ML23110A800

From kanterella
Jump to navigation Jump to search
Notice of Violation; Integrated Inspection Report 05000416/2023001 and NRC Investigation Report 4-2022-004
ML23110A800
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 05/10/2023
From: Jeffrey Josey
NRC/RGN-IV/DORS/PBC
To: Kapellas B
Entergy Operations
Rollins J
References
EA-22-104, EA-22-115, 4-2022-004 4-2022-004
Download: ML23110A800 (40)


See also: IR 05000416/2023001

Text

May 10, 2023

EA-22-104

EA-22-115

Brad Kapellas, Site Vice President

Entergy Operations, Inc.

Grand Gulf Nuclear Station

P.O. Box 756

Port Gibson, MS 39150

SUBJECT: GRAND GULF NUCLEAR STATION - NOTICE OF VIOLATION; INTEGRATED

INSPECTION REPORT 05000416/2023001 AND NRC INVESTIGATION

REPORT 4-2022-004

Dear Brad Kapellas:

This letter refers to an investigation completed on November 8, 2022, and an inspection

completed on March 31, 2023, by the U.S. Nuclear Regulatory Commission (NRC) at the Grand

Gulf Nuclear Station. The purpose of the investigation was to determine whether a willful

violation of NRC requirements occurred for the failure to write a condition report after it was

discovered that a required fire watch had not been established. On April 6, 2023, the NRC

inspectors discussed the results of the investigation and the inspection with you and other

members of your staff. A factual summary of the investigation is documented in Enclosure 2 and

the results of the inspection are documented in Enclosure 3.

The enclosed report documents a Severity Level IV violation of Title 10 of the Code of Federal

Regulations (10 CFR) Part 50, appendix B, criterion V, for the failure to initiate a condition report

after it was discovered that a required fire watch had not been established. The NRC evaluated

this violation in accordance with section 2.3.2 of the NRC Enforcement Policy, which can be

found at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html. The violation is

cited in Enclosure 1, Notice of Violation (Notice), and the circumstances surrounding it are

described in detail in the enclosed report. The violation did not meet the criteria to be treated as

a non-cited violation (NCV) because it involved willfulness.

The enclosed report also documents a Severity Level IV violation of 10 CFR 21.21(d) for the

failure to notify the Commission after the discovery of a defect associated with a substantial

safety hazard evaluation. The NRC evaluated this violation in accordance with section 2.3.2 of

the NRC Enforcement Policy. The violation is cited in Enclosure 1 and the circumstances

surrounding it are described in detail in the enclosed report. This violation did not meet the

criteria to be treated as an NCV because we determined that your staff failed to restore

compliance within a reasonable period after the violation was identified.

B. Kapellas 2

You are required to respond to this letter and should follow the instructions specified in the

enclosed Notice when preparing your response. The NRCs review of your response will also

determine whether further enforcement action is necessary to ensure your compliance with

regulatory requirements.

Based on the results of this inspection, the NRC has also determined that a violation of

10 CFR 21.21(a)(1) occurred. The violation involved the failure to evaluate deviations and

failures to identify defects associated with substantial safety hazards as soon as practicable and

in all cases within 60 days of discovery, in order to identify a reportable defect that could create

a substantial safety hazard. This violation was considered for escalated enforcement at Severity

Level III per the NRC Enforcement Policy. .However, in reviewing the specific circumstances of

this violation (i.e., the NRC resident staff was aware of the issue, and there was little to no

impact to the inspection process/regulatory process; the impact to overall containment leakage

is mitigated by the size of the valves; your staff entered the issue into the corrective action

program and issued a licensee event report after they concluded it was reportable under

10 CFR 50.73; and the valves were only supplied to the Grand Gulf Nuclear Station and no

other licensees) the NRC determined that it is more appropriately categorized as a Severity

Level IV violation. In addition, because the violation was entered into the corrective action

program, corrected by your staff, not repetitive, and not willful, it is being treated as an NCV,

consistent with section 2.3.2 of the NRC Enforcement Policy.

Additionally, two findings of very low safety significance (Green) are documented in this report.

One of these findings involved a violation of NRC requirements. Two Severity Level IV violations

without an associated finding are also documented in this report. We are treating these

violations as NCVs consistent with section 2.3.2 of the NRC Enforcement Policy.

Licensee-identified violations which were determined to be of very low safety significance are

documented in this report. We are treating these violations as NCVs consistent with

section 2.3.2 of the NRC Enforcement Policy.

In the preceding 12 months, the NRC issued five Severity Level IV traditional enforcement

violations as described in NRC Inspection Report 05000416/2022002, dated August 9, 2022,

and in this report. One violation was associated with willfulness and the other four violations

were associated with impeding the regulatory process. The NRC noted that the four violations

associated with impeding the regulatory process appear to show a gap in your process for

making required reports to the NRC. The NRC determined that one of the examples was not

representative of current plant performance. However, the NRC has determined that the other

three violations were indicative of current performance, and the NRC is evaluating whether

performance of Inspection Procedure 92723, Follow up Inspection for Three or More Severity

Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period, is

warranted. This decision will be documented in future correspondence.

If you contest the violations or the significance or severity of the violations documented in this

inspection report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector

at Grand Gulf Nuclear Station.

B. Kapellas 3

If you disagree with a cross-cutting aspect assignment or a finding not associated with a

regulatory requirement in this report, you should provide a response within 30 days of the date

of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the

Regional Administrator, Region IV; and the NRC Resident Inspector at Grand Gulf Nuclear

Station.

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a

copy of this letter, its enclosures, and your response, will be made available electronically for

public inspection in the NRC Public Document Room and from the NRCs ADAMS, accessible

from the NRC website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible,

your response should not include any personal privacy or proprietary information so that it can

be made available to the public without redaction.

Sincerely,

Signed by Josey, Jeffrey

on 05/10/23

Jeffrey E. Josey, Chief

Projects Branch C

Division of Operating Reactor Safety

Docket No. 05000416

License No. NPF-29

Enclosures:

1. Notice of Violation

2. Factual Summary

3. Inspection Report 05000416/2023001

cc w/ encl: Distribution via LISTSERV

ML23110A800

x Non-Sensitive x Publicly Available

x SUNSI Review

Sensitive Non-Publicly Available

OFFICE SES:ACES SRI:DORS/C ATL:ACES RC ASPE:DORS/C

NAME JKramer TSteadham RKumano DCylkowski JRollins

SIGNATURE /RA/ E /RA/ E /RA/ E /RA/ E /RA/ E

DATE 04/26/23 04/26/23 04/26/23 04/25/23 04/26/23

OFFICE ATL:DORS/IPAT RI:DORS/C OGC OE D:DORS

NAME WSchaup ASmallwood RCarpenter GGulla RLantz

SIGNATURE /RA/ E /RA/ E /NLO/ E /RA/ E /RA/ E

DATE 04/25/23 04/21/23 05/04/23 05/01/23 05/10/23

OFFICE BC:DORS/C

NAME JJosey

SIGNATURE /RA/ E

DATE 05/10/23

NOTICE OF VIOLATION

Entergy Operations, Inc. Docket No. 05000416

Grand Gulf Nuclear Station License No. NPF-29

EA-22-104

EA-22-115

During an NRC investigation completed on November 8, 2022, and an NRC inspection

completed on March 31, 2023, two violations of NRC requirements were identified. In

accordance with the NRC Enforcement Policy, the violations are listed below:

A. 10 CFR 21.21(a)(3) requires, in part, that entities subject to the regulations in

10 CFR Part 21 shall ensure that a director or responsible officer is informed as soon

as practicable, and, in all cases, within the 5 working days after completion of the

evaluation described in 10 CFR 21.21(a)(1).

10 CFR 21.21(d) requires, in part, that a director or responsible officer must notify the

Commission when he or she obtains information reasonably indicating a failure to

comply or a defect within 2 days following receipt of the information.

Contrary to the above, from August 13 to October 31, 2022, the licensee failed to notify

the Commission after the discovery of a defect associated with a substantial safety

hazard evaluation described in 10 CFR 21.21(a)(1). Specifically, the licensee identified

that the lack of lubrication on the containment personnel airlock equalizing valves

caused the excessive leakage and evaluated the condition as a substantial safety

hazard on August 3, 2022, but failed to make the timeliness requirements to notify the

Commission.

This is a Severity Level IV violation (NRC Enforcement Policy, section 6.9(d)(13). (EA-22-104)

B. 10 CFR Part 50, appendix B, criterion V requires, in part, that activities affecting quality

shall be accomplished in accordance with documented instructions, procedures, or

drawings, of a type appropriate to the circumstances.

Procedure EN-LI-102, Corrective Action Program, revision 45, a quality-related

procedure, attachment 1, step 21 states, in part, that any condition which materially

impacts the ability to implement the fire protection program including degraded fire

barriers and their subcomponents (penetration seals, fire doors and dampers), and fire

detection and suppression systems, be screened as an adverse condition in the

corrective action program.

Procedure EN-LI-102, step 5.2.4 requires, in part, that employees and contractors are

required to initiate condition reports for adverse conditions.

Contrary to the above, from September 15, 2021, to April 20, 2022, licensed personnel

failed to initiate a condition report for adverse conditions. Specifically, a licensed

operator deliberately failed to write a condition report for a condition which materially

impacted the ability to implement the fire protection program when a continuous fire

watch was not established.

Enclosure 1

This is a Severity Level IV violation (NRC Enforcement Policy, section 2.2.1.d). (EA-22-115)

Pursuant to 10 CFR 2.201, Entergy Operations, Inc. is hereby required to submit a written

statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN: Document Control

Desk, Washington, DC 20555-0001, with a copy to the Regional Administrator, U.S. Nuclear

Regulatory Commission, Region IV, 1600 East Lamar Blvd., Arlington, Texas 76011-4511,

and the NRC Resident Inspector at the Grand Gulf Nuclear Station, and email it to

R4Enforcement@nrc.gov within 30 days of the date of the letter transmitting this Notice. This

reply should be clearly marked as a Reply to a Notice of Violation, EA-22-104 and EA-22-115,

and should include for each violation: (1) the reason for the violation, or, if contested, the basis

for disputing the violation or severity level; (2) the corrective steps that have been taken and the

results achieved; (3) the corrective steps that will be taken; and (4) the date when full

compliance will be achieved.

Your response may reference or include previous docketed correspondence if the

correspondence adequately addresses the required response. If an adequate reply is not

received within the time specified in this Notice, the NRC may issue an order or a demand for

information requiring you to explain why your license should not be modified, suspended, or

revoked, or why such other action as may be proper should not be taken. Where good cause is

shown, consideration will be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis for your denial, to the Director, Office of Enforcement, U.S. Nuclear Regulatory

Commission, Washington, DC 20555-0001.

Your response will be made available electronically for public inspection in the NRC Public

Document Room and from the NRCs ADAMS, accessible from the NRC website at

http://www.nrc.gov/reading-rm/adams.html. Therefore, to the extent possible, your response

should not include any personal privacy or proprietary information so that it can be made

available to the public without redaction.

If personal privacy or proprietary information is necessary to provide an acceptable response,

then please provide a bracketed copy of your response that identifies the information that

should be protected and a redacted copy of your response that deletes such information. If you

request that such material is withheld from public disclosure, you must specifically identify the

portions of your response that you seek to have withheld and provide in detail the bases for your

claim (e.g., explain why the disclosure of information will create an unwarranted invasion of

personal privacy or provide the information required by 10 CFR 2.390(b) to support a request for

withholding confidential commercial or financial information).

Dated this 10th day of May 2023

2

FACTUAL SUMMARY

OFFICE OF INVESTIGATIONS REPORT 4-2022-004

On December 8, 2021, the U.S. Nuclear Regulatory Commission (NRC) Office of Investigations

Region IV initiated an investigation to determine if a licensed operator, employed by Entergy

Operations Inc. (licensee) at the Grand Gulf Nuclear Station (GGNS), deliberately failed to write

a condition report after licensee personnel discovered that a required fire watch had not been

established. The investigation was completed on November 8, 2022.

Licensee document 1-FTR-0406 required a continuous fire watch be established for the

division 1 and division 2 switchgear rooms beginning on September 14, 2021. On

September 15, 2021, a licensed operator identified that the required fire watch had not been

established. Following the discovery, the control room staff dispatched two non-licensed

operators to perform the fire watch duties until they were relieved by mechanical maintenance

personnel.

Procedure EN-LI-102, Corrective Action Program, revision 45, a quality-related procedure,

attachment 1, step 21, states, in part, that any condition which materially impacts the ability

to implement the fire protection program including degraded fire barriers and their

subcomponents (penetration seals, fire doors and dampers), and fire detection and

suppression systems, be screened as an adverse condition in the corrective action program.

Procedure EN-LI-102, step 5.2.4 requires, in part, that employees and contractors are required

to initiate condition reports for adverse conditions.

Based on the evidence obtained during the investigation, there was sufficient information to

demonstrate that a licensed operator deliberately failed to write a condition report for not

establishing a required fire watch. The licensed operator knew that no condition report had been

written by any other licensee employee, and the licensed operator knew that the failure to write

a condition report was contrary to licensee policy and NRC regulations.

Enclosure 2

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number: 05000416

License Number: NPF-29

Report Number: 05000416/2023001

Enterprise Identifier: I-2023-001-0011

Licensee: Entergy Operations, Inc.

Facility: Grand Gulf Nuclear Station

Location: Port Gibson, MS

Inspection Dates: January 1 to March 31, 2023

Inspectors: N. Greene, Senior Health Physicist

S. Hedger, Senior Emergency Preparedness Inspector

W. Schaup, Senior Project Engineer

E. Simpson, Health Physicist

A. Smallwood, Resident Inspector

T. Steadham, Senior Resident Inspector

Approved By: Jeffrey E. Josey, Chief

Projects Branch C

Division of Operating Reactor Safety

Enclosure 3

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Grand Gulf Nuclear Station, in

accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs

program for overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information. Licensee-identified

non-cited violations are documented in report sections: 71111.24 and 71153.

List of Findings and Violations

Failure to Initiate a Condition Report for a Condition Adverse to Quality

Cornerstone Significance/Severity Cross-Cutting Report

Aspect Section

Mitigating Severity Level IV None 71111.05

Systems NOV 05000416/2023001-01

Open

EA-22-115

The inspectors identified a Severity Level IV violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, for the failure to follow station

Procedure EN-LI-102, Corrective Action Program, that requires all employees and

contractors to initiate condition reports for adverse conditions. Specifically, after determining

a required fire watch was not posted, an adverse condition, a licensed operator failed

to promptly document the condition in a condition report.

Failure to Control Transient Combustibles in the Auxiliary Building

Cornerstone Significance Cross-Cutting Report

Aspect Section

Mitigating Green [H.1] - 71111.18

Systems NCV 05000416/2023001-02 Resources

Open/Closed

The inspectors identified four examples of a Green finding and non-cited violation of License

Condition 2.C(41), Fire Protection Program, for the licensees failure to implement all

provisions of the approved fire protection program described in the NRC Safety Evaluation

dated September 29, 2006, related to License Amendment 170 to operating license NPF-29.

Specifically, the licensee failed to store transient combustible materials in the auxiliary building

as required by the safety evaluation.

2

Failure to Adequately Verify Design Change

Cornerstone Significance Cross-Cutting Report

Aspect Section

Initiating Events Green None 71153

FIN 05000416/2023001-03

Open/Closed

A self-revealed Green finding was identified for the licensees failure to perform appropriate

design verifications of an engineering change associated with the feedwater heater level

control valves. As a result, the system response of a condensate booster pump trip was not

adequately analyzed which contributed to a loss of feedwater event and plant scram when a

condensate booster pump tripped on December 19, 2022. This event was reported as

Licensee Event Report 05000416/2022-003-00.

Failure to Submit a Licensee Event Report Within 60 Days

Cornerstone Severity Cross-Cutting Report

Aspect Section

Not Applicable Severity Level IV Not Applicable 71153

NCV 05000416/2023001-04

Open/Closed

The inspectors identified two examples of a Severity Level IV non-cited violation of

10 CFR 50.73(a), Licensee Event Report System, for the licensees failure to submit two

licensee event reports within 60 days after discovery of the event. Specifically, the licensee

determined on November 4, 2021, that an issue associated with jet pump summer

miscalibration resulted in multiple cases of operation in a condition prohibited by technical specification 3.2.2 and the licensee event report was submitted 76 days later, on

January 19, 2022. Additionally, the licensee determined on December 2, 2021, that an issue

associated with oscillation power range monitors was a reportable event and the licensee

event report was submitted 62 days later on February 2, 2022.

Failure to Evaluate a Deviation for 10 CFR Part 21 Applicability

Cornerstone Severity Cross-Cutting Report

Aspect Section

Not Applicable Severity Level IV Not Applicable 71153

NCV 05000416/2023001-05

Open/Closed

EA-22-104

The inspectors identified a Severity Level IV non-cited violation of 10 CFR 21.21(a)(1) for the

licensees failure to evaluate a deviation in a basic component within 60 days of discovery. As

a result, the licensee failed to evaluate a deviation identified on April 21, 2021, that was

associated with a reportable defect that could have created a substantial safety hazard were it

to have remained uncorrected within 60 days of discovery. The licensee completed the

evaluation on August 10, 2022, and determined that the deviation was associated with a

substantial safety hazard and was required to be reported under 10 CFR Part 21.

3

Failure to Make a Timely 10 CFR Part 21 Report

Cornerstone Severity Cross-Cutting Report

Aspect Section

Not Applicable Severity Level IV Not Applicable 71153

NOV 05000416/2023001-06

Open

EA-22-104

The inspectors identified a Severity Level IV violation of 10 CFR 21.21(a)(3) and

10 CFR 21.21(d) for the licensees failure to make a 10 CFR Part 21 report within the required

time limits specified in 10 CFR Part 21. Specifically, the licensee notified the responsible

officer 55 working days after making the determination that a substantial safety hazard existed

(50 working days late) and the report was made three calendar days after the responsible

officer was notified (one day late).

Additional Tracking Items

Type Issue Number Title Report Section Status

LER 05000416/2021-001-01 Primary Containment Outer 71153 Closed

Airlock Door Inoperable Due

to Unacceptable Leak Rate

LER 05000416/2021-004-00 Procedure Inadequacy 71153 Closed

Resulted in Core Monitoring

System Miscalibration and

Violation of Technical

Specification

LER 05000416/2021-005-00 Oscillation Power Range 71153 Closed

Monitors (OPRMs) Setpoint

Error Causes Technical

Specification Noncompliance

LER 05000416/2022-001-00 Manual Reactor Trip Due to 71153 Closed

the Loss of Balance of Plant

Transformer 23

LER 05000416/2022-003-00 Manual Reactor SCRAM due 71153 Closed

to a Loss of the Condensate

and Feed Water System

4

PLANT STATUS

Grand Gulf Nuclear Station, Unit 1, began the inspection period at 100 percent rated thermal

power (RTP). On March 31, 2023, operators reduced power to 67 percent RTP for a control rod

sequence exchange where it remained at or near for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed activities described in IMC 2515,

Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of

IPs. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel to assess licensee performance and compliance with Commission rules

and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1) residual heat removal train B on January 12, 2023

(2) low pressure core spray while residual heat removal B was out of service on

January 18, 2023

(3) division 1 standby service water on March 1, 2023

(4) residual heat removal train A on March 17, 2023

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the

division 2 standby diesel generator system on March 29, 2023.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (8 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1) low pressure core spray pump room on January 10, 2023

(2) auxiliary building, 139-foot elevation, fire area 1A316, on January 12, 2023

(3) containment, all elevations, on January 19, 2023

(4) division 1 control room ventilation room on February 2, 2023

5

(5) switchgear rooms 1A208 and 1A207 auxiliary building, 119-foot elevation, on

February 9, 2023

(6) auxiliary building hallways, 93-foot, 103-foot, 139-foot, and 166-foot elevations, on

February 10, 2023

(7) residual heat removal A pump room on March 9, 2023

(8) division 2 standby diesel generator on March 16, 2023

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an

unannounced fire brigade drill response to a simulated fire in the control building,

189-foot elevation, on January 25, 2023.

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in the auxiliary

building, 93-foot elevation, high pressure core spray, low pressure core spray, and

residual heat removal C pump rooms on January 10, 2023.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control

room during a downpower for rod sequence exchange on March 31, 2023.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a licensed operator training evolution in the

simulator on February 6, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following

structures, systems, and components (SSCs) remain capable of performing their intended

function:

(1) work order 593088, engineered safety feature transformer 11 relay replacement on

March 27, 2023

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to

ensure the following SSC remains capable of performing its intended function:

(1) work order 590923, replace two cards for the division 2 load shedder and sequencing

panel on February 9, 2023

6

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed:

(1) protected system lineup while residual heat removal B was out of service on

January 10, 2023

(2) protected system lineup while residual heat removal A was out of service on

January 20, 2023

(3) emergent work control due to reactor core isolation cooling system unavailability on

January 27, 2023

(4) maintenance risk assessment during division 2 work week on February 2, 2023

(5) risk management actions for transformer 23 underground power cable connections

on March 27, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1) condition report CR-GGN-2022-00296, potential moisture intrusion in reactor core

isolation cooling oil system on January 26, 2023

(2) condition report CR-GGN-2023-00633, reactor core isolation cooling trip throttle valve

failure to open on February 3, 2023

(3) condition report CR-GGN-2023-00721, material nonconformance for control rod drive

mechanism cap screws on February 7, 2023

(4) condition report CR-GGN-2023-00478, division 2 load shedding and sequencer

failure on February 9, 2023

(5) condition report CR-GGN-2023-00562, non-conservative moment of inertia for

recirculation pump on March 13, 2023

(6) condition report CR-GGN-2023-01532, snubber misaligned on March 14, 2023

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

(1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) revision to Procedure EN-DC-161, "Control of Combustibles," on March 14, 2023

7

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system

operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (5 Samples)

(1) work order 590923, division 2 load shedding and sequencer panel functional test on

January 25, 2023

(2) work order 591227, failed light socket for reactor core isolation cooling trip/throttle

valve position indicating lamp on February 10, 2023

(3) work order 559947-01, disassemble and inspect actuator on March 8, 2023

(4) work order 591510, control room air-conditioner train B power supply replacement on

March 24, 2023

(5) work order 52916166, clean, inspect, and lubricate air handling equipment on

March 31, 2023

Surveillance Testing (IP Section 03.01) (3 Samples)

(1) work order 53022722, anticipated transient without scram reactor vessel high

pressure channel A on February 15, 2023

(2) work order 53022735, reactor vessel water level 3 and level 8 functional test on

March 8, 2023

(3) work order 423277, remove and inspect snubber 1E12G013R11 on March 13, 2023

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) work order 52931269, motor operated valve periodic diagnostic test of

valve 1E51F010 on February 10, 2023

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1) work order 52995885 and 5295886, FLEX building 2 equipment testing on

February 8, 2023

71114.01 - Exercise Evaluation

Inspection Review (IP Section 02.01-02.11) (1 Partial)

(1) The inspectors evaluated the biennial emergency plan exercise conducted on

March 22, 2023. However, as of the end of the 1st Quarter 2023, the licensee had not

completed its critique process for the exercise. As such, the inspectors had not

completed the full evaluation of the exercise and the critique process. The inspectors

will complete the inspection in the 2nd Quarter, and the results of the inspection will

be documented in NRC Inspection Report 05000416/2023002.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated changes to the Emergency Action Level (EAL) Technical

Bases Document, revisions 2 and 3 (effective August 2022, and January 2023,

8

respectively). This involved review of a selection of additional licensee screening and

evaluation documentation. These evaluations and reviews do not constitute NRC

approval.

71114.08 - Exercise Evaluation - Scenario Review

Inspection Review (IP Section 02.01 - 02.04) (1 Sample)

(1) The inspectors reviewed the licensees preliminary exercise scenario that was

submitted to the NRC on January 19, 2023 (ML23019A183), for the exercise

scheduled to occur on March 22, 2023. The inspectors discussed the preliminary

scenario with Mike Lewis, Manager, Emergency Preparedness, and other members

of the emergency preparedness staff on February 15, 2023. The inspectors' review

does not constitute NRC approval of the scenario.

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of

radiation levels and the concentrations and quantities of radioactive materials, and

how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related

radiological hazards and the radiation protection requirements intended to protect

workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed and evaluated the following licensee processes for monitoring and

controlling contamination and radioactive material:

(1) observed the licensee conduct surveys of potentially contaminated packages and

equipment from the radiologically controlled area for release offsite and workers

exiting potential contaminated areas

(2) evaluated the licensee's physical and programmatic controls for the unconditional

release of non-contaminated and non-radioactive equipment from inside the

radiologically controlled area

Radiological Hazards Control and Work Coverage (IP Section 03.04) (2 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following

radiological work:

(1) high risk radiological work and job coverage for floor drain centrifugal disc filter

maintenance (RWP 2023-1070, Task 2 for work order 590804)

9

(2) high risk radiological work and job coverage to support the spent fuel pool cleanout

project (RWP 2022-1313, Task 1 for work order 583982)

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (4 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very

high radiation areas:

(1) Grand Gulf Nuclear Station turbine building, 113-foot elevation, door 1T204

(2) Grand Gulf Nuclear Station turbine building, 110-foot elevation, door 1T207

(3) Grand Gulf Nuclear Station radwaste building, 118-foot elevation, door OR208

(4) Grand Gulf Nuclear Station radwaste building, 136-foot elevation, door OR317

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP

Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician

performance as it pertains to radiation protection requirements.

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to radioactive source

term characterization.

External Dosimetry (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee processes, stores, and uses external

dosimetry.

Internal Dosimetry (IP Section 03.03) (3 Samples)

The inspectors evaluated the following internal dose assessments:

(1) a potential intake that occurred on March 8, 2022, while cutting out piping

(2) a potential intake that occurred on March 19, 2022, while removing insulation from

auxiliary room steam tunnel piping

(3) a potential intake that occurred on March 24, 2022, while performing nondestructive

examination testing

Special Dosimetric Situations (IP Section 03.04) (3 Samples)

The inspectors evaluated the following special dosimetric situations:

(1) three examples of declared pregnant worker's dose assessment

(2) effective dose equivalent for external exposure (EDEx) assessments for three

workers working as divers in non-uniformed radiation fields in 2022 under

RWP 2022-1531

(3) neutron dose tracking for work near the independent spent fuel storage installation

pad

10

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01) (1 Sample)

(1) January 1, 2022, through December 31, 2022

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)

(1) January 1, 2022, through December 31, 2022

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) January 1, 2022, through December 31, 2022

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) January 1, 2022, through December 31, 2022

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual

Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample

(IP Section 02.16) (1 Sample)

(1) January 1, 2022, through December 31, 2022

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) April 1, 2022, through December 31, 2022

EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13)

(1 Sample)

(1) April 1, 2022, through December 31, 2022

EP03: Alert And Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)

(1) April 1, 2022, through December 31, 2022

71153 - Follow Up of Events and Notices of Enforcement Discretion

Event Report (IP Section 03.02) (5 Samples)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000416/2021-001-00, Primary Containment Outer Airlock Door Inoperable

Due to Unacceptable Leak Rate (ML21137A090). The circumstances surrounding

this LER and a Severity Level IV non-cited violation is documented in the Inspection

Results section of this report. This LER is closed.

11

(2) LER 05000416/2021-004-00, Procedure Inadequacy Resulted in Core Monitoring

System Miscalibration and Violation of Technical Specification (ML22019A270). The

circumstances surrounding this LER and a Severity Level IV non-cited violation is

documented in the Inspection Results section of this report. This LER is closed.

(3) LER 05000416/2021-005-00, Oscillation Power Range Monitors (OPRMs) Setpoint

Error Causes Technical Specification Noncompliance (ML22033A065). The

circumstances surrounding this LER,a Severity Level IV non-cited violation, and a

licensee identified violation are documented in the Inspection Results section of this

report. This LER is closed.

(4) LER 05000416/2022-001-00, Manual Reactor Trip Due to the Loss of Balance of

Plant Transformer 23 (ML22241A113). The inspectors determined that it was not

reasonable to foresee or correct the cause discussed in the LER, therefore, no

performance deficiency was identified. The inspectors did not identify a violation of

NRC requirements. This LER is Closed.

(5) LER 05000416/2022-003-00, Manual Reactor SCRAM due to a Loss of the

Condensate and Feed Water System (ML23047A547). The circumstances

surrounding this LER and a Green finding is documented in the Inspection Results

section of this report. This LER is Closed.

INSPECTION RESULTS

Failure to Initiate a Condition Report for a Condition Adverse to Quality

Cornerstone Significance/Severity Cross-Cutting Report

Aspect Section

Mitigating Severity Level IV None 71111.05

Systems NOV 05000416/2023001-01

Open

EA-22-115

The inspectors identified a Severity Level IV violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, for the failure to follow station

Procedure EN-LI-102, Corrective Action Program, that requires all employees and

contractors to initiate condition reports for adverse conditions. Specifically, after determining

a required fire watch was not posted, an adverse condition, a licensed operator failed

to promptly document the condition in a condition report.

Description: On September 15, 2021, a licensed operator serving as the work control

supervisor, was asked to go to the maintenance department and locate a fire watch for the

division 1 and division 2 switchgear rooms because it had been determined that a required

continuous fire watch had not been posted. The control room sent two non-licensed operators

(NLOs) to perform fire watch duties until personnel from the maintenance department could

get to the division 1 and division 2 switchgear rooms to perform the continuous fire watch

duties and relieve the NLOs.

Licensee document limiting condition for operation (LCO) 1 FTR-21-0406 indicated on the

tagout instructions that a continuous fire watch was required because, once the tagout was

hung, it disabled portions of the fire protection system. When those portions of the fire

protection system are disabled, station procedures require establishing a continuous fire

watch in that area.

Along with the work control supervisor, several control room personnel including the shift

manager, control room supervisor, and the shift technical supervisor were aware that the

continuous fire watch had not be established.

12

On December 8, 2021, the NRCs Office of Investigations (OI) initiated an investigation to

determine whether the licensees actions involved a willful violation of a regulatory

requirement. A factual summary of the investigation is contained in Enclosure 2.

As a result of the investigation, the NRC determined that a condition report had not been

initiated to document that the licensee had failed to establish a required fire watch in

accordance with station procedures until April 20, 2022, when the NRC informed the licensee

that the action had not been performed. This is based upon the following:

Procedure EN-LI-102, Corrective Action Program, revision 45, a quality-related procedure,

attachment 1, step 21 states, in part, that any condition which materially impacts the ability to

implement the fire protection program including degraded fire barriers and their

subcomponents (penetration seals, fire doors and dampers), and fire detection and

suppression systems, be screened as an adverse condition in the corrective action program.

Procedure EN-LI-102, step 5.2.4 requires, in part, that employees and contractors are

required to initiate condition reports for adverse conditions.

On April 20, 2022, the licensee documented the condition adverse to quality in the corrective

action program as condition report CR-GGN-2022-04646.

Additionally, based on the evidence obtained during the investigation, there was sufficient

information to demonstrate that a licensed operator deliberately failed to write a condition

report for not establishing a required fire watch. The licensed operator knew that no condition

report had been written by any other licensee employee, and the licensed operator knew that

the failure to write a condition report was contrary to licensee policy and NRC regulations.

Corrective Actions: Immediate corrective actions were to establish the required fire watch. No

additional corrective actions were generated after documenting the adverse condition in

condition report CR-GGN-2022-04646.

Corrective Action References: This issue was entered into the licensees corrective action

program as condition report CR-GGN-2022-04646

13

Performance Assessment:

Performance Deficiency: The NRC determined that this violation was associated with a minor

performance deficiency. Licensee Procedure EN-LI-102, step 5.2.4c. requires, in part, that

employees and contractors are required to initiate condition reports for adverse conditions.

Specifically, after determining a required fire watch was not posted, an adverse condition, a

licensed operator failed to promptly document the condition in a condition report.

Cross-Cutting Aspect: None

Enforcement: The ROPs significance determination process does not specifically consider

willfulness in its assessment of licensee performance. Therefore, it is necessary to address

this violation which involves willfulness using traditional enforcement.-.

Severity: The NRC evaluated this violation in accordance with section 2.2.1.d. and

section 2.2.2 of the NRC Enforcement Policy. Because the issue involved willfulness, this

violation was determined to be Severity Level IV.

Violation: 10 CFR Part 50, appendix B, criterion V requires, in part, that activities affecting

quality shall be accomplished in accordance with documented instructions, procedures, or

drawings, of a type appropriate to the circumstances.

Procedure EN-LI-102, Corrective Action Program, revision 45, a quality-related procedure,

attachment 1, step 21 states, in part, that any condition which materially impacts the ability to

implement the fire protection program including degraded fire barriers and their

subcomponents (penetration seals, fire doors and dampers), and fire detection and

suppression systems, be screened as an adverse condition in the corrective action program.

Procedure EN-LI-102, step 5.2.4 requires, in part, that employees and contractors are

required to initiate condition reports for adverse conditions.

Contrary to the above, from September 15, 2021, to April 20, 2022, licensed personnel failed

to initiate a condition report for adverse conditions. Specifically, a licensed operator

deliberately failed to write a condition report for a condition which materially impacted the

ability to implement the fire protection program when a continuous fire watch was not

established.

Enforcement Action: This violation is being cited because the violation was willful.

Failure to Control Transient Combustibles in the Auxiliary Building

Cornerstone Significance Cross-Cutting Report

Aspect Section

Mitigating Green [H.1] - 71111.18

Systems NCV 05000416/2023001-02 Resources

Open/Closed

The inspectors identified four examples of a Green finding and non-cited violation of License

Condition 2.C(41), Fire Protection Program, for the licensees failure to implement all

provisions of the approved fire protection program described in the NRC Safety Evaluation

dated September 29, 2006, related to License Amendment 170 to operating license NPF-29.

Specifically, the licensee failed to store transient combustible materials in the auxiliary

14

building as required by the Safety Evaluation (SE).

Description: On February 9th, 2023, the inspectors toured the auxiliary building 93-foot,

103-foot, 119-foot, 139-foot, and 166-foot elevations including several risk significant fire

areas and combustible material exclusion zones as described in the SE dated

September 29, 2006. Section 4.2.2.1.8 of the SE states, in part, that combustible storage

areas are designated locations where transient combustible materials may be stored or

staged, and that outside these designated storage areas transient combustibles may only be

stored in sealed metal drums. Section 3.1.5 of the SE prohibits storing combustible materials

on the 93-foot elevation. The inspectors observed the following examples of combustible

materials that were not stored in accordance with these sections of the SE:

(Example 1) A combustible material storage permit issued on the 93-foot elevation per

procedure EN-DC-161 for rubber hose contrary to section 3.1.5. The combustible

material was also not stored in a sealed metal drum contrary to section 4.2.2.1.8. In

addition, the combustible material storage permit had expired 9 days prior to the

observation on January 31, 2023.

(Example 2) Also stored on the 93-foot elevation not in a sealed metal container were

several fiberglass ladders, rubber hoses, and rolls of plastic pearl weave used for

netting in a scaffolding storage area contrary to both sections 3.1.5 and 4.2.2.1.8.

(Example 3) On the 139-foot elevation, miscellaneous transient combustibles such as

a cart with a wooden deck, a rubber hose, a dust mop, and plastic wet floor signs

were found near door 1A310 in a safe storage area contrary to section 4.2.2.1.8. Safe

storage areas are not designated combustible material storage areas per plant

maintenance standard MS53. These items were not in a transient combustible

material storage area, and they were not stored in sealed metal drums.

(Example 4) Additionally, sections 3.1 through 3.4 of the SE include restrictions to limit

the size and location of combustible storage areas in the auxiliary building; however,

the licensees transient combustible permit program did not track or otherwise restrict

the size of combustible storage areas in the auxiliary building to remain in

conformance with the SE.

The inspectors reported the transient combustible material to the licensee who determined

that the transient combustibles were not controlled as described in the SE. The inspectors

determined that the procedure used to control transient combustibles, Procedure EN-DC-161,

Control of Combustibles, revision 25, did not capture the specific requirements as detailed

in the SE. Specifically, none of the examples identified above were inconsistent with

procedure EN-DC-161, but all four were inconsistent with the SE.

Because the licensee was unable to produce any evaluations which approved these

deviations, the inspectors concluded that procedure EN-DC-161 was not appropriately

controlling transient combustibles in accordance with the applicable license condition.

Corrective Actions: The licensee entered this issue into their corrective action program to

review the discrepancies and revise the procedure as appropriate.

Corrective Action References: This issue was entered into the licensees corrective action

program as condition reports CR-GGN-2023-00933 and CR-GGN-2023-01003

Performance Assessment:

Performance Deficiency: The licensees failure to implement procedures for the control

15

of combustible materials in the auxiliary building in accordance with the SE dated

September 29, 2006, was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Protection Against External Factors attribute of the

Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure

the availability, reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, the performance deficiency resulted in uncontrolled

combustible materials in multiple locations in the auxiliary building containing safe shutdown

components for both division 1 and division 2.

Significance: The inspectors assessed the significance of the finding using IMC 0609,

Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

Because the finding involved the ability to confine a fire, the inspectors applied IMC 0609,

Appendix F, Fire Protection SDP, to determine the findings significance. The inspectors

determined that there were adequate fire suppression and detection systems in the auxiliary

building, and therefore, they concluded that the performance deficiency was of very low

safety significance (Green).

Cross-Cutting Aspect: H.1 - Resources: Leaders ensure that personnel, equipment,

procedures, and other resources are available and adequate to support nuclear safety.

Enforcement:

Violation: License Condition 2.C(41), Fire Protection Program, states, in part, that the plant

shall implement and maintain in effect all provisions of the Fire Protection Program as

described in the Updated Final Safety Analysis Report (UFSAR), and as approved in the

Safety Evaluation dated September 29, 2006. The safety evaluation dated

September 29, 2006, states, in part, that transient combustibles may only be stored in sealed

metal containers outside designated combustible storage areas. Section 3.1.5 of the safety

evaluation dated September 29, 2006, prohibits combustible material storage areas on the

93-foot elevation of the auxiliary building. Section 4.2.2.1.8 of the safety evaluation dated

September 29, 2006, states, in part, that processes and procedures are in place at Grand

Gulf Nuclear Station to address the control of combustible loading throughout the plant.

Contrary to the above, on February 9, 2023, the licensee failed to implement and maintain in

effect all provisions of the Fire Protection Program as described in the Updated Final Safety

Analysis Report, and as approved in the Safety Evaluation dated September 29, 2006, as

evidenced by the following four examples:

(Example 1): A combustible material storage permit was issued on the 93-foot

elevation per procedure EN-DC-161 for rubber hose contrary to section 3.1.5. The

combustible material was also not stored in a sealed metal drum contrary to

section 4.2.2.1.8. In addition, the combustible material storage permit had expired

9 days prior to the observation on January 31, 2023.

(Example 2): Several fiberglass ladders, rubber hoses, and rolls of plastic pearl weave

used for netting in a scaffolding storage area were stored on the 93-foot elevation and

not in a sealed metal drum contrary to both sections 3.1.5 and 4.2.2.1.8.

(Example 3): On the 139-foot elevation, miscellaneous transient combustibles such as

a cart with a wooden deck, a rubber hose, a dust mop, and plastic wet floor signs

were found near door 1A310 in a safe storage area contrary to section 4.2.2.1.8. Safe

storage areas are not designated combustible material storage areas per plant

16

maintenance standard MS53. These items were not in a transient combustible

material storage area, and they were not stored in sealed metal drums.

(Example 4) Sections 3.1 through 3.4 of the SE include restrictions to limit the size

and location of combustible storage areas in the auxiliary building; however, the

licensees transient combustible permit program did not track or otherwise restrict the

size of combustible storage areas in the auxiliary building to remain in conformance

with the SE.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

section 2.3.2 of the Enforcement Policy.

Licensee-Identified Non-Cited Violation 71111.24

This violation of very low safety significance was identified by the licensee, has been entered

into the licensee corrective action program, and is being treated as a non-cited violation

consistent with Section 2.3.2 of the Enforcement Policy.

Violation: License Condition 2.C(41), Fire Protection Program, states, in part, that the plant

shall implement and maintain in effect all provisions of the fire protection program as

described in the UFSAR. UFSAR, section 9B.6, requires, in part, that the licensee govern the

operability requirements, required actions, and surveillance requirements specified in

Technical Requirements Manual, section 6.2. Technical Requirements Manual,

section 6.2.4.1, required that a continuous fire watch be established within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> of the

carbon dioxide system protecting the division 1, 2, or 3 switchgear rooms being declared

non-functional.

Contrary to the above, from 11:17 a.m. on September 14, 2021, until September 15, 2021,

the licensee failed to establish a continuous fire watch when the carbon dioxide system

protecting the division 1, 2, or 3 switchgear rooms was declared non-functional.

Significance/Severity: The inspectors assessed the significance of the finding using

Appendix F, Fire Protection Significance Determination Process. The finding represented a

high degradation of a fixed fire protection system. A regional senior reactor analyst performed

a Phase 2 screening using a bounding risk quantification which determined an increase in

core damage frequency of 4.4E-7/year, representing very low safety significance (Green).

The finding has very low safety significance (Green) because of the short time there was not

a fire watch and the low probability of a fire during that time.

Corrective Action References: This issue was entered into the licensees corrective action

program as condition report CR-GGN-2022-04646

Failure to Adequately Verify Design Change

Cornerstone Significance Cross-Cutting Report

Aspect Section

Initiating Events Green None 71153

FIN 05000416/2023001-03

Open/Closed

A self-revealed Green finding was identified for the licensees failure to perform appropriate

design verifications of an engineering change associated with the feedwater heater level

control valves. As a result, the system response of a condensate booster pump trip was not

adequately analyzed which contributed to a loss of feedwater event and plant scram when a

condensate booster pump tripped on December 19, 2022. This event was reported as

17

Licensee Event Report 05000416/2022-003-00.

Description: On December 19, 2022, with the plant operating at 100 percent power, an

electrical fault with the A condensate booster pump occurred which caused the pump to trip.

This trip caused an initial reduction in reactor water level because of an approximate

22 percent loss in total flow to the reactor feedwater pumps. In accordance with the reactor

feedwater malfunction offnormal event procedure 05-1-02-V-7, operators reduced reactor

recirculation flow to 70 Mlbm/hr using the fast detent option. This rapid reduction in

recirculation flow exacerbated the perturbation on the feedwater system and ultimately led to

the feedwater heater drain tank (HDT) level control valves closing to maintain level in the

HDT. However, the combination of a load reduction and the HDT level control valves closing

caused level in HDT to increase which created level oscillations that the HDT level control

valves were not able to recover from.

The response of the HDT level control valves caused a reduction in the flow from the HDT to

the reactor feedwater pumps because the valves were not sized appropriately to respond to a

loss of condensate booster pump. The valves responded too slowly to the transient to

maintain adequate suction pressure to the feedwater pumps which ultimately resulted in a trip

of the A reactor feedwater pump. Further complications in the feedwater system resulted in

continued lowering of feedwater flow to the reactor and a continuing lowering of reactor water

level. Prior to reaching the setpoint for an automatic scram, operators manually inserted a

scram and recovered from the transient without incident.

The licensee performed a root cause analysis of the cause of the feedwater transient and

determined that an inadequate engineering change performed in the 2011/2012 timeframe

was the root cause. Engineering change (EC) 23022 modified the HDT level control valves by

replacing the existing 8-inch valves with 12-inch valves. The inspectors reviewed the design

verification for this modification and determined that the licensee failed to identify that this

modification could affect the design, performance, or operation of the main feedwater pumps

and failed to identify valve stroke time as a critical parameter to the HDT level control valve

performance. Additionally, the licensee determined that the use of the fast detent reduction in

reactor recirculation flow in procedure 05-1-02-V-7 was not evaluated in design calculations

that evaluated HDT response to condensate booster pump transients. Performing such an

evaluation in conjunction with more thorough design verifications in EC 23022 likely would

have identified the design deficiency with the replacement HDT level control valves. The

inspectors concluded that this was not a procedure deficiency with procedure 05-1-02-V-7,

but rather another example of the inadequate modification to the HDT level control valves.

Licensee Procedure EN-DC-115, Engineering Change Process, revision 10, step 4.2,

required the design verifier to perform a thorough review of all information contained in the

engineering change to ensure that the document is technically adequate, procedurally

compliant, accurate, and of a quality to warrant approval and issuance. The mechanical

design engineering input for EC 23022 contained various screening criteria, one of which was

Affect the design, performance, or operation of pumps. Another screening criteria was

Affect hydraulic requirements such as pump net positive suction head, allowable pressure

drops, system curves, etc. Neither of these criteria were marked as being impacted. The

inspectors determined that, based on the demonstrable effects of the valve operation from

the condensate booster pump trip, the HDP level control valve modification affected both

criteria and was required to be evaluated by procedure EN-DC-115, but was not evaluated.

The licensee reported this event as Licensee Event Report 05000416/2022-003-00 on

18

February 16, 2023.

Corrective Actions: Licensee corrective actions included replacing the failed condensate

booster pump motor, implementing risk management actions to reduce the potential for

another condensate booster pump transient, and evaluating long term corrective actions

including modifications to the system.

Corrective Action References: This issue was entered into the licensees corrective action

program as condition report CR-GGN-2022-11392.

Performance Assessment:

Performance Deficiency: The failure to perform a thorough review of all information contained

in the engineering change to ensure that the document was technically adequate,

procedurally compliant, accurate, and of a quality to warrant approval and issuance was

contrary to licensee procedure EN-DC-115 and was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Design Control attribute of the Initiating Events

cornerstone and adversely affected the cornerstone objective to limit the likelihood of events

that upset plant stability and challenge critical safety functions during shutdown as well as

power operations. Specifically, the performance deficiency caused a reactor scram.

Significance: The inspectors assessed the significance of the finding using IMC 0609,

Appendix A, The SDP for Findings At-Power, exhibit 1. Because operators were able to

recover feedwater, the inspectors determined that the finding did not cause the loss of

mitigation equipment relied upon to transition the plant from the onset of the trip to a stable

shutdown condition. Consequently, the inspectors answered no to the transient initiators

screening question and the finding screened to a Green significance.

Cross-Cutting Aspect: None. Because the finding was the result of deficiencies that occurred

approximately 11 years prior to the event, a cross-cutting aspect is not applicable.

Enforcement: Inspectors did not identify a violation of regulatory requirements associated with

this finding.

Failure to Submit a Licensee Event Report Within 60 Days

Cornerstone Severity Cross-Cutting Report

Aspect Section

Not Severity Level IV Not 71153

Applicable NCV 05000416/2023001-04 Applicable

Open/Closed

The inspectors identified two examples of a Severity Level IV non-cited violation of

10 CFR 50.73(a), Licensee Event Report System, for the licensees failure to submit two

licensee event reports within 60 days after discovery of the event. Specifically, the licensee

determined on November 4, 2021, that an issue associated with jet pump summer

miscalibration resulted in multiple cases of operation in a condition prohibited by technical specification 3.2.2 and the licensee event report was submitted 76 days later, on

January 19, 2022. Additionally, the licensee determined on December 2, 2021, that an issue

associated with oscillation power range monitors was a reportable event and the licensee

event report was submitted 62 days later on February 2, 2022.

Description: First Example: Licensee Event Report (LER) 2021-004-00

19

As described in Inspection Report 05000416/2021003 (ML21312A172), the inspectors

identified a non-cited violation related to the licensees failure to identify a condition adverse

to quality associated with the jet pump flow indications. As a result, the licensee entered the

issue into the corrective action program as condition report CR-GGN-2021-05802. As part of

its evaluation, the licensee performed a past operability evaluation and ultimately reported the

issue as LER 2021-004-00, Procedure Inadequacy Resulted in Core Monitoring System

Miscalibration and Violation of Technical Specifications, (ML22019A270) on

January 19, 2022.

On November 4, 2021, the licensee concluded in the past operability evaluation that there

were 1677 instances in the past 3 years where the plant was operating in a condition

prohibited by technical specification (TS) LCO 3.2.2. LCO 3.2.2 required that all minimum

critical power ratios (MCPR) shall be greater than or equal to the MCPR operating limits

specified in the core operating limit report. Condition A of this LCO required that for any

MCPR not within limits to restore MCPR(s) to within limits within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. Condition B

required that if the required action of condition A was not met to reduce thermal power to less

than 21.8 percent RTP. For the 1677 cases identified, the licensee determined that MCPR

was not within limits for greater than 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> while reactor power was greater than

21.8 percent RTP.

On November 8, 2021, the licensee initiated a corrective action to condition report

CR-GGN-2021-05802 to revise the past operability evaluation to update the core monitoring

cases used in the thermal limit evaluation to exclude those ran during a transient and

re-evaluate the results. The licensee concluded the revised evaluation on November 18,

2021, and eliminated two of the 1677 cases. In discussions with engineering, the inspectors

learned that the purpose of the revised evaluation was only to determine the correct number

of cases where the TSs were violated. Engineering never had any doubt that the fundamental

conclusion that the TSs were violated would not change because the vast majority of the

already identified cases were during steady state operations and would not have been

affected by the revision.

Because the revised evaluation essentially confirmed the results of the original evaluation

and only sought to finalize the most accurate number of cases where the TSs were violated,

the inspectors concluded that the engineers who performed, checked, and approved the past

operability evaluation discovered the reportable condition on November 4, 2021. On

November 23, 2021, the licensee concluded that the identified condition prohibited by

TS 3.2.2 was a reportable condition. The licensee set a due date to submit the LER within

60 days of their determining that the condition was reportable rather than 60 days from the

date that the reportable condition was identified. Consequently, LER 2021-004-00 was

submitted 76 days after the condition was identified (November 4, 2021).

Licensee Procedure EN-LI-108, Event Notification and Reporting, revision 19, defines time

of discovery as the moment a condition is identified by anyone working at or for the facility.

This applies when dealing with Reportability. In the LER, the licensee stated that, On

November 18, 2021, a past operability evaluation determined that an issue associated with

the jet pump summer miscalibration was a reportable event. The inspectors determined that

because the licensee originally discovered the reportable condition on November 4, 2021,

and at no point during the revision process did the licensee ever have a reasonable belief that

the conclusion that the plant operated in a condition prohibited by TSs would change.

The inspectors reviewed the applicable TS, the licensees documents related to the discovery

20

such as the past operability evaluation and condition report CR-GGN-2021-05802, and the

circumstances surrounding the discovery of the failure to meet TS 3.2.2, and determined that:

TS 3.2.2 was not administrative in nature;

the event was not a case of a late surveillance test where the oversight was corrected,

the test was performed, and the equipment was found to be capable of performing its

specified safety functions; and

TS 3.2.2 was not revised prior to discovery of the event such that the operation or

condition was no longer prohibited at the time of discovery of the event.

The inspectors concluded that the underlying misunderstanding of what the date of discovery

is for past operability evaluations directly led to the failure to report the event within 60 days

as required by 10 CFR 50.73.

Second Example: LER 2021-005-00

As documented in this inspection report, the licensee identified on June 21, 2021, that they

failed to update the detect and suppress solution - confirmation density settings for the

oscillation power range monitors. In consultation with the vendor, the licensee performed a

past operability evaluation as documented in condition report CR-GGN-2021-04781. On

December 2, 2021, the licensee finished the past operability evaluation and determined that

the failure to update this setting resulted in operation in a condition prohibited by TSs.

On December 6, 2021, the licensee reviewed the past operability evaluation and concluded

that the condition was reportable as an LER due to violating TS 3.3.1.1. Similar to

LER 2021-004-00, the licensee assigned a due date to submit the LER within 60 days of their

determining that the condition was reportable rather than 60 days from the date that the

reportable condition was identified. On February 2, 2022, the licensee submitted

LER 2021-005-00, Oscillation Power Range Monitors Technical Specification

Noncompliance. The inspectors concluded that this LER was submitted 62 days after the

condition was identified on December 2, 2021.

The inspectors reviewed the applicable TS, the licensees documents related to the discovery

such as the past operability evaluation and condition report CR-GGN-2021-04781, and the

circumstances surrounding the discovery of the failure to meet TS 3.3.1.1, and determined

that:

TS 3.3.1.1 was not administrative in nature;

the event was not a case of a late surveillance test where the oversight was corrected,

the test was performed, and the equipment was found to be capable of performing its

specified safety functions; and

TS 3.3.1.1 was not revised prior to discovery of the event such that the operation or

condition was no longer prohibited at the time of discovery of the event.

During discussions with licensee management about these issues the inspectors determined

that the licensee had a misunderstanding of what the correct time of discovery was for

conditions such as these where a past operability evaluation had determined that a violation

of Technical Specifications had occurred. Licensee management believed that the time of

discovery for reporting timelines started when regulatory affairs determined that the issue was

reportable - not when the past operability evaluation concluded that the plant had operated in

a condition prohibited by Technical Specifications. The inspectors determined that the

21

licensees understanding was contrary to both licensee procedure EN-LI-108 and 10 CFR 50.73(a)(1), and that this misunderstanding would likely have continued without NRC

interaction.

The inspectors did not identify any additional violations as a result of these LER reviews. Both

LERs are closed.

Corrective Actions: The licensee entered the late reporting concern into the corrective action

program to correct the causes that led to the late reports.

Corrective Action References: This issue was entered into the licensees corrective action

program as condition report CR-GGN-2023-00700

Performance Assessment: The inspectors determined this violation was associated with a

minor performance deficiency. Specifically, the licensee failed to timely submit two LERs,

contrary to licensee procedure EN-LI-108. This performance deficiency was minor because

the inspectors answered No to all three screening questions in appendix B of IMC 0612.

Enforcement: The ROPs significance determination process does not specifically consider

the regulatory process impact in its assessment of licensee performance. Therefore, it is

necessary to address this violation using traditional enforcement .

Severity: The NRC determined this violation was Severity Level IV in accordance with

example 6.9.d.9 of the NRC Enforcement Policy because the licensee failed to submit an

LER in accordance with 10 CFR 50.73.

Violation: Title 10 CFR 50.73(a)(1) requires, in part, that a licensee shall submit an LER for

any event of the type described in this paragraph within 60 days after the discovery of the

event.

Title 10 CFR 50.73(a)(2) requires, in part, that the licensee shall report any operation or

condition which was prohibited by the plants TSs except as allowed by

10 CFR 50.73(a)(2)(i)(B)(1), 10 CFR 50.73(a)(2)(i)(B)(2), or 10 CFR 50.73(a)(2)(i)(B)(3).

Contrary to the above:

1. On January 4, 2022, the licensee failed to submit LER 2021-004-00 for a condition

which was prohibited by the plants TSs within 60 days after the discovery of the event

and the condition was not an exception as allowed by either

10 CFR 50.73(a)(2)(i)(B)(1), 10 CFR 50.73(a)(2)(i)(B)(2), or

10 CFR 50.73(a)(2)(i)(B)(3).

2. On February 1, 2022, the licensee failed to submit LER 2021-005-00 for a condition

which was prohibited by the plants TSs within 60 days after the discovery of the event

and the condition was not an exception as allowed by either

10 CFR 50.73(a)(2)(i)(B)(1), 10 CFR 50.73(a)(2)(i)(B)(2), or

10 CFR 50.73(a)(2)(i)(B)(3).

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

section 2.3.2 of the Enforcement Policy.

22

Failure to Evaluate a Deviation for 10 CFR Part 21 (Part 21) Applicability

Cornerstone Severity Cross-Cutting Report

Aspect Section

Not Severity Level IV Not 71153

Applicable NCV 05000416/2023001-05 Applicable

Open/Closed

EA-22-104

The inspectors identified a Severity Level IV non-cited violation of 10 CFR 21.21(a)(1) for the

licensees failure to evaluate a deviation in a basic component within 60 days of discovery. As

a result, the licensee failed to evaluate a deviation identified on April 21, 2021, that was

associated with a reportable defect that could have created a substantial safety hazard were

it to have remained uncorrected within 60 days of discovery. The licensee completed the

evaluation on August 3, 2022, and determined that the deviation was associated with a

substantial safety hazard and was required to be reported under Part 21.

Description: On February 22, 2021, during a local leak rate test for the 208-foot containment

personnel airlock outer door under work order (WO) 52884887-11, the as-found leak test

exceeded TS surveillance requirement 3.6.1.2.1 limit of 16,880 SCCM. Because the licensee

was not able to stabilize at test pressure due to the capability of the test equipment, an exact

leakage rate could not be obtained. The equalizing valve on the outer door 1M23F018D was

identified to be leaking and was replaced under WO 558041-01. The issue was entered into

the corrective action program as condition report CR-GGN-2021-01451.

After replacing the equalizing valve on the outer door, the licensee discovered that the

equalizing valve on the inner door 1M23F018C was also leaking. The reported leak rate of

9000 SCCM was above the Appendix J administrative limit of 944 SCCM. Inner

door 1M23F018C was rebuilt with new O-rings and was lubricated prior to reinstallation into

the airlock. Following door 1M23F018D replacement and door 1M23F018C rebuild, the local

leak rate test tested with satisfactory results.

On April 21, 2021, the licensee determined that the cause of excessive leakage for both

doors 1M23F018C and D was the failure to lubricate the valves prior to installation which

caused premature O-ring failure. Additionally, with the inner door opened, the leakage rate

would have exceeded TS requirements. Consequently, the licensee submitted

LER 05000416/2021-001-00 on May 14, 2021.

The valves were purchased on February 7, 2018, as basic components under purchase

order 10537921. The procurement documents required the valves to be furnished in

accordance with the vendors commercial grade dedication plan CGI-013. This dedication

plan required the vendor to disassemble the valves, replace the O-rings with dedicated

O-rings, lubricate the stem and O-rings, reassemble the valves, and perform final acceptance

testing before shipping the valves as basic components. However, the licensee determined

that neither valve was lubricated when they were installed and developed corrective actions

to revise the preventive maintenance instructions to ensure replacement valves are lubricated

prior to installation.

The inspectors determined that the licensee did not recognize that a deviation or failure to

comply potentially associated with a substantial safety hazard existed, and therefore, did not

evaluate the lack of lubrication as such. Licensee Procedure EN-LI-108-01, 10 CFR 21

Evaluations and Reporting, revision 13, required the issue to be screened for Part 21

reportability.

23

The licensee entered the inspectors concerns into their corrective action program, performed

an evaluation, determined that the issue was a reportable Part 21 event on August 3, 2022,

and made the initial notification on October 31, 2022.

The inspectors determined that the pertinent reporting criteria as required by

10 CFR 21.21(d)(4) was not provided in LER 05000416/2021-001-00, and therefore, the

licensee did not meet the reporting requirement exclusion as provided by 10 CFR 21.21(d)(2).

Specifically, the licensee failed to provide the following information in their LER describing the

valve failure:

identification of the basic component which failed to comply or contained a defect

identification of the firm supplying the basic component which failed to comply or

contained a defect

nature of the defect or failure to comply and the safety hazard which was created or

could be created by such defect or failure to comply

the date on which the information of such defect or failure to comply was obtained

any advice related to the defect or failure to comply about the basic component that

has been, is being, or will be given to purchasers or licensees

The inspectors reviewed the receipt inspection, certificate of conformance, and other

procurement documents and determined that the cause of the valve failure to meet TS

surveillance requirement 3.6.1.2.1 was not reasonably foreseeable by the licensee; therefore,

no performance deficiency related to the TS violation was identified. Additionally, traditional

enforcement related to the TS violation does not apply. This LER is closed.

Corrective Actions: The licensee reported the equalizing valve failure as a Part 21 notification

on October 31, 2022, and provided training on Part 21 requirements to applicable staff.

Corrective Action References: This issue was entered into the licensees corrective action

program as condition reports CR-GGN-2022-07146 and CR-GGN-2022-09773.

Performance Assessment: The inspectors determined this violation was associated with a

minor performance deficiency. Specifically, the failure to evaluate a deviation in a basic

component for 10 CFR Part 21 reportability was contrary to licensee procedure EN-LI-108-01

and was a performance deficiency. This performance deficiency was minor because the

inspectors answered No to all three screening questions in appendix B of IMC 0612. No

performance deficiency was identified for the failure to meet TS surveillance

requirement 3.6.1.2.1.

Enforcement: The ROPs significance determination process does not specifically consider

the regulatory process impact in its assessment of licensee performance. Therefore, it is

necessary to address this violation using traditional enforcement.

Severity: The NRC determined that this violation initially screens as Severity Level III in

accordance with section 6.9.c.5 of the NRC Enforcement Policy. However, in reviewing the

specific circumstances of this violation (i.e., the NRC resident staff was aware of the issue,

and there was little to no impact to the inspection process/regulatory process; the impact to

overall containment leakage is mitigated by the size of the valves; your staff entered the issue

into the corrective action program and issued a licensee event report after they concluded it

was reportable under 10 CFR 50.73; and the valves were only supplied to the Grand Gulf

Nuclear Station and no other licensees) the NRC determined that it is more appropriately

24

categorized as a Severity Level IV violation.

Title 10 CFR 21.21(a)(1) requires, in part, that entities subject to the regulations in

10 CFR Part 21 shall evaluate deviations and failures to comply to identify defects associated

with substantial safety hazards as soon as practicable and, except as provided in

10 CFR 21.21(a)(2), in all cases within 60 days of discovery, in order to identify a reportable

defect that could create a substantial safety hazard, were it to remain uncorrected.

Contrary to the above, from June 21, 2021, to August 3, 2022, the licensee failed to evaluate

deviations and failures to comply to identify defects associated with substantial safety

hazards as soon as practicable and in all cases within 60 days of discovery, in order to

identify a reportable defect that could create a substantial safety hazard, were it to remain

uncorrected. Specifically, on April 21, 2021, the licensee identified that the lack of lubrication

on the containment personnel airlock equalizing valves caused the excessive leakage and

failed to identify, within 60 days, that it as a substantial safety hazard. The licensee evaluated

the condition as a substantial safety hazard on August 3, 2022.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

section 2.3.2 of the Enforcement Policy.

Failure to Make a Timely Part 21 Report

Cornerstone Severity Cross-Cutting Report

Aspect Section

Not Severity Level IV Not 71153

Applicable NOV 05000416/2023001-06 Applicable

Open

EA-22-104

The inspectors identified a Severity Level IV violation of 10 CFR 21.21(a)(3) and

10 CFR 21.21(d) for the licensees failure to make a Part 21 report within the required time

limits specified in Part 21. Specifically, the licensee notified the responsible officer 55 working

days after making the determination that a substantial safety hazard existed (50 working days

late) and the report was made 3 calendar days after the responsible officer was notified

(1 day late).

Description: On August 3, 2022, the licensee completed an evaluation of the deviation

identified with door 1M23F018C and D, as discussed previously in this inspection report, and

determined that the reportable defect could create a substantial safety hazard were it to

remain uncorrected.

On October 6, 2022, the inspectors questioned the licensee on the Part 21 report because it

had not yet been made, and the inspectors discussed with the licensee the reporting

timelines contained in 10 CFR Part 21(a)(3) and 10 CFR Part 21(d)(3). The inspectors

determined that the licensees procedure for performing Part 21 reviews,

procedure EN-LI-108-01, revision 14, contained reporting time requirements that were

consistent with these two requirements. The inspectors were concerned that a Part 21

notification had not been made despite the site having determined several weeks prior that a

reportable defect existed.

On October 14, 2022, the licensee wrote condition report CR-GGN-2022-09773 to document

that the station concluded that a Part 21 notification was necessary but had not performed the

follow-up steps in the proper timeframe. The licensee informed the site vice president on

25

October 28, 2022, and made the initial Part 21 notification of a reportable defect on

October 31, 2022.

Corrective Actions: The licensee reported the equalizing valve failure as a Part 21 notification

on October 31, 2022, and provided training on Part 21 requirements to applicable staff.

Corrective Action References: This issue was entered into the licensees corrective action

program as condition reports CR-GGN-2022-09773 and CR-GGN-2022-10127.

Performance Assessment: The inspectors determined this violation was associated with a

minor performance deficiency. Specifically, the failure to make a timely Part 21 report was

contrary to licensee procedure EN-LI-108-01 and was a performance deficiency. This

performance deficiency was minor because the inspectors answered No to all three

screening questions in appendix B of IMC 0612.

Enforcement: The ROPs significance determination process does not specifically consider

the regulatory process impact in its assessment of licensee performance. Therefore, it is

necessary to address this violation using traditional enforcement.

Severity: The NRC determined this violation was Severity Level IV in accordance with

example 6.9.d.13 of the NRC Enforcement Policy because the licensee failed to implement

adequate 10 CFR Part 21 processes or procedures. Specifically, the licensee failed to

ensure that adequate process controls were in place to ensure that the required timelines

associated with the discovery of a defect associated with a substantial safety hazard were

met.

Title 10 CFR 21.21(a)(3) requires, in part, that entities subject to the regulations in

10 CFR Part 21 shall ensure that a director or responsible officer is informed as soon as

practicable, and, in all cases, within the 5 working days after completion of the evaluation

described in 10 CFR 21.21(a)(1).

Title 10 CFR 21.21(d) requires, in part, that a director or responsible officer must notify the

Commission when he or she obtains information reasonably indicating a failure to comply or a

defect within two days following receipt of the information.

Contrary to the above, from August 13, 2022, to October 31, 2022, the licensee failed to

notify the Commission after the discovery of a defect associated with a substantial safety

hazard evaluation described in 10 CFR 21.21(a)(1). Specifically, the licensee identified that

the lack of lubrication on the containment personnel airlock equalizing valves caused the

excessive leakage and evaluated the condition as a substantial safety hazard on August 3,

2022, but failed to make the timeliness requirements to notify the Commission.

Enforcement Action: This violation is being cited because the licensee failed to restore

compliance within a reasonable period of time after the violation was identified consistent with

section 2.3.2 of the Enforcement Policy.

Licensee-Identified Non-Cited Violation 71153

This violation of very low safety significance was identified by the licensee and has been

entered into the licensee corrective action program and is being treated as a non-cited

violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: The licensee identified a Green NCV of 10 CFR Part 50, Appendix B, Criterion XVI,

Corrective Action, when they identified the failure to adequately update the oscillation power

26

range monitor (OPRM) settings in both 2016 and 2019 which ultimately led to a reportable

event.

Title 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, requires, in part, that

conditions adverse to quality shall be promptly identified and corrected.

Contrary to the above, from June 23, 2018, until June 23, 2021, the licensee failed to

promptly identify and correct a condition adverse to quality. Specifically, with the OPRM

DSS-CD Tmax set to 3.5 seconds, the ability of the OPRMs to perform their intended safety

function was impacted until the setting was changed to 4.0 seconds on June 23, 2021. This

failure directly led to the failure to meet TS 3.3.1.1 for the affected function and the

subsequent TS noncompliance. Therefore, a separate TS 3.3.1.1 violation is not warranted.

This violation is being treated as a non-cited violation, consistent with section 2.3.2 of the

Enforcement Policy. As discussed in this inspection report, one additional violation for the

failure to make a timely report was identified as a result of this LER review. This LER is

closed.

Significance/Severity: The inspectors assessed the significance of the finding using

Appendix A, The Significance Determination Process (SDP) for Findings At-Power, exhibit 2

- Mitigating Systems Screening Questions. The finding screened to Green because it only

affected the OPRM RPS trip signal and did not affect the function of other redundant trips or

diverse methods of reactor shutdown.

Corrective Action References: This issue was entered into the licensees corrective action

program as condition reports CR-GGN-2021-04781 and CR-GGN-2021-06434

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On February 15, 2023, the inspectors presented the emergency preparedness exercise

scenario review inspection results to Mike Lewis, Manager, Emergency Preparedness

and other members of the licensee staff.

On March 2, 2023, the inspectors presented the occupational radiation safety inspection

results to Jason Richardson, Acting General Manager of Plant Operations, and other

members of the licensee staff.

On April 6, 2023, the inspectors presented the integrated inspection results to Brad

Kapellas, Site Vice President, and other members of the licensee staff.

On April 11, 2023, the inspectors presented the emergency preparedness performance

indicator verification and emergency plan change review inspection results to Brad

Kapellas, Site Vice President, and other members of the licensee staff.

27

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.04 Corrective Action CR-GGN- 2021-03871, 2022-01616, 2022-01772, 2022-05220, 2022-

Documents 10380, 2022-10931, 2023-00582, 2023-01532

71111.04 Procedures 04-1-01-P75-1 Standby Diesel Generator System 118

71111.04 Procedures 06-ME-1000-V-0001 Snubber Visual Inspection 108

71111.04 Work Orders WO 423277

71111.05 Corrective Action CR-GGN- 2023-00520

Documents

71111.05 Procedures 06-OP-SP64-R-0049 Fire Rated Sealed Penetrations Visual Inspection 113

71111.05 Procedures EN-DC-161 Control of Combustibles 25

71111.05 Procedures GGNS-MS-53 Control of Transient Combustible Material Exclusion and 1

Storage Areas

71111.12 Miscellaneous Receipt Inspection for PO 009900002

71111.12 Miscellaneous 009900002 Purchase Order

71111.12 Work Orders WO 590923, 593088

71111.13 Corrective Action CR-GGN- 2023-00633, 2023-00634, 2023-00636, 2023-00637, 2023-

Documents 00639, 2023-00640

71111.15 Calculations MC-Q1B33-92005

71111.15 Corrective Action CR-GGN- 2023-00478, 2023-00484, 2023-00562, 2023-00582, 2023-

Documents 00633, 2023-00721, 2023-01532

71111.15 Drawings Q1E12G03R11 Pipe Support Drawing 1

71111.15 Miscellaneous GGNS-NE-12-00025 Engineering Report

71111.18 Miscellaneous PR-PRHQN-2021-

00383

71111.18 Procedures EN-DC-161 Control of Combustibles 24, 25

71111.24 Corrective Action CR-GGN- 2021-01355, 2022-00634, 2022-00636, 2022-00637, 2022-

Documents 04646, 2023-00582, 2023-00633, 2023-00892

71111.24 Miscellaneous FTR-21-0406

71111.24 Work Orders WO 423277, 559947-01, 590923, 591227, 591510, 52916166,

52931269, 53022735

71114.01 Corrective Action CR-GGN- 2021-02198, 2022-02299, 2022-06688, 2022-06763, 2022-

Documents 06842, 2022-08537, 2022-08538, 2023-00218, 2023-01253,

2023-01264, 2023-01270

28

Inspection Type Designation Description or Title Revision or

Procedure Date

71114.01 Miscellaneous 2/22/2023 Dress Rehearsal Report 03/21/2023

71114.01 Procedures 10-S-01-12 Radiological Assessment and Protective Action 50

Recommendations

71114.01 Procedures 10-S-01-14 Emergency Radiological Monitoring 26

71114.01 Procedures 10-S-01-17 Emergency Personnel Exposure Control 19

71114.01 Procedures 10-S-01-34 Joint Information Center (JIC) Operations 23

71114.01 Procedures 10-S-01-6 Notification of Offsite Agencies and Plant On-Call 58

Emergency Personnel

71114.01 Procedures EN-EP-313 Offsite Dose Assessment using the Unified RASCAL 4

Interface

71114.01 Procedures EN-EP-609 Emergency Operations Facility (EOF) Operations 6

71114.01 Procedures EN-EP-801 Emergency Response Organization 18

71114.04 Miscellaneous 10 CFR 50.54(q)(3) Facility: GGNS, Title: GGNS EAL Technical Bases and 08/15/2022

Evaluation, Charts

Procedure/Document

Number: EAL

Technical Bases and

Charts, Revision: 2

71114.04 Miscellaneous 10 CFR 50.54(q)(3) Facility: GGNS, Title: GGNS EAL Technical Bases and 08/15/2022

Screening, Charts

Procedure/Document

Number: EAL

Technical Bases and

Charts, Revision: 2

71114.04 Miscellaneous 10 CFR 50.54(q)(3) Facility: GGNS, Title: GGNS EAL Technical Bases and 12/07/2022

Screening, Charts

Procedure/Document

Number: EAL

Technical Bases and

Charts, Revision: 3

71114.04 Miscellaneous 10 CFR 50.54(q)(3) Facility: GGNS, Title: GGNS EAL Technical Basis 12/07/2022

Screening,

Procedure/Document

Number: EAL

29

Inspection Type Designation Description or Title Revision or

Procedure Date

Technical Basis,

Revision: 3

71114.04 Miscellaneous GNRO2022-00011 Grand Gulf Nuclear Station, Unit 1; Emergency Action Level 09/08/2022

(EAL) Technical Basis Document, Revision 2

71114.04 Miscellaneous GNRO2023-00002 Grand Gulf Nuclear Station, Unit 1; Emergency Action Level 02/01/2023

(EAL) Technical Bases Document Revision 3; Grand Gulf

Nuclear Station, Unit 1; Docket No. 50-416, License No.

NPF-29

71114.04 Procedures 05-S-01-EP-4M1-3 Auxiliary Building Control/Radioactive Release Control 0

Modes 1-3

71114.04 Procedures 05-S-01-SAP-1M1-4 Severe Accident Procedure, RPV Control Modes 1-4 0

71114.04 Procedures 05-S-01-SAP-1M5 Severe Accident Procedure, RPV Control Mode 5 0

71114.04 Procedures 05-S-01-SAP-2M1-4 Severe Accident Procedure, Containment and Radioactive 0

Release Control Modes 1-4

71114.04 Procedures 05-S-01-SAP-2M5 Severe Accident Procedure, Containment and Radioactive 0

Release Control Mode 5

71114.04 Procedures EN-EP-305 Emergency Planning 10CFR50.54(q) Review Program 8

71114.08 Miscellaneous GIN 2021-00062 Grand Gulf Nuclear Station, EAL Technical Bases 1

71114.08 Miscellaneous GNRO-2015/00057 Grand Gulf Nuclear Station Hostile Action Based Exercise 08/14/2015

Scenario; Grand Gulf Nuclear Station, Unit 1; Docket No.

50-416; License No. NPF-29

71114.08 Miscellaneous GNRO/2018-00061 2019 Emergency Plan Full Participation Exercise Drill 01/08/2019

Scenario; Grand Gulf Nuclear Station - Unit 1; Docket

No. 50-416; License No. NPF-29

71114.08 Miscellaneous GNRO2021/00001 Grand Gulf Nuclear Station 2021 Graded Exercise Scenario; 01/14/2021

Grand Gulf Nuclear Station, Unit 1; Docket No. 50-416;

License No. NPF-29

71114.08 Miscellaneous GNRO2023-00001 Grand Gulf Nuclear Station 2023 Graded Exercise Scenario; 01/19/2023

Grand Gulf Nuclear Station, Unit 1; Docket No. 50-416;

License No. NPF-29

71114.08 Procedures 10-S-01-12 Radiological Assessment and Protective Action 49

Recommendations

71124.01 Corrective Action CR-GGN- 2022-02014, 2022-02368, 2022-02412, 2022-02794, 2022-

Documents 02802, 2022-03067, 2022-03269, 2022-04863, 2022-06893,

30

Inspection Type Designation Description or Title Revision or

Procedure Date

2022-06942, 2022-06943, 2022-07332, 2022-07727, 2022-

07743, 2022-08255, 2022-11356, 2022-20413

71124.01 Corrective Action CR-GGN- 2023-01296, 2023-01364, 2023-01371, 2023-01372

Documents

Resulting from

Inspection

71124.01 Procedures EN-RP-100 Radiation Worker Expectations 13

71124.01 Procedures EN-RP-101 Access Control for Radiologically Controlled Areas 17

71124.01 Procedures EN-RP-108 Radiation Protection Posting 23

71124.01 Procedures EN-RP-121 Radioactive Material Control 18

71124.01 Procedures EN-RP-152 Conduct of Radiation Protection 7

71124.01 Procedures EN-RP-210 Area Monitoring Program 1

71124.01 Radiation CTMT208 Containment 208-Foot Elevation 07/31/2022

Surveys

71124.01 Radiation CTMT208 Containment 208-Foot Elevation 07/17/2022

Surveys

71124.01 Radiation GGN-AS-030123- Air Sampling Report 03/01/2023

Surveys 0258

71124.01 Radiation Work RWP 2022-1313 Refuel Floor Miscellaneous Craft Support and Management 0

Permits (RWPs)

71124.01 Radiation Work RWP 2023-1070 Funda Filter Work 1

Permits (RWPs)

71124.01 Work Orders 583982 1G41A002 - Generated to Support Spent Fuel Pool 10/03/2022

Cleanout Project

71124.01 Work Orders 590804 SG17D003: Replace Floor Drain Filter Screens 1

71124.04 Corrective Action CR-GGN- 2020-11673, 2021-01524, 2021-01824, 2021-07014, 2022-

Documents 02368, 2022-03127, 2022-03415, 2022-03520, 2022-09337,

2022-10436, 2023-00693, 2023-00694, 2023-00695

71124.04 Corrective Action CR-GGN- 2023-01409

Documents

Resulting from

Inspection

71124.04 Corrective Action CR-HQN- 2023-00265, 2023-00269, 2023-00270, 2023-00271

Documents

31

Inspection Type Designation Description or Title Revision or

Procedure Date

Resulting from

Inspection

71124.04 Miscellaneous NRC Form 5 for various workers 2021, 2022

71124.04 Miscellaneous List of EDEX and Multipack Dosimetry 2022

71124.04 Miscellaneous Source Term Reduction 2022

71124.04 Miscellaneous 100518-0 NVLAP Certificate of Accreditation to ISO/IEC 17025:2017: 01/01/2023

Landauer, Inc. Ionizing Radiation Dosimetry

71124.04 Miscellaneous CR-GGN-2022- Whole Body Count and Dose Assessment 03/08/2022

02368

71124.04 Miscellaneous CR-GGN-2022- Whole Body Count and Dose Assessment 03/19/2022

03127

71124.04 Miscellaneous CR-GGN-2022- Whole Body Count and Dose Assessment 03/24/2022

03415

71124.04 Miscellaneous CR-GGN-2023- Whole Body Count and Dose Assessment 03/24/2022

01409

71124.04 Miscellaneous GGN-RPT-20-005R0 Evaluation of Grand Gulf Nuclear Station's Average Beta 05/06/2021

and Gamma Energy

71124.04 Miscellaneous GGN-RPT-21-002R0 Neutron Monitoring at Grand Gulf Nuclear Station 08/19/2021

71124.04 Procedures EN-RP-201 Dosimetry Administration 5

71124.04 Procedures EN-RP-202 Personnel Monitoring 15

71124.04 Procedures EN-RP-203 Dose Assessment 10

71124.04 Procedures EN-RP-204 Special Monitoring Requirements 11

71124.04 Procedures EN-RP-204-01 Effective Dose Equivalent (EDEX) Monitoring 3

71124.04 Procedures EN-RP-205 Prenatal Monitoring 5

71124.04 Procedures EN-RP-206 Dosimeter of Legal Record Quality Assurance 7

71124.04 Procedures EN-RP-208 Whole Body Counting/In-Vitro Bioassay 7

71124.04 Radiation Work RWP 2021-1082 DFS (Hi Storm 1F16D003BN\ MPC # 1F16D002BN) Work 0

Permits (RWPs) Order #502624

71124.04 Radiation Work RWP 2022-1508 Under Vessel Maintenance 2

Permits (RWPs)

71124.04 Radiation Work RWP 2022-1516 RF23 ISI and Support Activities 1

Permits (RWPs)

71124.04 Radiation Work RWP 2022-1531 Suppression Pool Diving and Vacuum with Diakont Robotic 3

Permits (RWPs) Decon Equipment

32

Inspection Type Designation Description or Title Revision or

Procedure Date

71124.04 Self-Assessments LO-GLO-2022- Pre-NRC Inspection Occupational Dose Assessment 01/30/2023

00086 IP 71124.04

71151 Corrective Action CR-GGN- 2022-06665, 2022-07790, 2022-08868, 2023-00218, 2023-

Documents 00219, 2023-00220

71151 Procedures EN-LI-114 Regulatory Performance Indicator Process 20

71153 Corrective Action CR-GGN- 2016-08765, 2017-12477, 2018-09890, 2019-01757, 2019-

Documents 01833, 2019-04639, 2021-01451, 2021-01536, 2021-02950,

2021-04781, 2021-05802, 2021-06434, 2022-06586, 2022-

07146, 2022-09773, 2022-10127, 2022-11392

71153 Engineering EC-23022 GGNS Extended Power Uprate Feedwater Heater Drain 0

Changes System Level Control Valve Modifications

71153 Engineering EC-91787 Issue Engineering Report GGNS-SA-21-00002 and Revise 1

Changes Engineering Report GGNS-N-16-00007

71153 Miscellaneous 10462339 Purchase Order 02/04/2016

71153 Miscellaneous 10472129 Purchase Order 02/17/2016

71153 Miscellaneous 10537921 Purchase Order 02/07/2018

71153 Miscellaneous 10619352 Purchase Order 08/25/2020

71153 Miscellaneous 55636 Receiving Inspection Report 05/22/2018

71153 Procedures EN-DC-115 Engineering Change Process 10

71153 Procedures EN-LI-108 Event Notification and Reporting 19

71153 Procedures EN-LI-108-01 10 CFR 21 Evaluations and Reporting 13 and 14

71153 Work Orders WO 526443, 526444, 526445, 526446, 558041, 52782092,

52839101, 52884887

33