ML14094A294
Letter Sequence Approval | |
---|---|
Initiation
Administration Questions
Answers
Results Other: CNL-15-095, Revision to the Reactor Pressure Vessel Surveillance Capsule Withdrawal Schedule for License Renewal, CNL-15-164, Second Annual Update, License Renewal Application, CNL-15-178, License Renewal Application - Clarifications (TAC Nos. MF0481 and MF0482), ML13032A251, ML13057A873, ML13067A201, ML13141A320, ML15236A067 | |
MONTHYEARML13024A0042013-01-0707 January 2013
[Table View]Transmittal of License Renewal Application Project stage: Request ML13032A2512013-01-10010 January 2013 Reactor Pressure Vessel Surveillance Capsule Withdrawal Schedule Revision Due to License Renewal Amendment Project stage: Other ML13057A8732013-03-0808 March 2013 Plan for the Scoping and Screening Regulatory Audit Regarding the Sequoyah Nuclear Plant, Unit 1 and 2, LRA Review Project stage: Other ML13067A2012013-03-11011 March 2013 Plan for the Aging Management Program Regulatory Audit Regarding the Sequoyah Nuclear Plant, Units 1 and 2 License Renewal Application Review (TAC Nos. MF0481 and MF0482) Project stage: Other ML13109A5152013-04-26026 April 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) Project stage: RAI ML13122A3402013-05-0808 May 2013 RAI for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) Project stage: RAI ML13119A0972013-05-21021 May 2013 Summary of Telephone Conference Call Held on April 22, 2013 Between the U.S. Nuclear Regulatory Commission and Tva,Concerning Requests for Additional Information Pertaining to the Sequoyah Nuclear Plant, License Renewal Application Project stage: RAI ML13142A3322013-05-21021 May 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) Project stage: RAI ML13128A5192013-05-31031 May 2013 Request for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application Project stage: RAI ML13134A2012013-06-0505 June 2013 RAI for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, LRA Project stage: RAI ML13163A4422013-06-0707 June 2013 Response to NRC Request for Additional Information Regarding the Scoping and Screening Methodology Review of the License Renewal Application, Set 3 Project stage: Response to RAI ML13144A7122013-06-11011 June 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (Tac Nos. MF0481 and MF0482)- Set 6 Project stage: RAI ML13134A3712013-06-13013 June 2013 5/9/2013 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Tennessee Valley Authority, Concerning Requests for Additional Information Pertaining to the Sequoyah Nuclear Plant, Units 1 and 2, License Ren Project stage: RAI ML13141A3202013-06-13013 June 2013 Letter Aging Management Programs Audit Report Regarding the Sequoyah Nuclear Plant, Units 1 and 2 Project stage: Other ML13150A4122013-06-24024 June 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) - Set 8 Project stage: RAI ML13178A2832013-06-25025 June 2013 Response to NRC Request for Additional Information Regarding the Reactor Vessel Internals Review of the License Renewal Application, Set 1 Project stage: Response to RAI ML13158A0162013-06-25025 June 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) Set 9 Project stage: RAI ML13190A2762013-07-0101 July 2013 Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, Set 4 Project stage: Response to RAI ML13192A3302013-07-0303 July 2013 Response to NRC Request for Additional Information Regarding the Review of License Renewal Application, Set 5 (TAC Nos. MF0481 and MF0482) Project stage: Response to RAI ML13204A3992013-07-11011 July 2013 Response to NRC Request for Additional Information Re Reactor Vessel Internals Review of the License Renewal Application, Set 6 Project stage: Response to RAI ML13213A0262013-07-25025 July 2013 Response to NRC Request for Additional Information Regarding the Review of License Renewal Application, Set 4/Buried Piping, Set 8, and Set 9 (TAC MF0481 and MF0482) Project stage: Response to RAI ML13213A0272013-07-29029 July 2013 Response to NRC Request for Additional Information Regarding the Review of License Renewal Application, Set 7 (TAC Nos. MF0481 and MF0482) Project stage: Response to RAI ML13213A0142013-07-30030 July 2013 Revised Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, Sets 1 and 3 (TAC MF0481 and MF0482) Project stage: Response to RAI ML13171A0362013-08-0101 August 2013 Summary of Telephone Conference Call Held on June 13, 2013, Between the NRC and Tennessee Valley Authority, Concerning RAI Pertaining to the Sequoyah Nuclear Plant, Units 1 and 2, LRA Project stage: RAI ML13204A2572013-08-0202 August 2013 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application (TAC Nos. MF0481 and MF0482) - Set 10 Project stage: RAI ML13225A3872013-08-0909 August 2013 Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units I and 2, License Renewal Application, Sets 1, 6, 7, and Revised Responses for 1.4-2, 1.4-3 and 1.4-4 (TAC Nos. MF0481 and MF0482) Project stage: Response to RAI ML13224A1262013-08-22022 August 2013 RAI for Review of Sequoyah, Units 1 & 2 License Renewal Application - Set 11 Project stage: RAI ML13238A2442013-08-30030 August 2013 RAI Set 12 Project stage: RAI ML13252A0362013-09-0303 September 2013 Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, Set 10 (30-day), B.1.9-1, B.1.4-4 Revised RAI Responses and Revision to LRA Page 2.4-44 (TAC Nos. MF0481 and MF0482) Project stage: Response to RAI ML13226A3712013-09-10010 September 2013 Summary of Telephone Conference Call Held on August 1, 2013, Between the U.S. Nuclear Regulatory Commission and Tennessee Valley Authority, Concerning Requests for Additional Information Pertaining to the Sequoyah Nuclear Plant, Units 1 Project stage: RAI ML13267A1592013-09-20020 September 2013 Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application, Set 11 (30-day), and Revised RAI Responses for B.1.14-1a, 2.5. Project stage: Response to RAI ML13247A4272013-09-23023 September 2013 Summary of Telephone Conference Call Held on August 19, 2013, Between the NRC and Tennessee Valley Authority, Concerning RAI Pertaining to the Sequoyah Nuclear Plant, Units 1 and 2, LRA Project stage: RAI ML13263A3382013-09-26026 September 2013 RAI Set 14 Project stage: RAI ML13268A4922013-09-27027 September 2013 RAI Set 15 Project stage: RAI ML13276A0182013-09-30030 September 2013 Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, Sets 10 (B.1.23-2a), 11 (4.1-8a), and 12 (30-day) Project stage: Response to RAI CNL-13-103, Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application, Sets 8 (B.1.33-1), 10 (3.0.3-1 Request 1), 12 (B.1.23-2b), 13 (30-day), 14 (B.0.4-1a)2013-10-17017 October 2013 Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application, Sets 8 (B.1.33-1), 10 (3.0.3-1 Request 1), 12 (B.1.23-2b), 13 (30-day), 14 (B.0.4-1a) Project stage: Response to RAI ML13282A3302013-10-18018 October 2013 RAI Set 16 Project stage: RAI CNL-13-104, Response to NRC Request for Additional Information Regarding the Review of License Renewal Application, Sets 11 (B.1.40-4a, B.1.25.1a), 13 (B.1.41-4a),14 (3.5.1-57, 3.5.1-87)2013-10-21021 October 2013 Response to NRC Request for Additional Information Regarding the Review of License Renewal Application, Sets 11 (B.1.40-4a, B.1.25.1a), 13 (B.1.41-4a),14 (3.5.1-57, 3.5.1-87) Project stage: Response to RAI CNL-13-105, Response to NRC Request for Additional Information Regarding Review of the License Renewal Application, Sets 10 (3.0.3-1, Requests 3, 4, 6), 12 (B.1.6-1b, B.1.6-2b), 16 (4.3.1-8a)2013-11-0404 November 2013 Response to NRC Request for Additional Information Regarding Review of the License Renewal Application, Sets 10 (3.0.3-1, Requests 3, 4, 6), 12 (B.1.6-1b, B.1.6-2b), 16 (4.3.1-8a) Project stage: Response to RAI CNL-13-106, Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units I and 2, License Renewal Application, Sets 13 (B.1.34-5a), 15 (4.2-1a), 16 (B.1.23-2c), 17 (B.1.23-2d), LRA Sections A.1.34 and B2013-11-15015 November 2013 Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units I and 2, License Renewal Application, Sets 13 (B.1.34-5a), 15 (4.2-1a), 16 (B.1.23-2c), 17 (B.1.23-2d), LRA Sections A.1.34 and B.1 Project stage: Response to RAI ML13323A0972013-12-0606 December 2013 RAI Set 18 Project stage: RAI CNL-13-130, Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, B.1.41-4b, 3.0.3-1 (Requests La, 3a, 4a, 6a), B.1.23-2e, 3.4.2.1.1-2a, Tables (3.4.1, 3.4.2-3-5, 3.3.1..2013-12-16016 December 2013 Response to NRC Request for Additional Information Regarding the Review of the License Renewal Application, B.1.41-4b, 3.0.3-1 (Requests La, 3a, 4a, 6a), B.1.23-2e, 3.4.2.1.1-2a, Tables (3.4.1, 3.4.2-3-5, 3.3.1.. Project stage: Response to RAI ML13353A5382013-12-23023 December 2013 RAI Set 19 Project stage: RAI ML13338A3332014-01-0808 January 2014 Summary of Telephone Conference Call Held on August 22, 2013, Between the U.S. Nuclear Regulatory Commission and Tennessee Valley Authority, Concerning Requests for Additional Information Pertaining to the Sequoyah Nuclear Plant, Units 1 an Project stage: RAI CNL-14-021, Response to Request for Clarification to NRC Request for Additional Information Re Review of License Renewal Application, LRA B.1.31, B.1.25.1b, B.1.34-8a, B.1.34-9A, LRA Annual Update (TAC MF0481 & MF0482)2014-03-0303 March 2014 Response to Request for Clarification to NRC Request for Additional Information Re Review of License Renewal Application, LRA B.1.31, B.1.25.1b, B.1.34-8a, B.1.34-9A, LRA Annual Update (TAC MF0481 & MF0482) Project stage: Supplement ML14059A3472014-03-0404 March 2014 Schedule Revision for the Review of the Sequoyah Nuclear Plant License Renewal Application (TAC Nos. MF0481 and MF0482) Project stage: Approval ML14063A5422014-03-0404 March 2014 TVA Response to Request for Clarification to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application, LRA B.1.31, B.1.25.1 B, B.1.34-Sa, B.1.34-9a, LRA Annual ... Project stage: Supplement ML14064A4732014-03-12012 March 2014 Request for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, LRA - Set 20 Project stage: RAI ML14094A2942014-04-11011 April 2014 Project Manager Change for the Safety Review of the Sequoyah Nuclear Plant, Units 1 & 2, License Renewal Application (TAC Nos. MF0481 & MF0482) Project stage: Approval CNL-14-052, TVA Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application: RAIs B.1.13-4 and 3.0.3-1-3c, Commitment 9.G, and 2013 LRA Annual Update (TAC Nos. MF042014-04-22022 April 2014 TVA Response to NRC Request for Additional Information Regarding the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application: RAIs B.1.13-4 and 3.0.3-1-3c, Commitment 9.G, and 2013 LRA Annual Update (TAC Nos. MF0481 Project stage: Response to RAI 2013-07-01 |
ML14094A294 | |
Person / Time | |
---|---|
Site: | Sequoyah |
Issue date: | 04/11/2014 |
From: | Yoira Diaz-Sanabria License Renewal Projects Branch 1 |
To: | James Shea Tennessee Valley Authority |
Sayoc E, 415-4084 | |
References | |
TAC MF0481, TAC MF0482 | |
Download: ML14094A294 (3) | |
Similar Documents at Sequoyah | |
---|---|
Category:Letter
MONTHYEARML24304A8492024-10-31031 October 2024
[Table view]December 2024 Requalification Inspection Notification Letter IR 05000327/20250102024-10-29029 October 2024 Notification of Sequoyah, Units 1 and 2 - Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000327/2025010 and 05000328/2025010 ML24298A1172024-10-24024 October 2024 Cycle 26, 180-Day Steam Generator Tube Inspection Report CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000327/LER-2024-001, Reactor Trip Due to a Turbine Trip2024-10-17017 October 2024 Reactor Trip Due to a Turbine Trip ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 05000328/LER-2024-001, Reactor Trip Due to an Electrical Trouble Turbine Trip2024-09-25025 September 2024 Reactor Trip Due to an Electrical Trouble Turbine Trip CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24267A0402024-09-19019 September 2024 Cycle 27 Core Operating Limits Report Revision 0 CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24185A1742024-09-18018 September 2024 Cover Letter - Issuance of Exemption Related to Non-Destructive Examination Compliance Regarding Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation ML24253A0152024-09-0808 September 2024 Emergency Plan Implementing Procedure Revisions ML24247A2212024-08-29029 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-21-160, NEI 03-08 Needed Guidance: PWR Lower Radial Support Clevis Insert X-750 Bolt Inspection Requirements, September 1, 2021 ML24247A1802024-08-28028 August 2024 Application to Revise the Fuel Handling Accident Analysis, to Delete Technical Specification 3.9.4, Containment Penetrations, and to Modify Technical Specification 3.3.6, Containment Ventilation Isolation Instrumentation for Sequoyah Nuclea IR 05000327/20240052024-08-26026 August 2024 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2024005 and 05000328/2024005 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), IR 05000327/20240022024-07-31031 July 2024 Integrated Inspection Report 05000327/2024002 and 05000328/2024002 ML24211A0572024-07-29029 July 2024 Submittal of Emergency Plan Implementing Procedure Revision ML24211A0542024-07-29029 July 2024 Operator License Examination Report ML24211A0412024-07-26026 July 2024 Unit 1 Cycle 26 Refueling Outage - 90-Day Inservice Inspection Summary Report ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24191A4652024-07-0909 July 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24177A0282024-06-25025 June 2024 Emergency Plan Implementing Procedure Revisions ML24176A0222024-06-24024 June 2024 Retraction of Interim Report of a Deviation or Failure to Comply – Transducer Model 8005N ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24145A0852024-05-30030 May 2024 1B-B Diesel Generator Failure - Final Significance Determination Letter ML24145A1052024-05-29029 May 2024 301 Exam Approval Letter ML24134A1762024-05-13013 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24128A0352024-05-0707 May 2024 Providing Supplemental Information to Apparent Violation ML24120A0582024-04-26026 April 2024 10 CFR 50.46 Annual Report for Sequoyah Nuclear Plant Units 1 and 2 ML24116A2612024-04-25025 April 2024 Interim Report of a Deviation or Failure to Comply - Transducer Model 8005N ML24114A0482024-04-23023 April 2024 Annual Radioactive Effluent Release Report for 2023 Monitoring Period CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24144A2362024-04-20020 April 2024 Discharge Monitoring Report (Dmr), March 2024 ML24144A2322024-04-20020 April 2024 Tennessee Multi-Sector Permit (Tmsp), 2024 Annual Discharge Monitoring Report for Outfalls SW-3, SW-3, and SW-9 ML24089A0882024-04-18018 April 2024 – Exemption from Select Requirements of 10 CFR Part 73; Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24102A1212024-04-18018 April 2024 Summary of Conference Call with Tennessee Valley Authority Regarding Sequoyah Nuclear Plant, Unit 1 Spring 2024 Steam Generator Tube Inspections CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000327/20240012024-04-17017 April 2024 Integrated Inspection Report 05000327/2024001 and 05000328/2024001 ML24109A0272024-04-16016 April 2024 Cycle 27 Core Operating Limits Report Revision 0 CNL-23-006, Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03)2024-04-15015 April 2024 Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03) ML24106A0502024-04-12012 April 2024 Discharge Monitoring Report (Dmr), February 2024 2024-09-08 |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April11, 2014 Mr. Joe W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority P. 0. Box 2000 Soddy-Daisy, TN 37384
SUBJECT:
PROJECT MANAGER CHANGE FOR THE SAFETY REVIEW OF THE SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MF0481 AND MF0482)
Dear Mr. Shea.
By letter dated January 7, 2013, Tennessee Valley Authority submitted an application pursuant to Title 10 of the Code of Federal Regulations (CFR) Part 54, to renew the operating license DPR-77 and DPR-79 for Sequoyah Nuclear Plant, Units 1 and 2 (SQN), for review by the U.S. Nuclear Regulatory Commission staff. This letter is to inform you of a change to the Safety Project Manager assigned to the SQN license renewal review. Effective April 14, 2013, Mr. Emmanuel Sayee will be the Safety Project Manager for SQN. All correspondence for the Project Manager associated with the safety review for SQN license renewal should be sent to:
Mr. Emmanuel Sayee, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-11 F1 Washington, DC 20555 Emmanuel Sayee can be reached at 301-415-4084 or by e-mail at emmanuel.sayoc@nrc.gov.
S1 c~rely, . ~~
1ra D~anaona, P ejects Branch 1 Chief ivision of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328 cc: Listserv
- .. ML14094A294 *concurred via email OFFICE LA:RPB2:DLR PM:RPB1:DLR BC:RPB1:DLR NAME IKino E Savoc Y Diaz-Sanabria DATE 4/8/2014 4/11/2014 4/11/2014
Letter to J. Shea from Y. Oiaz dated April 11, 2014
SUBJECT:
PROJECT MANAGER CHANGE FOR THE SAFETY REVIEW OF THE SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAG NOS. MF0481 AND MF0482)
DISTRIBUTION:
HARD COPY:
DLR RF RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRerb Resource RidsNrrDirRarb Resource RidsNrrDirRasb Resource beth.mizuno@nrc.gov brian. harris@nrc.gov john.pelchat@nrc.gov gena.woodruff@nrc.gov siva.lingam@nrc.gov wesley.deschaine@nrc.gov galen.smith@nrc.gov scott.shaeffer@nrc. gov jeffrey.hamman@nrc.gov craig.kontz@nrc.gov caudle.julian@nrc.gov generette.lloyd@epa.gov gmadkins@tva.gov clwilson@tva.gov hleeO@tva.gov dllundy@tva gov