IR 05000354/2014001
| ML15062A112 | |
| Person / Time | |
|---|---|
| Site: | Hope Creek |
| Issue date: | 03/04/2015 |
| From: | Glenn Dentel Reactor Projects Branch 3 |
| To: | Joyce T Public Service Enterprise Group |
| DENTEL, GT | |
| Shared Package | |
| ML15049A471 | List: |
| References | |
| IR 2014001 | |
| Download: ML15062A112 (5) | |
Text
March 4, 2015
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR HOPE CREEK GENERATING STATION (REPORT 05000354/2014001)
Dear Mr. Joyce:
On February 11, 2015, the U. S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Hope Creek Generating Station (Hope Creek). The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014 through December 31, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Hope Creek operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Hope Creek during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.
Additionally, an NRC audit of licensee efforts towards compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," is ongoing for various sites. The audit includes an onsite visit for the NRC staff to evaluate mitigating strategies as described in the licensee submittals, and to receive and review information relative to associated open items. This onsite audit will aid NRC staff in developing a final Safety Evaluation for the site. The audit at your site has not been scheduled and will be conducted in the future once a date has been set. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
In accordance with Title 10 of the Code of Federal Regulations, Part 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610) 337-5233 with any questions you have regarding this letter.
Sincerely,
/RA/
Glenn T. Dentel, Chief Projects Branch 3 Division of Reactor Projects
Docket No. 50-354 License No. NPF-57
Enclosure: Hope Creek Inspection/Activity Plan
cc w/encl: Distribution via ListServ
ML15062A112 SUNSI Review
Non-Sensitive Sensitive
Publicly Available Non-Publicly Available
OFFICE RI/DRP RI/DRP RI/DRP
NAME JHawkins/per email MSD MDraxton/ MSD GDentel/ GTD
DATE 02/24/15 02/25/15 03/04/15
Page 1 of 2 02/25/2015 08:54:34 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Hope Creek Inspection / Activity Plan 01/01/2015 - 06/30/2016 2/23EXM
- INITIAL OL EXAM
1 FY15-HOPE CREEK INITIAL OPERATOR LICENSING EXAM U01904 01/26/2015 01/30/2015
FY15-HOPE CREEK INITIAL OPERATOR LICENSING EXAM U01904 02/23/2015 02/27/2015 71152B
- PI&R - BIENNIAL
1 IP Problem Identification and Resolution 71152B 01/26/2015 01/30/2015
IP Problem Identification and Resolution 71152B 02/09/2015 02/13/2015 71124
- RAD CONTROLS
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/30/2015 04/04/2015
IP Occupational ALARA Planning and Controls 71124.02 03/30/2015 04/04/2015
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/30/2015 04/04/2015
IP Occupational Dose Assessment 71124.04 03/30/2015 04/04/2015
IP Radiation Monitoring Instrumentation 71124.05 03/30/2015 04/04/2015 7111108G
- INSERVICE INSPECTION
1 IP Inservice Inspection Activities - BWR 7111108G 04/20/2015 04/24/2015 71124
- RAD CONTROLS
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/20/2015 04/24/2015
IP Occupational ALARA Planning and Controls 71124.02 04/20/2015 04/24/2015
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 04/20/2015 04/24/2015
IP Occupational Dose Assessment 71124.04 04/20/2015 04/24/2015
IP Radiation Monitoring Instrumentation 71124.05 04/20/2015 04/24/2015 71124
- EFFLUENTS
1 IP Radiation Monitoring Instrumentation 71124.05 05/11/2015 05/15/2015
IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 05/11/2015 05/15/2015 EP
- EP PROGRAM INSPECTION
1 IP Alert and Notification System Testing 7111402 06/22/2015 06/26/2015
IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 06/22/2015 06/26/2015
IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 06/22/2015 06/26/2015 71124
- RAD CONTROLS
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 08/10/2015 08/14/2015
IP Occupational ALARA Planning and Controls 71124.02 08/10/2015 08/14/2015
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 08/10/2015 08/14/2015
IP Occupational Dose Assessment 71124.04 08/10/2015 08/14/2015
IP Radiation Monitoring Instrumentation 71124.05 08/10/2015 08/14/2015 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 02/25/2015 08:54:34 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Hope Creek Inspection / Activity Plan 01/01/2015 - 06/30/2016 CDBI
- COMPONENT DESIGN BASIS INSPECTION
1 IP Component Design Bases Inspection 7111121 09/21/2015 09/25/2015
IP Component Design Bases Inspection 7111121 10/05/2015 10/09/2015
IP Component Design Bases Inspection 7111121 10/19/2015 10/23/2015 71124
- RAD CONTROLS
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/16/2015 11/20/2015
IP Occupational ALARA Planning and Controls 71124.02 11/16/2015 11/20/2015
IP Radiation Monitoring Instrumentation 71124.05 11/16/2015 11/20/2015
IP Performance Indicator Verification 71151 11/16/2015 11/20/2015 71124.08
- RADWASTE
1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 12/07/2015 12/11/2015 TRI FI
- TRIENNIAL FIRE PROTECTION
1 IP Fire Protection [Triennial]
7111105T 03/14/2016 03/18/2016
IP Fire Protection [Triennial]
7111105T 03/28/2016 04/01/2016 EP
- EP EXERCISE EVALUATION
1 IP Exercise Evaluation 7111401 05/16/2016 05/20/2016 71124
- RADIATION PROTECTION
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 05/02/2016 05/06/2016
IP Occupational ALARA Planning and Controls 71124.02 05/02/2016 05/06/2016
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 05/02/2016 05/06/2016
IP Occupational Dose Assessment 71124.04 05/02/2016 05/06/2016
IP Radiation Monitoring Instrumentation 71124.05 05/02/2016 05/06/2016 71124
- ENVIRONMENTAL
1 IP Radiological Environmental Monitoring Program 71124.07 06/06/2016 06/10/2016 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.