2021-02018.
Qualification Records for Access Authorization Staff
09/29/2020
Qualification Records for Access Authorization Staff
09/18/2020
Reviewing Official Designation Memorandum
09/30/2019
Sample of Access Authorization Records
Sample of Badge Status Forms
CNS Blocked Badge List
06/30/2021
Sample of Fitness for Duty Drug and Alcohol Testing
Records
O-SS-JPM-AA-
1.0
Job Performance Measure Badge Issuance and Control
O-SS-JPM-AA-
2.0
Job Performance Measure Personnel in Processing
O-SS-JPM-AA-
3.0
Job Performance Measure Granting Unescorted Access
O-SS-JPM-AA-
4.0
Job Performance Measure Behavioral Observation Program
Miscellaneous
O-SS-JPM-AA-
5.0
Job Performance Measure Computer Interface
0-CNS-13
Personnel Access Data System
0-FFD-01
NPG Fitness for Duty Program and Behavioral Observation
Program
3.0
Access Authorization
3.2
Fair Credit Reporting Act
3.3
Re-investigation and Psychological Re-assessment
3.4
CNS Photo Badge Management
Procedures
3.5
Adjudication Matrix Procedure
Corrective Action
Documents
CR-CNS-2020-03923, CR-CNS-2020-04433, CR-CNS-2020-
05808, CR-CNS-2021-00100, CR-CNS-2021-02322, CR-
CNS-2021-04486, CR-CNS-2021-04487, CR-CNS-2021-
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
04488, CR-CNS-2021-04499
Miscellaneous
Security Event Log
08/10/2019 -
09/17/2021
1.2
Protection of Unclassified Safeguards Information
2.10
Local Law Enforcement Agency (LLEA)
2.14
Compensatory Measures
2.5
Personnel Access Control
2.6
Vehicle Entry/Exit
2.7
Material Entry/Exit
2.8
Access Control Devices
3.14
Non-Security Emergencies
3.15
Emergency Entry/Exit
Procedures
3.4
CNS Photo Badge Management
8