ML13135A573

From kanterella
Jump to navigation Jump to search
IR 05000416-13-002; 01/01/2013-04/06/2013; Grand Gulf Nuclear Station, Unit 1, Integrated Resident and Regional Report; Flood Protection Measures, Maintenance Risk Assessments and Emergent Work Control, Operability..
ML13135A573
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 05/15/2013
From: David Proulx
NRC/RGN-IV/DRP/RPB-C
To: Kevin Mulligan
Entergy Operations
Proulx D
References
IR-13-002
Download: ML13135A573 (86)


See also: IR 05000416/2013002

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I V

1600 EAST LAMAR BLVD

ARLINGTON, TEXAS 76011-4511

May 15, 2013

Kevin Mulligan

Vice President Operations

Entergy Operations, Inc.

Grand Gulf Nuclear Station

P.O. Box 756

Port Gibson, MS 39150

SUBJECT: GRAND GULF NUCLEAR STATION - NRC INTEGRATED INSPECTION

REPORT 05000416/2013002

Dear Mr. Mulligan:

On April 6, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

your Grand Gulf Nuclear Station, Unit 1. The enclosed inspection report documents the

inspection results, which were discussed on April 11, 2013, with you and other members of your

staff.

The inspections examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

Five NRC-identified and three self-revealing findings of very low safety significance (Green)

were identified during this inspection. Six of these findings were determined to involve

violations of NRC requirements.

If you contest these non-cited violations, you should provide a response within 30 days of the

date of this inspection report, with the basis for your denial, to the Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the

Regional Administrator, Region IV; the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at

Grand Gulf Nuclear Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the Regional Administrator, Region IV; and the NRC Resident Inspector at

Grand Gulf Nuclear Station.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is

K. Mulligan -2-

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

David L. Proulx, Acting Chief

Project Branch C

Division of Reactor Projects

Docket No.: 50-416

License No.: NPF-29

Enclosure: Inspection Report 05000416/2013002

w/ Attachment: Supplemental Information

cc w/ encl: Electronic Distribution for Grand Gulf Nuclear Station

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 05000416

License: NPF-29

Report: 05000416/2013002

Licensee: Entergy Operations, Inc.

Facility: Grand Gulf Nuclear Station, Unit 1

Location: 7003 Baldhill Road

Port Gibson, MS 39150

Dates: January 1 through April 6, 2013

Inspectors: R. Smith, Senior Resident Inspector

B. Rice, Resident Inspector

S. Achen, Reactor Inspector

J. Braisted, Reactor Inspector

S. Hedger, Operations Engineer

J. Laughlin, Emergency Preparedness Inspector, NSIR

S. Makor, Reactor Inspector

Approved David L. Proulx, Acting Branch Chief

By: Reactor Projects Branch C

Division of Reactor Projects

-1- Enclosure

SUMMARY OF FINDINGS

IR 05000416/2013002; 01/01/2013 - 04/06/2013; Grand Gulf Nuclear Station, Unit 1, Integrated

Resident and Regional Report; Flood Protection Measures, Maintenance Risk Assessments and

Emergent Work Control, Operability Evaluations and Functionality Assessments, Surveillance

Testing, Followup of Events and Notices of Enforcement Discretion.

The report covered a 3-month period of inspection by resident inspectors and announced

baseline inspections by region-based inspectors. Six Green non-cited violations and two Green

findings of significance were identified. The significance of most findings is indicated by their

color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, Significance

Determination Process. The cross-cutting aspect is determined using Inspection Manual

Chapter 0310, Components Within the Cross-Cutting Areas. Findings for which the

significance determination process does not apply may be Green or be assigned a severity level

after NRC management review. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 4, dated December 2006.

A. NRC-Identified Findings and Self-Revealing Findings

Cornerstone: Initiating Events

  • Green. The inspectors reviewed a self-revealing finding for the failure to ensure

the current transformer structure, the neutral bus housing, and the associated

mounting hardware were installed with adequate clearance to accommodate

thermal expansion. This failure resulted in an automatic reactor scram on

December 29, 2012, and a subsequent scram on January 4, 2013. Following the

second scram on January 4, 2012, the licensee determined the cause of the

scram was a trip of the phase A unit differential relay because of a ground fault

on the A phase of the generator neutral current transformer, due to inadequate

clearances. Immediate corrective actions included removing the damaged

current transformer and modifying the neutral bus housing. The plant scrams

were entered into the corrective action program as Condition Reports CR-GGN-

2012-13290 and CR-GGN-2013-00083.

The failure to install micarta plate bolts in accordance with manufacturer

specifications and ensure that the current transformer structure, the neutral bus

housing, and the associated mounting hardware had adequate clearance is a

performance deficiency. This finding is more than minor because it is associated

with the Initiating Events Cornerstone attribute of human performance and

adversely affected the cornerstone objective to limit the likelihood of events that

upset plant stability and challenge critical safety functions during shutdown and

power operations. Using NRC Inspection Manual Chapter 0609, Attachment 4,

"Initial Characterization of Findings," the inspectors determined that the issue

affected the Initiating Events Cornerstone. In accordance with NRC Inspection

Manual Chapter 0609, Appendix A, The Significance Determination Process

(SDP) for Findings at Power, the inspectors determined that the issue has very

low safety significance (Green) because it caused only a reactor trip and did not

-2-

cause a loss of mitigating equipment relied upon to transition the plant from the

onset of the trip to a stable shutdown condition. The finding has a cross-cutting

aspect in the human performance area associated with the resources component

because the licensee failed to provide adequate work instructions H.2(c)

(Section 4OA3).

  • Green. The inspectors reviewed a self-revealing non-cited violation of 10 CFR

50 Appendix B Criterion V, for the failure to provide adequate instructions to

remove foreign material from the exhaust port of relief valve 1B21F047A. As a

result, the valve failed to close at its reset setpoint following a reactor scram on

December 29, 2012. The valve failed to close at its reset setpoint of 1013 psig

and remained open until pressure fell to approximately 675 psig. The immediate

corrective actions were to remove the foreign material exclusion plug from the

exhaust port of valve 1B21-F047A and to ensure no plug was installed in any

other safety relief valve. The licensee entered this issue into the corrective action

program as Condition Report CR-GGN-2013-00100.

The failure to provide adequate instructions to remove foreign material from the

exhaust port of relief valve 1B21F047A is a performance deficiency. This finding

is more than minor because it is associated with the Initiating Events

Cornerstone attribute of human performance and adversely affected the

cornerstone objective to limit the likelihood of events that upset plant stability and

challenge critical safety functions during shutdown as well as power operations.

Using NRC Inspection Manual Chapter 0609, Attachment 4, "Initial

Characterization of Findings," the inspectors determined that the issue affected

the Initiating Events Cornerstone. In accordance with NRC Inspection Manual

Chapter 0609, Appendix A, The Significance Determination Process (SDP) for

Findings at Power, the inspectors determined that the issue has very low safety

significance (Green) because after a reasonable assessment of the degradation,

the finding could not result in exceeding the reactor coolant leak rate for a small

loss of coolant accident because the configuration of the safety relief valve was

such that it would close at approximately 675 psig. Also the finding did not affect

other systems used to mitigate a loss of coolant accident resulting in a total loss

of their function. The finding has a cross-cutting aspect in the area of human

performance associated with the decision-making component because the

licensee did not use a systematic process to make a safety-significant decision.

H.1(a) (Section 4OA3).

  • Green. The inspectors reviewed a self-revealing finding for the failure to identify

a degraded isophase bus duct view port window, which allowed water to intrude

into the duct and caused an automatic reactor scram on January 14, 2013. The

licensee took corrective action to stop the water intrusion into the isophase bus

duct and to electrically isolate the spare transformer from the energized

transformers. The licensee entered this issue into the corrective action program

as Condition Report CR-GGN-2013-00319.

The failure to identify a degraded isophase bus duct view port window is a

performance deficiency. The finding is more than minor because it is associated

-3-

with the Initiating Events Cornerstone attribute of human performance and

adversely affected the associated cornerstone objective to limit the likelihood of

those events that upset plant stability and that challenge critical safety functions

during power operations. Using NRC Inspection Manual Chapter 0609,

Attachment 4, "Initial Characterization of Findings," the inspectors determined

that the issue affected the Initiating Events Cornerstone. In accordance with

NRC Inspection Manual Chapter 0609, Appendix A, The Significance

Determination Process (SDP) for Findings at Power, the inspectors determined

that the issue has a very low safety significance (Green) because it caused only

a reactor trip and did not cause a loss of mitigating equipment relied on to

transition the plant from the onset of a trip to a stable shutdown condition. The

finding has a cross-cutting aspect in the area of human performance associated

with the decision-making component because the licensee did not use

conservative assumptions in decision-making H.1(b) (Section 4OA3).

5.4.1.a, for the failure to revise the scram procedure after temporarily modifying

the division-2 circuits that sense first-stage turbine pressure. Specifically, after a

steam sensing line failed, the licensee had introduced a dummy signal into the

subject circuits to comply with technical specifications; however, they failed to

revise Procedure 05-1-02-I-1, Reactor Scram, Revision 117, to reflect this

temporary modification. This resulted in additional scrams during scram recovery

for the scrams on December 29, 2012, and January 4, 2013. Immediate

corrective actions included modifying the scram procedure to require the

operators to turn off the units that provide the dummy signal to the division-2

circuits that sense first-stage turbine pressure following a reactor scram, allowing

the operators to reset the full scram promptly. The licensee entered this issue

into the corrective action program as Condition Report CR-GGN-2013-001259.

The failure to revise Procedure 05-1-02-I-1 following a temporary modification to

the division-2 circuits that sense first-stage turbine pressure is a performance

deficiency. The finding is more than minor because it is associated with the

Initiating Events Cornerstone attribute of human performance and adversely

affected the cornerstone objective to limit the likelihood of events that upset plant

stability and challenge critical safety functions during shutdown as well as power

operations. Using NRC Inspection Manual Chapter 0609, Attachment 4, "Initial

Characterization of Findings," the inspectors determined that the issue affected

the Initiating Events Cornerstone. In accordance with NRC Inspection Manual

Chapter 0609, Appendix A, The Significance Determination Process (SDP) for

Findings at Power, the inspectors determined that the issue has very low safety

significance (Green) because it only caused a reactor trip and did not cause the

loss of mitigating equipment relied upon to transition the plant from the onset of

the trip to a stable shutdown condition. The finding has a cross-cutting aspect in

the area of human performance associated with the work practices component

because licensee personnel failed to ensure that procedures impacted by a

temporary modification were properly revised to compensate for the installed

modification H.4(b) (Section 4OA3).

-4-

Cornerstone: Mitigating Systems

  • Green. The inspectors identified a non-cited violation of License Condition

2.C(41), Fire Protection Program, involving the failure to ensure that manhole

MH01 was properly sealed to prevent entry of flammable liquid. Specifically, on

February 20, 2013, four manhole covers had between one to three loose bolts

and evidence of water seepage. These vaults contain safety related cables for

standby service water trains A and B. Immediate corrective actions included

cleaning and tapping the bolt holes to ensure proper thread engagement, adding

work instructions to the preventative maintenance procedure to clean the

manhole bolt holes, and verifying that the other manholes containing safety-

related cables did not have similar issues with loose bolts on the manhole

covers. The licensee entered this issue in their corrective action program as

Condition Report CR-GGN-2013-01348.

This finding is more than minor because it is associated with the Mitigating

Systems Cornerstone attribute of protection against external factors and

adversely affected the cornerstone objective to ensure the availability, reliability,

and capability of systems that respond to initiating events to prevent undesirable

consequences. Using NRC Inspection Manual Chapter 0609, Attachment 4,

Initial Characterization of Findings, the inspectors determined that the issue

affected the Mitigating Systems Cornerstone and required the use of Inspection

Manual Chapter 0609, Attachment 4, Appendix F, Fire Protection Significance

Determination Process. However, an NRC senior reactor analyst determined

that the unique nature of this performance deficiency did not lend itself to

analysis by the methods provided in Appendix F. Therefore, a Phase 3 analysis

was performed. Based on a bounding analysis, the analyst determined that the

change in core damage frequency was approximately 1.5E-7/yr. The result was

low because of the relatively short periods of time that fuel was actually being

transferred, the low probability of transfer system failures, and the low likelihood

that a loss of normal service water initiator would occur following a fire in the

subject manholes. The finding has a cross-cutting aspect in the human

performance area associated with the resources component because the

licensee did not provide adequate work packages H.2(c) (Section 1R06).

Criterion V, for the licensees failure to monitor for ice accumulation on the

standby service water cooling towers in accordance with station procedures. On

January 17, 2013, the plant experienced a winter storm but operators did not

implement Standby Service Water System Operating Instruction, 04-1-01-P41-1,

Revision 137, Section 6.2, Cold Weather Operation, which directed the licensee

to monitor the standby service water cooling tower for ice accumulation when

weather conditions existed that could have resulted in icing of the cooling tower

fill material and missile grating. The licensee entered this issue into their

corrective action program as Condition Report CR-GGNS-2013-00426.

-5-

The failure to monitor for ice accumulation in accordance with station procedures

is a performance deficiency. The finding is more than minor because if left

uncorrected, it could lead to a more significant safety concern. Specifically, the

occurrence of ice accumulation on the standby service water cooling towers, if

unmonitored, could cause damage to the fill material and/or the tower missile

gratings, which would render the standby service water system inoperable.

Using NRC Inspection Manual Chapter 0609, Attachment 4, "Initial

Characterization of Findings," the inspectors determined that the issue affected

the Mitigating Systems Cornerstone. In accordance with NRC Inspection Manual

Chapter 0609, Appendix A, The Significance Determination Process (SDP) for

Findings at Power, the inspectors determined that the issue had a very low

safety significance (Green) because it was not a deficiency affecting the design

or qualification of a mitigating system, structure or component, does not

represent a loss of system or function, does not represent a loss of function for

greater than its technical specification allow outage time, and does not represent

a loss of function as defined by the licensees Maintenance Rule program for

greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The finding has a cross-cutting aspect in the human

performance area associated with the work control component because the

licensee failed to appropriately plan work activities based on environmental

conditions that may impact plant structures, systems and components H.3(a)

(Section 1R13).

Criterion III, Design Control, for the failure of the licensee to maintain design

control, incorporate, verify, and check new instrument drift values, and translate

the design basis requirements for multiple allowable values and trip setpoints

described in the technical specifications into setpoint calculations. During the

review of condition reports associated with an operability review of the licensees

transition from an 18- to 24-month operating cycle in August 2012, inspectors

identified that the licensee failed to maintain design control of multiple setpoint

calculations. In response to NRC inspector questioning, a licensee review of the

calculations identified that three of the 14 calculations reviewed contained

calculated allowable values that differed from the values contained in the

Technical Specifications associated with Level 8 Narrow Range, Reactor Scram

on High SDVP Water Level, and HPCS & RCIC Pump Suction Transfer on High

Suppression Pool Level. An assessment of the calculations also determined that

one other calculation contained an error that was introduced during the

replacement of the high-pressure turbine rotor in a recent refueling outage, which

would require a license amendment request. The licensee entered this condition

in their corrective action program as CR-GGN-2013-00371.

The failure to maintain design control, incorporate, verify, and check new

instrument drift values, and translate the design basis requirements into multiple

allowable values and trip setpoints described in the technical specifications into

facility setpoint calculations is a performance deficiency. This finding is more

than minor because it is associated with the Mitigating Systems Cornerstone

attribute of design control and affected the cornerstone objective of ensuring the

-6-

capability of the safety-related system to respond to initiating events to prevent

undesirable consequences. In accordance with NRC Inspection Manual Chapter

0609, Attachment 4, "Initial Characterization of Findings," the issue was

determined to affect the Mitigating Systems Cornerstone. Using Inspection

Manual Chapter 0609, Appendix A, The Significance Determination Process

(SDP) for Findings at Power, the inspectors determined the finding was of very

low safety significance (Green) because it was a design deficiency confirmed not

to result in a loss of the offsite power supply operability or functionality. This

finding has a cross-cutting aspect in the area of human performance decision-

making because the licensee did not use a systematic decision making process

and did not obtain interdisciplinary input on a risk significant decision H.1(a)

(Section 1R15).

  • Green. The inspectors identified a non-cited violation of License Condition

2.C(41), Fire Protection Program, for the failure to identify and correct a

condition adverse to fire protection. Specifically, the licensee failed to ensure

that fire brigade members had sufficient access through a scaffold built in the

diesel generator building hallway into the division-1 diesel generator room. The

immediate corrective actions included removing the scaffold in the diesel

generator building hallway. The licensee documented this issue in their

corrective action program as Condition Report CR-GGN-2013-01679.

The failure to take prompt corrective action to ensure adequate access for fire

brigade members through installed scaffolding in the diesel generator building

hallway to the division-1 diesel generator room is a performance deficiency. The

finding is more than because if left uncorrected, it would have the potential to

lead to a more significant safety concern. Specifically, the inability for fire

brigade members to gain access to safety related equipment in timely manner

could result in preventing prompt extinguishing of fires. Using NRC Inspection

Manual Chapter 0609, Attachment 4, "Initial Characterization of Findings," the

inspectors determined that the issue affected the Mitigating Systems

Cornerstone. In accordance with NRC Inspection Manual Chapter 0609,

Appendix A, The Significance Determination Process (SDP) for Findings at

Power, the inspectors determined that the issue has very low safety significance

(Green) because the finding involved a risk-significant fire area that had an

automatic fire suppression system. The inspectors determined the apparent

cause of this finding was that the licensee did not implement the corrective action

program with a low threshold for identifying scaffolding that could impede fire

brigade member response during a fire. Therefore the finding had a cross-

cutting aspect in the problem identification and resolution area associated with

the corrective action program component because the licensee failed to identify

conditions adverse to fire protection P.1(a) (Section 1R22).

B. Licensee-Identified Violations

None

-7-

REPORT DETAILS

Summary of Plant Status

Grand Gulf Nuclear Station (GGNS) began the inspection period starting up from a reactor

scram on December 29, 2012. Subsequently:

  • On January 1, 2013, the licensees tied to the grid and proceeded with power accession.
  • On January 4, 2013, at 11:37 p.m., during power accession, the reactor scrammed from

94 percent rated thermal power due to a phase A unit differential signal resulting in a

main generator/turbine trip with a reactor scram. The licensee determined the apparent

cause of the scram and commenced startup activities on January 8, 2013, and reached

100 percent rated thermal power on January 11, 2013.

  • On January 14, 2013, at 6:05 p.m., the reactor scrammed from 100 percent rated

thermal power due to a turbine generator trip caused by a generator neutral time

overcurrent relay tripping. The licensee placed the plant in cold shutdown condition and

conducted an investigation of the event. The licensee determined the apparent cause of

the scram and commenced startup activities on January 27, 2013, and achieved 100

percent rated thermal power on February 6, 2013.

  • On April 5, 2013, the operators reduced power to 65 percent rated thermal power to

conduct rod pattern adjustment, control rod exercise, channel bow testing and turbine

testing. The operators returned the plant to 100 percent rated thermal power on April 6,

2013.

The plant remained at 100 percent rated thermal power for the remainder of the quarter.

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R01 Adverse Weather Protection (71111.01)

.1 Readiness for Seasonal Extreme Weather Conditions

a. Inspection Scope

The inspectors performed a review of the adverse weather procedures for seasonal

extremes (e.g., extreme high temperatures, extreme low temperatures, or hurricane

season preparations). The inspectors verified that weather-related equipment

deficiencies identified during the previous year were corrected prior to the onset of

seasonal extremes and evaluated the implementation of the adverse weather

preparation procedures and compensatory measures for the affected conditions before

the onset of, and during, the adverse weather conditions.

-8-

During the inspection, the inspectors focused on plant-specific design features and the

procedures used by plant personnel to mitigate or respond to adverse weather

conditions. Additionally, the inspectors reviewed the Updated Final Safety Analysis

Report and performance requirements for systems selected for inspection, and verified

that operator actions were appropriate as specified by plant-specific procedures.

Specific documents reviewed during this inspection are listed in the attachment. The

inspectors also reviewed corrective action program items to verify that plant personnel

were identifying adverse weather issues at an appropriate threshold and entering them

into their corrective action program in accordance with station corrective action

procedures. The inspectors reviews focused specifically on the following plant systems:

  • Fire water pump house
  • Division 1, 2, and 3 diesel generator building breezeway

houses

These activities constitute completion of one readiness for seasonal adverse weather

sample as defined in Inspection Procedure 71111.01-05.

b. Findings

No findings were identified.

.2 Readiness for Impending Adverse Weather Conditions

a. Inspection Scope

Since thunderstorms with potential tornados and high winds were forecast in the vicinity

of the facility for January 10, 2013, the inspectors reviewed the plant personnels overall

preparations/protection for the expected weather conditions. On January 9, 2013, the

inspectors walked down the standby service water basins, the safety related

transformers, and emergency diesel generators because their safety-related functions

could be affected, or required, as a result of high winds, tornado-generated missiles, or

the loss of offsite power. The inspectors evaluated the plant staffs preparations against

the sites procedures and determined that the staffs actions were adequate. During the

inspection, the inspectors focused on plant-specific design features and the licensees

procedures used to respond to specified adverse weather conditions. The inspectors

also toured the plant grounds to look for any loose debris that could become missiles

during a tornado. The inspectors evaluated operator staffing and accessibility of

controls and indications for those systems required to control the plant. Additionally, the

inspectors reviewed the Updated Final Safety Analysis Report and performance

requirements for the systems selected for inspection, and verified that operator actions

were appropriate as specified by plant-specific procedures. The inspectors also

reviewed a sample of corrective action program items to verify that the licensee-

identified adverse weather issues at an appropriate threshold and dispositioned them

-9-

through the corrective action program in accordance with station corrective action

procedures. Specific documents reviewed during this inspection are listed in the

attachment.

These activities constitute completion of one readiness for impending adverse weather

condition sample as defined in Inspection Procedure 71111.01-05.

b. Findings

No findings were identified.

1R04 Equipment Alignment (71111.04)

.1 Partial Walkdown

a. Inspection Scope

The inspectors performed partial system walkdowns of the following risk-significant

systems:

  • Standby gas treatment A with B standby gas treatment out of service for

maintenance

maintenance

The inspectors selected these systems based on their risk significance relative to the

reactor safety cornerstones at the time they were inspected. The inspectors attempted

to identify any discrepancies that could affect the function of the system, and, therefore,

potentially increase risk. The inspectors reviewed applicable operating procedures,

system diagrams, Updated Final Safety Analysis Report, technical specification

requirements, administrative technical specifications, outstanding work orders, condition

reports, and the impact of ongoing work activities on redundant trains of equipment in

order to identify conditions that could have rendered the systems incapable of

performing their intended functions. The inspectors also inspected accessible portions

of the systems to verify system components and support equipment were aligned

correctly and operable. The inspectors examined the material condition of the

components and observed operating parameters of equipment to verify that there were

no obvious deficiencies. The inspectors also verified that the licensee had properly

identified and resolved equipment alignment problems that could cause initiating events

or impact the capability of mitigating systems or barriers and entered them into the

corrective action program with the appropriate significance characterization. Specific

documents reviewed during this inspection are listed in the attachment.

- 10 -

These activities constitute completion of five partial system walkdown samples as

defined in Inspection Procedure 71111.04-05.

c. Findings

No findings were identified.

.2 Complete Walkdown

a. Inspection Scope

On April 2, 2013, the inspectors performed a complete system alignment inspection of

the low-pressure core spray system to verify the functional capability of the system. The

inspectors selected this system because it was considered both safety significant and

risk significant in the licensees probabilistic risk assessment. The inspectors inspected

the system to review mechanical and electrical equipment line ups, electrical power

availability, system pressure and temperature indications, as appropriate, component

labeling, component lubrication, component and equipment cooling, hangers and

supports, operability of support systems, and to ensure that ancillary equipment or

debris did not interfere with equipment operation. The inspectors reviewed a sample of

past and outstanding work orders to determine whether any deficiencies significantly

affected the system function. In addition, the inspectors reviewed the corrective action

program database to ensure that system equipment-alignment problems were being

identified and appropriately resolved. Specific documents reviewed during this

inspection are listed in the attachment.

These activities constitute completion of one complete system walkdown sample as

defined in Inspection Procedure71111.04-05.

b. Findings

No findings were identified.

1R05 Fire Protection (71111.05)

.1 Quarterly Fire Inspection Tours

a. Inspection Scope

The inspectors conducted fire protection walkdowns that were focused on availability,

accessibility, and the condition of firefighting equipment in the following risk-significant

plant areas:

  • Electrical penetration room 1A407, 166 foot elevation, auxiliary building
  • Equipment area 1A417, 166 foot elevation, auxiliary building
  • Equipment area 1A424, 1A428, 1A434, 166 foot elevation, auxiliary building

- 11 -

  • Equipment area 1A403 & 1A420, 166 foot elevation, auxiliary building
  • Electrical penetration room 1A410, 166 foot elevation, auxiliary building

The inspectors reviewed areas to assess if licensee personnel had implemented a fire

protection program that adequately controlled combustibles and ignition sources within

the plant; effectively maintained fire detection and suppression capability; maintained

passive fire protection features in good material condition; and had implemented

adequate compensatory measures for out of service, degraded or inoperable fire

protection equipment, systems, or features, in accordance with the licensees fire plan.

The inspectors selected fire areas based on their overall contribution to internal fire risk

as documented in the plants Individual Plant Examination of External Events with later

additional insights, their potential to affect equipment that could initiate or mitigate a

plant transient, or their impact on the plants ability to respond to a security event. Using

the documents listed in the attachment, the inspectors verified that fire hoses and

extinguishers were in their designated locations and available for immediate use; that

fire detectors and sprinklers were unobstructed; that transient material loading was

within the analyzed limits; and fire doors, dampers, and penetration seals appeared to

be in satisfactory condition. The inspectors also verified that minor issues identified

during the inspection were entered into the licensees corrective action program.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of five quarterly fire-protection inspection samples

as defined in Inspection Procedure 71111.05-05.

b. Findings

No findings were identified.

.2 Annual Fire Protection Drill Observation (71111.05A)

a. Inspection Scope

On February 12, 2013, the inspectors observed a fire brigade activation for a simulated

fire in a non-safety related motor control center on the 139 foot elevation of the auxiliary

building. The observation evaluated the readiness of the plant fire brigade to fight fires.

The inspectors verified that the licensee staff identified deficiencies, openly discussed

them in a self-critical manner at the drill debrief, and took appropriate corrective actions.

Specific attributes evaluated were (1) proper wearing of turnout gear and self-contained

breathing apparatus; (2) proper use and layout of fire hoses; (3) employment of

appropriate fire fighting techniques; (4) sufficient firefighting equipment brought to the

scene; (5) effectiveness of fire brigade leader communications, command, and control;

(6) search for victims and propagation of the fire into other plant areas; (7) smoke

removal operations; (8) utilization of preplanned strategies; (9) adherence to the

preplanned drill scenario; and (10) drill objectives.

These activities constitute completion of one annual fire-protection inspection sample as

defined in Inspection Procedure 71111.05-05.

- 12 -

b. Findings

No findings were identified.

1R06 Flood Protection Measures (71111.06)

a. Inspection Scope

The inspectors reviewed the Updated Final Safety Analysis Report, the flooding analysis,

and plant procedures to assess susceptibilities involving internal flooding; reviewed the

corrective action program to determine if licensee personnel identified and corrected

flooding problems; inspected underground bunkers/manholes to verify the adequacy of

sump pumps, level alarm circuits, cable splices subject to submergence, and drainage

for bunkers/manholes; and verified that operator actions for coping with flooding can

reasonably achieve the desired outcomes. The inspectors also inspected the

manholes/vaults listed below. Specific documents reviewed during this inspection are

listed in the attachment.

  • January/February 2013, manholes/vaults 1, 2, 3, 20, and 21

These activities constitute completion of one bunker/manhole samples as defined in

Inspection Procedure 71111.06-05.

b. Findings

Introduction. The inspectors identified a Green non-cited violation of License Condition

2.C(41), Fire Protection Program, involving the failure to properly seal manhole MH01

to prevent entry of flammable liquid.

Description. On February 20, 2013, during the manhole/vault inspection of manhole

MH01, the licensee inspected all four compartments associated with manhole MH01. At

the inspectors request, the licensee removed the three additional manhole covers that

are not normally removed for the monthly inspection. During the removal of the manhole

covers, the licensee and inspectors discovered that each manhole cover had between

one to three loose bolts. The inspectors noted evidence of water seepage past these

loose bolts, which was contrary to the requirements of Grand Gulf Nuclear Stations

license bases documents for manhole MH01. This manhole contains safety related

cables for standby service water trains A and B. In Section 9.A.5.59 of the Fire Hazard

Analysis for Fire Area 59, the yard area, it is required to seal manhole MH01 with

pressure type water-, gas-, and steam-tight bolted lids, with rubber gaskets, to prevent

the potential entry of any flammable liquid.

The licensee entered this issue in their corrective action program as Condition Report

CR-GGN-2013-01348. Immediate corrective actions included cleaning and tapping the

bolt holes to ensure proper thread engagement, adding work instructions to the

preventative maintenance procedure to clean the manhole bolt holes, and verifying that

the other manholes containing safety related cables did not have similar issues with

- 13 -

loose bolts on the manhole covers. Long term corrective actions include the licensee

adding instructions to their work order to check bolts for tightness for all safety related

manholes each month.

Analysis. The failure to properly seal safety-related manholes to prevent the introduction

of flammable liquid is a performance deficiency. The performance deficiency is more

than minor because it is associated with the Mitigating Systems Cornerstone attribute of

protection against external factors and adversely affected the cornerstone objective to

ensure the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. Using NRC Inspection Manual Chapter

0609, Attachment 4, Initial Characterization of Findings, the inspectors determined that

the issue affected the Mitigating Systems Cornerstone and required the use of

Inspection Manual Chapter 0609, Attachment 4, Appendix F, Fire Protection

Significance Determination Process. However, an NRC senior reactor analyst

determined that the unique nature of this performance deficiency did not lend itself to

analysis by the methods provided in Appendix F. Therefore, a Phase 3 analysis was

performed. Based on a bounding analysis, the analyst determined that the change in

core damage frequency was approximately 1.5E-7/yr. The result was low because of

the relatively short periods of time that fuel was actually being transferred, the low

probability of transfer system failures, and the low likelihood that a loss of normal service

water initiator would occur following a fire in the subject manholes. The inspectors

determined the apparent cause of this finding was inadequate work instructions to

ensure manhole cover bolting is securely fastened. Therefore the finding has a cross-

cutting aspect in the human performance area associated with the resources component

because the licensee did not provide adequate work packages H.2(c).

Enforcement. License Condition 2.C(41), Fire Protection Program, states, in part, that

the plant shall implement and maintain in effect all provisions of the Fire Protection

Program as described in the Updated Final Safety Analysis Report. Updated Final

Safety Analysis Report Section 9A.5.59, Fire Area 59, Section 9A.5.59.3.a, required

that manhole MH01 be properly sealed with pressure type water-, gas-, and steam-tight

bolted lids, with rubber gaskets, to prevent the potential entry of any flammable liquid.

Contrary to this, on or before February 20, 2013, the licensee did not properly seal

manhole MH01 in accordance with the fire hazard analysis. The licensee restored

compliance by cleaning and tapping the bolt holes to ensure proper bolt thread

engagement. This violation is being treated as an NCV, consistent with Section 2.3.2.a

of the Enforcement Policy. The violation was entered into the licensees corrective

action program as Condition Report CR-GGN-2013-01348. (NCV 05000461/2013002-

01, Failure to Properly Seal Safety-related Manholes)

1R07 Heat Sink Performance (71111.07)

a. Inspection Scope

The inspectors reviewed licensee programs to verify heat exchanger performance and

operability for the following heat exchangers:

  • Division 3 standby diesel generator jacket water coolers

- 14 -

The inspectors verified that testing, inspection, maintenance, and chemistry control

programs are adequate to ensure proper heat transfer. The inspectors verified that the

periodic testing and monitoring methods, as outlined in commitments to NRC Generic

Letter 89-13, utilized proper industry heat exchanger guidance. Additionally, the

inspectors verified that the licensees chemistry program ensured that biological fouling

was properly controlled between tests. The inspectors reviewed previous maintenance

records of the heat exchangers to verify that the licensees heat exchanger inspections

adequately addressed structural integrity and cleanliness of their tubes. Specific

documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of three triennial heat sink inspection samples as

defined in Inspection Procedure 71111.07-05.

b. Findings

No findings were identified.

1R11 Licensed Operator Requalification Program and Licensed Operator Performance

(71111.11)

.1 Annual Inspection [Licensed Operator Requalification (71111.11A)]

The licensed operator requalification program involves two training cycles that are

conducted over a 2-year period. In the first cycle, the annual cycle, the operators are

administered an operating test consisting of job performance measures and simulator

scenarios. In the second part of the training cycle, the biennial cycle, operators are

administered an operating test and a comprehensive written examination. For this

annual inspection requirement the licensee was in the first part of the training cycle.

a. Inspection Scope

The inspector reviewed the results of the operating tests to satisfy the annual inspection

requirements.

On December 20, 2012, the licensee informed the lead inspector of the following results:

  • 7 of 7 crews passed the simulator portion of the operating test
  • 41 of 41 licensed operators passed the simulator portion of the operating test

examination

- 15 -

The licensed operator that did not pass the Job Performance Measure portion of the

examination has been unable to complete this portion due to medical issues. When the

licensed operator returns from medical leave, then the examination will be completed.

The inspector completed one inspection sample of the annual licensed operator

requalification program.

b. Findings

No findings were identified.

.2 Quarterly Review of Licensed Operator Requalification Program

a. Inspection Scope

On March 11, 2013, the inspectors observed a crew of licensed operators in the plants

simulator during requalification as found evaluation. The inspectors assessed the

following areas:

  • Licensed operator performance
  • The ability of the licensee to administer the evaluations
  • The modeling and performance of the control room simulator
  • The quality of post-scenario critiques
  • Follow-up actions taken by the licensee for identified discrepancies

These activities constitute completion of one quarterly licensed operator requalification

program sample as defined in Inspection Procedure 71111.11.

b. Findings

No findings were identified.

.3 Quarterly Observation of Licensed Operator Performance

a. Inspection Scope

On January 2, 2013, the inspectors observed the performance of on-shift licensed

operators in the plants main control room. At the time of the observations, the plant was

in a period of heightened activity due to resuming power ascension following the reactor

scram on December 29, 2012. The inspectors observed the operators performance of

the following activities:

  • Pre-job brief

- 16 -

  • Procedural compliance in responding to control room alarms
  • Technical specifications compliance while moving a control rod that had

previously been by-passed

In addition, the inspectors assessed the operators adherence to plant procedures,

including conduct of operations procedure and other operations department policies.

These activities constitute completion of one quarterly licensed-operator performance

sample as defined in Inspection Procedure 71111.11.

b. Findings

No findings were identified.

1R12 Maintenance Effectiveness (71111.12)

a. Inspection Scope

The inspectors evaluated degraded performance issues involving the following risk

significant systems:

  • Condenser air removal and offgas systems (N62/N64)

The inspectors reviewed events such as where ineffective equipment maintenance has

resulted in valid or invalid automatic actuations of engineered safeguards systems and

independently verified the licensee's actions to address system performance or condition

problems in terms of the following:

  • Implementing appropriate work practices
  • Identifying and addressing common cause failures
  • Characterizing system reliability issues for performance
  • Charging unavailability for performance
  • Trending key parameters for condition monitoring

- 17 -

  • Verifying appropriate performance criteria for structures, systems, and

components classified as having an adequate demonstration of performance

through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as

requiring the establishment of appropriate and adequate goals and corrective

actions for systems classified as not having adequate performance, as described

in 10 CFR 50.65(a)(1)

The inspectors assessed performance issues with respect to the reliability, availability,

and condition monitoring of the system. In addition, the inspectors verified maintenance

effectiveness issues were entered into the corrective action program with the appropriate

significance characterization. Specific documents reviewed during this inspection are

listed in the attachment.

These activities constitute completion of two quarterly maintenance effectiveness

samples as defined in Inspection Procedure 71111.12-05.

b. Findings

No findings were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)

a. Inspection Scope

The inspectors reviewed licensee personnel's evaluation and management of plant risk

for the maintenance and emergent work activities affecting risk-significant and safety-

related equipment listed below to verify that the appropriate risk assessments were

performed prior to removing equipment for work:

  • The week of January 7, 2013, during emergent severe weather in the area
  • The weeks of January 14 and 21, 2013, an assessment of outage risk during

shutdown for FO-19-04

  • The week of February 4, 2013, during service transformer 11 outage
  • The week of February 11, 2013, during service transformer 11 outage and

emergent severe weather in the area requiring the licensee to enter orange risk

  • The week of March 18, 2013, during emergent severe weather in the area

requiring the licensee to enter yellow risk

The inspectors selected these activities based on potential risk significance relative to

the reactor safety cornerstones. As applicable for each activity, the inspectors verified

that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4)

and that the assessments were accurate and complete. When licensee personnel

performed emergent work, the inspectors verified that the licensee personnel promptly

assessed and managed plant risk. The inspectors reviewed the scope of maintenance

work, discussed the results of the assessment with the licensee's probabilistic risk

- 18 -

analyst or shift technical advisor, and verified plant conditions were consistent with the

risk assessment. The inspectors also reviewed the technical specification requirements

and inspected portions of redundant safety systems, when applicable, to verify risk

analysis assumptions were valid and applicable requirements were met. Specific

documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of five maintenance risk assessments and

emergent work control inspection samples as defined in Inspection

Procedure 71111.13-05.

b. Findings

Introduction. The inspectors identified a Green non-cited violation of 10 CFR 50,

Appendix B, Criterion V, for the licensees failure to monitor for ice accumulation on the

standby service water cooling towers in accordance with station procedures.

Description. On January 17, 2013, the plant experienced a winter storm in which frozen

precipitation was observed in the area. Standby Service Water System Operating

Instruction, 04-1-01-P41-1, Revision 137, Section 6.2, Cold Weather Operation,

directed the licensee to monitor the standby service water cooling tower fill material and

missile grating for ice accumulation when weather conditions exist that could result in

icing of the cooling tower fill material and missile grating. Ice formation on fan blades,

fan shafts, and missile gratings during periods of frozen precipitation could result in fan

blade/shaft damage or destruction and/or blockage of the fan discharge flow path. On

January 18, 2013, the inspectors asked about the results of the monitoring effort and

whether any actions were necessary to mitigate ice accumulation. During discussions

with the shift manager, the inspectors learned that the operations department had

directed the outage control center to perform the procedurally required inspections, but

the inspections were not performed.

The licensee entered this issue into their corrective action program as Condition Report

CR-GGNS-2013-00426. Because the inspectors questions occurred after the ambient

temperature had risen well above freezing, there were no immediate safety concerns.

Analysis. The failure to monitor for ice accumulation in accordance with station

procedures is a performance deficiency. The performance deficiency is more than minor

and therefore a finding because if left uncorrected, it could lead to a more significant

safety concern. Specifically, the occurrence of ice accumulation on the standby service

water cooling towers, if unmonitored, could cause damage to the fill material and/or the

tower missile gratings, which would render the standby service water system inoperable.

Using NRC Inspection Manual Chapter 0609, Attachment 4, "Initial Characterization of

Findings," the inspectors determined that the issue affected the Mitigating Systems

Cornerstone. In accordance with NRC Inspection Manual Chapter 0609, Appendix A,

The Significance Determination Process (SDP) for Findings at Power, the inspectors

determined that the issue had a very low safety significance (Green) because it was not

a deficiency affecting the design or qualification of a mitigating system, structure or

component, does not represent a loss of system or function, does not represent a loss of

function for greater than its technical specification allow outage time, and does not

- 19 -

represent a loss of function as defined by the licensees Maintenance Rule program for

greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The finding had a cross-cutting aspect in the human performance

area associated with the work control component because the licensee failed to

appropriately plan work activities based on environmental conditions that may impact

plant structures, systems and components H.3(a).

Enforcement. Title 10 CFR 50, Appendix B, Criterion V states, in part, that activities

affecting quality shall be accomplished in accordance with procedures. Contrary to the

above, an activity affecting quality was not accomplished in accordance with procedures.

Specifically, Procedure 04-1-01-P41-1, Standby Service Water System, Revision 137,

required the licensee to monitor the standby service water cooling tower for icing when

conditions existed that could have resulted in icing of standby service water cooling

tower missile grating and fill material. Contrary to the above, on January 17, 2013, the

licensee failed to monitor for icing on the standby service water cooling tower when

conditions existed that could have resulted in icing of the standby service water cooling

tower fans and fill material. This issue is not an immediate safety concern because the

ambient temperatures rapidly rose above freezing that same day. This violation is being

treated as an NCV, consistent with Section 2.3.2.a of the Enforcement Policy. The

violation was entered into the licensees corrective action program as Condition Report

CR-GGN-2013-00426. (NCV 05000416/2013002-02, Failure to Monitor for Ice on

Standby Service Water Towers)

1R15 Operability Evaluations and Functionality Assessments (71111.15)

a. Inspection Scope

The inspectors reviewed the following assessments:

CR-GGN-2012-13293

and CR-GGN-2013-00812

  • Emergency safety features room cooler evaluation for the operability of standby

service water system train B and division 2 diesel generator

The inspectors selected these operability and functionality assessments based on the

risk significance of the associated components and systems. The inspectors evaluated

the technical adequacy of the evaluations to ensure technical specification operability

was properly justified and to verify the subject component or system remained available

such that no unrecognized increase in risk occurred. The inspectors compared the

operability and design criteria in the appropriate sections of the technical specifications

- 20 -

and Updated Final Safety Analysis Report to the licensees evaluations to determine

whether the components or systems were operable. Where compensatory measures

were required to maintain operability, the inspectors determined whether the measures

in place would function as intended and were properly controlled. Additionally, the

inspectors reviewed a sampling of corrective action documents to verify that the licensee

was identifying and correcting any deficiencies associated with operability evaluations.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of six operability evaluations inspection samples

as defined in Inspection Procedure 71111.15-05. The seventh bulleted item was counted

in Grand Gulf Nuclear Stations 2012005 quarterly inspection report, but the finding is

documented in this inspection report.

b. Findings

Introduction. The inspectors identified a Green non-cited violation of 10 CFR 50,

Appendix B, Criterion III, Design Control, for the failure to maintain design control,

incorporate, verify, and check new instrument drift values, and translate the design basis

requirements for multiple allowable values and trip setpoints described in the technical

specifications into setpoint calculations.

Description. During the review of condition reports associated with an operability review

of the licensees transition from an 18- to 24-month operating cycle in August 2012,

inspectors identified that the licensee failed to maintain design control of multiple

setpoint calculations. The inspectors questioned whether the licensee had incorporated

all of the existing outstanding calculation changes and numerous allowable values and

trip setpoints described in the GGNS technical specifications. Inspectors also

questioned whether the calculations and values were supported by the plant design. In

response, the licensee investigated and identified the following:

1. CR-GGN-2004-00021 originally identified that the technical specification allowable

value was non-conservative and the analytical limit was protected for nine instrument

setpoint calculations. The licensee also indicated that at that time it was possible to

revise the calculations to show that the existing allowable values are conservative.

2. April 2003, the licensee cancelled the procedure EDP-32 that supported these

particular calculations, but failed to update the affected calculations to reflect this

change that was still referenced in other calculations.

3. CR-GGN-2012-11939 stated that No open CR has been found that tracks the need

to revise these calculations and the associated procedures to correct the problems

originally identified in CR-2004-00021.

Additionally, the licensee performed an investigation that assessed each calculation

of concern to determine if the current Nominal Trip Setpoint value(s) and/or

Allowable Value(s) specified in their Technical Specifications were conservative with

respect to the associated calculations.

- 21 -

4. During the review of the calculations, the licensee identified that three of the 14

calculations reviewed contained calculated Allowable Values that differed from the

values contained in the Technical Specifications. Specifically:

  • JC-Q1B21-N683-1, Rev. 0, Level 8 Narrow Range
  • JC-Q1C11-N601-1, Rev. 1, Instrument Uncertainty and Setpoint Determination

for System C71 Loop N601 - Scram Reactor on High SDVP Water Level

  • JC-Q1E22-N655-1, Rev. 1, Instrument Uncertainty and Setpoint Determination

for Instrument Loops 1E22-N655, 1E22-N636-HPCS & RCIC Pump Suction

Transfer on High Suppression Pool Level

The licensee determined that safety functions associated with the affected Allowable

Values remained Operable due to conservatisms in the Nominal Trip Setpoints and

that current Technical Specification values were conservative with respect to the new

calculated values. The licensee re-performed the calculations to reflect available

margin improvement and captured the identified conditions in their corrective action

program.

5. The licensees assessment of the calculations also determined that one calculation

JC-Q1E31-N685, Revision 0, contained an error. The error was determined to have

been introduced during the replacement of the high-pressure turbine rotor in a recent

refueling outage. The licensee determined that the current Nominal Trip Setpoint

value and allowable value were conservative relative to the new calculated Nominal

Trip Setpoint.

The licensee has submitted a License Amendment Request to the NRC to revise the

allowable value associated with this calculation.

6. The inspectors also reviewed the procedure EN-DC-166, Key Calculation

Identification and Improvement Program, dated July 5, 2012, which identifies a

group of key calculations that will be reviewed by the licensee for accuracy and

consistency with station design and maintained at a higher priority than other site

calculations. Since the condition is associated with non-conservative technical

specification Allowable Values, it also required that an engineering evaluation be

performed. At this time, the licensees engineering change and associated 50.59 is

still in process.

The inspectors reviewed all fourteen calculations that were of concern, as well as the

new calculations for the four calculations that were determined to have

discrepancies. The inspectors also assessed how the licensee ensured the new

conservative Allowable Values were protected and reviewed the spurious trip

avoidance methodology that was used. The inspectors determined that the

available margin between the original calculations and the revised calculations for

the three calculations was maintained within limits specified in procedures.

- 22 -

The licensee entered this issue into their corrective action program as Condition Report

CR-GGN-2013-00371. The immediate corrective actions were that the licensee

determined that safety functions associated with the affected Allowable Values remained

Operable due to conservatisms in the Nominal Trip Setpoints and that current Technical

Specification values were conservative with respect to the new calculated values. The

licensee re-performed the calculations to reflect available margin improvement and

captured the identified conditions in their corrective action program.

Analysis. The failure to maintain design control, incorporate, verify, and check new

instrument drift values, and translate the design basis requirements into multiple

allowable values and trip setpoints described in the technical specifications into facility

setpoint calculations is a performance deficiency. Using Inspection Manual Chapter

0612, the inspectors determined this finding is more than minor because it was

associated with the Mitigating Systems Cornerstone attribute of design control and

affected the cornerstone objective of ensuring the capability of the safety-related system

to respond to initiating events to prevent undesirable consequences. In accordance with

NRC Inspection Manual Chapter 0609, Attachment 4, "Initial Characterization of

Findings," the issue was determined to affect the Mitigating Systems Cornerstone. In

accordance with NRC Inspection Manual Chapter 0609, Appendix A, The Significance

Determination Process (SDP) for Findings at Power, the inspectors determined the

finding was of very low safety significance (Green) because it was a design deficiency

confirmed not to result in a loss of the offsite power supply operability or functionality.

This finding has a cross-cutting aspect in the area of human performance decision-

making because the licensee did not use a systematic decision-making process and did

not obtain interdisciplinary input on a risk significant decision H.1(a).

Enforcement. Title 10 CFR 50, Appendix B, Criterion III, Design Control, the design

basis for structures, systems, and components will be translated into specifications,

drawings, procedures, and instructions and design control measures shall provide for

verifying or checking the adequacy of design, such as by the performance of design

reviews, by the use of simplified methods, or by performance of a suitable testing

program. Contrary to the above, from April 2003 to October 2012, the licensee failed to

adequately translate design basis information into specifications, drawings, procedures,

and instructions, and verify the adequacy of the design by the performance of design

reviews. Specifically, the licensee failed to maintain design control for Calculations JC-

Q1B21-N683-1, JC-Q1C11-N60101, JC-Q1E22-N655-1 that differed from the values

contained in the Technical Specifications, and Calculation JC-Q1E31-N685 contained an

error introduced by the replacement of the high-pressure turbine rotor. This violation is

being treated as an NCV, consistent with Section 2.3.2.a of the Enforcement Policy. The

violation was entered into the licensees corrective action program as Condition Report

CR-GGN-2013-0037. (NCV 05000416/2013002-03 Failure to Maintain Design Control

of Setpoint Calculations)

- 23 -

1R18 Plant Modifications (71111.18)

.1 Temporary Modifications

a. Inspection Scope

The inspectors reviewed key affected parameters associated with energy needs,

materials, replacement components, timing, heat removal, control signals, equipment

protection from hazards, operations, flow paths, pressure boundary, ventilation

boundary, structural, process medium properties, licensing basis, and failure modes for

the permanent modification listed below.

  • EC-41836 - A Phase Unit Differential Neutral CT Swap with A Phase

Generator Differential CT

The inspectors verified that modification preparation, staging, and implementation did

not impair emergency/abnormal operating procedure actions, key safety functions, or

operator response to loss of key safety functions; post-modification testing will maintain

the plant in a safe configuration during testing by verifying that unintended system

interactions will not occur; systems, structures and components performance

characteristics still meet the design basis; the modification design assumptions were

appropriate; the modification test acceptance criteria will be met; and licensee personnel

identified and implemented appropriate corrective actions associated with permanent

plant modifications. Specific documents reviewed during this inspection are listed in the

attachment.

This activity constitutes completion of one sample for temporary modification review as

defined in Inspection Procedure 71111.18-05.

b. Findings

No findings were identified.

1R19 Post-Maintenance Testing (71111.19)

a. Inspection Scope

The inspectors reviewed the following post-maintenance activities to verify that

procedures and test activities were adequate to ensure system operability and functional

capability:

  • Source range monitor B following corrective maintenance
  • Source range monitors E and F following corrective maintenance

corrective maintenance

- 24 -

maintenance

  • Service transformer 11 following periodic maintenance
  • Engineered safety features transformer 11 following periodic maintenance
  • Division 2 diesel generator following corrective maintenance

The inspectors selected these activities based upon the structure, system, or

component's ability to affect risk. The inspectors evaluated these activities for the

following (as applicable):

  • The effect of testing on the plant had been adequately addressed; testing was

adequate for the maintenance performed

  • Acceptance criteria were clear and demonstrated operational readiness; test

instrumentation was appropriate

The inspectors evaluated the activities against the technical specifications, the Updated

Final Safety Analysis Report, 10 CFR 50 requirements, licensee procedures, and various

NRC generic communications to ensure that the test results adequately ensured that the

equipment met the licensing basis and design requirements. In addition, the inspectors

reviewed corrective action documents associated with post-maintenance tests to

determine whether the licensee was identifying problems and entering them in the

corrective action program and that the problems were being corrected commensurate

with their importance to safety. Specific documents reviewed during this inspection are

listed in the attachment.

These activities constitute completion of nine post-maintenance testing inspection

samples as defined in Inspection Procedure 71111.19-05.

b. Findings

No findings were identified.

1R20 Refueling and Other Outage Activities (71111.20)

a. Inspection Scope

The inspectors reviewed the outage safety plan and contingency plans for the forced

outage, conducted January 14, 2013 through January 27, 2013, to confirm that licensee

personnel had appropriately considered risk, industry experience, and previous site-

specific problems in developing and implementing a plan that assured maintenance of

defense in depth. During the forced outage, the inspectors observed post scram actions

and monitored licensee controls over the outage activities listed below.

- 25 -

  • Configuration management, including maintenance of defense in depth, is

commensurate with the outage safety plan for key safety functions and

compliance with the applicable technical specifications when taking equipment

out of service.

  • Clearance activities, including confirmation that tags were properly hung and

equipment appropriately configured to safely support the work or testing.

  • Status and configuration of electrical systems to ensure that technical

specifications and outage safety-plan requirements were met, and controls over

switchyard activities.

  • Verification that outage work was not impacting the ability of the operators to

operate the spent fuel pool cooling system.

alternative means for inventory addition, and controls to prevent inventory loss.

  • Controls over activities that could affect reactivity.

specifications.

  • Startup and ascension to full power operation, tracking of startup prerequisites.
  • Licensee identification and resolution of problems related to forced outage

activities.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one other outage inspection sample as defined

in Inspection Procedure 71111.20-05.

b. Findings

No findings were identified.

1R22 Surveillance Testing (71111.22)

a. Inspection Scope

The inspectors reviewed the Updated Final Safety Analysis Report, procedure

requirements, and technical specifications to ensure that the surveillance activities listed

below demonstrated that the systems, structures, and/or components tested were

capable of performing their intended safety functions. The inspectors either witnessed

or reviewed test data to verify that the significant surveillance test attributes were

adequate to address the following:

  • Preconditioning

- 26 -

  • Evaluation of testing impact on the plant
  • Acceptance criteria
  • Test equipment
  • Procedures
  • Jumper/lifted lead controls
  • Test data
  • Testing frequency and method demonstrated technical specification operability
  • Test equipment removal
  • Restoration of plant systems
  • Fulfillment of ASME Code requirements
  • Updating of performance indicator data
  • Engineering evaluations, root causes, and bases for returning tested systems,

structures, and components not meeting the test acceptance criteria were correct

  • Reference setting data

The inspectors also verified that licensee personnel identified and implemented any

needed corrective actions associated with the surveillance testing.

  • January 3, 2013, division 3 diesel generator 24-hour run and quick restart
  • February 16, 2013, engineers safety features transformer 11 full flow sprinkler

test

  • February 26, 2013, division 2 diesel generator surveillance
  • February 27, 2013, local leak rate test for isolation valve 1E12-F406

restart

  • March 20, 2013, average power range monitor flow bias calibration
  • April 6, 2013, channel bow testing

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of nine surveillance testing inspection samples as

defined in Inspection Procedure 71111.22-05.

- 27 -

b. Findings

Introduction. The inspectors identified a Green non-cited violation of License Condition

2.C(41), Fire Protection Program, for the failure to correct a condition adverse to quality

with respect to fire protection. Specifically, after the licensee installed a scaffold in the

hallway near the doorway into the division-1 diesel generator room that interfered with

access into that room, the licensee failed to correct that condition for approximately 2

months.

Description. During January, 2013, the licensee installed a scaffold in the diesel

generator building, to enable workers to access a component for scheduled

maintenance. On March 6, 2013, during a surveillance inspection of the 24-hour run of

the division-1 diesel generator, the inspectors noted that the licensee had placed the

scaffold in the hallway near the access door for the division-1 diesel generator. They

also experienced difficulty transiting through the scaffolding poles to reach the door of

the generator room. After the inspectors told the control room supervisor of this issue,

the licensee determined that the scaffold would adversely affect response of fire brigade

members to a fire in the division-1 diesel generator room, and immediately removed the

scaffold. Through an extent-of-condition review, the licensee determined that two other

scaffolds in the auxiliary building south stairwell above and below the 166 foot elevation

were also blocking fire brigade access. The licensee established alternate routes for the

fire brigade to access areas blocked by these scaffolds. On March 11, 2013, the

licensee removed one scaffold from the south stairwell and modified the other to allow

fire brigade access.

The licensee documented this issue in their corrective action program as Condition

Report CR-GGN-2013-01679. The short-term corrective actions included removing the

scaffold in the diesel generator building hallway. The licensee also removed a scaffold

and modified an additional scaffold in the auxiliary building south stairwell. The

maintenance support superintendent told the inspectors that he had directed scaffolding

personnel to maintain a minimum 36-inch spacing for future scaffolds constructed on

site, and that he plans to work with his fleet peers to implement a change to the fleet

procedure to ensure scaffolds are properly constructed with respect to fire brigade

access.

Analysis. The failure to take prompt corrective action to ensure adequate access for fire

brigade members through installed scaffolding in the diesel generator building hallway to

the division-1 diesel generator room is a performance deficiency. This performance

deficiency is more than minor and is therefore a finding because if left uncorrected, it

would have the potential to lead to a more significant safety concern. Specifically,

continued inability for fire brigade members to gain access to safety related equipment in

timely manner could result in preventing promptly extinguishing fires. Using NRC

Inspection Manual Chapter 0609, Attachment 4, "Initial Characterization of Findings," the

inspectors determined that the issue affected the Mitigating Systems Cornerstone. In

accordance with NRC Inspection Manual Chapter 0609, Appendix A, The Significance

Determination Process (SDP) for Findings at Power, the inspectors determined that the

issue has very low safety significance (Green) because the finding involved a

- 28 -

risk-significant fire area that had an automatic fire suppression system. The inspectors

determined the apparent cause of this finding was that the licensee did not implement

the corrective action program with a low threshold for identifying scaffolding that could

impede fire brigade member response during a fire. Therefore the finding had a cross-

cutting aspect in the problem identification and resolution area associated with the

corrective action program component because the licensee failed to identify conditions

adverse to fire protection P.1(a).

Enforcement. License Condition 2.C(41), Fire Protection Program, states, in part, that

the plant shall implement and maintain in effect all provisions of the Fire Protection

Program as described in the Updated Final Safety Analysis Report. Updated Final

Safety Analysis Report Section 9B.2.1.9.c required, in part, that prompt and effective

corrective actions are taken to correct conditions adverse to the Fire Protection Program.

Contrary to this, on or before March 6, 2013, the licensee did not take prompt and

effective actions to correct a condition adverse to the Fire Protection Program.

Specifically, during January, 2013, the licensee installed a scaffold in a diesel generator

building hallway that interfered with fire-brigade access into the diesel generator room,

the licensee did not take action to correct that condition until the inspectors questioned

the scaffold configuration on March 6, 2013. As an immediate corrective action, the

licensee removed the scaffold in the diesel generator building hallway on March 6. This

violation is being treated as an NCV, consistent with Section 2.3.2.a of the Enforcement

Policy. The violation was entered into the licensees corrective action program as

Condition Report CR-GGN-2013-01679. (NCV 05000416/2013002-04, Failure to

Correct a Scaffold Affecting Fire Brigade Access)

Cornerstone: Emergency Preparedness

1EP4 Emergency Action Level and Emergency Plan Changes (IP 71114.04)

a. Inspection Scope

The NSIR headquarters staff performed an in-office review of the latest revisions of

various Emergency Plan Implementing Procedures (EPIPs) and the Emergency Plan

located under ADAMS accession numbers ML12345A425, ML12355A106 and

ML130230023 as listed in the Attachment.

The licensee determined that in accordance with 10 CFR 50.54(q), the changes made in

the revisions resulted in no reduction in the effectiveness of the Plan, and that the

revised Plan continued to meet the requirements of 10 CFR 50.47(b) and Appendix E to

10 CFR 50. The NRC review was not documented in a safety evaluation report and did

not constitute approval of licensee-generated changes; therefore, this revision is subject

to future inspection. The specific documents reviewed during this inspection are listed in

the Attachment.

These activities constitute completion of three samples as defined in Inspection

Procedure 71114.04-05.

- 29 -

b. Findings

No findings were identified.

1EP6 Drill Evaluation (71114.06)

.1 Emergency Preparedness Drill Observation

a. Inspection Scope

The inspectors evaluated the conduct of a routine licensee emergency drill on March 5,

2013, to identify any weaknesses and deficiencies in classification, notification, and

protective action recommendation development activities. The inspectors observed

emergency response operations in the simulator control room and the emergency offsite

facility to determine whether the event classification, notifications, and protective action

recommendations were performed in accordance with procedures. The inspectors also

attended the licensee drill critique to compare any inspector-observed weakness with

those identified by the licensee staff in order to evaluate the critique and to verify

whether the licensee staff was properly identifying weaknesses and entering them into

the corrective action program. As part of the inspection, the inspectors reviewed the drill

package and other documents listed in the attachment.

These activities constitute completion of one sample as defined in Inspection

Procedure 71114.06-05.

b. Findings

No findings were identified.

4OA1 Performance Indicator Verification (71151)

.1 Data Submission Issue

a. Inspection Scope

The inspectors performed a review of the performance indicator data submitted by the

licensee for the fourth quarter 2012 performance indicators for any obvious

inconsistencies prior to its public release in accordance with Inspection Manual

Chapter 0608, Performance Indicator Program.

This review was performed as part of the inspectors normal plant status activities and,

as such, did not constitute a separate inspection sample.

b. Findings

No findings were identified.

- 30 -

.2 Unplanned Scrams per 7000 Critical Hours (IE01)

a. Inspection Scope

The inspectors sampled licensee submittals for the unplanned scrams per 7000 critical

hours performance indicator for the period from the first quarter 2012 through the fourth

quarter 2012. To determine the accuracy of the performance indicator data reported

during those periods, the inspectors used definitions and guidance contained in NEI

Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6.

The inspectors reviewed the licensees operator narrative logs, issue reports, event

reports, and NRC integrated inspection reports for the period of January 2012 through

December 2012, to validate the accuracy of the submittals. The inspectors also

reviewed the licensees condition report database to determine if any problems had been

identified with the performance indicator data collected or transmitted for this indicator

and none were identified. Specific documents reviewed are described in the attachment

to this report.

These activities constitute completion of one unplanned scrams per 7000 critical hours

sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings were identified.

.3 Unplanned Power Changes per 7000 Critical Hours (IE03)

a. Inspection Scope

The inspectors sampled licensee submittals for the unplanned power changes per 7000

critical hours performance indicator for the period from the first quarter 2012 through the

fourth quarter 2012. To determine the accuracy of the performance indicator data

reported during those periods, the inspectors used definitions and guidance contained in

NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline,

Revision 6. The inspectors reviewed the licensees operator narrative logs, issue

reports, maintenance rule records, event reports, and NRC integrated inspection reports

for the period of January 2012 through December 2012, to validate the accuracy of the

submittals. The inspectors also reviewed the licensees condition report database to

determine if any problems had been identified with the performance indicator data

collected or transmitted for this indicator and none were identified. Specific documents

reviewed are described in the attachment to this report.

These activities constitute completion of one unplanned transients per 7000 critical

hours sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings were identified.

- 31 -

.4 Unplanned Scrams with Complications (IE04)

a. Inspection Scope

The inspectors sampled licensee submittals for the unplanned scrams with

complications performance indicator for the period from the first quarter 2012 through

the fourth quarter 2012. To determine the accuracy of the performance indicator data

reported during those periods, the inspectors used definitions and guidance contained in

NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline,

Revision 6. The inspectors reviewed the licensees operator narrative logs, issue

reports, event reports, and NRC integrated inspection reports for the period of January

2012 through December 2012, to validate the accuracy of the submittals. The

inspectors also reviewed the licensees condition report database to determine if any

problems had been identified with the performance indicator data collected or

transmitted for this indicator and none were identified. Specific documents reviewed are

described in the attachment to this report.

These activities constitute completion of one unplanned scrams with complications

sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings were identified.

4OA2 Problem Identification and Resolution (71152)

.1 Routine Review of Identification and Resolution of Problems

a. Inspection Scope

As part of the various baseline inspection procedures discussed in previous sections of

this report, the inspectors routinely reviewed issues during baseline inspection activities

and plant status reviews to verify that they were being entered into the licensees

corrective action program at an appropriate threshold, that adequate attention was being

given to timely corrective actions, and that adverse trends were identified and

addressed. The inspectors reviewed attributes that included the complete and accurate

identification of the problem; the timely correction, commensurate with the safety

significance; the evaluation and disposition of performance issues, generic implications,

common causes, contributing factors, root causes, extent of condition reviews, and

previous occurrences reviews; and the classification, prioritization, focus, and timeliness

of corrective actions. Minor issues entered into the licensees corrective action program

because of the inspectors observations are included in the attached list of documents

reviewed.

These routine reviews for the identification and resolution of problems did not constitute

any additional inspection samples. Instead, by procedure, they were considered an

integral part of the inspections performed during the quarter and documented in

Section 1 of this report.

- 32 -

b. Findings

No findings were identified.

.2 Daily Corrective Action Program Reviews

a. Inspection Scope

In order to assist with the identification of repetitive equipment failures and specific

human performance issues for follow-up, the inspectors performed a daily screening of

items entered into the licensees corrective action program. The inspectors

accomplished this through review of the stations daily corrective action documents.

The inspectors performed these daily reviews as part of their daily plant status

monitoring activities and, as such, did not constitute any separate inspection samples.

b. Findings

No findings were identified.

4OA3 Followup of Events and Notices of Enforcement Discretion (71153)

.1 Reactor Scram Due to Unit Differential Relay Trip

a. Inspection Scope

On January 4, 2013, Grand Gulf Nuclear Station experienced and unexpected reactor

scram from 94 percent rated thermal power the scram was due to a phase A unit

differential relay tripping, causing the generator lockouts to trip, resulting in a turbine trip

and reactor scram due to being greater than 35 percent power. The inspectors

responded to the plant and verified the site systems responded as designed and that the

operators stabilized the plant in accordance with station procedures. The licensee

determined a ground condition had occurred on the A phase of the generator neutral

current transformer. The ground condition was caused by inadequate spacing between

the current transformer and support bolts. During power operations, thermal expansion

and relative vibration allow the support bolts to make contact with the current

transformer and damage the insulation and cause a ground condition resulting in a main

generator trip and plant scram. The licensee took corrective action to remove the

damaged current transformer and corrected any other bolting issues prior to startup.

These activities constitute completion of one event follow-up as defined in Inspection

Procedure 71153-05.

b. Findings

1. Automatic Reactor Scram Caused by Ground Condition on the A Phase Neutral Current

Transformer

- 33 -

Introduction. The inspectors reviewed a Green self-revealing finding for the failure to

ensure the current transformer structure, the neutral bus housing, and the associated

mounting hardware were installed with adequate clearance to accommodate thermal

expansion. This failure resulted in an automatic reactor scram on December 29, 2012,

and a subsequent scram on January 4, 2013.

Description. On December 29, 2012, while operating at 100 percent rated thermal

power, the plant experienced an automatic reactor scram. Site personnel determined

the scram was caused by a trip of the phase A unit differential relay, which caused the

generator lockouts to trip and resulted in a turbine trip and reactor scram.

The licensee determined that the potential causes of the phase A unit differential relay

trip were either a spurious actuation of the differential relay, a fault in the current

transformer relay circuitry, or an internal fault of a current transformer (CT). Because the

licenses testing and inspection activities did not identify a definite failure mode, the

licensee determined that an intermittent failure of the phase A unit differential relay was

the most-likely cause of the relay trip. The licensee replaced the unit differential relays

for all three phases (A, B, and C), and returned the plant to online operations on

January 1, 2013. The licensee had installed monitoring equipment prior to restart, and

the monitoring equipment did not detect a phase-differential fault while the licensee

brought the generator online.

On January 4, 2012, while operating at 94 percent rated thermal power, the plant

experienced an automatic reactor scram. The licensee determined the cause of the

scram was a trip of the phase A unit differential relay, which caused the generator

lockouts to trip and resulted in a turbine trip and reactor scram. The monitoring

equipment installed following the initial scram indicated a ground condition occurred on

the A phase of the generator neutral CT. The licensee assembled a failure modes

analysis team to inspect the non-accessible areas of the main generator A phase neutral

CT. This team used a boroscope to identify the source of the ground condition. The

boroscope inspection showed that micarta plate bolts on the isophase bus transition box

below the CTs had not been installed according to manufacturer specifications. As a

result, clearance within the bus transition box was not adequate to accommodate the

thermal expansion of the CT structure, the neutral bus housing, and the associated

mounting hardware. Thus, during power operations, thermal expansion and relative

vibration between these components allowed a micarta plate bolt to make contact with

the A phase neutral CT, damage the insulation, and cause a ground condition. The

result was a main generator trip and plant scram.

The licensee entered the plant scrams into their corrective action process as Condition

Reports CR-GGN-2012-13290 and CR-GGN-2013-00083. Immediate corrective actions

included removing the damaged CT and modifying the micarta plate bolts to conform to

manufacturer specifications. The licensee also performed a root-cause analysis to

address recurrence.

Analysis. The failure to install micarta plate bolts in accordance with manufacturer

specifications and ensure that the current transformer structure, the neutral bus housing,

and the associated mounting hardware had adequate clearance is a performance

- 34 -

deficiency. The performance deficiency is more than minor and therefore is a finding

because it is associated with the Initiating Events Cornerstone attribute of human

performance and adversely affected the cornerstone objective to limit the likelihood of

events that upset plant stability and challenge critical safety functions during shutdown

and power operations. Using NRC Inspection Manual Chapter 0609, Attachment 4,

"Initial Characterization of Findings," the inspectors determined that the issue affected

the Initiating Events Cornerstone. In accordance with NRC Inspection Manual Chapter

0609, Appendix A, The Significance Determination Process (SDP) for Findings at

Power, the inspectors determined that the issue has very low safety significance

(Green) because it caused only a reactor trip and did not cause a loss of mitigating

equipment relied upon to transition the plant from the onset of the trip to a stable

shutdown condition. Therefore the finding has a cross-cutting aspect in the human

performance area associated with the resources component because the licensee failed

to provide adequate work instructions H.2(c).

Enforcement. This finding does not involve enforcement action because no violation of a

regulatory requirement was identified. This finding was entered into the licensees

corrective action program as Condition Reports CR-GGN-2012-13290 and CR-GGN-

2013-00083. Because this finding does not involve a violation and is of very low safety

significance, it is identified as a finding (FIN 05000416/2013002-06, Reactor Scram Due

to Ground Fault)

2. Failure to Provide Instructions to Remove Foreign Material from Safety Relief Valve

1B21-F047A Exhaust Port Resulting in the Valve Failing Open Beyond its Reset

Setpoint

Introduction. The inspectors reviewed a Green self-revealing non-cited violation of

10 CFR 50 Appendix B Criterion V, for the failure to provide instructions to remove a

foreign material exclusion plug from the exhaust port of safety relief valve 1B21-F047A,

which resulted in the valves failure to close at its reset setpoint following a reactor scram

on December 29, 2012.

Description. On December 29, 2012, while operating at 100 percent rated thermal

power, the plant experienced an automatic reactor scram due to a turbine trip. Following

the turbine trip/reactor scram and in response to the resulting pressure transient, 11

safety relief valves opened. Those valves opened on their mechanical relief setpoint,

which requires air to open the valves against spring pressure. The valves normally close

when the reset pressure is reached by exhausting air pressure off the valve and allowing

spring pressure to shut the valve. However, on December 29, safety relief valve 1B21-

F047A failed to close at its reset setpoint of 1013 psig, and remained open until steam

pressure dropped to approximately 675 psig. The licensee determined that the valve

was still operable for its safety relief function and its alternate depressurization function,

but inoperable for its mechanical relief function. Based on analysis that the valve was

operable for its safety functions, the licensee left the valve switch in the closed position

instead of the auto position for plant startup. After the plant scrammed again on

January 4, 2013, the licensee made a drywell/containment entry and determined by

physical examination of the valve, that a foreign material exclusion (FME) plug had been

left in the exhaust port of valve 1B21-F047A.

- 35 -

Through an extent-of-condition review, the licensee verified that no FME plug was

inserted into the exhaust port of any other safety relief valve. Through an investigation,

they determined that a lack of work instructions directing the removal of FME plugs was

the reason why the FME plug had been left in the exhaust port of valve 1B21-F047A .

Further review determined that although the licensee had refurbished safety relief valves

themselves in the past, the licensee had recently sent valve 1B21-F047A and several

other valves to a vendor for refurbishment and testing. Further review also revealed that

the vendors processes for completing this work differed from the licensees processes in

at least one noteworthy way: while the licensee had used tape to provide FME covers

over exhaust ports, the vendor installed FME plugs into those ports. The inspectors

considered that when the licensee made the decision to use a vendor to refurbish the

subject valves, they apparently did not recognize this difference, and consequently did

not develop instructions to remove the subject plugs.

The licensee documented this issue in their corrective action program as Condition

Report CR-GGN-2013-00100. The immediate corrective actions were to remove the

FME plug from the exhaust port of valve 1B21-F047A and ensure no other safety relief

valves had FME plugs installed. The licensee has developed long-term corrective

actions to establish detailed work instructions to ensure that no FME plug is left in any

safety relief valve.

Analysis. The failure to provide instructions to remove a foreign material exclusion plug

from the exhaust port of relief valve 1B21F047A is a performance deficiency. The

performance deficiency is more than minor and therefore, a finding because it is

associated with the Initiating Events Cornerstone attribute of human performance and

adversely affected the cornerstone objective to limit the likelihood of events that upset

plant stability and challenge critical safety functions during shutdown as well as power

operations. Using NRC Inspection Manual Chapter 0609, Attachment 4, "Initial

Characterization of Findings," the inspectors determined that the issue affected the

Initiating Events Cornerstone. In accordance with NRC Inspection Manual Chapter

0609, Appendix A, The Significance Determination Process (SDP) for Findings at

Power, the inspectors determined that the issue has very low safety significance

(Green) because after a reasonable assessment of the degradation, the finding could

not result in exceeding the reactor coolant leak rate for a small loss of coolant accident

because the configuration of the safety relief valve was such that it would close at

approximately 675 psig. Also the finding did not affect other systems used to mitigate a

loss of coolant accident resulting in a total loss of their function. The licensee

determined that the apparent cause of the finding was that when they decided to ask a

vendor to refurbish safety-relief valves, they did not realize that the vendor would install

FME plugs into the valves exhaust ports, and therefore did not develop instructions to

remove those plugs. Because that decision affected the mechanical relief function of a

safety relief valve, the inspectors considered that decision to be safety-significant.

Therefore, this finding had a cross-cutting aspect in the area of human performance

associated with the decision-making component because the licensee did not use a

systematic process to make a safety-significant decision. H.1(a)

- 36 -

Enforcement. Title 10 CFR 50, Appendix B, Criterion V, states, in part that activities

affecting quality shall be prescribed by procedures appropriate to the circumstances.

Contrary to this requirement, on or before April 18, 2012, an activity affecting quality was

not prescribed by procedures appropriate to the circumstances. Specifically, Procedure

07-S-15-4,Main Steam Safety/Relief Valve Removal and Installation, Revision 16,

Step 7.15, did not include instructions to remove FME plugs from the exhaust port air

control block of safety relief valves. The licensee has developed corrective actions to

establish detailed work instructions to ensure that no FME plug is left in any safety relief

valve. This violation is being treated as an NCV, consistent with Section 2.3.2.a of the

Enforcement Policy. The violation was entered into the licensees corrective action

program as Condition Report CR-GGN-2013-00100. (NCV 05000416/2013002-06,

Inadequate Procedure for Removal of a Foreign Material Exclusion Plug)

.2 Reactor Scram Due to Neutral Time Overcurrent Relay Trip

a. Inspection Scope

On January 14, 2013, the plant experienced an automatic reactor scram from 100

percent rated thermal power. The scram was due to a neutral time overcurrent relay

tripping, causing a generator lockouts to trip, resulting in a turbine trip and reactor scram

due to being greater than 35 percent power. The inspectors responded to the site and

verified the plant systems responded as designed, and that the operators stabilized the

plant in accordance with station procedures. The licensee determined that the ground

that was detected on the bus was caused by water intruding the isophase bus duct

through a degraded viewing port on top of the isophase bus duct and accumulating in

the vertical sections of the duct, collecting on a seal-off bushing which served as a

barrier in bus ducts to re-direct air flow to the spare transformer. The collection of water

on the seal-off bushings resulted in grounding of the main conductor to the duct wall that

in turn resulted in the neutral time overcurrent relay to pick up, which resulted in the

turbine generator trip. The licensee took corrective measures to stop the water intrusion

into the isophase bus duct and to electrically isolate the spare transformer from the

energized transformers prior to startup.

b. Findings

1. Failure to Identify a Degraded Isophase Bus Duct Resulting in Automatic Reactor Scram

Introduction. The inspectors reviewed a Green self-revealing finding for the failure to

identify a degraded isophase bus duct view port window which allowed water to intrude

into the isophase bus duct, and caused an automatic reactor scram on January 14,

2013.

Description. On October 2, 2012, the licensee generated condition report CR-GGN-

2012-11250 documenting cracked isophase bus duct viewing port windows. They

closed this condition report to condition report CR-GGN-2012-11188, in which they were

performing an apparent cause evaluation (ACE) for a degraded viewing-port window.

Procedure EN-LI-119, Apparent Cause Evaluation Process, Revision 16, requires that

the extent-of-condition review identify the total population of items that have or may have

- 37 -

the same problem as the one being evaluated. However, for the CR-GGN-2012-11188

ACE, the licensee limited the extent-of-condition review to only those viewing ports that

they could see from the ground. The licensee specifically did not identify the view ports

on top of the bus ducts as being susceptible to the same issues identified in the two

condition reports. This resulted in missing an opportunity to identify degraded viewing

ports on top of the isophase bus ducting.

On January 14, 2013, at 6:05 p.m., while operating at 100 percent rated thermal power,

the plant experienced an automatic reactor scram. Site personnel determined that the

scram was caused by a turbine generator trip resulting from tripping a generator neutral

time overcurrent relay. Their investigation detected a ground on the bus. They

determined that the cause of the grounded condition was water entering the isophase

bus duct through a degraded viewing port on top of the isophase bus duct. This water

accumulated in the vertical sections of the duct and collected on a seal-off bushing,

which served as a barrier in the bus ducts to re-direct air flow to the spare transformer.

The collection of water on the seal-off bushings resulted in the grounding of the main

conductor to the duct wall. This then resulted in the neutral time overcurrent relay picking

up and caused the turbine generator trip. The licensee took corrective measures to stop

the water intrusion into the isophase bus duct and to electrically isolate the spare

transformer from the energized transformers.

The licensee documented this issue in their corrective action program as Condition

Report CR-GGN-2013-00319. The corrective actions included adding a design change

to stop water intrusion into the isophase bus duct by replacing the viewing ports on top

of the duct with bolted down metal plates and gaskets. The licensee also performed a

root-cause analysis to address recurrence.

Analysis. The failure to identify a degraded isophase bus duct view port window is a

performance deficiency. This performance deficiency is more than minor and therefore

is a finding because it is associated with the Initiating Events Cornerstone attribute of

human performance and adversely affected the associated cornerstone objective to limit

the likelihood of those events that upset plant stability and that challenge critical safety

functions during power operations. Using NRC Inspection Manual Chapter 0609,

Attachment 4, "Initial Characterization of Findings," the inspectors determined that the

issue affected the Initiating Events Cornerstone. In accordance with NRC Inspection

Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for

Findings at Power, the inspectors determined that the issue has a very low safety

significance (Green) because it only caused a reactor trip and did not cause a loss of

mitigating equipment relied on to transition the plant from the onset of a trip to a stable

shutdown condition. The most-significant contributing cause to the performance

deficiency was that the licensee had decided to not inspect the viewing ports on the top

side of the isophase bus duct because they had assumed that those ports were not

degraded. Therefore, the finding has a cross-cutting aspect in the area of human

performance associated with the decision-making component because the licensee did

not use conservative assumptions in decision-making H.1(b).

Enforcement. This finding does not involve enforcement action because no violation of a

regulatory requirement was identified. This finding was entered into the licensees

- 38 -

corrective action program as Condition Report CR-GGN-2013-00319. Because this

finding does not involve a violation and is of very low safety significance, it is identified

as a finding. (FIN 05000416/2013002-07, Reactor Scram Due to Moisture in Isophase

Bus Duct )

2. Failure to Revise the Scram Procedure After Temporarily Modifying the Division-2

Circuits that Sense First-Stage Turbine Pressure

Introduction. The inspectors identified a Green non-cited violation of Technical

Specification 5.4.1.a, for the failure to revise the scram procedure after temporarily

modifying the division-2 circuits that sense first-stage turbine pressure. Specifically, due

to a failed steam sensing line, the licensee had introduced a dummy signal into the

subject circuits to comply with technical specifications; however, they had failed to revise

the scram procedure to reflect this temporary modification. This resulted in additional

scrams during scram recovery for the scrams on December 29, 2012, and January 4,

2013.

Description. On February 16, 2013, during follow up interviews for reactor scrams that

occurred on December 29, 2012, January 4, 2013, and January 14, 2013, the inspectors

questioned the cause of the repeat scrams following the original scrams, and discussed

issues with controlling reactor water level. The operators referenced Procedure 05-1-02-

I-1, Reactor Scram, Revision 117, that allowed them to reset the scram and then insert

the intermediate-range power detectors into the core one channel at a time to avoid a full

scram. However, with dummy signals applied to the division-2 circuits that sense first-

stage turbine pressure, they could reset only the division-1 side of the scram. The

licensee had temporarily installed this dummy signal to ensure that a reactor scram

circuit would actuate a reactor scram following a turbine trip with reactor power greater

than 35 percent rated thermal power. However, with power below 35 percent rated

thermal power and the signal applied, the dummy signal would not allow operators to

reset the half-scram on the division 2 side. Consequently, when the operators complied

with the scram procedure and inserted the intermediate-range power detectors into the

core on the division-1 side, they received intermittent spikes on division-1 instruments,

resulting in full scrams. Also, with the inability to reset the scram due to this alignment of

the first stage sensing circuits on the division 2 side, control rod drive system injection

added water to the reactor vessel, which complicated reactor water level control.

The licensee documented this issue in their corrective action program as Condition

Report CR-GGN-2013-001259. The short-term corrective actions included modifying the

scram procedure to require the operators to turn off the units that provide the dummy

signal to the division-2 circuits that sense first-stage turbine pressure following a reactor

scram, allowing the operators to reset the full scram promptly.

Analysis. The failure to revise Procedure 05-1-02-I-1 following a temporary modification

to the division-2 circuits that sense first-stage turbine pressure is a performance

deficiency. This performance deficiency is more than minor and therefore, a finding

because it is associated with the Initiating Events Cornerstone attribute of human

performance and adversely affected the cornerstone objective to limit the likelihood of

events that upset plant stability and challenge critical safety functions during shutdown

- 39 -

as well as power operations. Using NRC Inspection Manual Chapter 0609, Attachment

4, "Initial Characterization of Findings," the inspectors determined that the issue affected

the Initiating Events Cornerstone. In accordance with NRC Inspection Manual Chapter

0609, Appendix A, The Significance Determination Process (SDP) for Findings at

Power, the inspectors determined that the issue has very low safety significance

(Green) because it only caused a reactor trip and did not cause the loss of mitigating

equipment relied upon to transition the plant from the onset of the trip to a stable

shutdown condition. The finding had a cross-cutting aspect in the area of human

performance associated with the work practices component because licensee personnel

failed to ensure that procedures impacted by a temporary modification were properly

revised to compensate for the installed modification H.4(b).

Enforcement. Technical Specification 5.4.1.a requires that written procedures be

established, implemented, and maintained as recommended by NRC Regulatory Guide

1.33, Revision 2, Appendix A, February 1978. Regulatory Guide 1.33, Appendix A,

Section 1j recommends procedures for Bypass of Safety Functions and Jumper

Control. Procedure EN-DC-136, Temporary Modifications, Revision 8, Step 4.4[1],

implements this requirement and states, in part, that the operations manager, Ensures

development of new or revision of existing Operations procedures required to reflect the

configuration as affected by the Temporary Modification Package. Contrary to the

above, a procedure recommended by Regulatory Guide 1.33 was not implemented.

Specifically, on June 21, 2012, the operations manager did not ensure the development

of a new or revisions of existing operations procedures required to reflect the

configuration as affected by the Temporary Modification Package. Specifically, on June

21, 2012, after the licensee implemented a temporary modification that inserted a

dummy signal into the division-2 circuits that sense first-stage turbine pressure due to a

failed steam sensing line to comply with technical specifications, but the operations

manager did not ensure that Procedure 05-1-02-I-1, Reactor Scram, Revision 117 was

revised to reflect the temporary modification. As an immediate corrective action, the

licensee revised that procedure to require the operators to turn off the units that provide

the dummy signal to the subject circuits following a reactor scram. This violation is being

treated as an NCV, consistent with Section 2.3.2.a of the Enforcement Policy. The

violation was entered into the licensees corrective action program as Condition Report

CR-GGN-2013-01259. (NCV 05000416/2013002-08, Failure to Revise the Scram

Procedure After Temporary Modification)

4OA5 Other Activities

.1 Temporary Instruction 2515/182 - Review of the Implementation of the Industry Initiative

to Control Degradation of Underground Piping and Tanks

a. Inspection Scope

The inspectors reviewed the licensees programs for buried pipe and underground piping

and tanks to ensure that the attributes recommended in NEI 09-14 Rev. 1 are contained

in the licensees program. These attributes are listed in sections 3.3 A and 3.3 B of NEI

09-14 Rev. 1. The inspectors also reviewed the licensees programs for buried piping

- 40 -

and tanks to ensure the completion dates recommended by NEI 09-14 Rev. 1 are

contained in the licensees program. Furthermore, the inspectors reviewed the

licensees program to ensure that activities which correspond to specified completion

dates which have passed, have been completed.

The licensees buried piping and underground piping and tanks program was inspected

in accordance with paragraphs 03.01.a through 03.01.c (Phase 1) of the TI and was

found to meet all applicable aspects of NEI 09-14 Rev. 1, as set forth in Table 1 of the TI.

b. Findings

No findings were identified.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On January 16, 2012, the inspector presented inspection results to Mr. B. Ford, Senior

Licensing Manager (Corporate), and other members of the licensees staff. The licensee

acknowledged the issues presented. The inspector asked the licensee whether any materials

examined during the inspection should be considered proprietary. Any proprietary

documentation that was reviewed during the inspection was returned to the licensee or

disposed of appropriately.

The lead inspector obtained the final annual examination results and telephonically exited with

Mr. R. Collins, Superintendent, Simulator Support and Training, on February 6, 2013. The

inspector did not review any proprietary information during this inspection.

On March 1, 2013, the inspectors presented the final inspection results for the tri-annual heat

exchanger inspection, to Jay Miller, General Manager, Plant Operations, and other members of

the licensee staff. The licensee acknowledged the issues presented. The inspector asked the

licensee whether any materials examined during the inspection should be considered

proprietary. No proprietary information was identified.

On April 11, 2013, the inspectors presented the inspection results to Kevin Mulligan, Site Vice

President of Operations, and other members of the licensee staff. The licensee acknowledged

the issues presented. The inspector asked the licensee whether any materials examined during

the inspection should be considered proprietary. No proprietary information was identified.

4OA7 Licensee-Identified Violations

None.

- 41 -

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

W. Barlow, Heat Exchanger System Engineer

M. Causey, Senior Lead Technical Specialist

D. Chipley, Electrical Design Engineer

R. Collins, Superintendent, Simulator Support and Training

J. Dorsey, Security Manager

W. Drinkard, RHR System Engineer

H. Farris, Assistant Operations Manager

J. Gerard, Interim Operations Manager

J. Giles, Manager, Training

D. Jones, Chief Engineer

C. Justiss, Licensing

V. Kirk, SSW System Engineer

C. Lewis, Manager, Emergency Preparedness

J. Miller, General Plant Manager

R. Miller, Manager, Radiation Protection

K. Mulligan, Site Vice President Operations

L. Patterson, Manager, Program Engineering

C. Perino, Director, Nuclear Safety Assurance

R. Scarbrough, Specialist and Lead Offsite Liaison, Licensing

J. Seiter, Licensing

J. Shaw, Manager, System Engineering

T. Thurmon, Supervisor, Design Engineering-Mechanical

D. Wiles, Engineering Director

A-1 Attachment

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000416/2013002-01 NCV Failure to Properly Seal Safety-related Manholes (Section 1R06.b)05000416/2013002-02 NCV Failure to Monitor for Ice on Standby Service Water Towers

(Section 1R13.b)05000416/2013002-03 NCV Failure to Maintain Design Control for Setpoint Calculations

(Section 1R15.b)05000416/2013002-04 NCV Failure to Correct a Scaffold Affecting Fire Brigade Access

(Section 1R22.b)05000416/2013002-05 FIN Automatic Reactor Scram Caused by Ground Condition on the A

Phase Neutral Current Transformer (Section 4OA3.1.b)05000416/2013002-06 NCV Inadequate Procedure for Removal of a Foreign Material Exclusion

Plug (Section 4OA3.1.b)05000416/2013002-07 FIN Reactor Scram Due to Moisture in Isophase Bus Duct

(Section 4OA3.2.b)05000416/2013002-08 NCV Failure to Revise the Scram Procedure After Temporary

Modification (Section 4OA3.2.b)

Discussed

Temporary Instruction TI Review of the Implementation of the Industry Initiative to Control

2515/182 Degradation of Underground Piping and Tanks

A-2

LIST OF DOCUMENTS REVIEWED

Section 1R01: Adverse Weather Protection

PROCEDURES

NUMBER TITLE REVISION

04-1-01-N71-3 System Operating Instruction Auxiliary Cooling Tower 19

System

EN-IS-119 Emergency Evacuation 3

06-TE-1000-V- Culvert No. 1 Embankment Stability Inspection/Survey 100

0001

05-1-02-VI-2 Off Normal Event Procedure Hurricanes, Tornados, and 120

Severe Weather

04-1-03-A30-1 Equipment Performance Instruction, Cold Weather 23

Protection

04-1-01-P41-1 Standby Service Water System 136

OTHER DOCUMENTS

NUMBER TITLE REVISION

96/1022-00 Engineering Request Form, GGCR 1996-0553-00, GNRI 2

97/00074

CONDITION REPORTS

CR-GGN-2012-00143 CR-GGN-2012-04068 CR-GGN-2012-09928

CR-GGN-2012-00180 CR-GGN-2012-04644 CR-GGN-2012-09929

CR-GGN-2012-00188 CR-GGN-2012-05679 CR-GGN-2012-10158

CR-GGN-2012-00236 CR-GGN-2012-06941 CR-GGN-2012-10167

CR-GGN-2012-00251 CR-GGN-2012-08978 CR-GGN-2012-10174

CR-GGN-2012-00489 CR-GGN-2012-09113 CR-GGN-2012-10804

CR-GGN-2012-00493 CR-GGN-2012-09235 CR-GGN-2012-11203

CR-GGN-2012-01673 CR-GGN-2012-09454 CR-GGN-2012-12145

CR-GGN-2012-02744 CR-GGN-2012-09807 CR-GGN-2012-12564

CR-GGN-2012-03201 CR-GGN-2012-09921 CR-GGN-2013-00233

A-3

CR-GGN-2013-00426 CR-GGN-2012-00361 CR-GGN-2013-00758

CR-GGN-2013-00717 CR-GGN-2013-00426

WORK ORDERS

WO 52377825 01

Section 1R04: Equipment Alignment

PROCEDURES

NUMBER TITLE REVISION

04-1-01-E51-1 System Operating Instruction, Reactor Core Isolation 131

Cooling

04-1-01-E12-1 System Operating Instruction, Residual Heat Removal A 142

EN-MA-132 Housekeeping/Facility and Grounds Maintenance 3

01-S-07-9 Industrial Safety and Housekeeping Inspections 29

04-1-01-T48-1 System Operating Instruction: Standby Gas Treatment 34

04-1-01-E21-1 System Operating Instruction: Low Pressure Core Spray 38

01-S-07-43 Control of Loose Items, Temporary Electrical Power, and 6

Access to Equipment

EN-IS-111 General Industrial Safety Requirements 12

EN-MA-133 Control of Scaffolding 9

04-1-01-C71-1 System Operating Instruction: Reactor Protector System 33

OTHER DOCUMENTS

NUMBER TITLE REVISION

System Health Report: E21- Low Pressure Core Spray April 3, 2013

GLP-OPS-E2100 Operator Training: Low Pressure Core Spray (LPCS) 10

System - E21

GFIG-OPS- Figure 4, LPCS Pump and Valve Control Logic

E2100

GFIG-OPS- Figure 1, Low Pressure Core Spray (LPCS) System

E2100

E21 Low Pressure Core Spray System Power Point

Presentation

A-4

CONDITION REPORTS

CR-GGN-2013-00656 CR-GGN-2013-00729 CR-GGN-2013-00740

CR-GGN-2009-02069 CR-GGN-2009-05418 CR-GGN-2009-05763

CR-GGN-2009-02073 CR-GGN-2009-05419 CR-GGN-2009-05764

CR-GGN-2009-02085 CR-GGN-2009-05422 CR-GGN-2009-05766

CR-GGN-2009-02131 CR-GGN-2009-05425 CR-GGN-2009-05771

CR-GGN-2009-02682 CR-GGN-2009-05426 CR-GGN-2009-05772

CR-GGN-2009-03291 CR-GGN-2009-05440 CR-GGN-2009-05777

CR-GGN-2009-04468 CR-GGN-2009-05441 CR-GGN-2009-05778

CR-GGN-2009-04543 CR-GGN-2009-05444 CR-GGN-2009-05779

CR-GGN-2009-04855 CR-GGN-2009-05452 CR-GGN-2009-05780

CR-GGN-2009-04886 CR-GGN-2009-05474 CR-GGN-2009-05804

CR-GGN-2009-04901 CR-GGN-2009-05485 CR-GGN-2009-05806

CR-GGN-2009-04902 CR-GGN-2009-05487 CR-GGN-2009-05818

CR-GGN-2009-04919 CR-GGN-2009-05515 CR-GGN-2009-05822

CR-GGN-2009-04930 CR-GGN-2009-05521 CR-GGN-2010-00187

CR-GGN-2009-04951 CR-GGN-2009-05541 CR-GGN-2010-01240

CR-GGN-2009-04956 CR-GGN-2009-05544 CR-GGN-2010-05456

CR-GGN-2009-04959 CR-GGN-2009-05601 CR-GGN-2010-05991

CR-GGN-2009-04964 CR-GGN-2009-05612 CR-GGN-2011-00237

CR-GGN-2009-04965 CR-GGN-2009-05613 CR-GGN-2011-01275

CR-GGN-2009-04971 CR-GGN-2009-05620 CR-GGN-2011-03259

CR-GGN-2009-04983 CR-GGN-2009-05621 CR-GGN-2011-04014

CR-GGN-2009-04985 CR-GGN-2009-05622 CR-GGN-2011-05888

CR-GGN-2009-04987 CR-GGN-2009-05632 CR-GGN-2011-05889

CR-GGN-2009-04991 CR-GGN-2009-05635 CR-GGN-2011-06174

CR-GGN-2009-04994 CR-GGN-2009-05638 CR-GGN-2012-03280

A-5

CR-GGN-2009-04995 CR-GGN-2009-05655 CR-GGN-2012-03840

CR-GGN-2009-04998 CR-GGN-2009-05658 CR-GGN-2012-05363

CR-GGN-2009-05033 CR-GGN-2009-05659 CR-GGN-2012-05370

CR-GGN-2009-05084 CR-GGN-2009-05660 CR-GGN-2012-05455

CR-GGN-2009-05101 CR-GGN-2009-05680 CR-GGN-2012-05524

CR-GGN-2009-05114 CR-GGN-2009-05681 CR-GGN-2012-05536

CR-GGN-2009-05136 CR-GGN-2009-05708 CR-GGN-2012-05799

CR-GGN-2009-05158 CR-GGN-2009-05713 CR-GGN-2012-06454

CR-GGN-2009-05206 CR-GGN-2009-05721 CR-GGN-2012-06699

CR-GGN-2009-05244 CR-GGN-2009-05749 CR-GGN-2012-09264

CR-GGN-2009-05263 CR-GGN-2009-05751 CR-GGN-2012-09896

CR-GGN-2009-05343 CR-GGN-2009-05753 CR-GGN-2012-10030

CR-GGN-2009-05350 CR-GGN-2009-05756 CR-GGN-2012-10053

CR-GGN-2009-05353 CR-GGN-2009-05757 CR-GGN-2012-10148

CR-GGN-2009-05361 CR-GGN-2009-05758 CR-GGN-2012-11652

CR-GGN-2009-05415 CR-GGN-2009-05759 CR-GGN-2013-00985

CR-GGN-2013-01881 CR-GGN-2013-02300

ENGINEERING CHANGES

EC No.: 26182, Rev 0 EC No.: 28897, Rev 0 EC No.: 25801, Rev 0

WORK ORDERS

WO 00284166 01

Section 1R05: Fire Protection

PROCEDURES

NUMBER TITLE REVISION

06-OP-SP64-M- Unit I Fire Hose Station and Fire Extinguisher Maintenance 115

0047

Fire Pre-Plan A- Set Down Are Passage - 1A424, Spent Fuel Cask Handling 1

A-6

Section 1R05: Fire Protection

PROCEDURES

NUMBER TITLE REVISION

35 Area - 1A427, Set Down Area Passage - 1A428, Water

Sampling Station - 1A429, Set Down Area Passage - 1A434

Fire Pre-Plan A- Misc Equip Area Passages 1A403 & 1A420 Area 7 Elevation 0

31 166

Fire Pre-Plan A- Motor Control Center Room 1A410 Area 7 Elevation 166 0

33

Fire Pre-Plan A- Motor Control Center Room 1A407 Area 8 Elevation 166 0

32

Fire Pre-Plan A- Passage Area - 1A401, Misc Equip Area - 1A417, Area 1

29 Elevation 166

EN-TQ-125 Fire Brigade Drills, February 12, 2013 1

DRAWINGS

NUMBER TITLE REVISION

M-7103 Hose Station and Fire EXT. Locations Auxiliary Building and 1

Containment Plan at Elevation 161-10 and 166-0 Unit 1

CONDITION REPORTS

CR-GGN-2013-00932 CR-GGN-2013-00994 CR-GGN-2013-00974

CR-GGN-2013-01348 CR-GGN-2013-01371

Section 1R06: Flood Protection Measures

OTHER DOCUMENTS

NUMBER TITLE

9645-E-029.0 Technical Specification for 9,000-volt Power Cable

CONDITION REPORTS

CR-GGN-2013-00406 CR-GGN-2013-00403 CR-GGN-2012-12482

CR-GGN-2012-05620 CR-GGN-2013-00520 CR-GGN-2013-01348

A-7

CR-GGN-2013-01364

WORK ORDERS

WO 52425152 01 WO 52425153 01 WO 52462227 01

WO 52463541 01 WO 52464573 01 WO 00322812 01

WO 00308173 01 WO 00307759 01 WO 00303319 01

WO 00342828 01 WO 00342829 01 WO 00264016 01

Section 1R07: Heat Sink Performance

PROCEDURES

NUMBER TITLE REVISION

04-1-03-P41-2 SSW B Chemical Addition Run 6

04-1-03-P41-3 SSW C Chemical Addition Run 2

06-OP-1P41-M-0001 HPCS Service Water Operability Check 101

06-OP-1P41-M-0004 Standby Service Water (SSW) Loop A Operability 109

Check

06-OP-1P41-M-0005 Standby Service Water (SSW) Loop B Operability 112

Check

06-OP-1P41-Q-0004 Standby Service Water Loop A Valve and Pump 121

Operability Test

06-OP-1P41-Q-0006 HPCS Service Water System Valve and Pump 113

Operability Test

08-S-03-10 Chemistry Sampling Program 49

A-8

Section 1R07: Heat Sink Performance

PROCEDURES

NUMBER TITLE REVISION

17-S-03-29 GL-89-13 Thermal Performance Data Collection and 6

Analysis

17-S-06-22 SSW A Performance 12

EN-DC-316 Heat Exchanger Performance and Condition 4

Monitoring

EN-DC-325 Component Performance Monitoring 7

EN-EP-S-039-G Testing Standard for Safety-Related Heat 2

Exchangers Cooled by Standby Service Water

CALCULATIONS

NUMBER TITLE REVISION

8.9.2-N Alternate Shutdown Cooling 1

MC-Q1P41-09008 Tornado, Seismic and Thermal Performance Analysis of the 0

Stainless Steel Fill Replacement for SSW Cooling Towers

MC-Q1P41-11001 GGNS Standby Service Water Ultimate Heat Sink Thirty 0

Day Performance at EPU

MC-Q1P41-86007 Standby Service Water Ultimate Heat Sink Performance 0

MC-Q1P41-97020 Determination of Minimum Allowable SSW Flows (LOCA 9

Lineup) to Safety Related Heat Exchangers

MC-Q1P81-97034 Division 3 Engine Heat Rejection Rate 0

A-9

DRAWINGS

NUMBER TITLE REVISION

105D5106 Interface Control Pump & Motor First Made for Residual

Heat Removal System

5-046-12-102-004 Engine Jacket Water Cooler #12102 CPK 1

M-087.0- Outline Induction Motor 0

Q1P41C001A-A-

1.1-004

M-92200 CCW Heat Exchanger 6

VPF-KA3636-013 Heat Exchanger Specification Sheet - Jacket Water A

Cooler

OTHER DOCUMENTS

NUMBER TITLE REVISION/

DATE

1E12C002B - RHR B Seal Cooler Flow Rate February 22,

2013

1P41C001B - SSW B Pump Motor Cooler Flow Rate February 22,

2013

Heat Exchanger Program Health Report February 5, 2013

List of Generic Letter 89-13 Heat Exchanger Baseline February 28,

Eddy Current Testing Dates and Work Orders 2013

PM Basis for Heat Exchangers 2

Service Water System Health Report February 5, 2013

A-10

OTHER DOCUMENTS

NUMBER TITLE REVISION/

DATE

AECM-90/0007 Response to Generic Letter 89-13; Service Water January 29, 1990

System Problems Affecting Safety-Related Equipment

Attachment to Spec. Heat Exchanger Data Sheet - Component Cooling 5

No. 9645-M-072.0 Water Heat Exchangers

CCE-2006-002 Allow for all Water-to-Water Heat Exchangers to be May 2, 2006

Maintained through the Preventive Maintenance

Program

EPRI NP-7552 Heat Exchanger Performance Monitoring December 1991

EPRI TR-108009 Balance-of-Plant Heat Exchanger Condition December 1999

Assessment and Inspection Guide

EPRI TR-108923 Recommended Cleaning Practices for Service Water December 1997

Systems

GNRI-95/00044 Issuance of Amendment No. 120 to Facility Operating February 21,

License No. NPF-29 - Grand Gulf Nuclear Station, 1995

Unit 1 (TAC No. M88101)

NDEN-0250-000- Diesel Jacket Water Cooler - P81B00A - Final Report January 24, 2012

2011

UFSAR 15.2.6 Loss of AC Power 10

UFSAR 15.6.5 Loss-of-Coolant Accidents (Resulting from Spectrum LDC 03059

of Postulated Piping Breaks Within the Reactor

Coolant Pressure Boundary - Inside Containment)

UFSAR 9.2.2 Component Cooling Water System 0

UFSAR 9.5.5 Diesel Generator Cooling Water System 0

A-11

OTHER DOCUMENTS

NUMBER TITLE REVISION/

DATE

UFSAR Figure 9.2- Component Cooling Water System LDC 03009

10

UFSAR Figure 9.2-9 Component Cooling Water System LBDCR 11028

UFSAR Figure 9.5- Jacket Water System w/ Heat Exchanger LDC 03009

15

UFSAR Table 9.2-4 Standby Service Water System Component LDC 02022

Description

UFSAR Table 9.2-7 Component Cooling Water System Component LDC 01039

Description

UFSAR Table 9.5-3 Diesel Generator Cooling Water System Component LDC 97085

Data

VENDOR DOCUMENTS

NUMBER TITLE REVISION

21A9236 Engine-Generator for High Pressure Core Spray 5

System

21A9236AN Engine-Generator for High Pressure Core Spray 2

System

CONDITION REPORTS

CR-GGN-2010-00706 CR-GGN-2010-01465 CR-GGN-2010-01852

CR-GGN-2010-02342 CR-GGN-2011-00661 CR-GGN-2011-02384

A-12

CR-GGN-2011-05752 CR-GGN-2011-08010 CR-GGN-2011-08030

CR-GGN-2012-03613 CR-GGN-2012-04641 CR-GGN-2012-05501

CR-GGN-2012-09993 CR-GGN-2012-12060 CR-GGN-2012-12320

CR-GGN-2011-05009 CR-GGN-2012-09699 CR-GGN-2013-01491

CR-GGN-2010-04252 CR-GGN-2010-07957 CR-GGN-2011-00508

CR-GGN-2011-03037 CR-GGN-2011-03700 CR-GGN-2011-04951

CR-GGN-2011-08034 CR-GGN-2011-09163 CR-GGN-2012-01802

CR-GGN-2012-05788 CR-GGN-2012-06071 CR-GGN-2012-06676

CR-GGN-2012-12391 CR-GGN-2012-12398 CR-GGN-2010-05825

CR-GGN-2013-01492 CR-GGN-2013-01525

WORK ORDERS

WO 00310321 WO 50321488 WO 51794365

WO 00282182 WO 00283434 WO 00279043

WO 51512610 WO 00277934 WO 00219937

WO 52232784 WO 52370477

Section 1R11: Licensed Operator Requalification Program

OTHER DOCUMENTS

NUMBER TITLE REVISION /

DATE

List of Modifications that need to be made on TREX Load per January 10,

Control Room Walkdown 2013

A-13

Section 1R11: Licensed Operator Requalification Program

OTHER DOCUMENTS

NUMBER TITLE REVISION /

DATE

2013 Cycle 8 Licensed Operator Requal Simulator Training 1

Plan Simulator Differences

Operating Test Results December

20, 2012

Modifications that need to be made to the TREX load for February 25,

simulator training cycle 9, 2013 per Control Room walkdown 2013

2013 Cycle 9 Licensed Operator Requal Simulator Training 0

Plan Simulator Differences

GSMS-LOR- APRM Downscale/Loss of Condenser 19

WEX17 Vacuum/LOCA/Degraded ECCS (EP-2, EP-3)

GIN 2013/00050 Simulator Evaluation on March 11, 2013 D Shift March 11,

2013

Section 1R12: Maintenance Effectiveness

PROCEDURES

NUMBER TITLE REVISION /

DATE

EN-DC-205, Maintenance Rule Functional Failure Evaluation Template, December 1,

Attachment 9.1 CR-GGN-2011-08669 2011

EN-DC-204 Maintenance Rule Scope and Basis 2

EN-DC-150 Condition Monitoring of Maintenance Rule Structures 2

EN-DC-205 Maintenance Rule Monitoring 4

ER-GG-2002- Evaluate Division I and II Diesel Generators (P75) to 0

0466-000 determine if the governor setup complies with Reg. Guide 1

A-14

CALCULATIONS

NUMBER TITLE REVISION

MC-Q1P75- Standby Diesel Jacket Water Operating Parameters 1

98030

MC-Q1111-01005 Determination of Component Design Minimum Wall 1

Thickness for Internal Erosion/Corrosion Program Plan

(GGNS-MS-41) and Components Inspected per CR-GGN-

2001-0955, CA-006 and 009

OTHER DOCUMENTS

NUMBER TITLE REVISION

MS-38 Document Revision Notice,06-566 2

SDC-P75 Document Revision Notice, 05-1803 1

SEP-ISI-102 Program Section for ASME Section XI, Division 1 Inservice 1

Inspection Program

ENGINEERING CHANGES

EC # 0000007894

CONDITION REPORTS

CR-GGN-2011-04160 CR-GGN-2011-08686 CR-GGN-2011-09183

CR-GGN-2011-04622 CR-GGN-2011-08716 CR-GGN-2011-09257

CR-GGN-2011-05074 CR-GGN-2011-08725 CR-GGN-2011-09310

CR-GGN-2011-05488 CR-GGN-2011-08728 CR-GGN-2012-00471

CR-GGN-2011-05667 CR-GGN-2011-09096 CR-GGN-2012-00855

CR-GGN-2011-06494 CR-GGN-2011-09115 CR-GGN-2012-06863

CR-GGN-2011-06513 CR-GGN-2011-09155 CR-GGN-2012-07922

CR-GGN-2011-06591 CR-GGN-2011-09156 CR-GGN-2012-07935

CR-GGN-2011-06595 CR-GGN-2011-09166 CR-GGN-2012-08708

CR-GGN-2011-06937 CR-GGN-2011-09168 CR-GGN-2012-09276

CR-GGN-2011-08663 CR-GGN-2011-09169 CR-GGN-2012-09697

CR-GGN-2011-08669 CR-GGN-2011-09181 CR-GGN-2012-10754

A-15

CR-GGN-2004-04447 CR-GGN-2008-02177 CR-GGN-2010-00629

CR-GGN-2011-00070 CR-GGN-2011-01868 CR-GGN-2011-08716

CR-GGN-2012-05896 CR-GGN-2012-08708 CR-GGN-2010-00507

CR-GGN-2010-00532 CR-GGN-2010-00641 CR-GGN-2012-10918

CR-GGN-2012-10960 CR-GGN-2011-05211 CR-GGN-2012-07430

CR-GGN-2012-11140 CR-GGN-2011-05414 CR-GGN-2012-07666

CR-GGN-2012-11142 CR-GGN-2011-05747 CR-GGN-2012-07675

CR-GGN-2012-11177 CR-GGN-2011-06018 CR-GGN-2012-07816

CR-GGN-2012-11179 CR-GGN-2011-06530 CR-GGN-2012-08101

CR-GGN-2012-11404 CR-GGN-2011-06533 CR-GGN-2012-08136

CR-GGN-2012-11545 CR-GGN-2011-07559 CR-GGN-2012-08139

CR-GGN-2012-11687 CR-GGN-2011-07670 CR-GGN-2012-08169

CR-GGN-2012-11898 CR-GGN-2011-07735 CR-GGN-2012-08235

CR-GGN-2012-11899 CR-GGN-2011-07884 CR-GGN-2012-08236

CR-GGN-2012-11921 CR-GGN-2011-07909 CR-GGN-2012-08238

CR-GGN-2012-12510 CR-GGN-2011-07912 CR-GGN-2012-08268

CR-GGN-2012-12514 CR-GGN-2011-07958 CR-GGN-2012-08285

CR-GGN-2012-12518 CR-GGN-2011-07968 CR-GGN-2012-08652

CR-GGN-2012-12544 CR-GGN-2011-08079 CR-GGN-2012-08692

CR-GGN-2012-12685 CR-GGN-2011-08404 CR-GGN-2012-08810

CR-GGN-2012-12812 CR-GGN-2011-08750 CR-GGN-2012-09325

CR-GGN-2012-12877 CR-GGN-2011-09354 CR-GGN-2012-09716

CR-GGN-2012-12968 CR-GGN-2011-09371 CR-GGN-2012-09775

CR-GGN-2012-13080 CR-GGN-2012-00057 CR-GGN-2012-09839

CR-GGN-2012-13091 CR-GGN-2012-00072 CR-GGN-2012-09903

CR-GGN-2012-13242 CR-GGN-2012-00074 CR-GGN-2012-09996

CR-GGN-2013-00024 CR-GGN-2012-00145 CR-GGN-2012-09997

A-16

CR-GGN-2013-00059 CR-GGN-2012-00652 CR-GGN-2012-10026

CR-GGN-2013-00076 CR-GGN-2012-01156 CR-GGN-2012-10048

CR-GGN-2013-00090 CR-GGN-2012-01833 CR-GGN-2012-10172

CR-GGN-2013-00201 CR-GGN-2012-03913 CR-GGN-2012-10180

CR-GGN-2013-00217 CR-GGN-2012-03958 CR-GGN-2012-10291

CR-GGN-2013-00331 CR-GGN-2012-04050 CR-GGN-2012-10395

CR-GGN-2013-00337 CR-GGN-2012-04194 CR-GGN-2012-10594

CR-GGN-2013-00416 CR-GGN-2012-04424 CR-GGN-2012-10600

CR-GGN-2013-00473 CR-GGN-2012-04441 CR-GGN-2012-10616

CR-GGN-2013-00619 CR-GGN-2012-04845 CR-GGN-2012-10719

CR-GGN-2013-00690 CR-GGN-2012-05411 CR-GGN-2012-10722

CR-GGN-2013-00924 CR-GGN-2012-06723 CR-GGN-2012-10745

CR-GGN-2013-00978 CR-GGN-2012-07236 CR-GGN-2012-10866

CR-GGN-2013-01014 CR-GGN-2012-07371 CR-GGN-2012-10877

CR-GGN-2012-00303

Section 1R13: Maintenance Risk Assessment and Emergent Work Controls

PROCEDURES

NUMBER TITLE REVISION /

DATE

EN-WM-101, Online Emergent Work Add/Delete Approval form for the 9

Attachment 9.1 week of January 7, 2013

05-1-02-VI-2 Hurricanes, Tornados and Severe Weather, February 10, 120

2013 Entry

01-S-07-43 Control of Loose Items, Temporary Electrical Power, and 6

Access to Equipment

EN-EP-302 Severe Weather Response 0

EN-EP-303 Severe Weather Recovery 0

EN-IS-111 General Industrial Safety Requirements 12

EN-IS-123 Electrical Safety 9

A-17

Section 1R13: Maintenance Risk Assessment and Emergent Work Controls

PROCEDURES

NUMBER TITLE REVISION /

DATE

EN-MA-119 Material Handling Programs 15

EN-WM-104 On Line Risk Assessment 7

07-S-05-300 Control and use of Cranes and Hoists 113

06-TE-1000-V- Culvert No. 1 Embankment Stability Inspection\Survey 100

0001

05-1-02-VI-2 Hurricanes, Tornados and Severe Weather, February 12, 120

2013 Entry

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 7,

Description and Justification, WO 52462497-01 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 6,

Description and Justification, WO 52447574-01 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification, WO 52369078 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 7,

Description and Justification, WO 52363905 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 6,

Description and Justification, WO 338638-03 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification, WO 52462496 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification, WO Ops SOI 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 7,

Description and Justification, WO 52449563 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 7,

Description and Justification, WO 340986 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification, WO 52323348 01 2013

A-18

Section 1R13: Maintenance Risk Assessment and Emergent Work Controls

PROCEDURES

NUMBER TITLE REVISION /

DATE

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification, WO 52362522 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification, WO Dry Tube Strong Back 2013

Shipment

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 15,

Description and Justification, WO 52370068-01, 00340429- 2013

01, 52457198-01, 52457199-01

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 15,

Description and Justification, WO 52370068-01, 00340429- 2013

01, 52457198-01, 52457199-01, 52457197-01, 52455988-01,

52455987-01

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 14,

Description and Justification, WO 52421734-01 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification, WO 52452186-01, 52452186- 2013

02, 52452186-03, 52452186-04

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification, WO 52461116-01 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 14,

Description and Justification, WO 52456138, 52453953, 2013

52453954

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 7,

Description and Justification, WO 52459533 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 7,

Description and Justification, WO 52340213 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 14,

Description and Justification, WO 52453952-01, 52456129- 2013

01, 52456130-01

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 13,

Description and Justification, WO 52366069 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 13,

Description and Justification, WO 298667 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 13,

A-19

Section 1R13: Maintenance Risk Assessment and Emergent Work Controls

PROCEDURES

NUMBER TITLE REVISION /

DATE

Description and Justification, WO 341597-01, 341598-01, 2013

298713

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 11,

Description and Justification, WO 263365 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 5,

Description and Justification, WO 336528 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 12,

Description and Justification, Component ID P41C003C and 2013

D

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 13,

Description and Justification, WO 324771 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- February 12,

Description and Justification, WO 52455992, 52456139 2013

05-1-02-VI-2 Hurricanes, Tornados and Severe Weather, February 10, 120

2013 Entry

05-1-02-VI-2 Hurricanes, Tornados and Severe Weather, February 21, 120

2013 Entry

05-1-02-VI-2 Hurricanes, Tornados and Severe Weather, February 25, 120

2013 Entry

05-1-02-VI-2 Hurricanes, Tornados and Severe Weather, March 18-19, 120

2013 Entry

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- March 19,

Description and Justification, WO 345315 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- March 19,

Description and Justification, Various Work Orders 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- March 19,

Description and Justification, WO 302233 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- March 20,

Description and Justification, WO 52341331 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- March 20,

Description and Justification, WO 263743 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- March 20,

A-20

Section 1R13: Maintenance Risk Assessment and Emergent Work Controls

PROCEDURES

NUMBER TITLE REVISION /

DATE

Description and Justification, WO 341060 and 341071 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- March 20,

Description and Justification, WO 51662321-01 2013

EN-WM-101 Online Emergent Work Add/Delete Approval Form, Section A- March 20,

Description and Justification, WO 52472683, 52474315, 2013

52453420-01, 52472679-01, 52472679-02, 52453420-02

05-1-02-VI-2 Hurricanes, Tornados and Severe Weather, March 23, 2013 120

Entry

01-S-02-3 Temporary Change Notice, Directive # 01-S-18-6 June 28,

2012

02-S-01-17 Control of Limiting Conditions for Operation 124

01-S-18-6 Qualitative Risk Considerations for External Events, Level 2 011

SSCs, SSCs not in EOOS, & SSCs not Modeled

Appropriately

05-1-02-VI-2 Hurricanes, Tornados, and Severe Weather 122

OTHER DOCUMENTS

NUMBER TITLE DATE

Shutdown Condition 1, Time to 200 degrees F, .25 hour2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br />s: January 27,

Day 12.5 2013, 11:05 am

Shutdown Condition 1, Time to 200 degrees F, .5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />s: January 27,

Day 12 2013, 5:30 am

Shutdown Condition 1, Time to 200 degrees F, .85 hour9.837963e-4 days <br />0.0236 hours <br />1.405423e-4 weeks <br />3.23425e-5 months <br />s: January 26,

Day 12 2013, 7:15pm

Shutdown Condition 1, Time to 200 degrees F, .85 hours9.837963e-4 days <br />0.0236 hours <br />1.405423e-4 weeks <br />3.23425e-5 months <br /> January 26,

2013, 1:27 am

Shutdown Condition 1, Time to 200 degrees F, .8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />s: January 25,

Day 11 2013, 7:05 pm

Shutdown Condition 1, Time to 200 degrees F, .75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> January 24,

2013, 7:42 am

Shutdown Condition 1, Time to 200 degrees F, .75 hour8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br />s: January 24,

Day 9 2013, 2:10 am

A-21

OTHER DOCUMENTS

NUMBER TITLE DATE

Shutdown Condition 1, Time to 200 degrees F, .7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> January 23,

2013, 2:58 pm

Shutdown Condition 1, Time to 200 degrees F, .7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> January 23,

2013, 2:20 am

Shutdown Condition 1, Time to 200 degrees F, .7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> January 22,

2013, 4:43 pm

Shutdown Condition 1, Time to 200 degrees F, .65 hours7.523148e-4 days <br />0.0181 hours <br />1.074735e-4 weeks <br />2.47325e-5 months <br /> January 22,

2013, 1:00 am

Shutdown Condition 1, Time to 200 degrees F, .65 hours7.523148e-4 days <br />0.0181 hours <br />1.074735e-4 weeks <br />2.47325e-5 months <br /> January 21,

2013, 1:45 am

Shutdown Condition 1, Time to 200 degrees F, .65 hours7.523148e-4 days <br />0.0181 hours <br />1.074735e-4 weeks <br />2.47325e-5 months <br /> January 21,

2013, 12:00 pm

Shutdown Condition 1, Time to 200 degrees F, .6 hour6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />s: January 20,

Day 5 2013, 4:00 pm

Shutdown Condition 1, Time to 200 degrees F, .6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> January 20,

2013, 4:30 am

Shutdown Condition 1, Time to 200 degrees F, .5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />s: January 18,

Day 3 2013, 7:00 am

Shutdown Condition 1, Time to 200 degrees F, .45 hour5.208333e-4 days <br />0.0125 hours <br />7.440476e-5 weeks <br />1.71225e-5 months <br />s: January 17,

Day 3 2013, 5:00 pm

Shutdown Condition 1, Time to 200 degrees F, .4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> January 17,

2013, 5:30 am

Shutdown Condition 1, Time to 200 degrees F, .3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />s: January 16,

Day 2 2013, 10:00 am

Shutdown Condition 1, Time to 200 degrees F, .5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> January 15,

2013, 8:30 pm

Shutdown Condition 1, Time to 200 degrees F, .25 hours2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br /> January 15,

2013, 9:50 am

CONDITION REPORTS

CR-GGN-2013-01070

A-22

Section 1R15: Operability Evaluations

PROCEDURES

NUMBER TITLE REVISION

EN-OP-104 Operability Determination Process, April 12, 2012 6

06-IC-1B21-Q- REACTOR VESSEL LOW/HIGH WATER LEVEL (RPS) 106

1003 CALIBRATION SAFETY RELATED

06-IC-1B21-R- REACTOR VESSEL LOW/HIGH WATER LEVEL 107

0002 CALIBRATION SAFETY RELATED

06-IC-1B21-R- SAFETY/RELIEF VALVE HIGH PRESSURE TRIP/LOW LOW 107

0003 RELIEF/ECCS VESSEL PRESSURE INJECTION

PERMISSIVE CALIBRATION SAFETY RELATED

06-IC-1B21-R- REACTOR VESSEL WATER LEVEL 107

0008 CALIBRATION (ECCS}

SAFETY RELATED

06-IC-1821-R- REACTOR VESSEL WATER LEVEL (ADS) (RCIC) 101

0011 CALIBRATION

SAFETY RELATED

06-IC-1B21-R- REACTOR VESSEL WATER LEVEL (LEVELS 1 AND 2) 105

2005 CALIBRATION

SAFETY RELATED

06-IC-1B21-R- REACTOR VESSEL WATER LEVEL (HPCS) 104

2012 CALIBRATION SAFETY RELATED

06-IC-1C11-R- SCRAM DISCHARGE VOLUME HIGH WATER LEVEL (RPS) 105

2001 CALIBRATION SAFETY RELATED

06-IC-1E22-R- SUPPRESSION POOL HIGH WATER LEVEL CALIBRATION 102

0003 (HPCS) SAFETY RELATED

06-IC-1E22-R- HPCS SYSTEM FLOW RATE LOW (BYPASS) 104

0004 CALIBRATION

SAFETY RELATED

06-IC-1E31-R- RCIC/RHR AND RCIC STEAM LINE HIGH FLOW (RCIC 104

0023 ISOL)

CALIBRATION SAFETY RELATED

06-IC-1E31-R- RCIC STEAM SUPPLY LOW PRBSSURE CALIBRATION 103

1016 SAFETY RELATED

06*IC-1E51-R- SUPPRESSION POOL HIGH WATER LEVEL (RCIC) 101

0003 CALIBRATION SAFETY RELATED

A-23

DRAWINGS

NUMBER TITLE

169C9489 Purchase Part Relay

CALCULATIONS

NUMBER TITLE REVISION

MC-Q1P75-91119 Maximum Allowable Leakage From Division I and II 1

Generators Starting Air Storage Tanks

3.8.23-0 Standby Service Water Valve Room 0

MC-Q1P75- Lube Oil Requirements for the Division I and II Diesel 1

90194 Generators

MC-Q1Y47-09011 SSW Pump House Temperature for Normal and Recirculation 0

Flows

MC-Q1Y47- SSW Pump House Temperature During Station Blackout 0

09002 (SBO)

MC-Q1T46-95018 Calculations Sheet 2

MC-Q1T46-96037 ESF Switchgear Room Temperatures with the Room Coolers 0

Out of Service

JC-Q1B21-N616- SAFETY RELIEF LOW/LOW SET SETPOINT 0

1 CALCULATION

JC-Q1B21-N674- LEVEL 8 WIDE RANGE HPCS INJECTION VALVE 0

1 CLOSURE

JC-Q1B21-N680- LEVEL 3 SETPOINT CALCULATION 0

1

JC-Q1B21-N681- Level 1 Setpoint Calculation (Safety Related Tech. Spec.) 0

1

JC-Q1B21-N682- LEVEL 2, SAFETY RELATED. TECH. SPEC., SETPOINT 0

1 CALCULATION

JC-Q1B21-N683- LEVEL 8 NARROW RANGE 0

1

JC-Q1B21-N683- LEVEL 8 NARROW RANGE 1

1

JC-Q1B21-N693- LEVEL 8 NARROW RANGE RCIC TRIP 0

1

A-24

CALCULATIONS

NUMBER TITLE REVISION

JC-Q1B21-N697- LOW PRESSURE ECCS PRESSURE PERMISSIVE 0

1 SETPOINT CALCULATION

JC-Q1C11-N601- INSTRUMENT LOOP UNCERTAINTY AND SETPOINT 1

1 DETERMINATION FOR SYSTEM C71 LOOP N601 SCRAM

REACTOR ON HIGH SDVP WATER LEVEL

JC-Q1C11-N601- INSTRUMENT LOOP UNCERTAINTY AND SETPOINT 2

1 DETERMINATION FOR SYSTEM C71 LOOP N601 SCRAM

REACTOR ON HIGH SDVP WATER LEVEL

JC-Q1E12-N655- INSTRUMENT LOOP UNCERTAINTY AND SETPOINT 1

1 DETERMINATION FOR SYSTEM E12 LOOPS N655 AND

N656 RHR PUMP DISCHARGE PRESSURE PERMISSIVE

FOR ADS

JC-Q1E12-N655- INSTRUMENT LOOP UNCERTAINTY AND SETPOINT 2

1 DETERMINATION FOR SYSTEM E12 LOOPS N655 AND

N656 RHR PUMP DISCHARGE PRESSURE PERMISSIVE

FOR ADS

JC-Q1E22-N651- INSTRUMENT LOOP UNCERTAINTY AND SETPOINT 1

2 DETERMINATION FOR SYSTEM lE22 LOOP N65l

HPCS PUMP MINIMUM FLOW BYPASS VALVE HI

PRESSURE INTERLOCK

JC-Q1E22-N655- INSTRUMENT LOOP UNCERTAINTY AND SETPOINT 1

1 DETERMINATION FOR INSTRUMENT LOOPS 1E22-N655,

1E51-N636 HPCS & RCIC PUMP SUCTION

TRANSFER ON HI SUPPRESSION POOL LEVEL

JC-01E31-N685-1 INSTRUMENT LOOP UNCERTAINTY AND SETPOINT 0

DETERMINATION FOR SYSTEM EJl LOOP N685

RCIC TURBINE ISOLATION ON LOW INLET STEAM

PRESSURE

JC-01E31-N685-1 INSTRUMENT LOOP UNCERTAINTY AND SETPOINT 1

DETERMINATION FOR SYSTEM EJl LOOP N685

RCIC TURBINE ISOLATION ON LOW INLET STEAM

PRESSURE

JC-Q1E51-N655- INSTRUMENT LOOP UNCERTAINTY AND SETPOINT 0

1 DETERMINATION FOR SYSTEM E51 LOOP N655

RCIC TURBINE ISOLATION ON EXHAUST DIAPHRAGM

FAILURE

MC-Q1E22- LEVEL 8 TRIP FOR HPCS AND RCIC 0

12001

A-25

CALCULATIONS

NUMBER TITLE REVISION

EC-Q1111-88002 Thermal Life of Agastat Relays 1

OTHER DOCUMENTS

NUMBER TITLE REVISION /

DATE

ER No. GGNS- Safety Relief Valves Safety Function Lift Setpoint Tolerance 0

96-0005 Relaxation Summary Report

GGNS-SDC-B21 System Design Criteria Nuclear Boiler System 3

460000026 Instructions for Installation and Maintenance Safety Relief

Valves for Steam Service

QDR 0308-90 Quality Deficiency Report form April 30, 1991

9645-M-616.3 Material Requisition: Electric Unit Heaters 11

GGNS-SDC-Y47 Standby Service Water Pump House Ventilation System 1

(Y47)

GGNS-SDC-P75 Standby Diesel Generator System (P75) 1

460000444 Chromalox Forced Air Heater

Model DSRV-16-4 Associated Publications Manual Volume III, Book 1

Diesel

Engine/Generator

10 CFR 50.59 GGNS, EC 42886 9

Evaluation Form

GGNS-NE-11- Review of IRM AL Basis for 24 Month Fuel Cycle 0

00007

GGNS-NE-11- Review of B21-N679-1 and B21-N697-1 Setpoint Basis 0

00006 for 24 Month Fuel Cycle

GGNS-NE-11- Review of E21-N652-1 Setpoint Basis for 24 Month Fuel 0

00008 Cycle

GGNS-NE-11- Review of RWCU Differential Flow 0

00009

GGNS-NE-11- Review of E31-N684-1 Setpoint Basis for 24 Month Fuel 0

00010 Cycle

GGNS-NE-11- RCIC Turbine Exhaust Vent Line Trip and Low Steam 0

00011 Pressure Trip and Isolation AL Bases for 24 Month Fuel Cycle

A-26

OTHER DOCUMENTS

NUMBER TITLE REVISION /

DATE

SCN.98-001 STANDARD/SPECIFICATION CHANGE NOTICE: GGNS- 0

JS-09 Methodology for the Generation of Instrument Loop

Uncertainty & Setpoint Calculations

GEXI2012-00050 Grand Gulf Cycle 19 - Level 8 Setpoint Analytical Limit

Sensitivity

GNRO- License Amendment Request for Revision of Technical

2012/00132 Specification Allowable Value for Primary Containment and

Drywell isolation Instrumentation Function 3.c RCIC Steam

Supply Line Pressure - Low.

NEDC-31336P-A General Electric Instrument Setpoint Methodology

GIN 95-03473 Failure Rate of Agastat Relays December 27,

1995

GGNS-89-0028 Engineering Report on Functionality under High Ambient 2

Conditions of Auxiliary Building ESF Switchgear Room

Equipment Important to Safety

IEEE Std 323- IEEE Standard for Qualifying Class IE Equipment for Nuclear 1971

1974 Power Generating Stations

CONDITION REPORTS

CR-GGN-2013-00318 CR-GGN-2013-00957 CR-GGN-2013-00220

CR-GGN-2013-00810 CR-GGN-2013-00812 CR-GGN-2013-01204

CR-GGN-2013-01019 CR-GGN-2007-05281 CR-GGN-2011-03730

CR-GGN-2012-09971 CR-GGN-2012-11939 CR-GGN-2012-09896

CR-GGN-2012-11841 CR-GGN-2012-09894 CR-GGN-2013-01835

ENGINEERING CHANGES

EC 16428 EC 16989 EC 13993

EC 42886 EC 30652 EC 39574

A-27

WORK ORDERS

WO 00345315 01 EC 16989 EC 13993

Section 1R18: Plant Modifications

DRAWINGS

NUMBER TITLE REVISION

E-1046 Main Generator and Main Transformer CT Connections 009

E-1040 Plant Protection Logic Diagram 011

E-1045 N41 Three Line Meter & Relay Diagram 026

E-1002 One Line Meter & Relay Diagram 016

CONDITION REPORTS

CR-GGN-2012-13290 CR-GGN-2013-00083

ENGINEERING CHANGES

EC 41836 EC 41840 EC 41846

Section 1R19: Post-Maintenance Testing

PROCEDURES

NUMBER TITLE REVISION

06-OP-1C51-V- SRM Channel Function Test 110

0001, Attachment I

06-OP-1C51-V- SRM Channel Function Test 110

0001, Attachment II

06-OP-1G33-Q- Reactor Water Cleanup System Valve Operability 108

0001, Attachment II

06-OP-1M61-V- Local Leak Rate Test-Low Pressure Water 1

0003

06-OP-1E51-Q- RCIC System Quarterly Pump Operability Verification 134

0003

A-28

Section 1R19: Post-Maintenance Testing

PROCEDURES

NUMBER TITLE REVISION

06-OP-1C51-V- IRM Functional Test 107

0002, Attachment I

06-OP-1C51-V- IRM Functional Test 107

0002, Attachment II

04-S-04-2 Operation of Electrical Circuit Breakers 56

07-S-02-2 Special Guidance for the Performance of Electrical 5

Activities

DRAWINGS

NUMBER TITLE REVISION

M-242.0-Q1-1.2- 20 150 Pound Swing Check Valve Weld End with Outside 4

101 Lever and Weight

OTHER DOCUMENTS

NUMBER TITLE REVISION /

DATE

SRM and IRM Troubleshooting

BWR Owners Group Valve Technical Resolution Group, Final April 30, 1996

Report: Appendix J-Generic Letter 89-10 Correlation

0900596 Structural Integrity Associates, Baseline Risk Implementation A

Analysis: Grand Gulf Nuclear Station

HVA TD Report Summary: ESF-11 Second Test February 13,

2013

HVA TD Report Summary: ESF-11 Final Test February 13,

2013

Two-winding Transformer, Service Transformer 11 February 6,

2013

Pre-Maintenance Service Transformer 11 March 9,

2009

Two-Winding Transformer Data Sheet

GEK 42296 GE Motor Generator Package Set, Model 6PA4326A103 1

A-29

CONDITION REPORTS

CR-GGN-2013-00435 CR-GGN-2013-00440 CR-GGN-2013-00687

CR-GGN-2013-00689 CR-GGN-2013-00692 CR-GGN-2013-00696

CR-GGN-2013-00736 CR-GGN-2013-00738 CR-GGN-2013-00739

CR-GGN-2013-01027 CR-GGN-2013-01020 CR-GGN-2013-01035

WORK ORDERS

WO 00338860 01 WO 00338860 04 WO 319783

WO 52306016 01 WO 00089947 01 WO 00237152 01

WO 00299863 01 WO 00340488 01 WO 00335727 01

WO 00317521 01 WO 00337745 01 WO 00337245 02

WO 52411201 01 WO 52411202 05 WO 00295355 01

WO 00295355 05 WO 00332005 01 WO 00332006 01

WO 52386967 01, 09, 11 WO 00341598 01 WO 00331994 01

WO 00316857 01 WO 52463180 01 WO 00345940 01, 02

WO 00341915 01 WO 00265232 01 WO 52323390 01

ENGINEERING CHANGES

EC 43454

A-30

Section 1R20: Refueling and Other Outage Activities

PROCEDURES

NUMBER TITLE REVISION

07-S-12-128 Isolated Phase BUS Attachment Sheet General Location, 2

Page 1

01-S-06-12 GGNS Surveillance Program 111

03-1-01-1 Cold Shutdown to Generator Carrying Minimum Load 154

EN-OP-115 Conduct of Operations 13

EN-OP-103 Reactivity Management Program 5

07-S-12-128 General Maintenance Instruction, Isolated Phase BUS 2

Attachment Sheet General Location

03-1-01-3 Integrated Operating Instruction Plant Shutdown 122

DRAWINGS

NUMBER TITLE REVISION

D-7208-11-A2 22KV, 25,600A, 125 KV B11 Existing BUS Layout With 1.P.B

Modifications

T-157102 Assembly of Flexible Disconnect Links & Housing-Links

Installed

Isophase Air Flow Diagram

Isophase Air Flow Simplified Diagram

E-1045 N41 Three Line Meter & Relay Diagram Generator and Main 26

Transformer

Trouble Shooting Plan, BUS Duct Side

OTHER DOCUMENTS

NUMBER TITLE REVISION /

DATE

DC HIPOT/MEGGER, ISO-PHASE BUS January 24,

2013

Remaining Open Actions and Operability Information for CRs January 24,

with ODMI Flags 2013

Unassigned CRs January 24,

2013

A-31

OTHER DOCUMENTS

NUMBER TITLE REVISION /

DATE

Cycle 19 Outage, OPS Cold Shutdown surv review, By Performance (Yes or 0

FO-19-04 No)

Remaining Open Actions for Open GGN CRs with January 24,

Operability Code: OPERABLE DNC or OPERABLE_COMP 2013

MEAS

N21F010B Action Plan per 01-S-06-26 step 6.2.7

N36F012B Action Plan per 01-S-06-26 step 6.2.7, 6B

Feeder/Bleeder trip valve

Restart Evaluation for Scram 128

Failure Mode Analysis Worksheet Main Generator trip on

main generator neutral time over-current relay 1N41M705

(451N/UT11)

PO 19-01 Shutdown Operations Protection Plan 13

Forced Outage Cold FO-19-04- Critical Path January 27,

2013

Forced Outage Cold FO-19-04- Critical Path January 22,

2013

Forced Outage Cold FO-19-04- Critical Path January 17,

2013

FO-19-04 Generator Trip Discovery Information

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 17,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 20,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 21,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 17,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 18,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 19,

Update 2013

A-32

OTHER DOCUMENTS

NUMBER TITLE REVISION /

DATE

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 22,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 23,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 24,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 25,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 26,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 27,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 28,

Update 2013

Grand Gulf Nuclear Station FO-19-04 Forced Outage Daily January 29,

Update 2013

GGNS Action Plan for Recovery from FO-12-02

CONDITION REPORTS

CR-GGN-2013-00339 CR-GGN-2013-00340 CR-GGN-2013-00430

CR-GGN-2013-00432 CR-GGN-2013-00438 CR-GGN-2013-00461

CR-GGN-2013-00464 CR-GGN-2013-00685

WORK ORDERS

WO 00338868-38

ENGINEERING CHANGES

EC 42136 EC 41836

A-33

Section 1R22: Surveillance Testing

PROCEDURES

NUMBER TITLE REVISION

06-OP-1P81-R- HPCS Diesel Generator 18 Month Functional Test- Test No. 121

0001 3- 24 Hour Rated Load Test/DG Hot Start Test

06-OP-1P81-R- HPCS Diesel Generator 18 Month Functional Test-General 121

0001 Instructions

06-OP-1E51-Q- RCIC System Quarterly Pump Operability Verification 134

0003

07-S-24-P75- Periodic Inspection and Adjustment of Hydraulic Valve Lifters 10

E001AB-2 on the DSRV-16-4 Delaval Diesel Engine

06-OP-1P75-M- Standby Diesel Generator 12 Functional Test: February 27, 132

0002, Attachment 2013, 3:30 am

II

06-OP-1P75-M- Standby Diesel Generator 12 Functional Test: February 26, 132

0002, Attachment 2013, 5:34 pm

II

06-OP-1P75-M- Standby Diesel Generator 12 Functional Test: February 26, 132

0002, Attachment 2013, 4:22 pm

II

04-1-05-E12-3 Residual Heat Removal Loop C and Pass Return Penetration 000

06-OP-1M61-V- Local Leak Rate Test, Low Pressure Water for 1E12F406 1

0003 (Failure)

06-OP-1M61-V- Local Leak Rate Test, Low Pressure Water for 1E12F406 1

0003 (Passed)

02-S-01-28 Diesel Generator Start Information Sheet, Diesel Generator 4

No: 11, Start No: 1397

06-IC-IC51-R- APRM Recirculation Flow Transmitter Calibration 104

0075

17-S-02-4 Performance and System Engineering Instruction Post 14

Refueling Outage Data Collection and Analysis

EN-OP-109 Drywell Leakage 2

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 08-49 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 24-05 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 44-05 14

A-34

Section 1R22: Surveillance Testing

PROCEDURES

NUMBER TITLE REVISION

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 60-29 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 36-05 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 60-45 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 20-61 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 44-61 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 16-57 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 60-21 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 20-05 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 60-41 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 04-45 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 08-13 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 08-53 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 56-13 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 52-57 14

04-1-03-C11-7 Control Rod Settle and Insertion Test, Control Rod 56-53 14

CALCULATIONS

NUMBER TITLE DATE

M-1358H Pipe Anchors Diesel Generator Building July 19, 1982

OTHER DOCUMENTS

NUMBER TITLE REVISION /

DATE

1P81PT01 Air Start Reliability Test 1

1P75PT01 Air Storage Tank Capacity Test 1

E-236 Emergency Diesel Generator Qualification Test Summary December

28, 1976

91/1006 Change System P75, Division I and II Low Pressure Lockout 0

Setpoint

A-35

OTHER DOCUMENTS

NUMBER TITLE REVISION /

DATE

Discussion of Solenoid Valves on Packing Leak-Off Lines

6.B.4 EDG Hydraulic Lifter Instruction Manual

GG USFAR Appendix 9B Fire Protection Program

Attachment 9.5 Operability Evaluation CR-GGN-2013-01977 6

EN-RE-215 Reactivity Maneuver Plan 2

CONDITION REPORTS

CR-GGN-2013-00218 CR-GGN-2013-00674 CR-GGN-2013-00688

CR-GGN-2013-00710 CR-GGN-2013-01261 CR-GGN-2013-01679

CR-GGN-2013-02013 CR-GGN-2013-02377

WORK ORDERS

WO 52342314 01 WO 00321520 01 WO 52323349 02

WO 00345315 01 WO 00345315 01 WO 52348931 01

1EP4: Emergency Action Level and Emergency Plan Changes

NUMBER TITLE REVISION

10-S-01-1 Activation of the Emergency Plan 122

Emergency Plan 69

Evacuation Time Estimate Study Update

Section 1EP6: Drill Evaluation

OTHER DOCUMENTS

NUMBER TITLE DATE

Emergency Notification Form, Message Number 1 March 5,

2013

A-36

Section 1EP6: Drill Evaluation

OTHER DOCUMENTS

NUMBER TITLE DATE

Emergency Notification Form, Message Not Sent March 5,

2013

Emergency Notification Form, Message Number 2 March 5,

2013

Emergency Notification Form, Message Number 3 March 5,

2013

Emergency Notification Form, Message Number 4 March 5,

2013

Emergency Notification Form, Message Number 5 March 5,

2013

Emergency Notification Form, Message Number 6 March 5,

2013

Emergency Notification Form, Message Number 7 March 5,

2013

Emergency Notification Form, Message Number 8 March 5,

2013

GGNS 2013 Green Team Drill, Emergency Facilitator Log March 5,

EOF 2013

Attachment 2, Objectives/Evaluation Criteria March 5,

2013

GGNS 2013 Green Team, Repair and Corrective Action- March 5,

Admin Status Board 2013

GGNS 2013 Green Team, Emergency Notification (Display) March 5,

2013

CONDITION REPORTS

CR-GGN-2013-01647 CR-GGN-2013-01655 CR-GGN-2013-01657

CR-GGN-2013-01659 CR-GGN-2013-01662 CR-GGN-2013-01663

CR-GGN-2013-01664 CR-GGN-2013-01667 CR-GGN-2013-01668

A-37

Section 4OA1: Performance Indicator Verification

PROCEDURES

NUMBER TITLE REVISION

EN-LI-114 Performance Indicator Process, Unit 1, 1st Qtr 2012 5

EN-LI-114 Performance Indicator Process, Unit 1, 2nd Qtr 2012 5

EN-LI-114 Performance Indicator Process, Unit 1, 3rd Qtr 2012 5

EN-LI-114 Performance Indicator Process, Unit 1, 4 h Qtr 2012 6

Section 4OA3: Event Follow-Up

PROCEDURES

NUMBER TITLE REVISION /

DATE

01-S-06-26 Post-Trip Analysis, GG Unit 1, Scram No. 127 20

EN-LI-119 Apparent Cause Evaluation (ACE) Process 16

EN-LI-118-08, Revised Failure Mode Analysis Worksheet CR-GGN000083 0

Attachment 9.2

EN-LI-118-08, Revised Failure Mode Analysis Worksheet: Main Generator 1

Attachment 9.2 trip on main generator time over-current relay 1N41M705

01-S-06-5 Reactor Plant Event Notification Worksheet, EN #48673 110

01-S-06-26 Post-Trip Analysis, GG Unit 1, Scram No. 128 20

01-S-06-26 Post Trip Analysis, Written Statements Format 20

05-1-02-I-1 Off-Normal Event Procedure, Reactor Scram 117

05-1-02-I-1 Off-Normal Event Procedure, Reactor Scram 119

01-S-02-3 Temporary Change Notice, Directive # 07-S-15-4 April 3, 2012

EN-DC-136 Temporary Modifications 8

DRAWINGS

NUMBER TITLE REVISION

E-1002 One Line Meter & Relay Diagram Generator and Main 16

Transformer, Unit 1

E-1045 NA1 Three Line Meter & Relay Diagram Generator and Main 26

Transformer

A-38

OTHER DOCUMENTS

NUMBER TITLE DATE

NRR Reactor Operating Events: Event Notification Report 48652 January 5,

2013

Unit Differential Relay Information January 4,

2013

Unit Differential Relay Information January 7,

2013

Grand Gulf Nuclear Station FO-19-04 Daily Update January 15,

2013

Grand Gulf Nuclear Station FO-19-04 Daily Update January 16,

2013

Grand Gulf Nuclear Station FO-19-04 Initial Brief

Single Trend Point - C34N004A January 14,

2013

Grand Gulf Operations Logs-Days January 14,

2013

Grand Gulf Cycle 19, Sequence No 19, 3Dm January 14,

V6.59.01/P11E10 2013

Sequence of Event Log January 14,

2013

Investigation of Cause of the January 14, 2013, SCRAM and

Actions Taken to Correct

Failure Mode Analysis Worksheet: Main Generator trip on

main generator neutral time over-current relay 1N41M705

Attachment 9.11 Entergy Operations, Grand Gulf Nuclear Station, RCE for February 15,

Generator Trip and Reactor Scram, CR-GGN-2013-0319 2013

NRC Requested Information for FO47A

CONDITION REPORTS

CR-GGN-2013-00061 CR-GGN-2013-00062 CR-GGN-2013-00063

CR-GGN-2013-00064 CR-GGN-2013-00065 CR-GGN-2013-00066

CR-GGN-2013-00067 CR-GGN-2013-00068 CR-GGN-2013-00069

A-39

CR-GGN-2013-00070 CR-GGN-2013-00071 CR-GGN-2013-00072

CR-GGN-2013-00073 CR-GGN-2013-00074 CR-GGN-2013-00075

CR-GGN-2013-00076 CR-GGN-2013-00077 CR-GGN-2013-00078

CR-GGN-2013-00079 CR-GGN-2013-00080 CR-GGN-2013-00081

CR-GGN-2013-00082 CR-GGN-2013-00083 CR-GGN-2013-00084

CR-GGN-2013-00085 CR-GGN-2013-00086 CR-GGN-2013-00087

CR-GGN-2013-00088 CR-GGN-2013-00089 CR-GGN-2013-00090

CR-GGN-2013-00091 CR-GGN-2013-00092 CR-GGN-2013-00093

CR-GGN-2013-00094 CR-GGN-2013-00095 CR-GGN-2013-00096

CR-GGN-2013-00097 CR-GGN-2013-00098 CR-GGN-2013-00099

CR-GGN-2013-00100 CR-GGN-2013-00101 CR-GGN-2013-00102

CR-GGN-2013-00103 CR-GGN-2013-00104 CR-GGN-2013-00105

CR-GGN-2013-00106 CR-GGN-2013-00107 CR-GGN-2013-00108

CR-GGN-2013-00109 CR-GGN-2013-00110 CR-GGN-2013-00111

CR-GGN-2013-00112 CR-GGN-2013-00113 CR-GGN-2013-00114

CR-GGN-2013-00115 CR-GGN-2013-00116 CR-GGN-2013-00117

CR-GGN-2013-00118 CR-GGN-2013-00119 CR-GGN-2013-00120

CR-GGN-2013-00121 CR-GGN-2013-00122 CR-GGN-2013-00123

CR-GGN-2013-00124 CR-GGN-2013-00125 CR-GGN-2013-00126

CR-GGN-2013-00127 CR-GGN-2013-00128 CR-GGN-2013-00129

CR-GGN-2013-00130 CR-GGN-2013-00131 CR-GGN-2013-00132

CR-GGN-2013-00133 CR-GGN-2013-00134 CR-GGN-2013-00135

CR-GGN-2013-00136 CR-GGN-2013-00137 CR-GGN-2013-00138

A-40

CR-GGN-2013-00139 CR-GGN-2013-00140 CR-GGN-2013-00141

CR-GGN-2013-00142 CR-GGN-2013-00143 CR-GGN-2013-00319

CR-GGN-2013-00323 CR-GGN-2013-00322 CR-GGN-2013-00319

CR-GGN-2013-01259 CR-GGN-2013-01678 CR-GGN-2013-00587

CR-GGN-2013-00100 CR-GGN-2013-11250 CR-GGN-2013-11188

WORK ORDERS

WO 52285169 01

TI-182

PROCEDURES

NUMBER TITLE REVISION

EN-DC-343 Underground Piping and Tanks Inspection and Monitoring 6

Program

EN-DC-105 Configuration Management 3

EN-DC-174 Engineering Program Sections 4

OTHER DOCUMENTS

NUMBER TITLE REVISION

NEI 09-14 Guideline for the Management of Underground Piping and 1

Tank Integrity

0900596-2 Grand Gulf Nuclear Power Station Native and Interrupted 1

APEC Survey

CEP-UPT-0100 Underground Piping and Tanks Inspection and Monitoring 1

Electric Power Research Institute: BPIRD Data Submission 0.1

Template, January 14, 2013

SEP-UIP-GGN Underground Components Inspection Plan 0

En-ES-S-002- Underground Piping and Tanks General Visual Inspection 1

MULTI

SI Project Structural Integrity Associates, Inc Technical Report for A

Number: Baseline Risk Implementation Analysis, Grand Gulf Nuclear

0900596 Station

A-41

OTHER DOCUMENTS

NUMBER TITLE REVISION

CEP-UPT-0100 Underground Piping and Tanks Inspection and Monitoring 2

ECH-EP-12- Guidelines for Management of Reasonable Assurance of 0

00001 Integrity for Above and Underground SSCs Containing

Radioactive Material

FTK-ESPP- Underground Piping/Tanks Program Owner 5

G00121

EC No. Documentation of Buried Pipe and Tanks / Sumps in the 0

0000042092 GGNS Piping Program

CONDITION REPORTS

CR-GGN-2007-04941 CR-GGN-2013-00362

A-42