IR 05000298/2022002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000298/2022002
ML22207A043
Person / Time
Site: Cooper Entergy icon.png
Issue date: 07/28/2022
From: Jeffrey Josey
NRC/RGN-IV/DORS
To: Dent J
Nebraska Public Power District (NPPD)
Josey J
References
IR 2022002
Download: ML22207A043 (25)


Text

July 28, 2022

SUBJECT:

COOPER NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000298/2022002

Dear Mr. Dent:

On June 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Cooper Nuclear Station. On July 18, 2022, the NRC inspectors discussed the results of this inspection with Mr. K. Dia, General Manager of Plant Operations, and other members of your staff. The results of this inspection are documented in the enclosed report.

One Severity Level IV violation without an associated finding is documented in this report. We are treating this violation as a non-cited violation (NCV) consistent with section 2.3.2 of the Enforcement Policy.

No NRC-identified or self-revealing findings were identified during this inspection.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC resident inspector at Cooper Nuclear Station.

J. Dent, Jr.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Jeffrey E. Josey, Chief Projects Branch C Division of Operating Reactor Safety Docket No. 05000298 License No. DPR-46

Enclosure:

As stated

Inspection Report

Docket Number:

05000298

License Number:

DPR-46

Report Number:

05000298/2022002

Enterprise Identifier:

I-2022-002-0010

Licensee:

Nebraska Public Power District

Facility:

Cooper Nuclear Station

Location:

Brownville, NE

Inspection Dates:

April 1 to June 30, 2022

Inspectors:

K. Chambliss, Resident Inspector

D. Dodson, Senior Reactor Inspector

M. Doyle, Acting Senior Resident Inspector

H. Freeman, Senior Project Engineer

S. Hedger, Senior Emergency Preparedness Inspector

C. Henderson, Senior Resident Inspector

W. Sifre, Senior Reactor Inspector

M. Stafford, Acting Senior Resident Inspector

H. Strittmatter, Emergency Preparedness Inspector

W. Tejada, Physical Security Inspector

F. Thomas, Reactor Inspector

Approved By:

Jeffrey E. Josey, Chief

Projects Branch C

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Cooper Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Safety Relief Valve Lift Settings Outside of Technical Specifications Required Setpoints Cornerstone Severity Cross-Cutting Aspect Report Section Not Applicable Severity Level IV NCV 05000298/2022002-01 Open/Closed Not Applicable 71153 A self-revealed, Severity Level IV non-cited violation of Technical Specification 3.4.3,

Safety/Relief Valves and Safety Valves, was identified when the licensee discovered through as-found test results that two of the eight Target Rock safety relief valve pilot assemblies failed to lift within the technical specifications lift setpoint requirements.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000298/2021-002-00 Valve Test Failures Result in Condition Prohibited by Technical Specifications 71153 Closed

PLANT STATUS

Cooper Nuclear Station began the inspection period at rated thermal power. On April 29, 2022, power was lowered to approximately 60 percent for core management. The plant was returned to rated thermal power on May 3, 2022. On May 21, 2022, power was lowered to approximately 70 percent for core management. The plant was returned to rated thermal power on May 24, 2022. On June 3, 2022, power was lowered to approximately 85 percent for core management. The plant was returned to rated thermal power on June 4, 2022. On June 17, 2022, power was lowered to approximately 70 percent for core management. The plant was returned to rated thermal power on June 20, 2022. On June 24, 2022, power was lowered to approximately 70 percent for core management. The plant was returned to rated thermal power on June 25, 2022. The unit remained at rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal high temperatures for the following systems:

service water

emergency diesel generators

reactor building heating, ventilation, and air conditioning

control room air conditioning

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated that flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding on April 28, 2022.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)division 1 emergency diesel generator on April 14, 2022 (2)division 1 residual heat removal on April 29, 2022 (3)standby gas treatment A on April 29, 2022 (4)core spray train A on June 17, 2022

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the division 2 residual heat removal service water system on June 21, 2022.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)reactor building northeast quadrant, 881-foot 9-inch and 859-foot 9-inch elevations, on April 12, 2022 (2)reactor building standby liquid control area, 976-foot elevation, on April 28, 2022 (3)flex support building 1, 903-foot 6-inch elevation, on May 13, 2022 (4)reactor building general area, 903-foot 6-inch elevation, on May 24, 2022 (5)control building cable spreading room, 918-foot elevation, on May 25, 2022

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) reactor building southwest quadrant on May 3, 2022

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) reactor equipment cooling heat exchanger B evaluation on May 12, 2022

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during downpower to 65 percent for core management on April 30, 2022.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a simulator training scenario on April 20, 2022.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1)service water function F04 near (a)(1) on June 2, 2022 (2)fire protection function F03 near (a)(1) on June 15, 2022 (3)reactor water cleanup function F03 at (a)(1) on June 15, 2022

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)emergency diesel generator isolation switch operability test on April 12, 2022 (2)planned Yellow risk for valve SW-MO-89B failure on April 18, 2022 (3)startup transformer maintenance window on May 10, 2022 (4)week 2220 emergent issues risk management on May 19, 2022 (5)4160 V, bus 1G, relay test on May 23, 2022 (6)high-pressure coolant injection drip leg drain test on June 27, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)water leaking from REC-269 on April 14, 2022 (2)valve SW-MO-89A minimum flow setting incorrect on April 21, 2022 (3)valve SW-MO-89B failure to open on May 4, 2022 (4)wetted residual heat removal conduit on May 13, 2022 (5)reactor equipment cooling pump B breaker high-temperature delta on June 15, 2022 (6)division 2 H2/O2 analyzer failed surveillance on June 27, 2022

71111.17T - Evaluations of Changes, Tests, and Experiments Sample Selection (IP Section 02.01)

The inspectors reviewed the following evaluations, screenings, and/or applicability determinations for 10 CFR 50.59 from June 13 to June 16, 2022.

(1)performance analysis and design (PAD) 162270, engineering evaluation EE-19-030, RCIC Minimum Flow Bypass Valve Closure Requirement Evaluation (50.59 Screening)

(2) PAD 172302, licensing basis document change request 2020-017, Modification of Technical Specification Basis Action B.3.1 and B.3.2 (50.59 Screening)

(3)procedure change request emergency procedure 5.1FLOOD, "FLOOD," revision 29 (50.59 Screening)

(4) PAD 202349, condition report CR-CNS-2020-02917, Compensatory Measure for Reactor Equipment Cooling Leakage (50.59 Screening)
(5) PAD 172276, design engineering change (DEC) 5329608, HV-DPIC-835A and/or B Replacement (50.59 Screening)
(6) PAD 172274, temporary configuration change (TCC) 5328958, Diesel Generator Cooling Water Alternate Discharge Flow Path (50.59 Screening)
(7) PAD 202422, compensatory measure for condition report CR-CNS-2021-02034 (50.59 Screening)

(8)evaluation 2021-1/TCC-5395350, MS-AOV-790AV Packing Leak Repair (50.59 Evaluation)

(9) PAD 192336, Cooper Nuclear Station vessel internals program, revision 30.0 (50.59 Screening)
(10) PAD 202385, engineering evaluation 05-001, Core Shroud Weld Flaw Analysis for Core Shroud Circumferential Welds performed by Structural Integrity Associates per NEI 96-07, revision 1 (50.59 Screening)
(11) PAD 202405, engineering evaluation 21-001, RCIC-LS-74 Evaluation of Setpoint and Tolerances (50.59 Screening)
(12) PAD 202410, Cooper Nuclear Station vessel internals program, revision 30.1 (50.59 Screening)
(13) PAD 2O2411, engineering evaluation 2L-OO7, Use-As-ls Engineering Evaluation for MS-V-205 (50.59 Screening)
(14) PAD 202443, DEC 5404656, Implement SCR 202I-OO3 for HPCI-FIS-78 (Switch 1)

(50.59 Screening)

(15) PAD 202480, Revise Limiting Component Analysis for Containment Spray Motor-Operated Valves (50.59 Screening)
(16) PAD 202494, Cooper Nuclear Station vessel internals program, revision 31 (50.59 Screening)

(17)procedure change request (PCR) 2.2.20, system operating procedure 2.2.20, Standby AC Power System (Diesel Generator), revision 110

(18) PCR 2.2.69.3, system operating procedure 2.2.69.3, Residual Heat Removal Suppression Pool Cooling and Containment Spray, revision 52
(19) PAD 192321, TIP [Traversing In-core Probe] Drive Control Unit Replacement (50.59 Screening)
(20) PAD 192323, TSTF-402 LCO 3.8.1 Redundant Required Features (50.59 Screening)
(21) PAD 202370, L3501 345 KV Relay Settings Change (50.59 Screening)
(22) PAD 202372, 345 KV Panel 305 Sync Fuse Change (50.59 Screening)
(23) PAD 202395, HPCI [High-Pressure Coolant Injection] Nutherm Loss of Voltage Relay Removal (50.59 Screening)
(24) PAD 202425, Cooper 345 KV Switchyard Reactor 3401 Hydran Removal (50.59 Screening)
(25) PAD 202470, Update of NEDC 87-131D (50.59 Screening)
(26) PAD 202483, 345 KV Switchyard Replace PCB 3310 (50.59 Screening)
(27) PAD 202487, OG-MOT-OGVP (VPA) Motor Change Evaluation (50.59 Screening)
(28) PAD 202464, TSTF-554, Revise Reactor Coolant Leakage Requirements (50.59 Applicability Determination)
(29) PAD 202408, Alternate Recorder for RWCU-FR--97A/B (50.59 Screening)

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1)standby gas treatment system change in drawdown to negative pressure interval and control room dose during a postulated loss of coolant accident on April 27, 2022

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1)traversing in-core probe ball valve repair on April 14, 2022 (2)residual heat removal B maintenance window on May 16, 2022 (3)valve SW-V-538 replacement on May 19, 2022 (4)control room air conditioning compressor and dryer filter replacement on May 25, 2022

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (4 Samples)

(1)standby liquid control pumps operability test on April 14, 2022 (2)reactor high-pressure channel functional test on June 17, 2022 (3)torus air and water temperature calibration on June 28, 2022 (4)high-pressure coolant injection system operability test on June 29, 2022

Inservice Testing (IP Section 03.01) (1 Sample)

(1)closure testing of diesel generator starting air receiver inlet check valves on April 16, 2022

FLEX Testing (IP Section 03.02) (1 Sample)

(1) FLEX 175 kW emergency diesel generator 1 on June 16, 2022

71114.01 - Exercise Evaluation

Inspection Review (IP Section 02.01-02.11) (1 Sample)

(1) The inspectors evaluated the biennial emergency plan exercise conducted on May 24, 2022. The exercise scenario simulated a security event; a jet pump failure causing fuel clad damage; an anticipated transient without scram; and a steam leak from the reactor core isolation cooling (RCIC) system. The last part of the scenario resulted in a failure of both primary and secondary containment leading to an unmonitored release to the environment.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following Emergency Plan changes and risk significant implementing procedure changes:

emergency plan implementing procedure (EPIP) 5.7.1, "Emergency Classification," revision 72 (NRC notified 3/8/2022, effective 2/16/2022)

Emergency Action Level Technical Basis Document, revision 0 The inspectors also evaluated the 10 CFR 50.54(q) emergency plan change process and practices between March 1, 2021, and March 20, 2022. This involved review of a selection of additional licensee screening and evaluation documentation. These evaluations and reviews do not constitute NRC approval.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

(1)emergency preparedness dress rehearsal drill on April 5, 2022

71114.08 - Exercise Evaluation - Scenario Review

Inspection Review (IP Section 02.01 - 02.04) (1 Sample)

(1) The inspectors reviewed the licensee's preliminary exercise scenario that was submitted to the NRC on March 22, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22083A153) for the exercise scheduled to occur on May 24, 2022. The inspectors discussed the preliminary scenario with Mr. P. Martin, Manager, Emergency Preparedness, and other members of the emergency preparedness staff on April 20, 2022. The inspectors' review does not constitute NRC approval of the scenario.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) April 1, 2021, through March 31, 2022

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) April 1, 2021, through March 31, 2022

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) April 1, 2021, through March 31, 2022 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) April 1, 2021, through March 31, 2022 EP03: Alert and Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
(1) April 1, 2021, through March 31, 2022

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)control and tracking of long-term scaffolding in the reactor building on June 1, 2022 (2)an unqualified shift technical engineer standing watch 25 times on June 9, 2022

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program for quality issues relating to the content, control, and promptness that might be indicative of a more significant issue with the corrective action program.

71153 - Follow-Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000298/2021-002-00, Valve Test Failures Result in Condition Prohibited by Technical Specifications, (ML21137A329). The circumstances surrounding this LER and a Severity Level IV non-cited violation is documented in the Inspection Results section of this report.

INSPECTION RESULTS

Safety Relief Valve Lift Settings Outside of Technical Specifications Required Setpoints Cornerstone Severity Cross-Cutting Aspect Report Section Not Applicable Severity Level IV NCV 05000298/2022002-01 Open/Closed Not Applicable 71153 A self-revealed, Severity Level IV non-cited violation of Technical Specification 3.4.3, Safety/Relief Valves and Safety Valves, was identified when the licensee discovered through as-found test results that two of the eight Target Rock safety relief valve pilot assemblies failed to lift within the technical specifications lift setpoint requirements.

Description:

Licensee Event Report 05000298/2021-002-00, Valve Test Failures Result in Condition Prohibited by Technical Specifications, (ML21137A329), was associated with two of the eight Target Rock safety relief valve (SRV) pilot assemblies as-found setpoints being outside of the +/-3 percent setpoint band required for their operability. This was discovered between March 18 and March 20, 2021, during as-found testing on all eight SRV pilot assemblies that were removed during the fall 2020 refueling outage. The licensee discovered that the two SRV pilot valves stuck due to corrosion bonding. The licensee determined that these two SRVs were inoperable for an indeterminate period of time from November 14, 2018, when the unit entered mode 2 (beginning of operating cycle) to September 26, 2020, when the unit entered mode 4 (beginning of refueling outage). The inspectors reviewed the licensee event report and determined that the report adequately documented the summary of the event including the cause and potential safety consequences. The inspectors also reviewed other documents that indicate that this type of failure is a known industry issue associated with this type of valve.

Corrective Actions: The licensee replaced all eight of the SRV pilot valve assemblies with refurbished valves during the fall 2020 refueling outage. The currently installed valves were certified, tested, and as-left values were verified to be within +/-1 percent of their setpoints. The licensee is tracking industry initiatives to address the known corrosion bonding phenomenon and is working on a technical specification amendment to address this issue.

Corrective Action References: condition reports CR-CNS-2019-01277, CR-CNS-2021-01483, and CR-CNS-2021-01511

Performance Assessment:

The NRC determined this violation was not reasonably foreseeable and preventable by the licensee and therefore is not a performance deficiency.

Enforcement:

Enforcement Policy, section 2.2.4, states that violations with no associated performance deficiency will be dispositioned using traditional enforcement. Therefore, operating reactor violations with no associated performance deficiencies should be assigned a severity level and are, thus, not described as findings or assigned a color (e.g., Green).

Severity: This violation is characterized as a Severity Level IV non-cited violation based on its similarity to Severity Level IV, example 6.1.d.1, in the Enforcement Policy. The inspectors also reviewed the Enforcement Policy, section 3.10, Reactor Violations with no Performance Deficiencies.

Violation: Cooper Nuclear Station Technical Specification 3.4.3, Safety/Relief Valves (SRVs)and Safety Valves (SVs), condition A, requires that with one or more required SRVs or SVs inoperable, that the unit be in mode 3 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and mode 4 in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Contrary to the above, two required SRVs were inoperable from November 14, 2018, to September 26, 2020, and the unit did not enter mode 3 and mode 4 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> respectively.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On April 20, 2022, the inspectors presented the emergency preparedness exercise scenario review inspection results to Mr. P. Martin, Manager, Emergency Preparedness, and other members of the licensee staff.

On June 16, 2022, the inspectors presented the Cooper Nuclear Station 10 CFR 50.59 inspection results to Mr. K. Dia, General Manager of Plant Operations, and other members of the licensee staff.

On June 30, 2022, the inspectors presented the emergency preparedness exercise inspection results to Mr. K. Dia, Acting Vice President and Chief Nuclear Officer, and other members of the licensee staff.

On July 18, 2022, the inspectors presented the integrated inspection results to Mr. K. Dia, General Manager of Plant Operations, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0-BARRIER-

REACTOR

Reactor Building

0-CNS-FAP-WM-06

OPS Department Warm Weather Checklist

14.27.4

Reactor Building Floor Drain Sump Level Calibration

2.2.39

HVAC Diesel Generator Building

2.2.47

HVAC Reactor Building

2.2.84

HVAC Main Control Room and Cable Spreading Room

5.10FLEX

Flex Support Guidelines (FSGs)

5.10FLEX.32

Dam Accident Mitigation System (DAMS)

5.1Flood

Flood

Procedures

7.0.11

Flood Control Barriers

71111.01

Work Orders

WO 5344013

Corrective Action

Documents

CR-CNS-

22-02063

DWG 2006,

Sheet 1

Circulating, Screen Wash & Service Water System

DWG 2006,

Sheet 4

Service Water System Flow Diagram

DWG 2036,

Sheet 1

Reactor Building Service Water System

DWG 2037

Flow Diagram H&V Standby Gas Treatment & Off Gas

Filters

DWG 2040

Flow Diagram Residual Heat Removal System

Drawings

DWG 2045

Flow Diagram Core Spray System

2.2.69

Residual Heat Removal System

104

2.2.70

RHR Service Water Booster Pump System

2.2.71

Service Water System

135

2.2.73

Standby Gas Treatment System

2.2A.CS.DIV1

Core Spray Component Checklist (DIV 1)

2.2A.DG.DIV1

Standby AC Power System (Diesel Generator) Component

Checklist (DIV 1)

71111.04

Procedures

2.2A.RHR.DIV1

Residual Heat Removal System Component Checklist

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

(DIV 1)

2.2A.RHR.DIV2

Residual Heat Removal System Component Checklist

2.2A.RHR.DIV2

Residual Heat Removal System Component Checklist

(DIV 2)

2.2A.RHRSW.DIV2

RHR Service Water Booster Pump System Component

Checklist (DIV 2)

2.2A.SGT.DIV1

Standby Gas Treatment System Component Checklist

(DIV 1)

2.2A.SW.DIV0

Service Water System Non-Divisional Component

Checklist

2.2A.SW.DIV0

Service Water System Non-Divisional Component

Checklist

2.2A.SW.DIV2

Service Water System Component Checklist (DIV 2)

2.2B.RHR.DIV1

Residual Heat Removal System Instrument Valve Checklist

(DIV 1)

2.2B.RHR.DIV2

Residual Heat Removal System Instrument Valve Checklist

(DIV 2)

2.2B.RHR.DIV2

Residual Heat Removal System Instrument Valve Checklist

(DIV 2)

2.2B.RHRSW.DIV2

RHR Service Water Booster Pump System Instrument

Valve Checklist (DIV 2)

2.2B.SGT.DIV1

Standby Gas Treatment System Instrument Valve

Checklist (DIV 1)

2.2B.SW.DIV0

Service Water System Non-Divisional Instrument Valve

Checklist

2.2B.SW.DIV2

Service Water System Instrument Valve Checklist (DIV 2)

2.2B.SW.DIV2

Service Water System Instrument Valve Checklist (DIV 2)

Work Orders

WO 5343188, 5343240

Corrective Action

Documents

CR-CNS-

22-02221, 2022-02233

CNS-FP-211

Reactor Building Northeast Quadrant Elevations 881-9

and 859-9

CNS-FP-215

Reactor Building First Floor Elevation 903-6

71111.05

Fire Plans

CNS-FP-220

Reactor Building SBLC Area Elevation 976-0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CNS-FP-229

Control Building Cable Spreading Room Elevation 918-0

CNS-FP-397

FLEX Equipment Storage Facility Bldg. #1

0-BARRIER-MAPS

Barrier Maps

Procedures

0-BARRIER-

REACTOR

Reactor Building

Corrective Action

Documents

CR-CNS-

2013-04701, 2022-01138

Miscellaneous

NEDC 09-102

Internal Flooding - HELB, MELB, and Feedwater Line

Break

0-BARRIER-

REACTOR

Reactor Building

14.27.4

Reactor Building Floor Drain Sump Level Calibration

5.1FLOOD

Flood

Procedures

7.0.11

Flood Control Barriers

71111.06

Work Orders

WO 5363552

13.15.1

Reactor Equipment Cooling Heat Exchanger Performance

Analysis

3.34

Heat Exchanger Program Implementation

Procedures

7.2.42.3

Heat Exchanger Tube Plugging

71111.07A

Work Orders

WO 5406546

Corrective Action

Documents

CR-CNS-

22-01836

EOP-1A

RPV Control (1-3)

Miscellaneous

EOP-31

Primary Containment Control (1-3)

2.1.10

Station Power Changes

21

2.1.9

Low Power Operation for Maintenance Activities

Procedures

2.2.14

2kV Electrical System

71111.11Q

Work Orders

WO 5435655

Corrective Action

Documents

CR-CNS-

2019-05496, 2019-06302, 2020-06131, 2022-01143, 2022-

01643, 2022-01672

DWG 2006,

Sheet 1

Flow Diagram Circulating, Screen Wash & Service Water

Systems

71111.12

Drawings

DWG 2006,

Flow Diagram Circulating, Screen Wash & Service Water

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Sheet 4

Systems

DWG 2016,

Sheet 2

Flow Diagram for Pumphouse and Storage Tanks

DWG 2036,

Sheet 1

Flow Diagram Reactor Building Service Water System

FP-F03

Maintenance Rule Function FP-F03 Performance Criteria

Basis

RWCU-F03

Maintenance Rule Function RWCU-F03 Performance

Criteria Basis

SW-F04

Maintenance Rule Function SW-F04 Performance Criteria

Basis

Miscellaneous

VM-0725

Moore Products Composite Manual

15.2SW.601

SW Bay Emergency Sparger Functional Test

15.SWBP.201

Emergency Core Flooding Supply Valves Flushing

3-EN-DC-205

Maintenance Rule Monitoring

7C0

Procedures

5.8.8

Alternate Boron Injection and Preparation

Work Orders

WO 5375518

Corrective Action

Documents

CR-CNS-

22-02074, 2022-02084, 2022-02685

Protected Equipment Tagout, RHRB-1-SW-MOV-89B

INOP

04/18/2022

Protected Equipment Tagout, EE-1-WK 2219 EE-SSST

05/10/2022

Protected Equipment Tagout, DGB-1-DG2 Week 2220

05/16/2022

0-BARRIER-MISC

Miscellaneous Buildings

0-CNS-06

Site Risk Significance Standards

0-CNS-WM-104

On-Line Schedule Risk Assessment

Miscellaneous

0-PROTECT-EQP

Protected Equipment Program

0-CNS-FAP-OM-

031

Emergent Issue Response, Risk Classification, and

Oversight Determination

6.1DG.104

Diesel Operability Test with Isolation Switches in Isolate

(DIV 1)

71111.13

Procedures

6.HPCI.204

HPCI-SOV-SSV64 and HPCI-SOV-SSV87 IST Closure

Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

WO 5343188, 5357684, 5414295

Corrective Action

Documents

CR-CNS-

2019-02761, 2021-00343, 2021-01450, 2021-02271, 2021-

03035, 2021-03273, 2021-03646, 2021-04054, 2022-

01607, 2022-01631, 2022-01643, 2022-01667, 2022-

01671, 2022-01672, 2022-01777, 2022-01778, 2022-

01789, 2022-02084, 2022-02158, 2022-02688, 2022-

2705, 2022-02726, 2022-02729, 2022-02745

CNS-EQ-129

EQ Configuration Detail - Limitorque Valve Actuator

N05

DWG 2031

Flow Diagram Reactor Building - Closed Cooling Water

System

N65

Drawings

DWG 2036

Flow Diagram Reactor Building - Service Water System

A6

ECR Number - CR-CNS-2022-01672

04/21/2022

ECR Number - CR-CNS-2022-01643-CA-006

04/21/2022

Overthrust/Overtorque Evaluation Sign-Off and Review

Sheet, SW-MOV-MO89B

04/18/2022

ODM - MCC-K(4D)

Operational Decision Making Review for MCC-K(4D)

VM-0217

5800 Horizontal Split Case Pumps

VM-0986

Limitorque Composite Manual

VM-1183

Hydrogen/Oxygen Monitoring System

Miscellaneous

VM-1369

Peneberthy Composite Manual

0.9

Tagout

108

2.2.70

RHR Service Water Booster Pump System

6.1SWBP.101

RHR Service Water Booster Pump Flow Test and Valve

Operability Test (DIV1)

Procedures

7.5.3

MOV Diagnostics

71111.15

Work Orders

WO 5443432

NEDC 00-041

Limiting Component Analysis for Containment Spray Motor

Operated Valves

Calculations

NEDC 96-018

Design Specification for Valve Limiting Component

Analysis

1C1

Corrective Action

Documents

CR-CNS-

2016-02281, 2018-07146, 2019-02583, 2021-01653, 2021-

2034, 2021-02943

71111.17T

Corrective Action

Documents

CR-CNS-

22-02530, 2022-02555, 2022-02570

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Resulting from

Inspection

2041

Cooper Nuclear Station Isometric Key Reactor Building

Main Steam System

AF/29

3038, Sheet 7

Control Elementary Diagrams

3058

Cooper Nuclear Station, DC One-Line Diagram

3059, Sheet 5

Cooper Nuclear Station, EE-Panel-BB2 125VDC Load And

Fuse Schedule

3062, Sheet 3

Cooper Nuclear Station, DC Control Elementary Diagram

3063, Sheet 4

Cooper Nuclear Station, DC Control Elementary Diagrams

45003608

Flow Diagram, Reactor Building Heating and Ventilating

791E260, Sheet 2

Elem [Elementary] Diag [Diagram] - Traversing Incore

Probe Calibration Sys [System] Cooper

N03

791E266, Sheet 5

Elementary Diagram Primary Containment Isolation

System

791E266, Sheet 6

Elementary Diagram Primary Containment Isolation

System

791E266, Sheet 8

Elementary Diagram, Primary Containment Isolation

System

791E271, Sheet 1

Cooper Nuclear Station, HPCI [High-Pressure Coolant

Injection] System Elementary Diagram

791E271, Sheet 10

Elementary Diagram HPCI System, Cooper Nuclear

Station

791E271, Sheet 11

Cooper Nuclear Station, HP Coolant Injection System

Elementary Diagrams

791E271, Sheet 7

Cooper Nuclear Station, Elementary Diagram HPCI

System

791E271, Sheet 8

Cooper Nuclear Station, HPCI System Elementary

Diagram

N20

NC66688

Cooper 345KV Substation One-Line Switching Diagram

NF89767

Cooper 345KV Substation Connection Diagram Reactor

No. 3401

Drawings

X2629-204

MS-1 Main Steam

Engineering

CED 6013561

Reactor Building Ventilation Exhaust System Upgrade

03/23/2005

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DC 5319938

HPCI LOV [Loss of Voltage] Relay Removal

DEC 5314933

TIP Drive Control Unit Replacement

DEC 5329608

HV-DPIC-835A&B Replacement

DEC 5345657

Alternate Recorder for RWCU-FR-97A/B

DEC 5404656

HPCI-FIS-78 SCR 202I-003 for Switch 1

EE 19-030

RCIC Minimum Flow Bypass Valve Closure Requirements

Evaluation

EE 21-001

RCIC-LS-74 Evaluation of Setpoint and Tolerances

15C15

EE 21-007

Use-As-ls Engineering Evaluation for MS-V-205

03/24/2021

EE 21-018

Update of NEDC 87-131D

2/20/2021

EE 22-004

OG-MOT-OGVP (VPA) Motor Change Evaluation

TCC 5328958

Diesel Generator Cooling Water Alternate Discharge Flow

Path

Changes

TCC 5395350

MS-AOV-790AV Packing Leak Repair

CNS Inservice Testing Program Basis Document

2336

CNS Vessel lnternals Program

Cooper 345kV -

930096

NPPD Relay Setting Request

05/14/2020

MSPI EAC Dec

2019

Regulatory Performance Indicator Process for MSPI EAC

01/18/2020

Miscellaneous

VM 1869

Vendor Manual for Siemens Model 353 Process

Automation Controller

2/00/2011

0-CNS-LI-100

Process Applicability Determination

0-CNS-LI-101

10CFR50.59 Evaluations

0.4

Procedure Change Process

2.0.1

Conduct of Operations Procedure - Plant Operations Policy

2.0.1.2

Conduct of Operations Procedure - Operations Procedure

Policy

2.0.1.3

Conduct of Operations Procedure - Time Critical Operator

Action Control and Maintenance

2.0.3

Conduct of Operations

105

2.3_9-3-1

Alarm Procedure - Panel 9-3 - Annunciator 9-3-1

Procedures

3-EN-DC-115

Engineering Change Process

15C16

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

3.4.4

Temporary Configuration Change

IP-ENG-001

Standard Design Process

1C0

Miscellaneous

VM-0248

Crane Valve Composite Manual

Procedures

7.7.10.2

P1-B Welding Procedure Specification

71111.19

Work Orders

WO 27024, 5345882, 5346891, 5373673, 5383074,

5406580, 5412710, 5412711, 5423432, 5442690

Corrective Action

Documents

CR-CNS-

22-02108, 2022-02780, 2022-02785, 2022-02807

Drawings

DWG 2036

Flow Diagram Reactor Building - Service Water System

A6

0-CNS-WM-104

On-Line Schedule Risk Assessment

2.3.1

General Alarm Procedure

6.1DG.402

IST Closure Testing of DGSA Receiver Inlet Check Valves

(DIV 1)

6.1PC.303

PCIS Main Steam Line High Flow Channel Calibration

(DIV 1)

6.HPCI.103

HPCI IST and 92 Day Test Mode

6.LOG.601

Daily Surveillance Log - Modes 1, 2, and 3

2

6.RHR.706

Reactor High-Pressure Channel Functional Test

6.SLC.101

SLC Pump Operability Test

EOP-3A

Primary Containment Control (1-3)

Procedures

EOP-5A

Secondary Containment Control (1-3)

71111.22

Work Orders

WO 5344852, 5353642, 5354557, 5356861, 5437883

Corrective Action

Documents

CR-CNS-

20-00227, 2020-00349, 2020-00526, 2020-00670, 2020-

01442, 2021-00892, 2021-02452, 2021-02749, 2021-

2769, 2021-02957, 2021-03197, 2021-03560, 2021-

03792, 2021-05452, 2022-00028, 2022-02226, 2022-

229, 2022-02234

February 25, 2020, Full Team Dress Rehearsal Exercise

03/16/2020

21 NRC/FEMA Biennial Exercise - ERO Team "D"

06/24/2021

February 2, 2021, Full Team B Drill

03/01/2021

21 Biennial Exercise Dress Rehearsal

05/05/2021

April 5, 2022, Full Team 2 & B Dress Rehearsal Drill

04/15/2022

71114.01

Miscellaneous

22 Emergency Management Performance Evaluation

2/09/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Dress Rehearsal Drill

22 Emergency Management Performance Evaluation

Drill

2/16/2022

July 31, 2018, Biennial NRC-Graded Exercise Summary

Report

08/10/2018

Updated Final Safety Analysis

Emergency Plan for Cooper Nuclear Station

EAL Technical Basis Document

Controller/Evaluator

Log

TSC, Engineering Team Lead

05/24/2022

Controller/Evaluator

Log

TSC, Engineering Mechanical

05/24/2022

Controller/Evaluator

Log

TSC, Lead Evaluator

05/24/2022

Controller/Evaluator

Log

TSC, Security Coordinator

05/24/2022

Emergency Action

Log

Ops/EOP Adviser

05/24/2022

Emergency Action

Log

TSC Communicator

05/24/2022

Notification Report

Number 3

Drill SA6.1 Alert Declaration, 10:03 a.m.

05/24/2022

Notification Report

Number 4

Drill FS1.1 Site Area Emergency Declaration, 10:23 a.m.

05/24/2022

Notification Report

Number 5

Drill AG1.2 General Emergency Declaration, 10:41 a.m.

05/24/2022

Notification Report

Number 6

Drill AG1.2 General Emergency Follow-Up, 11:03 a.m.

05/24/2022

Notification Report

Number 7

Drill AG1.2 General Emergency Follow-Up, 12:02 p.m.

05/24/2022

TSC Log

May 24th Biennial Exercise, CNS TSC Log Keeper

TSC09

Position Instruction Manual

Procedures

5.7.1

4, EAL Classification Matrix

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

5.7.1

Emergency Classification

5.7.11

Early Dismissal/Evacuation of Site Personnel

5.7.12

Emergency Radiation Exposure Control

5.7.16

Release Rate Determination

5.7.17

CNS-DOSE Assessment

5.7.20

Protective Action Recommendations

5.7.7

Activation of TSC

5.7.9

Activation of EOF

5.7ENS

ENS Communicator

Engineering

Changes

DEC-5416038

TSC/OSC Upgrades

Emergency Plan for Cooper Nuclear Station

Updated Final Safety Analysis

EAL Technical Basis Document

21-37

Emergency Preparedness Regulatory Review (50.54(q))

21-63

Emergency Preparedness Regulatory Review (50.54(q))

5.7.1

Emergency Classification

5.7.1, Attachment 4

EAL Classification Matrix

5.7.1, Attachment 4

EAL Classification Matrix

50.54(q) Evaluation

Number: 2021-94

Activity/Document Number: TSC/OSC Upgrade, Title:

"Digital Upgrade and Remodel of TSC/OSC"

01/10/2022

50.54(q) Evaluation

Number: 2022-06

Activity/Document Number: DEC 5338473, Title: EPN

Component Replacement

2/03/2022

50.54(q) Screen

Number: 2021-092

Activity/Document Number: 5.7.1, Revision Number: 72,

Title: Emergency Classification

01/04/2022

50.54(q) Screen

Number: 2021-94

Activity/Document Number: DEC-5416038, Revision

Number: 0, Title: TSC/OSC Upgrades

01/07/2022

50.54(q) Screen

Number: 2022-06

Activity/Document Number: DEC-5338473, Title: EPN

Component Replacement

2/03/2022

83307

Intranet Document Control System

05/24/2021

Miscellaneous

NLS2022006

Emergency Plan Implementing Procedure, Cooper Nuclear

Station, Docket No. 50-298, DPR-46

03/08/2022

71114.04

Procedures

0.29.1

License Basis Document Changes

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0.29.4

Other Regulatory Reviews

5.7.1, Attachment 4

EAL Classification Matrix

Miscellaneous

NLS2022013

Emergency Plan Full Participation Exercise Drill Scenario,

Cooper Nuclear Station, Docket No. 50-298, DPR-46

03/22/2022

2.1.5

Reactor Scram

5.2FUEL

Fuel Failure

5.7.1

Emergency Classification

71114.08

Procedures

5.7.20

Protective Action Recommendations

Corrective Action

Documents

CR-CNS-

21-02749, 2021-03221

A Prompt Alert and Notification System Design Report for

the Cooper Nuclear Station

Miscellaneous

Performance Indicator Documentation and Data Review

Forms from April 2021 through March 2022

0-EN-LI-114

Regulatory Performance Indicator Process

17C0

8.8.1.14

Radiochemical Iodines Analysis

EPDG No. 2,

C-1

Semi-Monthly Alert and Notification System Siren Testing

71151

Procedures

EPDG No. 2,

C-5

Annual Full-Cycle Sounding of Alert and Notification

System Sirens

Corrective Action

Documents

CR-CNS-

21-05061, 2022-01643, 2022-01646, 2022-01647, 2022-

01777, 2022-01778, 2022-01789, 2022-01869, 2022-

01870, 2022-01871, 2022-01896, 2022-01912, 2022-

2737, 2022-02821

Miscellaneous

USA M-1

CFR 50.59 Resource Manual

0-CNS-LI-100

Process Applicability Determination

0-CNS-LI-102

Corrective Action Process

0.5.OPS

Operations Review of Condition Reports/Operability

Determinations

Procedures

7.0.7

Scaffolding Construction and Control

71152S

Work Orders

WO 5367582

71153

Corrective Action

Documents

CR-CNS-

2019-01277, 2021-01483, 2021-01511