Letter Sequence RAI |
---|
|
Results
Other: CNL-15-095, Revision to the Reactor Pressure Vessel Surveillance Capsule Withdrawal Schedule for License Renewal, CNL-15-164, Second Annual Update, License Renewal Application, CNL-15-178, License Renewal Application - Clarifications (TAC Nos. MF0481 and MF0482), ML13032A251, ML13057A873, ML13067A201, ML13141A320, ML15236A067
|
MONTHYEARML13024A0042013-01-0707 January 2013 Transmittal of License Renewal Application Project stage: Request ML13032A2512013-01-10010 January 2013 Reactor Pressure Vessel Surveillance Capsule Withdrawal Schedule Revision Due to License Renewal Amendment Project stage: Other ML13057A8732013-03-0808 March 2013 Plan for the Scoping and Screening Regulatory Audit Regarding the Sequoyah Nuclear Plant, Unit 1 and 2, LRA Review Project stage: Other ML13067A2012013-03-11011 March 2013 Plan for the Aging Management Program Regulatory Audit Regarding the Sequoyah Nuclear Plant, Units 1 and 2 License Renewal Application Review (TAC Nos. MF0481 and MF0482) Project stage: Other ML13109A5152013-04-26026 April 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) Project stage: RAI ML13122A3402013-05-0808 May 2013 RAI for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) Project stage: RAI ML13119A0972013-05-21021 May 2013 Summary of Telephone Conference Call Held on April 22, 2013 Between the U.S. Nuclear Regulatory Commission and Tva,Concerning Requests for Additional Information Pertaining to the Sequoyah Nuclear Plant, License Renewal Application Project stage: RAI ML13142A3322013-05-21021 May 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) Project stage: RAI ML13128A5192013-05-31031 May 2013 Request for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application Project stage: RAI ML13134A2012013-06-0505 June 2013 RAI for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, LRA Project stage: RAI ML13163A4422013-06-0707 June 2013 Response to NRC Request for Additional Information Regarding the Scoping and Screening Methodology Review of the License Renewal Application, Set 3 Project stage: Response to RAI ML13144A7122013-06-11011 June 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (Tac Nos. MF0481 and MF0482)- Set 6 Project stage: RAI ML13134A3712013-06-13013 June 2013 5/9/2013 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Tennessee Valley Authority, Concerning Requests for Additional Information Pertaining to the Sequoyah Nuclear Plant, Units 1 and 2, License Ren Project stage: RAI ML13141A3202013-06-13013 June 2013 Letter Aging Management Programs Audit Report Regarding the Sequoyah Nuclear Plant, Units 1 and 2 Project stage: Other ML13150A4122013-06-24024 June 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) - Set 8 Project stage: RAI ML13178A2832013-06-25025 June 2013 Response to NRC Request for Additional Information Regarding the Reactor Vessel Internals Review of the License Renewal Application, Set 1 Project stage: Response to RAI ML13158A0162013-06-25025 June 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) Set 9 Project stage: RAI ML13190A2762013-07-0101 July 2013 Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, Set 4 Project stage: Response to RAI ML13192A3302013-07-0303 July 2013 Response to NRC Request for Additional Information Regarding the Review of License Renewal Application, Set 5 (TAC Nos. MF0481 and MF0482) Project stage: Response to RAI ML13204A3992013-07-11011 July 2013 Response to NRC Request for Additional Information Re Reactor Vessel Internals Review of the License Renewal Application, Set 6 Project stage: Response to RAI ML13213A0262013-07-25025 July 2013 Response to NRC Request for Additional Information Regarding the Review of License Renewal Application, Set 4/Buried Piping, Set 8, and Set 9 (TAC MF0481 and MF0482) Project stage: Response to RAI ML13213A0272013-07-29029 July 2013 Response to NRC Request for Additional Information Regarding the Review of License Renewal Application, Set 7 (TAC Nos. MF0481 and MF0482) Project stage: Response to RAI ML13213A0142013-07-30030 July 2013 Revised Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, Sets 1 and 3 (TAC MF0481 and MF0482) Project stage: Response to RAI ML13171A0362013-08-0101 August 2013 Summary of Telephone Conference Call Held on June 13, 2013, Between the NRC and Tennessee Valley Authority, Concerning RAI Pertaining to the Sequoyah Nuclear Plant, Units 1 and 2, LRA Project stage: RAI ML13204A2572013-08-0202 August 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) - Set 10 Project stage: RAI ML13225A3872013-08-0909 August 2013 Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units I and 2, License Renewal Application, Sets 1, 6, 7, and Revised Responses for 1.4-2, 1.4-3 and 1.4-4 (TAC Nos. MF0481 and MF0482) Project stage: Response to RAI ML13224A1262013-08-22022 August 2013 RAI for Review of Sequoyah, Units 1 & 2 License Renewal Application - Set 11 Project stage: RAI ML13238A2442013-08-30030 August 2013 RAI Set 12 Project stage: RAI ML13252A0362013-09-0303 September 2013 Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, Set 10 (30-day), B.1.9-1, B.1.4-4 Revised RAI Responses and Revision to LRA Page 2.4-44 (TAC Nos. MF0481 and MF0482) Project stage: Response to RAI ML13226A3712013-09-10010 September 2013 Summary of Telephone Conference Call Held on August 1, 2013, Between the U.S. Nuclear Regulatory Commission and Tennessee Valley Authority, Concerning Requests for Additional Information Pertaining to the Sequoyah Nuclear Plant, Units 1 Project stage: RAI ML13267A1592013-09-20020 September 2013 Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application, Set 11 (30-day), and Revised RAI Responses for B.1.14-1a, 2.5. Project stage: Response to RAI ML13247A4272013-09-23023 September 2013 Summary of Telephone Conference Call Held on August 19, 2013, Between the NRC and Tennessee Valley Authority, Concerning RAI Pertaining to the Sequoyah Nuclear Plant, Units 1 and 2, LRA Project stage: RAI ML13263A3382013-09-26026 September 2013 RAI Set 14 Project stage: RAI ML13268A4922013-09-27027 September 2013 RAI Set 15 Project stage: RAI ML13276A0182013-09-30030 September 2013 Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, Sets 10 (B.1.23-2a), 11 (4.1-8a), and 12 (30-day) Project stage: Response to RAI CNL-13-103, Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application, Sets 8 (B.1.33-1), 10 (3.0.3-1 Request 1), 12 (B.1.23-2b), 13 (30-day), 14 (B.0.4-1a)2013-10-17017 October 2013 Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application, Sets 8 (B.1.33-1), 10 (3.0.3-1 Request 1), 12 (B.1.23-2b), 13 (30-day), 14 (B.0.4-1a) Project stage: Response to RAI ML13282A3302013-10-18018 October 2013 RAI Set 16 Project stage: RAI CNL-13-104, Response to NRC Request for Additional Information Regarding the Review of License Renewal Application, Sets 11 (B.1.40-4a, B.1.25.1a), 13 (B.1.41-4a),14 (3.5.1-57, 3.5.1-87)2013-10-21021 October 2013 Response to NRC Request for Additional Information Regarding the Review of License Renewal Application, Sets 11 (B.1.40-4a, B.1.25.1a), 13 (B.1.41-4a),14 (3.5.1-57, 3.5.1-87) Project stage: Response to RAI CNL-13-105, Response to NRC Request for Additional Information Regarding Review of the License Renewal Application, Sets 10 (3.0.3-1, Requests 3, 4, 6), 12 (B.1.6-1b, B.1.6-2b), 16 (4.3.1-8a)2013-11-0404 November 2013 Response to NRC Request for Additional Information Regarding Review of the License Renewal Application, Sets 10 (3.0.3-1, Requests 3, 4, 6), 12 (B.1.6-1b, B.1.6-2b), 16 (4.3.1-8a) Project stage: Response to RAI CNL-13-106, Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units I and 2, License Renewal Application, Sets 13 (B.1.34-5a), 15 (4.2-1a), 16 (B.1.23-2c), 17 (B.1.23-2d), LRA Sections A.1.34 and B2013-11-15015 November 2013 Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units I and 2, License Renewal Application, Sets 13 (B.1.34-5a), 15 (4.2-1a), 16 (B.1.23-2c), 17 (B.1.23-2d), LRA Sections A.1.34 and B.1 Project stage: Response to RAI ML13323A0972013-12-0606 December 2013 RAI Set 18 Project stage: RAI CNL-13-130, Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, B.1.41-4b, 3.0.3-1 (Requests La, 3a, 4a, 6a), B.1.23-2e, 3.4.2.1.1-2a, Tables (3.4.1, 3.4.2-3-5, 3.3.1..2013-12-16016 December 2013 Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, B.1.41-4b, 3.0.3-1 (Requests La, 3a, 4a, 6a), B.1.23-2e, 3.4.2.1.1-2a, Tables (3.4.1, 3.4.2-3-5, 3.3.1.. Project stage: Response to RAI ML13353A5382013-12-23023 December 2013 RAI Set 19 Project stage: RAI ML13338A3332014-01-0808 January 2014 Summary of Telephone Conference Call Held on August 22, 2013, Between the U.S. Nuclear Regulatory Commission and Tennessee Valley Authority, Concerning Requests for Additional Information Pertaining to the Sequoyah Nuclear Plant, Units 1 an Project stage: RAI CNL-14-021, Response to Request for Clarification to NRC Request for Additional Information Re Review of License Renewal Application, LRA B.1.31, B.1.25.1b, B.1.34-8a, B.1.34-9A, LRA Annual Update (TAC MF0481 & MF0482)2014-03-0303 March 2014 Response to Request for Clarification to NRC Request for Additional Information Re Review of License Renewal Application, LRA B.1.31, B.1.25.1b, B.1.34-8a, B.1.34-9A, LRA Annual Update (TAC MF0481 & MF0482) Project stage: Supplement ML14059A3472014-03-0404 March 2014 Schedule Revision for the Review of the Sequoyah Nuclear Plant License Renewal Application (TAC Nos. MF0481 and MF0482) Project stage: Approval ML14063A5422014-03-0404 March 2014 TVA Response to Request for Clarification to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application, LRA B.1.31, B.1.25.1 B, B.1.34-Sa, B.1.34-9a, LRA Annual ... Project stage: Supplement ML14064A4732014-03-12012 March 2014 Request for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, LRA - Set 20 Project stage: RAI ML14094A2942014-04-11011 April 2014 Project Manager Change for the Safety Review of the Sequoyah Nuclear Plant, Units 1 & 2, License Renewal Application (TAC Nos. MF0481 & MF0482) Project stage: Approval CNL-14-052, TVA Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application: RAIs B.1.13-4 and 3.0.3-1-3c, Commitment 9.G, and 2013 LRA Annual Update (TAC Nos. MF042014-04-22022 April 2014 TVA Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application: RAIs B.1.13-4 and 3.0.3-1-3c, Commitment 9.G, and 2013 LRA Annual Update (TAC Nos. MF0481 Project stage: Response to RAI 2013-07-01
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML23307A0832023-11-0808 November 2023 Enclosure - Request for Additional Information HDI-Sequoyah NDE Exemption Request 10-30-2023 ML23307A0822023-11-0808 November 2023 Request for Additional Information August 4, 2022, Exemption Request for Deviating from the Conditions of Certificate of Compliance No. 1032, Amendment No. 3, Related to Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation ML23062A5952023-02-27027 February 2023 Staff follow-up Questions to Tva'S 12/19/2022 Response of the Staff'S Rsi Regarding 08/04/2022 SQN Exemption Request ML23062A5942023-02-27027 February 2023 Enclosure - NRC SQN Exemption Rsi Response Staff Follow Up Questions ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22257A0622022-09-14014 September 2022 Requalification Program Inspection - Sequoyah Nuclear Plant ML22255A0842022-09-0909 September 2022 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-04 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22214A1582022-08-0202 August 2022 NRR E-mail Capture - Request for Additional Information for Sequoyah Units 1 and 2 License Amendment Request for Fire and Seismic PRA Modification to 10 CFR 50.69 (L-2022-LLA-0033) ML22151A0102022-05-27027 May 2022 NRR E-mail Capture - Revised Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22151A0092022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22146A3322022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Related to Sequoyah Nuclear Plant'S LAR to Adopt TSTF-505 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML21237A4952021-08-25025 August 2021 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021-04 ML21160A0352021-06-0303 June 2021 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021-03 ML21095A0482021-04-0505 April 2021 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Request to Transition to Westinghouse Fuel ML21092A0972021-04-0202 April 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML20259A4782020-09-15015 September 2020 Emergency Preparedness Program Inspection Request for Information ML20261H4172020-09-14014 September 2020 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Hydrologic UFSAR Update ML20261H4162020-09-0202 September 2020 NRR E-mail Capture - Draft Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, Request to Revise UFSAR Hydrologic Analysis ML20189A2112020-07-0101 July 2020 Request for Additional Information Regarding Hydrologic UFSAR Update ML20106F1042020-04-14014 April 2020 Request for Additional Information Regarding the Hydrologic Analysis LAR ML20161A3902020-04-0909 April 2020 Request for Supporting Information for the Sequoyah SPRA Audit Review - Follow-up to Plant Response Question 5 ML20098D8612020-04-0707 April 2020 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000327/2020012 and 05000328/2020012) and Request for Information) ML20036E2842020-02-0505 February 2020 20200123 - Sequoyah Radiation Safety Inspection Document Request Letter ML19323D7562019-11-18018 November 2019 Nrc'S Request for Additional Information - Exigent Amendment ML19235A0992019-08-22022 August 2019 Emergency Preparedness Program Inspection Request for Information ML19162A2462019-06-11011 June 2019 RP Inspection Document Request 2019-03 ML19149A6222019-05-29029 May 2019 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, Request for Alternative to 18-ISI-1 EPID: L-2019-LLR-0006 ML19148A7912019-05-28028 May 2019 NRR E-mail Capture - Sequoyah Nuclear Plant and Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request for Alternative to OM Code Requirements ML19015A4192019-01-15015 January 2019 NRR E-mail Capture - RAI - Sequoyah Nuclear Plant, Units 1 and 2, LAR to Adopt 10 CFR50.69 Risk-informed SSC ML18344A0752018-12-10010 December 2018 NRR E-mail Capture - Request for Additional Information - Sequoyah 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers and to Revise Updated Final Analysis Report (SQN-TS-17-04) ML18296A0022018-10-22022 October 2018 NRR E-mail Capture - Additional Information Needs - Sequoyah Units 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers Revise Updated Final Analysis Report (SQN-TS-17-04) ML18283B0592018-10-10010 October 2018 NRR E-mail Capture - Additional Information Needs Identified During Audit - Sequoyah 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers Revise Updated Final Analysis Report (SQN-TS-17-04) ML18283A6232018-09-25025 September 2018 04 RP Inspection Document Request ML18233A1942018-08-21021 August 2018 NRR E-mail Capture - Additional Information Needs Identified - Sequoyah 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers and to Revise Updated Final Analysis Report (SQN-TS-17-04) ML18138A1102018-05-17017 May 2018 Enclosurequest for Additional Information (Letter to E. D. Schrull Request for Additional Information Regarding Tennessee Valley Authority'S Decommissioning Funding Plan Update for Browns Ferry and Sequoyah Isfsis) ML18057A6372018-02-23023 February 2018 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet Topical Report TVA-NPG-AWA16 - EPIC: L-2016-TOP-0011) ML17191A2062017-07-0606 July 2017 NRR E-mail Capture - Sequoyah Nuclear Station, Unit 1 & 2 - Request for Additional Information Related to LAR for Technical Specification 3.8.1.17 Note Modification (CAC Nos. MF9398 and MF9399) ML17150A0792017-05-23023 May 2017 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet LAR for EAL Change to Adopt NEI-99-01 Rev.6 (CAC Nos. MF9054 - MF9060) ML17112A0402017-04-20020 April 2017 NRR E-mail Capture - Sequoyah Nuclear Station, Unit 1 & 2 - Request for Additional Information Related to LAR for Technical Specification 3.8.1, AC SOURCES-OPERATING ML17004A0612017-01-0404 January 2017 Notification of NRC Triennial Fire Protection Inspection (Team)(Report 05000327/2017007 and 05000328/2017007) ML15194A3882015-07-13013 July 2015 Request for Additional Information Related to LAR to Revise Ice Condenser Ice Mas Tech Spec ML15175A2912015-06-24024 June 2015 E-mail Re. Request for Additional Information RR RP-07 ML15159B1642015-06-22022 June 2015 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application-Set 25 (TAC Nos. MF0481 and MF0482) ML15050A0962015-02-19019 February 2015 E-mail Re. Request for Additional Information Related to LAR to Ice Condendser Inc Mass Tech Spec ML15042A4702015-02-11011 February 2015 E-mail Re. Request for Additional Information Related to License Amendment Request to Revise Technical Specification on Ultimate Heat Sink ML14318A8052014-11-12012 November 2014 Requalification Program Inspection - Sequoyah Nuclear Plant ML14254A2042014-09-22022 September 2014 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application - Set 22 (TAC Nos. MF0481 and MF0482) ML14220A2132014-08-0808 August 2014 E-mail Re. Request for Additional Information Regarding Voluntary Risk Initiative National Fire Protection Association Standard 805 2023-02-27
[Table view] Category:Letter
MONTHYEARML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24018A0142024-01-17017 January 2024 Engine Systems, Inc., Report No. 10CFR21-0137, Rev. 1, 56913-EN 56913 ML24011A3182024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), October 2023 ML24011A3172024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), September 2023 ML24011A3202024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), December 2023 ML24011A3162024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), August 2023 ML24011A3192024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), November 2023 IR 05000327/20234422024-01-11011 January 2024 95001 Supplemental Inspection Report 05000327/2023442 and 05000328/2023442 and Follow-Up Assessment Letter ML24010A2132024-01-10010 January 2024 CFR 21.21 Final Report Regarding Siemens Medium Voltage Circuit Breakers ML24018A0952024-01-0404 January 2024 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance Report No. 10CFR21-0137, Rev. 0 ML24004A0332024-01-0303 January 2024 Interim Report of a Deviation or Failure to Comply Crompton Instruments Type 077 Ammeter ML24004A0402024-01-0303 January 2024 Response to NRCs November 8, 2023, Request for Additional Information - Related to Independent Spent Fuel Storage Installation CNL-23-068, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) ML23346A1222023-12-12012 December 2023 Annual Non-Radiological Environmental Operating Report - 2023 IR 05000327/20234202023-11-28028 November 2023 Security Baseline Inspection Report 05000327/2023420 and 05000328/2023420 CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23324A4362023-11-0909 November 2023 Exam Corporate Notification Letter Aka 210-day Letter ML23307A0822023-11-0808 November 2023 Request for Additional Information August 4, 2022, Exemption Request for Deviating from the Conditions of Certificate of Compliance No. 1032, Amendment No. 3, Related to Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation IR 05000327/20230032023-11-0303 November 2023 Integrated Inspection Report 05000327/2023003 and 05000328/2023003 ML23306A1592023-11-0202 November 2023 Enforcement Action EA-22-129 Inspection Readiness Notification ML23292A0792023-10-19019 October 2023 Tennessee Valley Authority - Emergency Plan Implementing Procedure Revision, Includes EPIP-5, Revision 58, General Emergency IR 05000327/20230112023-10-16016 October 2023 Triennial Fire Protection Inspection Report 05000327/2023011 and 05000328/2023011 ML23285A0882023-10-12012 October 2023 Submittal of Sequoyah Nuclear Plant, Units 1 and 2, Submittal of Updated Final Safety Analysis Report Amendment 31 ML23284A4252023-10-11011 October 2023 10 CFR 50.59 and 10 CFR 72.48 Changes, Tests, and Experiments Summary Report; Commitment Summary Report; and Update to the Fire Protection Report ML23283A2792023-10-10010 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Requirements Manual ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23277A0462023-10-0404 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Specification Bases ML23275A0272023-09-29029 September 2023 Submittal of Discharge Monitoring Report (DMR) Quality Assurance Study 43 Final Report 2023 ML23271A1662023-09-28028 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision IR 05000327/20234032023-09-14014 September 2023 Cyber Security Inspection Report 05000327/2023403 and 05000328/2023403 (Cover Letter) ML23257A0062023-09-14014 September 2023 Enforcement Action EA-22-129 Inspection Postponement Request ML23254A2192023-09-11011 September 2023 Emergency Plan Implementing Procedure Revisions ML23254A0652023-09-0707 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000327/20230052023-08-29029 August 2023 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2023005 and 05000328/2023005 ML23233A0122023-08-17017 August 2023 Unit 1 Cycle 25 Refueling Outage - 90-Day Inservice Inspection Summary Report - Supplement ML23233A0142023-08-15015 August 2023 Discharge Monitoring Report (Dmr), July 2023 ML23215A1212023-08-0303 August 2023 301 Exam Administrative Items (2B) Normal Release ML23215A1572023-08-0303 August 2023 Enforcement Action EA-22-129 Inspection Readiness Notification CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-01-04
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 21,2013 Mr. Joe W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority P.O. Box 2000 Soddy-Daisy, TN 37384
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MF0481 AND MF0482)
Dear Mr. Shea:
By letter dated January 7,2013, Tennessee Valley Authority submitted an application pursuant to Title 10 of the Code of Federal Regulations (CFR) Part 54, to renew the operating license DPR-77 and DPR-79 for Sequoyah Nuclear Plant, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC) staff. The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
These requests for additional information were discussed with Henry Lee, and a mutually agreeable date for the response is within 60 days from the date of this letter. If you have any questions, please contact me at 301-415-1427 or e-mail Richard.Plasse@nrc.gov.
Sincerely, Richard A. Pia se, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328
Enclosure:
Requests for Additional Information cc w/encl: Listserv
May21,2013 Mr. Joe W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority P.O. Box 2000 Soddy-Daisy, TN 37384
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MF0481 AND MF0482)
Dear Mr. Shea:
By letter dated January 7, 2013, Tennessee Valley Authority submitted an application pursuant to Title 10 of the Code of Federal Regulations (CFR) Part 54, to renew the operating license DPR-77 and DPR-79 for Sequoyah Nuclear Plant, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC) staff. The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
These requests for additional information were discussed with Henry Lee, and a mutually agreeable date for the response is within 60 days from the date of this letter. If you have any questions, please contact me at 301-415-1427 ore-mail Richard.Plasse@nrc.gov.
Sincerely, IRA!
Richard A. Plasse, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328
Enclosure:
Requests for Additional Information cc w/encl: Listserv DISTRIBUTION: See following pages ADAMS Accession No.:ML13142A332 OFFICE LA:DLR PM:RPB1 :DLR BC:RPB1:DLR PM: RPB1:DLR NAME YEdmonds MYoo Y Diaz-Sanabria R Plasse DATE 5/16/2013 5/17/2013 5/21/2013 5/21/2013 OFFICIAL RECORD COpy
SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION LRA Section B.1.4 - Buried and Underground Piping and Tanks RAI B.1.4-1
Background:
LRA Section B.1.4 states that the Buried and Underground Piping and Tanks Program will be consistent with the program described in NUREG-1801,Section XI. M41. However, LRA Section 2.1.3, "Interim Staff Guidance Discussion," states, in relation to LR-ISG-2011-03, "Changes to the Generic Aging Lessons Learned (GALL) Report Revision 2 Aging Management Program (AMP) XI.M41 , 'Buried and Underground Piping and Tanks'," that, "[t]he revised guidance has been considered in the integrated plant assessment and is reflected in the aging management results presented in Section 3 and the aging management program description presented in Appendix B, Section B.1.4."
LR-ISG-2011-03 was issued on August 2, 2012. It represents the current staff position on the aging management of buried and underground piping and tanks.
Issue:
It is not clear to the staff with which AMP the applicant will be consistent-- LR-ISG-2011-03, as stated in LRA Section 2.1.3, or GALL Report AMP XI.M41.
Request:
State with which program you will be consistent. Revise the LRA to reflect any changes that may be needed.
RAI B.1.4-2
Background:
LRA Table 3.3.2-1, "Fuel Oil System," states that steel tanks exposed to concrete (embedded in concrete) have no aging effects requiring management and no recommended AMP. LRA Table 3.3.2-1 cites Item 3.3.1-112.
LR-ISG-2011-03 defines "buried" as tanks in direct contact with soil or concrete and includes these tanks within the scope of the Buried and Underground Piping and Tanks AMP. SRP-LR Table 3.4-1, Item 3.4.1-47 states that steel tanks exposed to concrete or soil should be managed for loss of material by GALL Report AMP XI. M41, "Buried and Underground Piping and Tanks."
Enclosure
Issue:
It is the staff's intent that to be consistent with LR-ISG-2011-03, tanks buried in concrete are managed by LR-ISG-2011-03, and Item 3.4.1-47 is cited instead of 3.3.1-112. The ambiguity between the two items occurred because during the development of GALL Report Revision 2, Item 3.3.1-112 was not changed to be consistent with the newly developed AMP XI.M41.
Request:
State the basis for why reasonable assurance can be established that the buried (encased in concrete) fuel oil storqge tanks will be appropriately age managed to meet their intended function consistent with the current licensing basis if no AMP is used to manage potential aging effects, or include these tanks within the scope of the Buried and Underground Piping and Tanks Program.
RAI8.1.4-3
Background:
During the audit, the staff noted the following with regard to the "preventive actions" program element of the Buried and Underground Piping and Tanks AMP:
a) Section 4.7.5, Category I Backfill of procedure G9, "Earth and Rock Foundations and Fi"s During Construction, Modification and Maintenance for Nuclear Plants," states that, "[u]nless otherwise specified by engineering documents, earthfill, fine granular fill, coarse granular fill, and rockfill may be used as Category I fill, and the particular type suited for the conditions shall be specified in engineering documents." Earthfill is, in part, defined as possibly containing organic material. Rockfi" has no size limit except for the longest dimension must be less than three times the thickness.
b) Problem Evaluation Report (PER) 63662 stated that the granular backfill for the refill of a fire protection piping excavation did not meet specifications for the number 16 and 30 sieve requirements. The initiator requested that the engineering organization accept the backfill as-is.
c) PER 525994 stated that coating damage occurred to buried radioactive waste piping due to fretting from a copper grounding wire.
d) PER 22693 stated that damage occurred to buried nonsafety-related essential raw water cooling piping that is used to fill the safety-related fire pump forebay during a flooding event.
During the audit, the applicant stated that this piping is in scope because the pumps are used to fill the steam generators and reactor coolant system during a flood event. The PER further stated that the damage occurred because the piping is not coated.
LR-ISG-2011-03 recommends that backfill in the vicinity of buried steel pipe meet ASTM 0448-08, size 67. In addition, it is recommended that coatings meet Table 1, "Generic External Coating Systems with Material Requirements and Recommended Practices for Application" of NACE SP0169-2007, "Control of External Corrosion on Underground or Submerged Metallic Piping Systems," or use of other coatings is justified in the License Renewal Application.
Enclosure
Issue:
a) It is not clear to the staff that earthfill (due to the potential presence of organic materials) and rockfill (due to its size) are consistent with the backfill recommendations of LR-ISG-2011-03, or whether either of these types of backfill was or could be used in the vicinity of in-scope components.
b) It is not clear to the staff how the backfill described in PER 63662 compares to that recommended in LR-ISG-2011-03 and whether the backfill was subsequently used as backfill in the vicinity of in-scope piping.
c) The piping described in PER 525994 is not in scope; however, it is not clear whether the procedure controls for backfill in the vicinity of this piping are the same as for those of in-scope piping, and if this is the case, whether the condition was an isolated event.
d) It is not clear to the staff how much in-scope buried piping is not coated or how the program, when implemented, will account for non-coated buried piping.
Request:
- 1. State if earthfill or rockfill has been or will be used as backfill in the vicinity of buried in-scope components. If this backfill had or will be used, state the basis for why reasonable assurance can be established that the buried in-scope components will meet their intended function consistent with the current licensing basis.
- 2. If the nonconforming backfill described in PER 63662 was used in the vicinity of buried in-scope piping, state how it compares to the recommendations for backfill quality in LR-ISG-2011-03. If the nonconforming backfill is not consistent with the backfill quality recommendations in LR-ISG-2011-03, state the basis for why reasonable assurance can be established that the buried in-scope components will meet their intended function consistent with the current licensing basis.
- 3. State if the procedure controls for backfilling buried in-scope piping components are or were similar to those for the piping described in PER 525994. If they are or were, state the basis for why reasonable assurance can be established that the buried in-scope components will meet their intended function consistent with the current licensing basis.
- 4. State the plant system, material type, and quantity of in-scope buried piping that is not coated. State what adjustments will be made to the Buried and Underground Piping and Tanks Program to account for uncoated, buried in-scope piping.
Enclosure
RAI B.1.44
Background:
LRA Section 8.1.4 states, "[i]f cathodic protection is not provided prior to the period of extended operation, the program will include documented justification that cathodic protection is not warranted."
LR-ISG-2011-03 states that the justification for not having cathodic protection must be provided in the LRA.
Issue:
During the audit, the staff reviewed a Corrpro Report titled, "TVA - Sequoyah Nuclear Plant Buried Piping Integrity Program Corrosion Assessment Report." This report cited several examples demonstrating that the soil at Sequoyah is corrosive and recommended installation of cathodic protection in some locations with in-scope piping. Based on input received during audit breakout sessions, it was noted that a new study was recently completed by a different vendor.
The new study was not available for review by the staff during the audit.
Request:
- 1. If cathodic protection will not be installed, provide an analysis for not providing cathodic protection 10 years prior to commencing the period of extended operation consistent with the recommended detail in LR-ISG-2011-03 Section 2.a.iii.
- 2. If cathodic protection will not be installed, state the results of a 1O-year search of plant-specific operating experience related to in-scope and out-of-scope buried piping consistent with the recommended detail in LR-ISG-2011-03 Section 2.a.iv.
- 3. Based on the results of (a) and (b) above, state what adjustments to the program will be implemented if cathodic protection is not installed and the study results demonstrate adverse results. If no adjustments will be made, state the basis for why reasonable assurance can be established that the buried in-scope components will meet their intended function consistent with the current licensing basis.
Enclosure
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MF0481 AND MF0482)
DISTRIBUTION:
HARDCOPY:
DLRRF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDIrRerb Resource RidsNrrDIrRarb Resource RidsNrrDlrRasb Resource beth.mizuno@nrc.gov <OGC>
brian.harris@nrc.gov <OGC>
john. pelchat@nrc.gov <gov't liaison officer>
gena. woodruff@nrc.gov <gov't liaison officer>
siva.lingam@nrc.gov <dorl PM>
wesley.deschaine@nrc.gov <res insp>
galen.smith@nrc.gov <res insp>
scott.shaeffer@nrc.gov (RII) jeffrey. hamman@nrc.gov (RII) craig.kontz@nrc.gov (RII) caudle.julian@nrc.gov (RII) generette.lloyd@epa.gov (RIV gmadkins@tva.gov clwilson@tva.gov hleeO@tva.gov dllundy@tva.gov Enclosure