November 1, 2022

SUBJECT:

GRAND GULF NUCLEAR STATION - SECURITY BASELINE INSPECTION REPORT 05000416/2022403

Dear:

Brad Kapellas:

On September 16, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Grand Gulf Nuclear Station. On September 29, 2022, after additional in-office inspection the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low security significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

A licensee-identified violation which was determined to be of very low security significance is documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Grand Gulf Nuclear Station.

The following cross-cutting aspect was assigned to a finding using Inspection Manual Chapter 0310 Aspects Within Cross Cutting Areas: [H.4] - Teamwork.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Grand Gulf Nuclear Station.

This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

The enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).

Sincerely, Ray L. Kellar, P.E., Chief Physical Security Branch Division of Radiological Safety & Security Docket No. 05000416 License No. NPF-29 Enclosure:

As stated cc w/o encl: Distribution via LISTSERV Signed by Kellar, Ray on 11/01/22

ML22299A040 (Cover letter w/ enclosure(s))

Non-Public Designation Category: MD 3.4 Non-Public (A.3 - A.7 or B.1)

ADAMS ACCESSION NUMBER: ML22305A557 (Cover letter)

Entire Report: Non-Sensitive Publicly Available SUNSI Review RLK Sensitive Non-Publicly Available Cover Letter Only: Non-Sensitive Publicly Available SUNSI Review RLK Sensitive Non-Publicly Available OFFICE PSI:PSB PSI:PSB SRI:PBC C:PSB C:PBC C:PSB NAME RLanfear TWeir TSteadham RKellar JJosey RKellar DATE 10/31/22 11/1/22 10/31/22 10/31/22 10/31/22 11/1/22