ML110760579

From kanterella
Jump to navigation Jump to search
IR 05000298-10-006, on October 18,2010 - March 14, 2011, Nebraska Public Power District; Cooper Nuclear Station: Triennial Fire Protection Team Inspection, Preliminary White Finding
ML110760579
Person / Time
Site: Cooper Entergy icon.png
Issue date: 03/17/2011
From: Anton Vegel
Division of Reactor Safety IV
To: O'Grady B
Nebraska Public Power District (NPPD)
References
EA-11-024 IR-10-006
Download: ML110760579 (55)


See also: IR 05000298/2010006

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

March 17, 2011

EA 11-024

Brian J. O'Grady, Vice President-Nuclear

and Chief Nuclear Officer

Nebraska Public Power District

Cooper Nuclear Station

72676 648A Avenue

Brownville, NE 68321

SUBJECT: COOPER NUCLEAR STATION - NRC TRIENNIAL FIRE PROTECTION

INSPECTION REPORT 05000298/2010006; PRELIMINARY WHITE FINDING

Dear Mr. O'Grady:

On November 5,2010, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at the Cooper Nuclear Station. The enclosed inspection report documents the

inspection results, which were discussed in an exit meeting on March 14, 2011, with

Mr. D. Buman, Director of Engineering, and other members of your staff.

During this inspection, the NRC staff examined activities conducted under your license as they

relate to public health and safety and compliance with the Commission's rules and regulations

and with the conditions of your license. Within these areas, the inspection consisted of selected

examination of procedures and representative records, observations of activities, and interviews

with personnel.

Based on the results of this inspection, the NRC has identified two findings that were evaluated

for risk under the Significance Determination Process. Violations were associated with each of

the findings.

The attached report discusses a finding that was preliminarily determined to be a White finding,

a finding with low-to-moderate increased safety significance which may require additional NRC

inspections. This finding was assessed based on the best available information, including

influential assumptions, using the applicable Significance Determination Process (SOP). As

described in Section 1R05.01 of the attached report, this finding involves the failure to verify that

procedure steps to safely shutdown the plant in the event of a fire would actually reposition

three motor operated valves to the required positions and the concurrent failure to address a

previous finding that involved the same procedure steps. This finding has preliminary low-to-

moderate safety significance because it involves llJultiple fire areas and risk factors that were

not dependent on specific fire damage. The scenarios of concern involve larger fires in specific

areas of the piant which trigger operators to implement fire response procedures to place the

plant in a safe shutdown condition. Since performing some of those actions using the

Nebraska Public Power District 2-

procedures as not have aligned three valves to their required positions, this would

challenge the operators' ability to establish adequate core cooling. This finding does not

represent an immediate safety concern because your staff promptly changed the procedures to

!ocally reposition position the valves.

This finding is also an apparent violation of NRC requirements and is being considered for

escalated enforcement action in accordance with the NRC Enforcement Policy. The current

Enforcement Policy is included on the NRC's web site at .:..:.==~..:....:...:...=:...~.;::..::..:-==c:::=c::...

In accordance with Inspection Manual Chapter 0609, we intend to complete our evaluation

using the best available information and issue our final determination of safety significance

within 90 days of this letter. The significance determination process encourages an open dialog

between the staff and the licensee; however the dialogue should not impact the timeliness of the

staff's final determination. Before we make a final decision on this matter, we will hold a

Regulatory Conference to provide you an opportunity to present to the NRC your perspectives

on the facts and assumptions used by the NRC to arrive at the finding and assess its

significance. The Regulatory Conference should be held within 30 days of the receipt of this

letter and we encourage you to submit supporting documentation at least one week prior to the

conference in an effort to make the conference more efficient and effective. This Regulatory

Conference will be open for public observation.

At the Regulatory Conference, in addition to providing your perspectives on the finding and the

significance, please be prepared to discuss (1) the cause(s) for the performance deficiency, (2)

corrective actions taken or planned for the performance deficiency, and (3) the reasons why

your corrective actions for Violation 05000298/2008008-01, a finding with low-to-moderate

safety significance, were not adequate to verify that the procedure would have worked as

intended.

Please contact Neil O'Keefe at (817) 860-8137 within 10 days of receipt of this letter to schedule

a date for the Regulatory Conference. If we have not heard from you within 10 days, we will

continue with our significance determination and enforcement decision. The final resolution of

this matter will be conveyed in separate correspondence.

Because the NRC has not made a final determination for this matter, no Notice of Violation is

being issued for this inspection finding at this time. In addition, please be advised that the

characterization of the apparent violation described in the enclosed inspection report may

change as a result of further NRC review.

Based on the results of this inspection, the NRC has also identified one additional issue that

was evaluated under the risk significance determination process as having very low safety

significance (Green). The finding was determined to involve a violation of NRC requirements.

However, because it was entered into your corrective action program, the NRC is treating the

finding as a noncited violation, consistent with Section 2.3.2 of the NRC Enforcement Policy.

The NCV is described in the subject inspection report. If you contest the noncited violation or

the significance of the noncited violation, you should provide a response within 30 days of the

date of this inspection report, with the basis for your denial, to the Nuclear Regulatory

Commission, ATIN: Document Control Desk, Washington DC 20555-0001, with copies to: (1)

the Regional Administrator, Region IV; (2) the Director, Office of Enforcement, U. S. Nuclear

Regulatory Commission, Washington, DC 20555-0001; and (3) the NRC Resident Inspector at

Nebraska Public Power District -3-

Cooper Nuclear Station. addition, if you disagree with the characterization of any finding in

this report, you should provide a response within 30 days of the date of this inspection report,

with the basis for your disagreement, to the Regional Administrator, Region IV, and the NRC

Resident Inspector at Cooper Nuclear Station. The information you provide wil! be considered

in accordance with Inspection Manual Chapter 0305.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure(s), and your response, if you choose to provide one, will be made available

electronically for public inspection in the NRC Public Document Room or from the NRC's

document system (ADAMS), accessible from the NRC Web site at ~~:::".,,",-:c.:~.~~=,,::::~=~;:L.

To the extent possible, your response should not include any personal privacy

or proprietary, information so that it can be made available to the Public without redaction.

Sincerely,

Anton Vegel, D T -

Division of Reactor Safety

Docket No. 50-298

License No. DPR-46

Enclosure: Inspection Report No. 05000298/2010006

w/Attachments: Supplemental Information

Final Significance Determination Summary

cc w/enclosure:

Distribution via ListServ for CNS

U COMMISSION

Docket: 50-298

License: DPR-46

Report Nos.: 05000298/2010006

Licensee: Nebraska Public Power District

Facility: Cooper Nuclear Station

Location: 72676 648A Avenue

Brownville, NE 68321

Dates: October 18, 2010 through March 14, 2011

Team Leader: J. Mateychick, Senior Reactor Inspector, Engineering Branch 2

Inspectors: S. Alferink, Reactor Inspector, Engineering Branch 2

E. Uribe, Reactor Inspector, Engineering Branch 2

J. Watkins, Reactor Inspector, Engineering Branch 2

G. George, Reactor Inspector, Engineering Branch 1

Approved By: Anton Vegel, Director

n;\I;",jnn

1-01'1

nf RQ<:>f'tnr <::<:>fQt\l

v I V l V I I V I 1 ' ...... c..tVLVI "-'-Alw]

-1- Enclosure

SUMMARY

IR 05000298/2010006; October 18,2010 - March 14, 2011, Nebraska Public Power District;

Cooper Nuclear Station: Triennial Fire Protection Team Inspection.

This report covers a two week fire protection team inspection, follow-up inspection and

significance determination effort by specialist inspectors from Region IV. One finding was

identified with an associated apparent violation, vvhich was preliminary determined to have low-

to-moderate safety significance (White). Two Green findings, which were noncited violations

(NCVs), were also identified. The significance of most findings is indicated by their color

(Green, White, Yellow, Red) using Inspection Manual Chapter 0609, "Significance

Determination Process." Findings for which the significance determination process (SOP) does

not apply may be Green or be assigned a severity level after NRC management review. The

crosscutting aspects, where applicable, were determined using Inspection Manual Chapter 0310, "Components Within the Cross Cutting Areas." The NRC's program for overseeing the

safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor

Oversight Process," Revision 4, dated December 2006.

A. NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

.. Apparent Violation. An apparent violation of 10 CFR Part 50, Appendix B, Criterion

V, "Instructions, Procedures, and Drawings," and Criterion XVI, "Corrective Action,"

with a preliminary white significance, was identified for failure to ensure that some

steps contained in Emergency Procedures at Cooper Nuclear Station would work as

written and the concurrent failure to assure that a condition adverse to quality was

promptly identified and corrected, respectively. Specifically, steps in Emergency

Procedure 5.4 POST-FIRE, "Post-Fire Operational Information," and Emergency

Procedure 5.4 FIRE-SID, "Fire Induced Shutdown From Outside Control Room,"

intended to reposition motor operated valves from the motor starter cabinet, would

not have worked as written because the steps were not appropriate for the

configuration of three valve motor starters. This finding was entered into the

licensee's corrective action program under Condition Reports CR-CNS-201 0-08193

and CR-CNS-2010-08242, however the licensee failed to adequately correct the

procedure and the procedure remained unworkabie.

The failure to verify that procedure steps needed to safely shutdown the plant in the

event of a fire would actually reposition motor operated valves to the required

positions and the simultaneous failure to address the previous finding that the same

procedure steps would not work as written, was a performance deficiency. This

finding was more than minor safety significance because it impacted the Mitigating

Systems cornerstone objective to ensure the availability, reliability, and capability of

systems that respond to external events (such as fire) to prevent undesirable

consequences. This finding affected both the procedure quality and protection

against external factors (such as fires) attributes of this cornerstone objective. This

finding was determined to have a preliminary lovv-to-moderate safety significance

(White) during a Phase 3 evaluation using best available information. This problem,

-2- Enclosure

which has existed since 1997, involves risk factors that were not dependent on

specific fire damage. The scenarios of concern involve larger fires in specific areas

of the plant which trigger operators to implement fire response procedures to place

the plant in a safe shutdown condition. Since some of those actions could not be

completed using the procedures as written, this would challenge the operators' ability

to establish adequate core cooling. This finding had a crosscutting aspect in the

Corrective Action Program component, under the Problem Identification and

Resolution area (P.1 (c) - Evaluation), because the licensee failed to properly

evaluate the circuit operation or conduct verification tests to ensure that corrective

actions for a previous violation would reliably position the three valves. Upon

identification of this issue, both emergency procedures were revised to assure

correct valve alignment by manually operating the valve locally. Therefore, this

finding does not represent a current safety concern. (Section 1R05.1)

monitor the performance of the emergency lighting system against the established

performance criteria. The licensee included the emergency lighting system in the

Maintenance Rule program and specified that the emergency light batteries must be

capable of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of operation, as required by 10 CFR Part 50, Appendix R, Section

iii.J. The team identified that the licensee did not perform tests that demonstrated

the capability of the emergency lights to last for 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />; therefore, the licensee failed

to monitor the performance of the emergency lights against the established

performance criteria. This finding was entered into the licensee's corrective action

program under Condition Reports CR-CNS-201 0-08014 and CR-CNS-2010-08250.

The failure to monitor the performance of the emergency lighting system against the

performance criteria stated in the Maintenance Rule program was a performance

deficiency. The performance deficiency was more than minor because it was

associated with the protection against external events (fire) attribute of the Mitigating

Systems Cornerstone and it adversely affected the cornerstone objective of ensuring

the availability, reliability, and capability of systems that respond to initiating events

to prevent undesirable consequences. Specifically, the failure to ensure that

emergency lights would last for 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> could adversely affect the ability of operators

to perform all of the manual actions required to support safe shutdown in the event of

a fire. The significance of this finding was evaluated using Inspection Manual

Chapter 0609, Appendix F, "Fire Protection Significance Determination Process,"

because the performance deficiency affected fire protection defense-in-depth

strategies invoiving post fire safe shutdown systems. The finding was assigned a

low degradation rating since the finding minimally impacted the performance and

reliability of the fire protection program element. Specifically, the team determined

that the licensee's preventive maintenance strategy provided reasonable assurance

that the emergency lights would last sufficiently long for the operators to perform the

most time-critical manual actions required to support safe shutdown in the event of a

fire. The team also noted that operators were required to obtain and carry

flashlights. Therefore, the finding screened as having very low safety significance

(Green). This finding had a crosscutting aspect in the area of Human Performance

associated with Decision Making because the licensee failed to identify possible

unintended consequences of the decision to change the maintenance program for

the emergency lights. Specifically, the licensee failed to identify that deleting

-3- Enclosure

light testing impacted

(Section 1 R05.B)

B. Licensee-Identified Violations

None

-4- Enclosure

REPORT DETAILS

i. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1ROS Fire Protection (71111.0STTP)

This report presents the results of a triennial fire protection inspection conducted in

accordance with NRC Inspection Procedure 71111.0STTP, "Fire Protection-NFPA

Transition Period (Triennial)," at Cooper Nuclear Station. The licensee committed to

adopt a risk informed fire protection program in accordance with National Fire Protection

Association Standard 80S (NFPA-80S), but had not yet completed the program

transition. The inspection team evaluated the implementation of the approved fire

protection program in selected risk-significant areas, with an emphasis on the

procedures, equipment, fire barriers, and systems that ensure the post-fire capability to

safely shut the plant down.

Inspection Procedure 71111.0STTP requires selecting three to five fire areas for review.

The inspection team used the fire hazards analysis section of the Cooper Nuclear

Station Individual Plant Examination of External Events to select the following five

risk-significant fire zones (inspection samples) for review:

  • Fire Area I / Fire Zone 2A Control Rod Drive Units - North

Reactor Building Elevation 903' 6"

  • Fire Area I / Fire Zone SB Reactor Motor Generator Set Area

Reactor Building Elevation 976' 0"

  • Fire Area II I Fire Zone 3A Switchgear Room 1F

Reactor Building Elevation 931' 6"

  • Fire Area IX / Fire Zones 14A Diesel Generator 1A Room

Diesel Generator Building Elevation 903' 6"

  • Fire Area IX / Fire Zones 14C Diesel Oil Day Tank Room

Diesel Generator Building Elevation 903' 6"

The inspection team evaluated the licensee's fire protection program using the

applicable requirements, which included plant Technical Specifications, Operating

License Condition 2.C.(S); NRC safety evaluations; 10 CFR S0.48; Branch Technical

Position 9.S-1; and 10 CFR SO, Appendix R. The team also reviewed related documents

that included the Final Safety Analysis Report (FSAR), Section 9.S; the fire hazards

analysis; and the post-fire safe shutdown analysis.

Specific documents reviewed by the team are listed in the attachment. Five fire area

inspection samples were completed. Also, one B.S.b strategy review sample was

completed.

-S- Enclosure

.1 Protection of Safe Shutdown Capabilities

a. Inspection Scope

The team reviewed the piping and instrumentation diagrams, safe shutdown equipment

list, safe shutdown design basis documents, and the post fire safe shutdown analysis to

verify that the licensee properly identified the components and systems necessary to

achieve and maintain safe shutdown conditions for fires in the selected fire areas. The

team observed walkdowns of the procedures used for achieving and maintaining safe

shutdown in the event of a fire to verify that the procedures properly implemented the

safe shutdown analysis provisions.

For each of the selected fire areas, the team reviewed the separation of redundant safe

shutdown cables, equipment, and components located within the same fire area. The

team also reviewed the licensee's method for meeting the requirements of 10 CFR

50.48; Branch Technical Position 9.5-1, Appendix A; and 10 CFR Part 50, Appendix R,

Section III.G. Specifically, the team evaluated whether at least one post-fire safe

shutdown success path would remain free of fire damage in the event of a fire. In

addition, the team verified that the licensee met applicable license commitments.

b. Findings

Introduction. An apparent violation of 10 CFR Part 50, Appendix B, Criterion Vand

Criterion XVI, with a preliminary White significance, was identified for the repeated

failure to ensure that some steps contained in emergency procedures at Cooper Nuclear

Station would work as written. Specifically, steps in Emergency Procedure 5.4 POST-

FIRE, "Post Fire Operational Information," and Emergency Procedure 5.4 FIRE-SID,

"Fire Induced Shutdown From Outside Control Room," intended to reposition motor

operated valves at the motor starter cabinet, would not have worked as written because

the steps were not appropriate for the configuration of the motor starters.

Description. Post-fire safe shutdown strategies at the Cooper Nuclear Station require

equipment operations to be performed in accordance with one of two emergency

procedures. For most fire areas, plant shutdown is performed using Emergency

Procedure 5.4 POST-FIRE, "Post-Fire Operational Information," Revision 37, in

conjunction with other plant procedures. For areas where fires might necessitate

evacuation of the control room, alternative shutdown is performed using Emergency

Procedure 5.4 FIRE-SID, "Fire Induced Shutdown From Outside the Control Room,"

Revision 38.

The team performed a walkthrough of Emergency Procedure 5.4 POST-FIRE for

selected fire areas by observing plant operators simulate actions required by the

procedure. This procedure required operators to reposition multiple motor-operated

valves (MOVs) from each valve's motor starter cabinet. The procedure steps direct

operators to open the motor starter cabinet, remove the control power fuses, then press

designated contactors for a specified amount of time to reposition the valve to the

required position.

-6- Enclosure

The team was concerned that some of the procedure steps might not be reliably

performed by the operators because bulky electrical safety gloves might not allow

access to recessed contactors. When the licensee attempted to demonstrate their

method, they identified that it would not work for one type of contactor. The internal

configuration of the contactor would not complete the power circuit by depressing it. The

manufacturer describes the design as having "direct magnet drive with positive pull-in of

contactors." Since control power was removed by pulling fuses before operating the

contactors, the magnet system would not engage the power contacts to the valve motor.

The inspectors noted that the operator performing the procedure steps would have no

indication that the valve(s) did not reposition. Because the procedures do not

specifically require checking the valve positions for most fire locations, the failure to

reposition would not be readily apparent.

The three valves with this type of contactor were residual heat removal (RHR) system

valves RHR-MO-25A and RHR-MO-25B, Train A and B Inboard Injection Isolation

Valves, and reactor recirculation (RR) system valve RR-MO-53A, Reactor Recirculation

A Pump Discharge Valve. The procedural deficiency in Emergency Procedure

5.4 POST-FIRE impacted the response to fires in 11 fire areas, each involving one

valve. One of the valves, RHR-MO-25B, is operated in the same manner during

alternative shutdown in accordance with Emergency Procedure 5.4 FIRE-SID, which

contained the same procedural deficiency, for fires in two additional fire areas. The 13

affected fire areas are listed below:

Fire Area

CB-A Control Building Reactor Protection System Room 1A, Seal Water

Pump Area, and Hallway

CB-A-1 Control Building Division 1 Switchgear Room and Battery Room

CB-B Control Building Division 2 Switchgear Room and Battery Room

CB-C Control Building Reactor Protection System Room 1B

CB-D Control Room, Cable Spreading Room, Cable Expansion Room,

and Auxiliary Relay Room

RB-DI (SE) Reactor Building RHR Pump B/HPCI Pump Room

RB-Di (SW) Reactor Building South/Southwest 903, Southwest Quad 889 and

859, and RHR Heat Exchanger Room B

RB-FN Reactor Building 903, Northeast Corner

RB-J Reactor Building Critical Switchgear Room 1F

RB-K Reactor Building Critical Switchgear Room 1G

RB-M Reactor Building North/Northwest 931 and RHR Heat Exchanger

Room A

RB-N Reactor Building South/Southwest 931 and RHR Heat Exchanger

Room B

TB-A Turbine Building (multiple areas)

Opening either valve RHR-MO-25A or valve RHR-MO-25B is necessary to establish

alternative shutdown cooling. Alternative shutdown cooling involves using a train of

RHR to take suction from the suppression pool, inject the low pressure water to flood the

reactor vessel, and recirculate the water through the safety relief valves (SRVs) back to

the suppression pool. Establishing alternative shutdown cooling can be very time-

sensitive. If high-pressure coolant injection (HPCI) is not available, the licensee

-7- Enclosure

provided calculations that show that core damage can occur in as little as 15 minutes

after valve RHR-MO-258 fails to open.

Valve RR-MO-53A is the discharge isolation valve for Reactor Recirculation Pump 1-A.

This valve is only required for cold shutdown. For some fire areas, the normal shutdown

cooling mode of RHR system operation was credited in the fire safe shutdown analysis

to be available. In shutdown cooling mode, the RHR system takes suction from the

suction pipe of reactor recirculation system loop "A". The reactor coolant is then cooled

and returned to a reactor recirculation loop discharge pipe. The failure to close either

valve RR-MO-53A or RR-MO-43A would result in a short circuit of the shutdown cooling

flow, bypassing the reactor vessel. The cool down from hot shutdown conditions and the

transition to normal shutdown cooling allows time to close either valve RR-MO-53A or

RR-MO-43A using local manual operation.

In 2004, a related but separate violation (NCV 05000298/2004008-01) was issued for

failure to protect cables from fire damage for MOVs required to be available for post fire

safe shutdown. The licensee committed to adopt a risk-informed fire protection program

in accordance with 10 CFR 50.48(c) and NFPA-805, and planned to address the 2004

violation through their NFPA-805 conversion. To be able to delay correcting the 2004

violation, the licensee was required to verify that the compensatory measures for the

violation (the operator manual actions) were adequate to ensure safety, in this case to

be able to safely shut the plant down in the event of a fire.

Inspection Report 05000298/2004008 noted reliability concerns with the method of

operating the MOVs. These included the fact that the contactors were not labeled to

ailow operators to know which contactors the procedure instructed them to operate, no

indication was available at the motor starter cabinet for the operator to know the valves

had reached their required position, and valve position was not verified locally at the

valves. As part of corrective action, the licensee installed "open" and "closed" labels

near contactors in the motor starter cabinets.

In 2007, inspectors identified that some of the operator manual actions used as

compensatory measures for the 2004 violation would not have repositioned 10 of the

MOVs. The procedures did not account for the fact that these 10 MOVs had different

motor starter circuits than most valves. Despite installing labels following the 2004

violation, the licensee failed to recognize that these 10 MOVs had a more complex

circuit design which required two or three contactors to be operated at the same time,

while the procedures only required operating one "open" or one "close" contactor. A

White finding with an associated violation (Violation 05000298/2008008-01, EA 07-204)

was issued for having an inadequate procedure and failing to verify that the procedure

would work.

Inspection Report 05000298/2008007 again documented the reliability concerns that

there were no valve position indications at the MOV motor starter cabinets, and the

procedures did not direct local valve position checks. Additional reliability concerns were

also documented concerning the adequacy of the procedures and the instrumentation

available to diagnose the failure of an MOV to reposition.

The licensee took corrective actions to change and verify the procedures to address the

2008 finding; however the licensee's efforts again failed to identify details of the

-8- Enclosure

electrical design which would result in the procedure steps not repositioning three

MOVs.

Analysis. The failure to verify that procedure steps needed to safely shutdown the plant

in the event of a fire would actually reposition motor operated valves to the required

positions, and to address a previous finding that the same procedure steps would not

work as written, was a performance deficiency. This performance deficiency is of more

than minor safety significance because it impacted the Mitigating Systems cornerstone

objective to ensure the availability, reliability, and capability of systems that respond to

external events (such as fire) to prevent undesirable consequences. This finding

affected both the procedure quality and protection against external factors (such as fires)

attributes of this cornerstone objective.

The significance determination process (SOP) Phase 1 Screening Worksheet (Manual

Chapter 0609, Attachment 4), Table 3b directs the user to Manual Chapter 0609,

Appendix F, "Fire Protection Significance Determination Process," because it affected

fire protection defense-in-depth strategies involving post fire safe shutdown systems.

However, the Assumptions and Limitations section of Appendix F states that finings

involving multiple fire areas are beyond the scope of Appendix F, and findings involving

control room evacuation are not explicitly treated in Appendix F. Therefore, a Phase 3

analysis was performed.

The license claimed that the issue involved a performance deficiency that only

impacted cold shutdown, and therefore should be screened as Green during a Phase

1 SOP. The NRC concluded that this finding cannot be screened out because the

complexity of the issue (e.g., multiple fire areas affected) precludes simple screening,

and because the plant conditions and system dependencies prevent a conclusion

that only cold shutdown is affected.

Manual Chapter 0308 describes the basis for Appendix F screening out issues involving

only cold shutdown as follows:

The second question screens findings to green that impact only the ability of the

plant to achieve cold shutdown. This is consistent with the common risk analysis

practice of defining hot shutdown as success. That is, both fire PRAs

[probabilistic risk assessments] and Internal Events PRAs typically assume that

achieving a safe and stable hot shutdown state constitutes success and the end

state for accident sequence analyses. Note that this screening step applies only

to findings against 10CFR50 Appendix R, Section III.G.1.b. All other regulatory

provisions are considered to involve, in part or in whole, measures provided for

preservation and protection of the post-fire hot shutdown capability and will not

be screened in this step (e.g., fire prevention, fire suppression, fire brigade, fire

barriers, etc.).

The licensee's fire safe shutdown strategy and implementing procedures for the

scenarios of concern direct operators to proceed to cold shutdown within a few hours.

Operation in hot shutdown and cold shutdown rely on the suppression pool with limited

capability for cooling the suppression pool. This strategy is too complex to allow simple

risk screening for this finding.

- 9- Enclosure

A risk analysis was performed previously for the 2008 procedural problems that affected

ten valves, including the three valves addressed by this performance deficiency. This

was documented in Inspection Report 05000298/2008008 (EA 07-204). In both the

2008 and current cases, valves RHR-MOV-25A, RHR-MOV-25B, and RHR-MOV-53A

were incapable of being remotely operated from the motor starter as prescribed by

Procedures 5.4 POST-FIRE and 5.4 FIRE-SID. Therefore, the linked event tree model

developed for the risk estimate performed in 2008 was used to assess the significance

of the current issue for these three valves.

Fires that do not require control room evacuation are addressed in Procedure

5.4 POST-FIRE. For fire areas that do not involve control room evacuation, the analyst

concluded that the risk for the current finding is less than 1.0E-7 (this is unchanged from

2008 evaluation).

The risk attributable to post fire remote shutdown (control room abandonment

sequences) results predominantly from the failure of Valve RHR-MOV-25B to open as

described in Procedure 5.4 FIRE-SID. This is the credited train and the only procedural

means for initiating alternative shutdown cooling during the recovery actions. Changes

were made to Procedure 5.4 FIRE-SID subsequent to the 2008 issue which were

credited in the current analysis and resulted in a decrease in the risk significance of the

subject valves.

The non-recovery probability was decreased by a factor of 78 for the current finding

because of changes that were made to Procedure 5.4 FIRE-SID. These changes in

Attachment 1 of the procedure directed the operator at the remote shutdown panel to

close SRVs if RHR injection was not observed to be successful and stabilize conditions

using high pressure injection. Also, it directed operators to delay securing HPCI (if it

was running) until RHR injection is confirmed. Additionally, Attachment 2 to the

procedure directed the reactor building operator to open valve RHR-MOV-25B manually

if the valve did not operate. However, there is limited instrumentation available at the

remote shutdown panel to be able to recognize and diagnose that the valve did not

open, and no available indications at the motor starter cabinet. Therefore, the operator

who might be able to diagnose the failure of RHR-MO-25B did not have a procedure with

the critical recovery step, and the operator with the correct recovery step in his

procedure did not have the capability to know whether it was needed.

Using the linked event tree model and a period of exposure of one year, the analyst

calculated the f..CDF to be 2.0E-6/yr for postulated fires leading to the abandonment of

the main control room. The analyst concluded that the performance deficiency was of

low to moderate significance (White).

A more detailed description to the Phase 3 analysis is attached to this report.

The NRC expects that licensees will ensure that issues potentially impacting nuclear

safety are promptly identified, fully evaluated, and that actions are taken to address

safety issues in a timely manner, commensurate with their significance. Additionally, the

NRC expects that for significant problems, licensees will conduct effectiveness reviews

of corrective actions to ensure that the problems are resolved. Because the licensee

- 10- Enclosure

failed to properly evaluate the circuit operation or conduct verification tests to ensure that

corrective actions for a previous violation would reliably position the three valves, the

team concluded that this finding has a crosscutting aspect in the Corrective Action

Program component, under the Problem Identification and Resolution area (P.1 (c) -

Evaluation).

Enforcement. Title 10 of the Code of Federal Regulations, Part 50, Appendix S,

Criterion V, "Instructions, Procedures, and Drawings," requires, in part, that activities

affecting quality shall be prescribed by documented instructions, procedures, or

drawings, of a type appropriate to the circumstances and shall be accomplished in

accordance with these instructions, procedures, or drawings.

Title 10 of the Code of Federal Regulations, Part 50, Appendix S, Criterion XVI requires,

in part:

Measures shall be established to assure that conditions adverse to quality, such

as failures, malfunctions, deficiencies, deviations, defective material and

equipment, and nonconformances are promptly identified and corrected. In the

case of Significant conditions adverse to quality, the measures shall assure that

the cause of the condition is determined and corrective action taken to preclude

repetition.

Emergency Procedure 5.4 POST-FIRE, "Post-Fire Operational Information," Revision

37, and Emergency Procedure 5.4 FIRE-SID, "Fire Induced Shutdown From Outside the

Control Room," Revision 38, were designated as quality-related procedures used to

implement operator actions to safely shutdown the plant in response to a fire. Violation

05000298/2008008-01 (EA 07-204) documented a significant condition adverse to

quality in that steps in Emergency Procedure 5.4 POST-FIRE and Emergency

Procedure 5.4 FIRE-SID would not achieve and maintain a safe shutdown condition in

the event of certain fires.

Contrary to the above, between July 1997 and November, 2010, the licensee failed to

ensure that activities affecting quality were prescribed by documented procedures

appropriate to the circumstances, and to assure that a significant condition adverse to

quality was promptly corrected. Specifically, Emergency Procedure 5.4 POST-FIRE and

Emergency Procedure 5.4 FIRE-SID were changed in 1997 to add steps that were

inappropriate to the circumstances because they would not work as written to reposition

three motor operated valves needed to establish core cooling. The licensee failed to

properly verify and validate procedure steps when the procedure changes were made

and on multiple occasions between July 1997 and November 2010, including verification

and validation actions performed in response to Violation 05000298/2008008-01 ..

In addition, contrary to the above, between July 2008 and November 2010, the licensee

failed to identify, correct, and preclude repetition of a Significant condition adverse to

quality. Specifically, Violation 05000298/2008008-01 identified a significant condition

adverse to quality in that Emergency Procedure 5.4 POST-FIRE and Emergency

Procedure 5.4 FIRE-SID would not work as written and the licensee had failed to verify

and validate procedure steps to ensure that they would work to accomplish the

necessary tasks. While addressing that violation, the licensee failed to perform sufficient

- 11 - Enclosure

circuits to identify and correct a problem with valves RHR-MOV-25A, RHR-MOV-25B,

and RHR-MOV-53A.

The licensee entered this issue into their corrective action program as Condition

Reports CR-CNS-2010-08193 and CR-CNS-2010-08242. This violation is being treated

as an apparent violation (AV) , consistent with the Enforcement Policy: AV

05000298/2010006-01, Inadequate Post-Fire Safe Shutdown Procedures.

Because the licensee failed to correct this condition as part of Violation

05000298/2008008-01, and because Violation 05000298/2008008-01 did not receive

enforcement discretion, this finding was not appropriate for enforcement discretion .

.2 Passive Fire Protection

a. Inspection Scope

The team walked down accessible portions of the selected fire areas to observe the

material condition and configuration of the installed fire area boundaries (including walls,

fire doors, and fire dampers) and verify that the electrical raceway fire barriers were

appropriate for the fire hazards in the area. The team compared the installed

configurations to the approved construction details, supporting fire tests, and applicable

license commitments.

The team reviewed installation, repair, and qualification records for a sample of

penetration seals to ensure that the fill material possessed an appropriate fire rating and

that the installation met the engineering design. The team also reviewed similar records

for the rated fire wraps to ensure the material possessed an appropriate fire rating and

that the installation met the engineering design.

b. Findings

No findings were identified .

.3 Active Fire Protection

a. Inspection Scope

The team reviewed the design, maintenance, testing, and operation of the fire detection

and suppression systems in the selected fire areas. The team verified that the manual

and automatic detection and suppression systems were installed, tested, and maintained

in accordance with the National Fire Protection Association code of record or approved

deviations, and that each suppression system was appropriate for the hazards in the

selected fire areas.

The team performed a walkdown of accessible portions of the detection and suppression

systems in the selected fire areas. The team also performed a walkdown of major

system support equipment in other areas (e.g., fire pumps) to assess the material

condition of these systems and components.

The team reviewed the electric and diesel fire pump flow and pressure tests to verify that

- 12 - Enclosure

the pumps met their design requirements. The team also reviewed high pressure

carbon dioxide suppression system functional tests and inspections to verify that the

system capability met the design requirements.

The team assessed the fire brigade capabilities by reviewing training, qualification, and

drill critique records. The team also reviewed pre-fire plans and smoke removal plans

for the selected fire areas to determine if appropriate information was provided to fire

brigade members and plant operators to identify safe shutdown equipment and

instrumentation, and to facilitate suppression of a fire that could impact post-fire safe

shutdown capability. In addition, the team inspected fire brigade equipment to determine

operational readiness for fire fighting.

The team observed an unannounced fire drill, conducted on November 1, 2010, and the

subsequent drill critique using the guidance contained in Inspection

Procedure 71111.05AQ, "Fire Protection Annual/Quarterly." The team observed fire

brigade members fight a simulated fire in the Reactor Building, located in a switchgear

room. The team verified that the licensee identified problems, openly discussed them in

a self-critical manner at the drill debrief, and identified appropriate corrective actions.

Specific attributes evaluated were: (1) proper wearing of turnout gear and self-contained

breathing apparatus; (2) proper use and layout of fire hoses; (3) employment of

appropriate fire fighting techniques; (4) sufficient fire fighting equipment was brought to

the scene; (5) effectiveness of fire brigade leader communications, command, and

control; (6) search for victims and propagation of the fire into other areas; (7) smoke

removal operations; (8) utilization of pre-planned strategies; (9) adherence to the pre-

planned drill scenario; and (10) drill objectives.

b. Findings

No findings were identified .

.4 Protection From Damage From Fire Suppression Activities

a. Inspection Scope

The team performed plant walkdowns and document reviews to verify that redundant

trains of systems required for hot shutdown, which are located in the same fire area,

would not be subject to damage from fire suppression activities or from the rupture or

inadvertent operation of fire suppression systems. Specifically, the team verified that:

  • A fire in one of the selected fire areas would not directly, through production of

smoke, heat, or hot gases, cause activation of suppression systems that could

potentially damage all redundant safe shutdown trains.

  • A fire in one of the selected fire areas or the inadvertent actuation or rupture of a

fire suppression system would not directly cause damage to all redundant trains.

  • Adequate drainage was provided in areas protected by water suppression

systems.

b. Findings

- 13 - Enclosure

No findings were identified,

,5 Alternative Shutdown Capability

a, Inspection Scope

Review of Methodology

The team reviewed the safe shutdown analysis, operating procedures, piping and

instrumentation drawings, electrical drawings, the Final Safety Analysis Report, and

other supporting documents to verify that hot and cold shutdown could be achieved and

maintained from outside the control room for fires that require evacuation of the control

room, with or without offsite power available,

Plant walkdowns were conducted to verify that the plant configuration was consistent

with the description contained in the safe shutdown and fire hazards analyses, The

team focused on ensuring the adequacy of systems selected for reactivity control,

reactor coolant makeup, reactor decay heat removal, process monitoring

instrumentation, and support systems functions.

The team also verified that the systems and components credited for shutdown would

remain free from fire damage. Finally, the team verified that the transfer of control from

the control room to the alternative shutdown location would not be affected by

fire-induced circuit faults (e.g., by the provision of separate fuses and power supplies for

alternative shutdown controi circuits).

Review of Operational Implementation

The team verified that licensed and non-licensed operators received training on

alternative shutdown procedures. The team also verified that sufficient personnel to

perform a safe shutdown were trained and available onsite at all times, exclusive of

those assigned as fire brigade members.

A walkthrough of the post fire safe shutdown procedure with licensed and non-licensed

operators was performed to determine the adequacy of the procedure, The team

verified that the operators could be reasonably expected to perform specific actions

within the time required to maintain plant parameters within specified limits. Time critical

actions that were verified included restoring electrical power, establishing control at the

remote shutdown and local shutdown panels, establishing reactor coolant makeup, and

establishing decay heat removal.

The team reviewed manual actions to ensure that they had been properly reviewed and

approved and that the actions could be implemented in accordance with plant

procedures in the time necessary to support the safe shutdown method for each fire

area.

The team also reviewed the periodic testing of the alternative shutdown transfer

capability and instrumentation and control functions to verify that the tests are adequate

to demonstrate the functionality of the alternative shutdown capability,

- 14 - Enclosure

b. Findings

No findings were identified.

.6 Circuit Analysis

a. I nSl2ection SCOl2e

This segment of inspection is suspended for plants in transition to a risk-informed fire

protection program in accordance with NFPA 805. Therefore, the team did not evaluate

this area.

b. Findings

No findings were identified .

.7 Communications

a. Insl2ection Scol2e

The team inspected the contents of designated emergency storage lockers and

reviewed the alternative shutdown procedure to verify that portable radio

communications and fixed emergency communications systems were available,

operable, and adequate for the performance of designated activities. The team verified

the capability of the communication systems to support the operators in the conduct and

coordination of their required actions. The team also verified that the design and

location of communications equipment such as repeaters and transmitters would not

cause a loss of communications during a fire. The team discussed system design,

testing, and maintenance with the system engineer.

The team reviewed the licensee's response to Condition Report CR-CNS-201 0-07848.

The team verified the licensee properly implemented the Maintenance Rule program

with respect to the communications systems required for alternative shutdown.

b. Findings

No findings were identified.

.8 Emergency Lighting

a. Insl2ection Scol2e

The team reviewed the portion of the emergency lighting system required for alternative

shutdown to verify that it was adequate to support the performance of manual actions

required to achieve and maintain hot shutdown conditions and to illuminate access and

egress routes to the areas where manual actions would be required. The team

evaluated the locations and positioning of the emergency lights during a walkthrough of

the alternative shutdown procedure.

- 15 - Enclosure

The team verified that the licensee installed emergency lights with an 8-hour capacity,

maintained the emergency light batteries in accordance with manufacturer

recommendations, and tested and performed maintenance in accordance with piant

procedures and industry practices. The team also verified the licensee properly

implemented the Maintenance Rule program with respect to the emergency lighting

systems required for alternative shutdown.

The team identified several concerns with the adequacy of the emergency lights during

the walkthrough of the alternative shutdown procedure. In response to these concerns,

the licensee performed blackout tests to demonstrate the adequacy of the installed

emergency lights. The team observed blackout tests in the following areas:

  • Control Building Corridor, 903' Elevation
  • Control Building Basement, 881' Elevation
  • Diesel Generator 2 Room

b. Findings

Introduction. The team identified a Green noncited violation of 10 CFR 50.65(a)(2) for

the failure to monitor the performance of the emergency lighting system against the

established performance criteria.

Description. During the inspection, the team reviewed the licensee's maintenance

program for the emergency lighting system. The team determined that the licensee did

not perform tests that demonstrated the capability of the emergency lights to last 8

hours. Instead, the licensee replaced each emergency light battery at a prescribed

frequency. The licensee previously demonstrated the capability of the emergency lights

to last 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> via the performance of internal resistance measurements. In 2008, the

licensee modified their maintenance program to remove the internal resistance

measurements and rely upon the prescribed replacement strategy.

The team also reviewed the licensee's implementation of their Maintenance Rule

program with respect to the emergency lighting system. The licensee included the

emergency lighting system into the Maintenance Rule program and included a

performance criterion for the emergency light batteries to support 8-hours of operation,

as required by 10 CFR Part 50, Appendix R, Section III.J.

Since the licensee did not perform tests that demonstrated the capability of the

emergency lights to last 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />, the team determined that the licensee failed to monitor

the performance of the emergency lights against the established performance criteria.

Analysis. The failure to monitor the performance of the emergency lighting system

against the performance criteria stated in the Maintenance Rule program was a

performance deficiency. The performance deficiency was more than minor because it

was associated with the protection against external events (fire) attribute of the

Mitigating Systems Cornerstone and it adversely affected the cornerstone objective of

ensuring the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. Specifically, the failure of the emergency

lights to last 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> could adversely affect the ability of operators to perform the manual

actions required to support safe shutdown in the event of a fire.

- 16 - Enclosure

The significance of this finding was evaluated using Manual Chapter 0609, Appendix F,

"Fire Protection Significance Determination Process," because the performance

deficiency affected fire protection defense-in-depth strategies involving post-fire safe

shutdown systems. The team assigned the performance deficiency to the Post-fire Safe

Shutdown category since it affected systems or functions relied upon for post-fire safe

shutdown.

The finding was assigned a low degradation rating since the finding minimally impacted

the performance and reliability of the fire protection program element. Specifically, the

team determined that the licensee's preventive maintenance strategy provided

reasonable assurance that the emergency lights would last sufficiently long for the

operators to perform the most time critical manual actions required to support safe

shutdown in the event of a fire. The team also noted that operators were required to

obtain and carry flashlights. Therefore, the finding screened as having very low safety

significance (Green).

The NRC expects that licensee decisions demonstrate that nuclear safety is an

overriding priority and to conduct effectiveness reviews of safety-significant decisions to

identify possible unintended consequences. Because the licensee failed to identify that

deleting emergency light testing impacted Maintenance Rule performance monitoring,

the team concluded that this finding had a crosscutting aspect in the area of human

performance associated with decision making. Specifically, the licensee failed to identify

possible unintended consequences of the decision to change the maintenance program

for the emergency lights. [H.1 (b)]

Enforcement. Title 10 of the Code of Federal Regulations, Part 50, Section 65,

Paragraph (a)(1), requires, in part, that licensees shall monitor the performance or

conditions of structures, systems, or components (SSCs) within the scope of the

maintenance rule as defined by 10 CFR 50.65 (b), against licensee established goals, in

a manner sufficient to provide reasonable assurance that such SSCs are capable of

fulfilling their intended functions.

Title 10 of the Code of Federal Regulations, Part 50, Section 65, Paragraph (a)(2)

states, in part, that monitoring as specified in 10 CFR 50.65 (a)(1) is not required where

it has been demonstrated that the performance or condition of a SSC is being effectively

controlled through the performance of appropriate preventive maintenance, such that the

SSC remains capable of performing its intended function.

The licensee's Maintenance Rule program included the emergency lighting system and

established a performance criterion that the emergency lighting system batteries support

8-hours of operation, as required by 10 CFR Part 50, Appendix R, Section IILJ.

Contrary to the above, from October 3, 2008 to November 5, 2010, the licensee failed to

demonstrate that the performance of the emergency lighting system was effectively

controlled through the performance of appropriate preventive maintenance and did not

smonitor the emergency lighting system against licensee established goals. Specifically,

the licensee failed to demonstrate that the emergency lighting system remained capable

of providing 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of illumination for post-fire safe shutdown.

- 17 - Enclosure

The licensee entered this issue into their corrective action program as Condition

Reports CR-CNS-2010-08014 and CR-CNS-2010-08250. Because this violation was of

very low safety significance and it was entered into the licensee's corrective action

program, this violation is being treated as a noncited violation, consistent with the

Enforcement Policy: NCV 05000298/2010006-03, Failure to Monitor the Performance of

the Emergency Lights Against the Maintenance Rule Criteria .

.9 Cold Shutdown Repairs

a. Inspection Scope

The team verified that the licensee identified repairs needed to reach and maintain cold

shutdown and had dedicated repair procedures, equipment, and materials to accomplish

these repairs. Using these procedures, the team evaluated whether these components

could be repaired in time to bring the plant to cold shutdown within the time frames

specified in the design and licensing bases. The team verified that the repair equipment,

components, tools, and materials needed for the repairs were available and accessible

on site.

b. Findings

No findings were identified .

. 10 Compensatory Measures

a. Inspection Scope

The team verified that compensatory measures were implemented for out-of-service,

degraded, or inoperable fire protection and postfire safe shutdown equipment, systems,

or features (e.g., detection and suppression systems and equipment; passive fire

barriers; or pumps, valves, or electrical devices providing safe shutdown functions). The

team also verified that the short-term compensatory measures compensated for the

degraded function or feature until appropriate corrective action could be taken and that

the licensee was effective in returning the equipment to service in a reasonable period of

time.

b. Findings

A finding related to this review was documented in Section 1R05.01. No additional

findings were identified .

. 11 B.5.b Inspection Activities

a. Inspection Scope

The team reviewed the licensee's implementation of guidance and strategies intended to

maintain or restore core, containment, and spent fuel pool cooling capabilities under the

circumstances associated with loss of large areas of the plant due to explosions or fire

as required by Section B.5.b of the Interim Compensatory Measures Order, EA-02-026,

dated February 25: 2002 and 10 CFR 50.54(hh)(2).

- 18 - Enclosure

The team reviewed a licensee's strategy to verify that they continued to maintain and

implement procedures, maintain and test equipment necessary to properly implement

the strategy, and to ensure that station personnel are knowledgeable and capable of

implementing the procedure. The team performed a visual inspection of portable

equipment used to implement the strategy to ensure availability and material readiness

of the equipment, including the adequacy of portable pump trailer hitch attachments, and

verify the availability of onsite vehicles capable of towing the portable pump. The team

assessed the offsite ability to obtain fuel for the portable pump, and foam used for

firefighting efforts. The team reviewed the following strategy as an inspection sample:

  • 5.3 Alt-Strategy, "Alternative Core Cooling Mitigating Strategies," Revision 023,

Attachment 4, "Manual Operation of RCIC [reactor core isolation cooling]."

b. Findings

No findings were identified.

4. OTHER ACTIVITIES [OA]

40A2 Identification and Resolution of Problems

Corrective Actions for Fire Protection Deficiencies

a. Inspection Scope

The team selected a sample of condition reports associated with the licensee's fire

protection program to verify that the licensee had an appropriate threshold for identifying

deficiencies. In addition, the team reviewed the corrective actions proposed and

imolemented to verifv that thev were effective in correctina irlentifierl rlefir.ienr.ie!=: The

  • " - - - - - ~.1 - ~ .- - - - - _. - - . _. - - - . - - -- - '.;;I - _. - ** _ *.* - - - - ** _ . _ ** _. - - * * * * --

team also evaluated the quality of recent engineering evaluations through a review of

condition reports, calculations, and other documents during the inspection.

b. Findings

Findings related to this review are documented in Sections 1R05.01 and 1R05.05. No

additional findings were identified.

- 19 - Enclosure

40A6 Meetings, Including Exit

Exit Meeting Summary

The team presented the inspection results to Mr. D. Willis, General Manager, Plant

Operations, and other members of the licensee staff at a debrief meeting on November

5, 2010. The licensee acknowledged the findings presented.

The team presented the inspection results to Mr. D. Suman, Director of Engineering, and

other members of the licensee staff at an exit meeting on March 14, 2011. The licensee

acknowledged the findings presented.

The inspectors confirmed that proprietary material examined during the inspection had

been returned.

ATTACHMENTS: SUPPLEMENTAL INFORMATION

FINAL SIGNIFICANCE DETERMINATION SUMMARY

- 20 - Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

licensee Personnel

J. Aldana, Security Coordinator

R. Alexander, Electrical Superintendent

J. Austin, System Engineering Manager

1. Barker, Quality Assurance Manager

J. Bebb, Security Manager

S. Bebb, Administrative Services Manager

M. Bergmeier, Operation Support Group Supervisor

K. Billesbach, Materials, Purchasing and Contracts Manager

D. Buman, Director of Engineering

K. Cardy, Fire Protection Engineer

G. Chinn, Contractor

L. Deuhirst, Corrective Actions and Assessments Manager

R. Dyer, Engineering Support Program Engineer

J. Dykstra, Electrical Engineering Program Supervisor

R. Estrada, Design Engineering Manager

J. Flaherty, Senior Staff licensing Engineer

J Gage, Reactor Operator

R. Gauchat, Security Training Supervisor

1. Hattovy, Engineering Support Manager

D. Jones, Safety Coordinator

1. Kahland, Reactor Operator

C. Long, Engineering Specialist

D. McGargill, Non-licensed Operator

1. Mue!!er, Senior Reactor Operator

K. Newcomb, Fire Marshal

D. Oshlo, Information Technology Manager

R. Penfield, Operations Manager

D. Seylock, Training Manager

J. Shrader, Fire Safety Lead, Nebraska Public Power District

D. Van Der Kap, licensing Manager

M. Van Winkle, Electrical Design Supervisor

D. Weniger, Valves Program Engineer

D. Willis, General Manager, Plant Operations

A. Zaremba, Director of Nuclear Safety Assessment

NRC personnel

M. Chambers, Resident Inspector

S. Vaughn, NRR/DIRS/IPAB

J. Bowen, NRR/DIRS/IRIB

D. Loveless, Senior Reactor Analyst, RIV/DRS

M. Runyan, Senior Reactor Analyst, RIV/DRS

A-1 Attachment 1

UST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000298/2009006-01 AV Inadequate Post-Fire Safe Shutdown Procedures

(Section 1R05.01)

Opened and Closed

05000298/2009006-02 NCV Failure to Correct a Condition Adverse to Quality

Related to Post-Fire Safe Shutdown

(Section 1R05.05)

Closed None

UST OF ACRONYMS

ADAMS Agencywide Documents Access and Management System

BWR Boiling Water Reactor

CR Condition Report

CFR Code of Federal Regulations

DRS Division of Reactor Safety

FSAR Final Safety Analysis Report

HPCi High Pressure Coolant Injection

LPSI Low Pressure Safety Injection

MOV Motor Operated Valve

NCV Noncited Violation

NFPA National Fire Protection Association

NRC Nuclear Regulatory Commission

PAR Publicly Available Records

PRA Probabilistic Risk Assessment

RCIC Reactor Core Isolation Cooling

RHR Residu'al Heat Removal

SDP Significance Determination Process

SRV Safety/Relief Valve

A-2 Attachment 1

LIST OF DOCUMENTS REVIEWED

CALCULATIONS

Number Title Revision

NEDC 01-030 HPCI Room Heatup During Appendix R Shutdown from 2

Alternative Shutdown Panel

NEDC 09-080 Multiple Spurious Operation Expert Panel Results 0

NEDC 85-081 Pressure Drop in Steam Line to the HPCI Turbine OCi

NEDC 94-034H Containment Analysis for Appendix R - Shutdown from 2

Alternative Shutdown Room

NEDC 95-003 Determination of Allowable Operating Parameters for 23

CNS MOV Program MOVs

CONDITION REPORTS (CRs)

CR-CNS-2004-03595 CR-CNS-2004-05511 CR-CNS-2006-03138

CR-CNS-2007 -01248 CR-CNS-2007 -04155 CR-CNS-2007 -07065

C R -C N S-2008-05653 CR-CNS-2008-5751 CR-CNS-2008-05766

CR-CNS-2007 -08253 CR-CNS-2010-02387 CR-CNS-2010-03500

CR-CNS-2010-05023 CR-CNS-2010-05269 CR-CNS-2010-05855

CR-CNS-2010-05856 CR-CNS-2010-06942 CR-CNS-2010-06184

CR-CNS-2010-06236 CR-CNS-2010-06245 CR-CNS-2010-06258

CR-CNS-2010-06264 CR-CNS-2010-06441 CR-CNS-2010-06775

CR-CNS-2010-06942 CR-CNS-201 0-0701 0 CR-CNS-2010-07527

CR-CNS-2010-07527 CR-CNS-2010-07553 CR-CNS-2010-07553

CR-CNS-2010-07757* CR-CNS-2010-07762* CR-CNS-2010-07776*

CR-CNS-2010-07803* CR-CNS-2010-07813* CR-CNS-2010-07823*

CR-CNS-201 0-07831 * CR-CNS-2010-07839* CR-CNS-2010-07847*

CR-CNS-2010-07848* CR-CNS-2010-07857* CR-CNS-2010-07859*

CR-CNS-201 0-07861 * CR-CNS-201 0-07914 * CR-CNS-2010-08163*

CR-CNS-2010-08165* CR-CNS-2010-08166* CR-CNS-2010-08167*

I CR-CNS-201 0-08201 * I CR-CNS-201 0-08221 * I CR-CNS-2010-08250*

A-3 Attachment 1

[ CR-CNS-2010-08253*

  • Condition Report initiated due to inspection activities.

DRAWINGS

Number Title Revision

14EK-0144 Diesel Engine Generator Schematic Diagram N22

85B-70008 Sheet

Wiring Diagram WD-12, 13, & 14 F.v.R Starter NOO

159

Ruskin Model NIBD23 3 Hour Type C - U.L. Labeled

0709-003 B

Horizontal Fire Damper 1 X 1

Ruskin Model NIBD23 3 Hour Type A - U.L. Labeled

0717-005 N01

Horizontal Fire Damper

Ruskin Model NIBD23 3 Hour Type C - U.L. Labeled

00735-001 0

Horizontal Fire Damper 1 X 1

Flow Diagram - Circulating, Screen Wash and Service I

2006 Sheet 1 N76

Water Systems

Flow Diagram - Reactor Building - Closed Cooling

2031 Sheet 2 N65

Water System

Flow Diagram - Reactor Building - Service Water

2036 Sheet 1 N98

System

Flow Diagram, Reactor Buiding Floor & Roof Drain N49

2038 Sheet 1

Systems .-.~---

Flow Diagram, Reactor Buiding Floor & Roof Drain

2038 Sheet 2 N03

Systems

2040 Sheet 1 Flow Diagram - Residual Heat Removal System N80

2042 Flow Diagram - Reactor Building - Main Steam System N85

2045 Sheet 1 Flow Diagram - Core Spray System N58

2016 Sheet 1C Flow Diagram - Fire Protection - Reactor Building N03

Fire Protection System - Flow Diagram For Pumphouse

2016 Sheet 2 N30

and Storage Tanks

2016 Sheet 4 Halon and Cardox System Flow Diagram N04

Reactor Building-Main Steam System-Cooper Nuclear

2041 N23

Station

2629-1 8" MS-1 & 10" MS-1 Main Steam N17

Auxiliary One Line Diagram Motor Control Center Z,

3002 Sheet 1 Switchgear Bus 1A, 1B, 1E, And Critical Switchgear N44

I Bus 1F, And 1G

A-4 Attachment 1

Auxiliarl One Line Diagram Motor Control Center C, D,

3004 Sheet 3 N22

H, J, DG1, And DG2

3012 Sheet 1 Main Three Line Diagram N08 I

3012 Sheet 2 Main Three Line Diagram N06

3012 Sheet 3 Main Three Line Diagram N19

3012 Sheet 4 Main Three Line Diagram N13

3012 Sheet 5 Main Three Line Diagram N15

3012 Sheet 6 Main Three Line Diagram N17

3012 Sheet 7 Main Three Line Diagram N08

3012 Sheet 8 Main Three Line Diagram N07

3012 Sheet 8a Main Three Line Diagram N05

3012 Sheet 9 Main Three Line Diagram N09

3012 Sheet 10 Main Three Line Diagram N11

I 3012 Sheet 12 Electrode Boiler Switchgear Main Three Line Diagram N03

3019 Sheet 3 4160V Switchgear Elementary Diagrams N36

3020 Sheet 4 4160V Switchgear Elementary Diagrams N20

3020 Sheet 8 4160V Switchgear Elementary Diagrams N32

3020 Sheet 9 4160V Switchgear Elementary Diagrams N22

3020 Sheet 4 4160V Switchgear Elementary Diagrams N20

4160V Switchgear Elementary Diagrams

3024 Sheet 8 N32

Lighting Plan

3045 Sheet 14 Control Elementary Diagrams N48

3058 D.C. One Line Diagram N53

3058 Sheet 1 D.C. One Line Diagram N53

3059, Sheet 1 D.C. Panel Schedules Cooper Nuclear Station 36

3065 Sheet 17 Control Elementary Diagrams N44

3065 Sheet 17a Control Elementary Diagram N11

3177 Outdoor Grounding Plans And Details N02

3251 Sheet 11 4160V Switchgear Connection Wiring Diagram N20

480V Motor Control Center R Connection Wiring

3253 Sheet R-1 N15

I Diagram

A-5 Attachment 1

3257, Sheet 71 Alternative Shutdown ADS Panel Internal Connections N06

3700 Sheet 16 Annunciator Elementary Ladder Diagram N05

3720 Sheet 1 Multiplexer Input Wiring ANN-MUX-10 N04

3726 Sheet 1 Multiplexer Input Wiring ANN-MUX-16 N03

3727 Sheet 1 Multiplexer Input Wiring ANN-MUX-17 N05

Annunciator Loop Diagram ANN-MUX-01 Devices

3751 Sheet 7 NOO

Sheet No. 6B

3757 Sheet 1 Annunciator Loop Diagram ANN-MUX-07 N01

3766 Sheet 1 Annunciator Loop Diagram ANN-MUX-16 N02

3767 Sheet 1 Annunciator Loop Diagram ANN-MUX-17 N04

Horizontal Drawout M/C Switchgear Device And

0133C8690 Sheet 15 1-17-1973

Harness Identification

0223R0558 Sheet 32 Power And Control Circuits Line-Up 08 Units 1 And 2 N22

Piping Isometric - Wet Sprinkler System Electrical

453200226 Trays In North East Corner Reactor Building - Floor N04

Elevation 903'-6" I

454016108 Contract E69-20 Fire Protection System N10

454016113 Contract E69-20 Fire Protection System N01

454016115 Contract E69-20 Fire Protection System N01

f"'~~.~~~. r::c" "" r::;~~ n~~.~_.; __ C' .. _._~ h..A A

454016116 vUlllI Clvl !::U;:1-':'U I-II 0 r I UlOvllU11 u Y:::'lOIII l'iU'"t

Nebraska Public Power District Contract Number

454016126 N04

E-69-20

115D6011, Sheet 1 Local Rack 25-50 NOO

729E720BB High Pressure Coolant Injection System N03

730E149BB, Sheet 1 Functional Control Diagram N05

730E149BB, Sheet 2 Main Steam Line Isolation Valve Control System Logic N04

791 E253 Sheet 1 Automatic Blowdown System Elementary Diagram N30

791 E253 Sheet 2 Automatic Blowdown System Elementary Diagram N27

791 E253 Sheet 3 Automatic Blowdown System Elementary Diagram N11

Elementary Diagram Reactor Core Isolation Cooling

791 E264 Sheet 7 N15

System (13-113)

...,,, ... ""..., ... C'L... __ '" ~ Cooper Nuclear Station-HPCI System-Elementary ....1""1"\

l'i 1;:1

11;:1IE':'1 I, ullOOlU

I Diagram

A-6 Attachment 1

Elementary Diagram Primary Containment Isolation

791 E266 Sheet 12 N12

System (16-23)

791E514 Sheet 1 Connection Diagram Panel 9-21 N23

791 E514 Sheet 2 Connection Diagram Panel 9-21 N01

944E689 Sheet 1 Elementary Diagram (Mod) Low-Low Set N13

CNS-EO-105 Sheet 1 EO Configuration Detail GE/PCI Pressure Switch N01

EO Configuration Detail, GE/PCI Pressure Switch

CNS-EO-i05 Sheet 2 N01

Tabulation Sheet

932'-6" Reactor Building - North Wall Critical

CNS-FP-146 N06

Switchgear Room 1G Fire area Boundary Drawing

Fire Area Boundary Drawing Diesel Generator Room

CNS-FP-170 N05

"1" South Wall

Fire Area Boundary Drawing Diesel Generator Room

CNS-FP-171 N05

"2" North Wall

Fire Protection Pre-Fire Plan Reactor Building First I

CNS-FP-215 N04

Floor Elevation 903'-6"

Fire Protection Pre-Fire Plan Reactor Building Critical

CNS-FP-216 N03

Switchgear Room 1F Elevation 932'-6"

Fire Protection Pre-Fire Plan Reactor Building MG Set

CNS-FP-221 N05

Area Elevation 976'-0"

Fire Protection Pre-Fire Plan Diesel Generator Building

CNS-FP-236 N05

D.G. # 1 Elevations 917'-6" and 903'-6" I I

CNS-FP-285 Sheet 1 CNS Fire Barrier Penetration Seal Details N04

Safe Shut Down Component Locations & Emergency

CNS-EE-186 4

Route Lighting, 903'-6" Diesel Generator Building

CNS-LRP-3, Sheet 4 Local Rack 25-50 Structure NOO

CNS-LRP-3, Sheet 8 Local Rack 25-50 Structure N01

CNS-LRP-3, Sheet 9 Local Rack 25-50 Structure N02

E0223R0558, Sheet Power And Control Circuits Line-Up 09 Units 1 And 2

N23

33 Lighting Plan Sheet 2

Integrated Control Circuit Diagram CS-MOV-M012A

E501 Sheet 17A N01

Core Spray Inboard Injection Valve

E501 Sheet 17B Integrated Control Circuit Diagram RHR-MOV-M025A N02

Integrated Control Circuit Diagram RHR-MOV-M027 A

E501 Sheet 17C N02

RHR Loop A Injection Outboard Isolation

Integrated Control Circuit Diagram RHR-MOV-M018

E501 Sheet 2'),A I\In1

I RHR Suction Cooling Inboard Isolation Valve

A-7 Attachment 1

Integrated Control Circuit Diagram SW-MOV-M089A

E50i Sheet 26A N01

RHR Heat Exchanger A Service Water Outlet

Integrated Control Circuit Diagram RCIC-MOV-M021

I E501 Sheet 29C

RCIC Injection

N01

E501 Sheet 30 Motor Operated Valves Connection Diagrams N08

Integrated Control Circuit Diagram RHR-MOV-M017

E501 SHEET30C N01

RHR Shutdown Cooling Supply Outboard isolation

Integrated Control Circuit Diagram HPCI-MOV-M058

E501 Sheet 33A N01

HPCI Pump Suction From Suppression Pool

E501 Sheet 44 Motor Operated Valves Connection Diagrams N02

Integrated Control Circuit Diagram RHR-MOV-M025B

E501 Sheet 45A N02

RHR Loop B Injection Inboard Isolation

Integrated Control Circuit Diagram SW-MOV-M089B

E501 Sheet 48A N02

RHR Heat Exchanger B Service Water Outlet

E507 Sheet 24 Connection Wiring Diagram Reactor Building N08

E507 Sheet 29 Connection Wiring Diagrams Reactor Building N03

Reactor Building Terminal Box 242 Connection Wiring

I E507 Sheet 235 Diagram

N01

G5-262-743 Sheet 1 Emergency Diesel Generator No.1 Electrical Schematic N23

G5-262-746 Sheet 2 Emergency Diesel Generator No.1 Electrical Schematic N18

G5-262-746 Sheet 3 Emergency Diesel Generator No.1 Electrical Schematic N23

G5-262-746 Sheet 4 Emergency Diesel Generator No.1 Electrical Schematic N12

Emergency Diesel Generator No.1 Internal Wiring

G5-262-746 Sheet 5 N19

Diagram

Emergency Diesel Generator No.1 Control Panel Wiring

G5-262-746 Sheet 6 N16

Diagram

X2629-200 MS-1 Main Steam N06

FIRE IMPAIRMENTS

FP08-01-FP-SD-61 A&B FP10-01-NO APPDX R FP10-01-FP-SD-533

LIGHT CEILING TILE

FP10-02-FP-HT-3 FLOODED FP1 0-01-FC9ASDG1 OOF FP1 0-01-EE-LTG-APP R

FP10-02-6.FP.302 FP10-01-COMP RM TILES FP10-01-FP-PNL-CAS

FP1 0-01-RW BLDG HORNS FP1 0-01-CORE BORES FP10-01-SWP RM HALON

FP10-01-EE-LTG-R18 BULB FP10-02-FP-HT-12 FP1 0-02-FP-HT-15

FAIL IMPAIRED INACCESSABLE

FP10-01-APPDX R F\f\J FP1 0-01-VVVV FALSE ALRM FP1 n-n1-FP A'pP R

I OVERFILL I AHU1

A-8 Attachment 1

PREVENTIVE MAINTENANCE TASKS

14624836 14624889 [4663722 [4663770 14712840 [4713833

PROCEDURES

Number Title Revision

Ad min istrative

Conduct of the Condition Report Process 67

Procedure 0.5

Administrative

Operating Experience Program 21

Procedure 0.10

Administrative

CNS Fire Protection Plan 60

Procedure 0.23

Administrative

Hot Work 42

Procedure 0.39

Administrative

Fire Watches and Fire Impairments 6

Procedure 0.39.1

Emergency

Procedure 5.3ALT- Alternative Core Cooling Mitigating Strategies 23

STRATEGY

Emergency

Procedure 5.4FIRE- Fire Induced Shutdown From Outside Control Room 38

SID

Emergency

Procedure 5.4POST- Post-Fire Operational Information 36 and 37

FIRE

Maintenance

Appendix RISSO Lighting Functional Test 20

Procedure IS.EE.302

Maintenance

3M Interam E-5A Fire Wrap Fire Resistive Assembly 12

Procedure 7.3.21.7

Non-TS Surveillance

Fire Detection System Tri-Annual Test (Group 1) 15

Procedure 15.FP.303

Non-TS Surveillance

Critical Switchgear Room Duct Wrap Visual Inspection 2

Procedure 15.FP.652

3.9 ASME OM Code Testing Of Pumps and Valves 25

(""t. * * _ __ =11.,- __ -.._ A ........ ,.... .. Ii.-. 'r 1._ r":._ " .. :1. ,... ~ ..' '-' _ r A"' ....... " ...... '"

I f'\U'::> Tram

. "._ I \ A A

I .::>UI Vt:::IIIC:lII(;t::: IVIi::H1UC:lI v C:llve '"-II (;Ull ,"-onnnUity f'\;:'U-f'\U;:' I I

A-9 Attachment 1

Procedure Panel

6.ADS.202

Surveillance

1ST Closure Test of HPCI-CV-10CV and RCIC-CV-

Procedure 7

10CV

6.CSCSA04

Surveillance

Annual Testing of Fire Pumps 30

Procedure 6.FP.102

Surveillance Fire Damper Assembly Examination (Fire Protection

Procedure 6.FP.203 System 18 Month Examination)

o and 9

Surveillance

Operations Power Block Sprinkler System Testing 17

Procedure 6.FP.301

Surveillance

Automatic Deluge and Pre-Action Systems Testing 19

Procedure 6.FP.302

Surveillance

Fire Detection System Circuitry Operability 7

Procedure 6.FP.304

Surveillance

Fire Barrier/Fire Wall Visual Examination 12

Procedure 6.FP.606

Surveillance

Calibration Procedure for HPCI Pressure

Procedure 8

Instrumentation

6.HPC1.306

Surveillance

Procedure HPCI Turbine Trip and Initiation Logic Functional Test 7

6.HPC1.311

Surveillance

Safety Valve and Relief Vaive Position indication '13

Procedure

Operability Check And LLS Logic Test

6.SRV.303

Surveillance

Diesel Generator C02 Operability Teat (DIV 1) 10

Procedure 6.1 FP.301

Surveillance

Fire Detection System 184 Day Examination 9

Procedure 6.1 FP.302

Surveillance

High Pressure C02 Cylinder Examination (DIV 1) 12

Procedure 6.1 FP.601

Surveillance Safe Shutdown BBESI Emergency Lighting Unit

14

Procedure 7.3.12.2 Examination and Maintenance

Surveillance

Appendix RISBO Lighting Functional Test 20

Procedure 15.EE.302

Surveillance

Fire Detection System Tri-Annual Test (Group 3) 10

Procedure 15.FP.305

I System Operating I Communication Systems 41

A-10 Attachment 1

MISCELLANEOUS DOCUMENTS

Number Title Revision

COR002-18-02 OPS-Reactor Core Isolation Cooling 17

Cutler-Hammer Instructions For Size 1 Or 2 Type B Thermal June 1998

Overload Relay, 3 Pole, Ambient Compensated Or

Non-Compensated I.L.16954A

Design Criteria Fire Protection Systems May 10, 2010

Document 11

Engineering Evaluation of Critical Switchgear Rooms 1F and 1G 0

Evaluation Number Fire Barrier Separation

EE 09-031

Evaluation Number Appendix R MOV Overthrust Evaluation 0

EE 04-046

Engineering I Ruskin Manufacturing Company - Site Storage and 2

Procedure Number Handling of NIED-23 Curtain Type Fire Dampers

E-510

EODP.2.210 Electroswitch Series 24 (3 Sheets On EO 10

Certification of Model 2421 OB Switch)

Letter LOA8200158 Fire Protection Rule 10 CFR 50, Appendix R June 28, 1982

Letter LOA83001 09 Fire Protection Rule 10 CFR 50, Appendix R, March 18,

Preliminary Supplemental Response (Revised) 1983

Nebraska Public Response to Appendix A to Branch Technical December 17,

Power District Letter Position APCB 9.5-1 Guidelines for Fire Protection 1976

for Nuclear Power Plants

Nebraska Public Revisions and Additional Information Fire Protection April 6, 1977

Power District Letter Review

~~ebraska Public Fire Protection Rule 10 CFR 50, Appendix R, June 02, 1983

Power District Letter Preliminary Supplemental Response (Revision 2)

NRC Letter K. R. Goller, NRC, to Nebraska Public Power District November 29,

1977

NRC Letter G. Lear, NRC, to Nebraska Public Power District February 24,

1978

NRC Letter T. Ippolito, NRC, to Nebraska Public Power District May 23,1979

NRC Letter T. ippolito, NRC, to Nebraska Public Power District September 18,

A-11 Attachment 1

NRC Letter Ippolito, NRC, to Nebraska Public Power District November 21,

I 1980 I

NRC Letter D. Vassallo, NRC, to Nebraska Public Power District April 29, 1983

NRC Letter D. Vassallo, NRC, to Nebraska Public Power District September 21,

1983

NRC Letter D. Eisenhut, NRC, to Nebraska Public Power District September 21,

1983

NRC Letter Safety Evaluation For Appendix R to 10 CFR Part April 16, 1984

50, Items II.G.3 and III.L, Alternative or Dedicated

Shutdown Capability

NRC Letter Outstanding Fire Protection Modifications August 21,

1985

NRC Letter W. Long, NRC, to Nebraska Public Power District April 10, 1986

NRC Letter W. Long, NRC, to Nebraska Public Power District September 9,

1986

NRC Letter Cooper Nuclear Station - Amendment No. 126 to November 7,

Facility Operation License No. DPR-46 1988

NRC Letter Cooper Nuclear Station - Amendment No. 127 to February 3,

Facility Operation License No. DPR-46 1989

NRC Letter Revocation Of Exemption From 10 CFR Part 50, August 15,

Appendix R - Cooper Nuclear Station 1995

NRC Letter Conversion To Improved Technical Specifications July 31, 1998

For The Cooper Nuclear Station - Amendment No.

178 To Facility Operating License No. DPR-46

OTH015-92-02 Lesson Plan Post Fire Shutdown Outside The 09

Control Room Procedures (5.4POST-FIRE,

5.4FIRE-S/D,5.1ASD)

Siemens-Allis DC DC Contactors Special Purpose 2 Pole, 600V Max No Date

Contactors AC or DC Operated Paaes 147 And 148

Siemens Overload Manufactures Data Thermal Overload Relays Type April 1997

2 Sheets 3UA59

Siemens Overload Manufacture's Data On Bimetallic Thermally No Date

4 Sheets Delayed Overload Relays Type 3UA5, 3UA6 Class

10

Southwest Research NPPD PO# 4500092806 Williams Fire Pump Diesel July 29,2008

Institute Oil Test Summary Report

Southwest Research NPPD PO# 4500100440 Williams Fire Pump Diesel Revision 1

Institute Oil Analytical Test Report May 11,2009

Southwest Research NPPD PO# 4500102145 Williams Fire Pump Diesel May 18, 2010

Institute Oil Analvtical Test Report

I Technical Publication I Electroswltch Senes 24 Instrument and Control I February 1998 I

A-12 Attachment 1

24-1 Switches For Power Industry and Heavy Duty

Industrial Applications

Technical Fire Protection Systems July 29, 2010

Requirements

Manual Section 3.11

Technical Alternative Shutdown System Amendment

Specification 3.3.3.2 233

Updated Safety Alternative Shutdown Capability July 24, 2001

Analysis Report

Section VII-18

Updated Safety Fire Protection System January 08.

Analysis Report 2004

Section X-9

Updated Safety Appendix R Safe Shutdown January 29,

Analysis Report 2003

Section X-18

Updated Safety Fire Protection Program April 16, 2010

Analysis Report

Section XIII-1 0

VM-1730 Emergency Lighting 1

Westinghouse Starter Manufactures Data Sheets Showing 460 VAC A201, April 1984

Information A211, A251 Size 2 Magnetic Contactor Non-

Reversing Or Reversing I. L. 16961 A

257HA354AC GE Design Specification, Sheet 2 2

790523 Amendment No. 56 to Facility Operating License No. 001

DPR-46

4605196 Sample Fuel Oil And Send For Analysis For Williams July 29, 2008

B.5.b Credited Pump

4625867 Sample Fuel Oil And Send For Analysis For Williams April 29, 2009

B.5.b Credited Pump

4664953 Sample Fuel Oil And Send For Analysis For Williams May 03,2010

B.5.b Credited Pump

1ST Reference/Acceptance Limits Data File 205

SYSTEM TRAINING MANUALS

Number Title Revision

COR002-11-02 High Pressure Coolant Injection 26

COR002-19-02 Reactor Equipment Cooling 20

,..,,, /"\,.., n __ :-I .. _I I I_,-L r"\ ____ **._1 ,..,..,

I r\t:::'IUUdl

""r"\n/"\(v~ ("\."-".1. ____

nt:dl r\t:IIIUVdl "y:stt:::rll L.t

A-13 Attachment 1

WORK ORDERS

4704976 4704973 4705129 4636801 4704980 4705274 4704985 4704986

4705369 4541652 4680341 4600849 4601469 4625865 4627329 4629553

4634534 4636434 4643635 4648115 4649842 4656140 4659221 4659685

4662049 4664951 4688234 4691445 4694802 4702636 4704770 4711699

4712867 4713861

A-14 Attachment 1

FINAL SIGNIFICANCE DETERMINATION SUMMARY

COOPER TRIENNIAL FIRE PROTECTION ISSUE

Significance Determination Basis

a. Phase 1 Screening Logic, Results, and Assumptions

In accordance with NRC Inspection Manual Chapter 0612, Appendix B, "Issue

Screening," the issue was determined to be more than minor because it was

associated with the equipment performance attribute and affected the mitigating

systems cornerstone objective to ensure the availability, reliability, or function of a

system or train in a mitigating system in that 3 motor-operated valves would not have

functioned following a postulated fire in multiple fire zones. The following summarizes

the valves and fire areas affected:

  • Valves Affected

RHR-MO-25A Residual Heat Removal (RHR) A Inboard Injection Valve

RHR-MO-25B RHR B Inboard Injection Valve

RR-MO-53A Reactor Recirculation Pump A Discharge Valve

  • Fire Areas Affected

CB-A-1 Control Building Division 1 Switchgear Room and Battery Room

CB-B Control Building Division 2 Switchgear Room and Battery Room

CB-C Control Building Reactor Protection System Room 1B

CB-D Control Room, Cable Spreading Room, Cable Expansion Room,

and Auxiliary Relay Room

RB-DI (SW) Reactor Building South/Southwest 903, Southwest Quad 889 and

859, and RHR Heat Exchanger Room B

RB-DI (SE) Reactor Building RHR Pump B/HPCI Pump Room

RB-J Reactor Building Critical Switchgear Room 1F RB-K Reactor

Building Critical Switchgear Room 1G

RB-M Reactor Building North/Northwest 931 and RHR Heat

ExchangerRoom

RB-N Reactor Building South/Southwest 931 and RHR Heat

Exchanger Room B

TB-A Turbine Building (multiple areas)

The significance determination process (SDP) Phase 1 Screening Worksheet

(Manual Chapter 0609, Attachment 4), Table 3b directs the user to Manual Chapter

0609, Appendix F, "Fire Protection Significance Determination Process," because it

affected fire protection defense-in-depth strategies involving post fire safe shutdown

systems. However, Manual Chapter 0308, Attachment 3, Appendix F, "Technical

Basis for Fire Protection Significance Determination Process for at Power

Operations," states that Manual Chapter 0609, Appendix F, does not include explicit

B-1 Attachment 2

treatment of fires in the main control room. The Phase 2 process can be utilized in

the treatment of main control room fires, but it is recommended that additional

guidance be sought in the conduct of such an analysis.

b. Phase 2 Risk Estimation

Based on the complexity and scope of the subject finding and the significance of the

finding to main control room fires, the analyst determined that a Phase 2 estimation

was not appropriate.

c. Phase 3 Analysis

A risk analysis was performed previously of a similar problem that affected the three

valves addressed by this performance deficiency. This was documented in EA 07-204,

Report Number 05000298/2008008, dated June 13, 2008. In both cases, Valves RHR-

MOV-25A, RHR-MOV-25B, and RHR-MOV-53A were incapable of being remotely

operated from the motor starter as prescribed by Procedure 5.4FIRE-S/O. The risk

estimate performed in 2008 as it pertains to these three valves (the 2008 Phase 3 also

included several other valves) remains valid for the current situation. However, changes

were made to Procedure 5.4FIRE-SID subsequent to the 2008 issue. These changes

were credited in the current analysis and resulted in a decrease in the risk significance of

the subject valves. Text from the 2008 risk analysis is shown in italics throughout this

document.

In accordance with Manual Chapter 0609, Appendix A, the analyst performed a Phase 3

analysis using input from the Nebraska Public Power District, "Individual Plant

Examination for External Events (IPEEE) Report- 10 CFR 50. 54 (f) Cooper Nuclear

Station, NRC Docket No. 50-298, License No. DPR-46, dated October 30, 1996, the

JJ

Standardized Plant Analysis Risk (SPAR) Model for Cooper, Revision 3.31, dated

September 2007, licensee input (see documents reviewed list in Enclosure 3), a

probabilistic risk assessment using a linked event tree model created by the analyst for

evaluating main control room evacuation scenarios, and appropriate hand calculations.

[Note: The SPAR model used in the 2008 analysis has been superseded by newer

versions. However, the risk result gained from the portion of the analysis that

used this model (non-alternative shutdown scenarios) was not significant to the

current risk estimate. Virtually all of the risk associated with the current issue

results from the alternative shutdown scenarios for which a specific SPAR model

was created. Therefore, the use of the older mode! has no consequence.]

Assumptions:

1. For fire zones that do not have the possibility for a fire to require the main

control room to be abandoned, the ignition frequency identified in the

IPEEE is an appropriate value.

2. The fire ignition frequency for the main control room (PF1F) is best

quantified by the licensee's revised value of 6.88 x 10- 3/yr.

B-2 Attachment 2

3. Of the original 64 fire scenarios evaluated, 18 were determined to be

redundant and were eliminated, 41 of the remaining (documented in Table

1) were identified as the predominant sequences associated with fires that

did not result in control room abandonment. [Note: the current issue did

not include all of the fire scenarios from the 2008 issue, but all of the

current fire scenarios are included in the 2008 compilation]

4. The baseline conditional core damage probability for a control room

evacuation at the Cooper Nuclear Station is best represented by the creation

of a probabilistic risk assessment tool previously created by the analyst using

a linked event tree method. The primary event tree used in this model is

displayed as Figure 1 in the Attachment. The baseline conditional core

damage probability as calculated by the linked event tree model was

1.14 x 10- 1, which is similar to the generic industry value of 0.1.

5. The analyst used an event tree, RECOVERY-PA TH, shown in Figure 2 in the

Attachment, to evaluate the likelihood of operator recovery via either

restoration of HPCI or manually opening Valve RHR-MO-258. The resulting

non-recovery probability was 7. 9 x 10-2 . [Note: This value was adjusted to

1.01 E-3 in the current analysis based on improvements made to

Procedure 5.4FIRE-SID.]

6. The risk related to a failure of Valve RHR-MO-258 to open following an

evacuation of the main control room was evaluated using the analyst's linked

event tree model. The conditional core damage probability calculated by the

linked event tree model was 1.19 x 10- 1 .

7. Any fire in the main control room that is large enough to grow and that goes

unsuppressed for 20 minutes will lead to a control room evacuation.

8. Any fire that is unsuppressed by automatic or manual means in the auxiliary

relay room, the cable spreading room, the cable expansion room or

Area R8-FN will result in a main control room evacuation.

9. The Cooper SPAR model, Revision 3.31, represents an appropriate tool for

evaluation of the core damage probabilities associated with postulated fires

that do not result in main control room evacuation.

10. All postulated fires in this analysis resulted in a reactor scram. In addition,

the postulated fire in Fire Area R8-K resulted in a loss-of-offsite power.

11. Valves RHR-MO-25A and RHR-MO-258 are low pressure coolant injection

system isolation valves. These valves can prevent one method of decay heat

removal in the shutdown cooling mode of operation.

12. For Valves RHR-MO-25A and RHR-MO-258, the subject performance

deficiency only applies to the portion of the post fire procedures that direct the

transition into shutdown cooling.

8-3 Attachment 2

13. Valve RHR-MO-25B must opened from the motor-control center for operators

to initiate alternative shutdown cooling from the alternative shutdown panel

following a main control room evacuation.

14. Valve RHR-MO-53A is the discharge isolation valve for Reactor Recirculation

Pump 1-A. The failure to close either this valve or Valve RR-MO-43A would

result in a short circuit of the shutdown cooling flow to the reactor vessel. The

performance deficiency did not apply to Valve RR-MO-43A.

15. The exposure time used for evaluating this finding should be determined in

accordance with Inspection Manual Chapter 0609, Appendix A, Attachment 2,

"Site Specific Risk-Informed Inspection Notebook Usage Rules. Given that

JJ

the performance deficiency was known to have existed for many years, the

analyst used the 1-year of the current assessment cycle as the exposure

period.

16. Based on fire damage and/or procedures, equipment affected by a postulated

fire in a given fire zone is unavailable for use as safe shutdown equipment.

17. The performance deficiency would have resulted in each of the demanded

valves failing to respond fol/owing a postulated fire.

18. In accordance with the requirements of Procedure 5.4POST-FIRE, operators

would perform the post-fire actions directed by the procedure following a fire in

an applicable fire zone. Therefore, the size and duration of the fire would not

be relevant to the failures caused by the performance deficiency.

19. Given Assumption 18, severity factors and probabilities of 17017-

suppression were not addressed for postulated fires that did not result in

main control room evacuation.

Postulated Fires Not Involving Main Control Room Evacuation:

The risk significance from fires not involving control room evacuation was determined to be

insignificant for the current finding. This was estimated by referring to the 2008 risk

evaluation. Text in italics is from the 2008 report and Table 1 is reproduced for the fire

areas that involve RHR-MOV-25A, RHR-MOV-258, or RHR-MOV-53A.

The senior reactor analyst used the SPAR model for Cooper Nuclear Station to estimate

the change in risk, associated with fires in each of the associated fire scenarios (Table 1,

Items 1 - 41) that was caused by the finding. Average unavailability for test and

maintenance of modeled equipment was assumed, and a cutset truncation of

a

1. x 10- 13 was used. For each fire zone, the analyst calculated a baseline conditional

core damage probability consistent with Assumptions 9, 10, 25 [now 17] and 26 [now

18].

8-4 Attachment 2

For areas where the postulated fire resulted in a reactor scram, the frequency of the

transient initiator, IE-TRANS, was set to 1.0. All other initiators were set to the house

event "FALSE," indicating that these events would not occur at the same time as a

reactor scram. Likewise, for Fire Area RB-K, the frequency of the loss-of-offsite power

initiator, IE-LOOP, was set to 1.0 while other initiators were set to the house event

"FALSE."

With input from the detailed IPEEE notebooks, maintained by the licensee, the analyst

was able to better assess the fire damage in each zone. This resulted in a more realistic

evaluation of the baseline fire risk for the zone, and lowering the change in risk for each

example.

Consistent with guidance in the Reactor Accident Sequence Precursor Handbook,

including NRC document, "Common-Cause Failure Analysis in Event Assessment,

(June 2007), " the baseline established for the fire zone, and Assumptions 22 through 26,

[now 15 through 19] the analyst modeled the resulting condition following a postulated

fire in each fire zone by adjusting the appropriate basic events in the SPAR model. Both

the baseline and conditional values for each fire zone are documented in Table 1.

As shown in Table 1, the analyst calculated a chanf',e in core damage frequency (IlCDF)

associated with these 41 fire scenarios of 2.9 x 1(J /yr. [Note: This result included fire

areas not affected by the current finding.]

The analyst evaluated the licensee's qualitative reviews of the 13 fire scenarios that were

impacted by the failure of the HPCI turbine to trip. In these scenarios, HPCI floods the

steam lines and prevents further injection by either HPCI or reactor core isolation cooling

system. Qualitatively, not all fires will grow to a size that causes a loss of the trip function

due to spatial separation. Additionally, not al/ unsuppressed fires would cause a failure of

the HPCI trip function. Finally, no operator recovery was credited in these evaluations.

Given that these qualitative factors would all tend to decrease the significance of the

finding, the analyst believed that the total change in risk would be significantly lower than

the 2.9 x 10-6/yr documented above. Based on analyst judgment and an assessment of

the evidence provided by the licensee, an occurrence factor of O. 1 was applied to the 13

fire scenarios. This resulted in a total IlCDF of 7.8 x 1Q-7/y r. Therefore, the analyst

determined that this value was the best estimate of the safety significance for these 41 fire

scenarios.

From Table 1, the total risk associated with fire areas that involve Valves RHR-MOV-25A,

RHR-MOV-25B, or RHR-MOV-53A is 5.5E-7. As noted above, in the 2008 analysis, there

were qualitative reasons for lowering this risk estimate. Also, because the previous

evaluation included the contribution from several other valves that affected the same fire

areas, the risk attributable to the current evaluation is lower. For these reasons, the analyst

concluded that the risk for the current finding is less than 1.0E-7 for fire areas that do not

involve control room evacuation.

B-5 Attachment 2

--

TABLE 1

Postulated Fires Not Involving Main Control Room Evacuation

Fire Estimated

Area/Shutdown Area/- Scenario Scenario Ignition Base CCDP Case CCDP delta-CDF Function Al'fected

Zone Number Description Frequency

Strate~IY Contribution

RHRA

RBC-CF 1C 1 Pump Room

2.94E-03 B.B2E-07 B.i5E-05 2.37E.07

2 MCC K 3.02E-03 2.76E-05 1.2BE-04 3.03E-07

3 MCCQ 3.93E-03 2.76E-05 1.2BE-04 3.95E-07

4 MCCR 3.43E-03 2.76E-05 1.2BE-04 3.44E-*07

5 MCC RB 1.62E-03 1.12E-03 1.21 E-03 1.46E-07

6 MCC S 2.23E-03 1.12E-03 1.21 E-03 2.01 E-07 Shut HPCI-MO-14,

7 MCCY 3.B3E-03 1.12E-03 1.21 E-03 3.45E-*07 HPCI-MO-16,

B Panel AA3 9.9BE-04 2.76e-05 1.2BE-04 1.00E-07 RHR-MO-921,

2AJ2C 9 Panel BB3 9.9BE-04 1.12E-03 1.21 E-03 B.9BE-OB RWCU-MO-1B and

RCIC Starter 5.27E-06 1.02E-07 MS-MO-77

10 1.32E-03 8.27E-05

Rack

11 250V Div 1 Rack 5. 1OE-04 2.76E-05 1.2BE-04 5.12E-OB

12 250V Div 2 Rack 2.09E-04 1.12E-03 1.21 E-03 1.BBE-OB

13 ASD Panels 3.02E-04 1.12E-03 1.21 E-03 2.72E-OB

CB-A 14 6.74E-03 7.64E-04 7.64E-04 O.OOE+OO

15 1.36E-03 2.61 E-06 2.61 E-06 O.OOE+OO

16 RPS Room 1A 4.15E-03 1.75E-07 1.75E-07 O.OOE+OO Open RHR-MO-25B

17 2.42E03 3.57E-04 3.5BE-04 4.B4E-10 and RHR-MO-67

Hallway (used B.74E-OB

1B 1.09E-02 2.05E-05 2.B5E-05

~-

CB corridor)

8-6 Attachment 2

--

--Fire Estimated

Area/- Scenario Scenario Ignition

Area/Sh utdown Number Description Base CCDP Case CCDP delta-CDF Function Affected

Strategy Zone Frequency Contribution

DC Switchgear

Open RHR-MO-17,

BH 19 Room 1A 4.27E-03 3.49E-03 3.49E-04 1.2BE-*09

RHR-MO-25B, and

CB-A'I RHR-MO-67

BE 20 Battery Room 2.25E-03 8.74E-06 1.03E-05 3.51 E-*09

1A

-- DC Switchgear

8G 21 Room 1B 4.27E-03 1.82E-03 1.83E-03 3.42E-OB

CB-B Open RHR-MO-25A

8F 22 Battery Room 2.25E-03 4.81 E-06 5.73E-06 2.07E-09

1B --

8B 23 4.15E-03 1.75E-07 1.77E-07 5.81 E-12 Open RHR-MO-17,

CB-C RPS Room 1A RHR-MO-25A, and

8C 24 4.15E-03 1.75E-07 1.77E-07 5.81 E-12 RHR-MO-67

_.

RHR Heat

Shut HPCI-MO-14

RB-DI (SW) 2D 25 Exchanger 6.70E-04 8.66E-05 8.68E-05 1.27E-10

and RR-MO-53A

Room B

RHR B/HPCI Shut HPCI-MO-14

RB-DI (SE) 1D/1 E 26 4.28E-03 6.48E-05 1.44E-04 3.37E-07

Pump Room and RR-MO-53A

Open RHR-MO-17,

Switchgear

RB-J 3A 27 3.71 E-03 5.28E-05 5.28E-05 O.OOE+OO RHR-MO-2EiB, and

Room iF RHR-MO-67

Switchgear 1.77E-02

RB-L 3B 28 3.71E-03 1.77E-02 O.OOE+OO Open RHR-MO-25A

Room 1G

RB Elevation

3C/3DI 29

932 1.13E-02 7.06E-06 8.99E-06 2.18E.08

3E Open RHR-MO-17

RB-M

and RHR-MO-25B

RHR Hx Room 6.70E-04 7.06E-06 8.99E-06 1.29E-09

2B 30 A --

3C/3D Reactor Building

RB-N 31 1.13E-02 1.22E-05 1.38E-05 1.81 E-08 Open RHR-MO-25A

13E Elevation 932

RHR Heat

2D 32 Exchanger 6.70E-04 1.22E-05 1.38E-05 1.07E-09

Room B

8-7 Attachment 2

Firea

Area/Shutdown

Strate(

Area/-

Zone

Scenario

Number

Scenario

Description

Ignition

Frequency

Base CCDP Case CCDP

Estimated

delta-CDF

Contribution

Function

TB-A Condenser Pit

110 33 3.10E-03 4.83E-06 6.20E-06 4.25E-09

Area

Reactor

11E 34 Feedwater 6.25E-03 4.83E-06 6.20E-06 8.56E-*09

Pump Area

11 L 35 Pipe Chase 6.70E-04 4.83E-06 6.20E-06 9.18E-10

Condenser and 4.83E-06

12C 36 Heater Bay Area 3.27E-03 6.20E-06 4.48E-09

Open RHR-M017,

RHR-MO-25A, and

RHR-MO-67

120 37 TB Floor 9033 3.45E-03 4.83E-06 6.20E-06 4.73E-09

Operating Floor

13A 38 5.76E-03 4.83E-06 6.20E-06 7.89E-09

Non-critical

Switchgear

13B 39 3.79E-03 4.83E-06 6.20E-06 5.19E-09

Room

13C 40 Electric Shop 8.56E-04 4.83E-06 6.20E-06 1.17E-09

130 41 I&C Shop 8.90E-04 4.83E-06 6.20E-06 1.22E-09

Total Estimated .6COF for 41 Postulated Fire Scenarios 1291E-06

8-8 Attachment 2

Post-Fire Remote Shutdown Calculations:

Note: The risk attributable to post-fire remote shutdown (control room abandonment

sequences) results predominantly from the inability to operate Valve RHR-MOV-258 as

described in Procedure 5.4FIRE-SID. This is the credited train and the only procedural

means for initiating shutdown cooling during the recovery actions. The additional risk

contribution from RHR-MOV-25A and RHR-MOV-53A is negligible.

As documented in Assumptions 4, 5, and 6, the analyst created a linked event tree model,

using the Systems Analysis Programs for Hand-on Integrated Reliability Evaluation

(SAPHIRE) software provided by the Idaho National Laboratory, to evaluate the risks related

to fire-induced main control room abandonment at the Cooper Nuclear Station. This linked

event tree was used to evaluate the increased risk from the subject performance deficiency

during the response to postulated fires in the main control room, the auxiliary relay room, the

cable spreading room, the cable expansion room or Fire Area RB-FN. The primary event

tree used in this model is displayed as Figure 1 in the Attachment.

As documented in Assumption 5, the analyst used an event tree to evaluate the

likelihood of operator recovery via either restoration of l-IPCI or manually opening

Valve RHR-MO-25B. The resulting non-recover; probability was 1.01 E-3. The

derivation of this result is discussed below. This result applied only to sequences

where HPCI provides injection flow. In cases where HPCI fails or is not available,

there is much less time available to recover from the failure. For this case, a SPAR-

H evaluation was performed, and is discussed below.

Note: In the 2008 analysis, the non-recovery probability for HPCI success

sequences was determined to be 7.9E-2. This non-recovery probability was

decreased by a factor of 78 for the current finding because of changes that were

made to Procedure 5.4FIRE-SID. These changes directed operators to close SRVs if

RHR injection was not observed to be successful. Also, it directed operators to delay

securing HPCI until RHR injection is confirmed.

In the 2008 analysis, recovery credit was only applied to sequences that contained

an early success (lack of failure or unavailability) of HPCI. This is because with the

use of HPCI, a considerable amount of decay heat is removed prior to the point of

attempting to open RHR-MOV-258 in Procedure 5.4FIRE-S/D, and ample time is

available to diagnose the failure and manually open the valve prior to fuel damage.

Also, HPCI can be re-initiated in theSe cases to maintain reactor parameters, and the

new procedures instruct operators to keep HPCI online until low-pressure injection is

confirmed. However, if HPCI is out of service for maintenance or experiences a

failure, the only success path is to establish RHR low pressure injection and the time

available is very limited. According to the licensee's MAAP analysis, incipient core

damage will occur 15 minutes after RHR-MOV-258 fails to open unless it is opened

(manually) by that time. For early HPCI failures, it is assumed in this analysis

(consistent with the 2008 analysis) that there is enough time to reach the step in

Procedure 5.4FIRE-S/D where RHR-MOV-258 is opened. If it fails to open (1.2E-2 in

the base case, 1.0 in the condition case), operators have 15 minutes to diagnose the

situation (injection failure) and develop a strategy that includes visually checking the

position of RHR-MOV-258 and opening it manually to at least 23 hand wheel turns to

gei sufficieni fiow io prevent core damage.

The analyst considered whether changes to Procedure 5.4FIRE-S/O subsequent to

8-9 Attachment 2

the 2008 risk analysis could allow some recovery credit to be applied to sequences

involving early HPCI failure in the current analysis. One possible reason to do this is

that the revised procedure directs the operator at the alternative shutdown panel to

close SRVs in the event that RHR injection cannot be verified. This would have the

effect of delaying the depletion of water inventory in the core. However, the

diagnosis of this situation would likely take a long time. The operator at the

alternative shutdown panel would be difficult to determine quickly, whether low

pressure injection was successful because of a lack of direct indication (total RHR

flow is displayed, but the effect of successful injection would only be a slight increase

in the total RHR flow rate until Valve RHR-MO-34B is throttled closed to divert the

flow that was previously directed to the suppression pool). The reactor level

indication would likely be the first indication of unsuccessful injection, but a lowering

level could well be misinterpreted as a shrink from the injection of colder water. Also,

if the operator used the alternative method prescribed in the procedure, which is used

when nitrogen pressure is determined to be reliably available, he is directed to use

SRVs to maintain pressure within a band of 150-200 psig. This could result in

masking the lowering level from a lack of injection. For these reasons, the analyst

determined that recovery for early HPCI failure sequences would be challenging.

A SPAR-H evaluation was performed to estimate a non-recovery probability for HPCI

failure sequences. AI! non-nomina! PSFs are shown in the following table:

Diagnosis (nominal =1.0E-2) Action (nominal = 1.0E-3)

Available Time Barely Adequate (2/3 Time Required (10)

nominal) (10)

Stress High (2) High (2)

Complexity Moderate (2) Nominal

ExperiencelTraining Nominal High (0.5)

Procedures Poor (5) Nominal

Ergonomics Nominal 50% Poor, 50% nominal-(5.5)

Total PSF Product 200 55

HEP 0.67 0.05

Total HEP 0.72

The licensee's thermal-hydraulic analysis indicated that approximately 15 minutes of

time would be available to open RHR-MOV-25B enough turns to provide adequate

core flow after the step in the procedure to open RHR-MOV-25B failed. The analyst

assumed that a nominal time to diagnose the problem is 15 minutes and the nominal

time to close the valve is 5 minutes. The available 15 minutes was partitioned with

10 minutes for diagnosis and 5 minutes for action. This explains the selection of the

factors above for available time for both diagnosis and action.

B-10 Attachment 2

Stress would be high in both cases. For diagnosis, complexity was considered be

moderate because of the need to observe several indications while following a

procedure that only addresses successful operation of the equipment and that directs

further actions to be taken that are unrelated to diagnosing equipment failures. In

addition, procedures for diagnosis were considered to be poor because of a lack of

direction to the operator at the alternative shutdown panel to check the position of

RHR-MOV-25B if a reactor vessel rise is not observed. Although there is a

procedural step for the reactor building operator to check the valve position, it is

specifically prescribed for cable spreading room fires only, and it is not clear that he

would do this for other alternative shutdown fires unless directed by the operator at

the alternative shutdown panel. The analyst considered experience and training to

be high for MOV manual operations at the plant because it is a frequently performed

task. Ergonomics for action were divided half and half between poor and nominal

because it would take an unusually large force to open the valve against the full

shutoff head of the RHR pump. In addition, there is a somewhat unfavorable

geometry for this operation.

Procedure 5.4FIRE-S/D, Attachment 2, Step 1.20.7 instructs the reactor building operator to

verify that RHR-MOV-258 is open if the fire is in the cabie spreading room. If the valve is

observed to not be open, Step 1.20.8 instructs the operator to open the breaker and manually

open the valve. There is some uncertainty as to \,AJhether the operator \*'Vou!d proceed VJith

Step 1.20.8 (after correctly skipping Step 1.20.7) if the fire was not in the cable spreading

room. The analyst concluded that the text of Step 1.20.8 ("If the valve did not operate,

perform following .. ") is written in such a way that it presumes that the operator has performed

the valve position verification of Step 1.20.7. Therefore, if Step 1.20.7 is skipped, it would be

logical to mark Step 1.20.8 "N/A."

The analyst concluded that the recovery probability for cable spreading room fires would be

nominal because it involves a direct observation of the valve position, followed by a well-

trained and proceduralized evolution. Therefore, for cable spreading room fires, the non-

recovery probability was assigned a value of 1.1 E-2 (nominal SPAR-H value). Unlike the

value used for "action" in the SPAR-H tabulation above, in this case there would be extra time

available for the operator to open the valve manually because no time would be needed for

diagnosis. For all other fire areas that cause alternative shutdown, the non-recovery value of

0.72 was used as discussed above. The following table summarizes the recovery

assumptions:

Non-Recovery Value

HPCI Success 1.01 E-3

Early HPCI Failure

1.1 E-2

Cable Spreading Room

Early HPCI Failure

0.72

All Other ASD Areas

Using the linked event tree model described in Assumption 4, the analyst calculated the

Condition CDF as 7.79E-6/yr. The base CDF was 5.81 E-6/yr. With a one-year exposure

time, the delta-CDF is 2.0E-6/yr. Almost all of the risk (approximately 99%) resulted from

sequences that involve alternative shutdown fires (other than the cable spreading room) that

include early failures or unavailability of HPCI.

8-11 Attachment 2

dominant cutsets are shown below in Table 2.

Table2

Main Control Room Abandonment Sequences

Postulated Fire Sequence I Mitigating Functions Results

Auxiliary Relay Room 4-01- rly Failure of HPCI

re to Open MO-2SB 1.3 x 10-6/yr

Early Failure of HPCI

Main Control Room 3-01-12

Failure to Open MO-2SB 3.4 x 10*7/yr

4-31-1-1-1-1- Early Failure of HPCI

Auxiliary Relay Room 1.8 x 10*7/yr

12 Failure to Open MO-2SB

3-31-1-1-1-1- Early Failure of HPCI

Main Control Room 4.6 x 10-8/yr

12 Failure to Open MO-2SB

Early Failure of HPCI

Auxiliary Relay Room 4-01-03 3.4 x 10-8/yr

Failure to Open MO-2SB

The following text from the 2008 analysis discusses the derivation of the control room

abandonment frequency. This information was considered applicable to the current evaluation.

Control Room Abandonment Frequency

NUREGICR-2258, "Fire Risk Analysis for Nuclear Power Plants, provides that control room

JJ

evacuation would be required because of thick smoke if a fire went unsuppressed for 20

minutes. Given Assumption 6 and assuming that a fire takes 2 minutes to be detected by

automatic detection and/or by the operators, there are 18 minutes remaining in which to

suppress the fire prior to main control room evacuation being required. NRC Inspection

Manual Chapter 0609, Appendix F, Table 2.7.1, "Non-suppression Probability Values for

Manual Fire Fighting Based on Fire Duration (Time to Damage after Detection) and Fire

Type Category," provides a manual non-suppression probability (PNS) for the control room of

1.3 x 10-2 given 18 minutes from time of detection until time of equipment damage. This is a

reasonable approach, although fire modeling performed by the licensee indicated that 16

minutes was the expected time to abandon the main control room based on habitability.

In accordance with Inspection Manual Chapter 0609, Appendix F, Task 2.3.2, the

analyst used a severity factor of O. 1 for determining the probability that a postulated

fire would be self sustaining and grow to a size that could affect plant equipment.

Given these values, the analyst calculated the main control room evacuation

frequency for fires in the main control room (FE VA C) as foiiows:

= 6.88 x 1Q-3Iyr * 0.1 * 1.3 x 10-2

= 8.94 x 10*61yr

In accordance with Procedure 5. 4FIRE-SID, operators are directed to evacuate the

main control room and conduct a remote shutdown, if a fire in the main control room or

any of the four areas documented in Assumption 8, if plant equipment spuriously

actuates/de- energizes equiprner;t, or if instrutnentatioll becomes unreliable.

8-12 Attachment 2

Therefore, for all scenarios except a postulated fire in the main control room, the

probability of non- suppression by automatic or manual means are documented in

Table 3, below.

Table 3

Control Room Abandonment Frequency

Fire Area Ignition Severity Automatic Manual Abandonment

Frequency Suppression Suppression Frequency

(per year) (per year)

Main Control

6.88 x 10-3 0.1 none 1.3 x 10-2 8.94 X 10-6

Room

Auxiliary Relay

1.42 x 10-3 0.1 none 0.24 3.41 x 10-5

Room

Cable Expansion

1.69 x 10-4 0.1 2 x 10-2 0.24 8.11 x 10-8

Room

Cable Spreading

4.27 x 10-

3

1 0.1 5 x 10-2 0.24 5.12 x 10-6

Room 1

Reactor Building

1.43 x 10-

3

1 0.1 2 x 10- 2

0.24 6.86 x 10-7

903' (RB-FN)

Total MCR Abandonment: 4.89 x 10-5

The licensee's total control room abandonment frequency was 1.75 x 10-5 . For the main

control room fire, the licensee's calculations were more in-depth than the analyst's. The

remaining fire areas were assessed by the licensee using IPEEE data. However, the

following issues were noted with the licensee's [2008J assessment:

Kitchen fires were not inciuded in iicensee's evaiuation

This would tend to increase the ignition frequency

This might add more heat input than the electrical cabinet fires

modeled by the licensee

Habitability Forced Abandonment

Non-suppression probability did not account for fire brigade

response time or the expected time to damage.

Reduced risk based on 3 specific cabinets causing a loss of

ventilation early, when it should have increased the risk. Fire

modeling showed that fires in these cabinets could damage

nearby cables and cause ventilation damper(s) to close.

Risk Assessment Calculation ES-91 uses an abandonment value of

7

9.93 x 10- . However, the supporting calculation performed by EPM

IIC'ON ~ n? Av 1n- 6

LfVv\...# V.V"- I V .

B-13 Attachment 2

Equipment Failure Control Room Abandonment

Criteria for leaving the control room did not accurately reflect the

guidance that was procedura/ized.

  • The evaluation of the Cable Expansion Room stated that the only fire source

was self-ignition of cables. This was modeled as a hot work fire, and it

included a probability that administrative controls for hot work and fire

watches would prevent such fires from getting large enough to require

control room abandonment. This is inappropriate for self-ignition of cables,

since there would not really be any fire watch present. Adjusting for this

would increase the risk in this area by two orders of magnitude.

The licensee concluded that fires in equipment in the four alternative

shutdown fire areas outside the main control room (see Assumption

8) would not result in control room abandonment without providing a

technical basis. The licensee's Appendix R analysis concluded that

fire damage in these rooms require main control room evacuation to

prevent core damage.

The analyst used the main control room abandonment frequencies documented in Table 3. In

addition, sensitivities were run using the licensee's values.

Recovery Following Failure of Valve RHR-MO-258 (HPCI success sequences only)

As noted above, the recovery value determined in the 2008 analysis was 7.9E-2. The

following table presents the revised split fractions based on the improvements to Procedure

5.4FIRE-S/D.

... .... 1 ...

I aDle~

Split Fractions for RECOVERY -PATH

Top Event How Assessed Failure Probability

LEVEL-DOWN SPAR-H (Diagnosis OnlY} 1.75E-4

SRV-STATUS SPAR-H (Diagnosis Onhl 1.75E-3

CLOSE-SRVS SPAR-H (Action Only) 4.38E-4

RESTORE-HPCI SPAR-H (Combined) 7.0E-4

OPEN-MO-258 SPAR-H (Combinedl 2.89E-1

Using the event tree in Figure 2 and the split fractions in Table 4, the analyst calculated a

combined non-recovery probability of 1.01 E-3.

The licensee's combined non-recovery probability was 4.0 x 10-3 . [Note: this value is

based on the licensee's evaluation before the aforementioned improvements were

made to the procedure]. The licensee used a similar approach to quantify this value.

However, the licensee assumed that operators would always shut the safety-relief valves

upon determining that reactor pressure vessel water level was decreasing. The analyst

assumed that some percentage of operators would continue to follow the procedure and

attempt to recover from the failed RHR valve or try alternative methods of low-pressure

injection. In addition, the analyst identified the following issues that impacted the licensee's

analysis:

8-14 Attachment 2

The inspectors determined that it would require 112 ft-fbs of force to manually

open Valve RHR-MO-25B. The analyst determined that this affected the

ergonomics of this recovery. Some operators may assume that the valve is on

the backseat when large forces are required to open it. Some operators might be

incapable of applying this force to a 2-foot diameter hand wheel.

The analyst noted that the following valves would be potential reasons for lack of

injection flow and/or may distract operators from diagnosis that Valve RHR-MO-

025B is closed:

RHR-81 B, RHR Loop B Injection Shutoff Valve, could be closed.

RHR-27CV, RHR Loop B Injection Line Testable Check Valve,

could be stuck closed.

RHR-MO-274B, Injection Line Testable Check Valve Bypass

Valve, could be opened as an alternative.

Operators could search for an alternative flow path.

The licensee's [2008J evaluation did not include sequences involving the failure of

the HPCI system shortly after main control room evacuation in their risk evaluation.

These sequences represented approximately 26 percent of the I'lCDF as calculated

by the analyst. These sequences are important for the following reasons:

Failure of HPClleads to the need for operators to rapidly depressurize

the reactor to establish alternative shutdown cooling. Decay heat will

be much higher than for sequences involving early HPCI success.

Also, depressurization under high decay heat and high temperature

result in greater water mass loss. This will significantly reduce the

time available for recovery actions.

HPCI success sequences provide long time frames available with

HPCI operating. This reduces decay heat, increases time for

recovery, and permits the establishment of an emergency response

organization. Those factors are not applicable to early HPCI failure

sequences.

The basis for operating HPCI was not well documented by the licensee. During

many of the extended sequences, suppression pool temperature went well above

the operating limits for HPCI cooling and remained high for extended periods of

time. The following facts were determined through inspection:

The design temperature for operating HPCI is 140'F based on

process flow providing oil cooling.

General Electric provided a transient operating temperature of 170'F

for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

8-15 Attachment 2

In the licensee's best case evaluation of the performance

deficiency, the suppression pool would remain above 150'F for

10.6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

The licensee used a case-specific combined recovery in assessing the risk of this

performance deficiency. Most of the recoveries discussed by the licensee would

have been available with or without the performance deficiency. Therefore, these

should be in the baseline model and portions of the sequences subtracted from

the case evaluation. This is the approach used by the analyst in the linked event

trees model. The licensee stated during the regulatory conference that credit

should be given for diesel-driven fire water pump injection. This is one of the

licensee's alternative strategies. However, the inspectors determined, and the

licensee concurred, that this alternative method of injection requires that Valve

RHR-MO-258 be open. Therefore, no credit was given for this alternative

strategy.

Conclusions:

The analyst concluded that the performance deficiency was of low to moderate significance

(VVhite). Ill,S documented in Table 1, for a period of exposure of 1 year, the analyst determined

a best estimate .6.CDF for fire scenarios that did not require evacuation of the main control room

of less than 1.0E-7/yr. using both quantitative and qualitative techniques. Additionally, using the

linked event tree model described in Assumption 4 for a period of exposure of 1 year, the

analyst calculated the .6.CDF to be 2.0E-6/yr. for postulated fires leading to the abandonment of

the main control room. This resulted in a total best estimate .6.CDF of 2.0E-6/yr.

8-16 Attachment 2

Figure 1

-- --

Reactor Failure to Failure to Failure to Failure to Failure to Failure to

Shutdown from Establish AC Establish Level Establish Torus Properly Cool the Establish Reestablish HPCI

Alternate Power anci Pressure Cooling Reactor Shutdown Cooling Before CD

--

I

REMOTE_SD ASD-EPS ASD-HPSI ASD-SPC ASD-COOL ASD-SDC ASD-REHEAT # I END~STATE:~__

1 OK

2 OK

I 3 CD

4 OK

I 5 CD

6 OK

_.

[ 7 OK

I 8 CD

9 CD

10 OK

Depress Only

HPCI Recover Only

11 10K

I 12 I CD

13 CD

14 CD

15 CD

REMOTE-SO - 2008/06/11


A-1 Attachment 2

Figure

2

r-------,-------,-----------, I

Valve 258 Fails op. erators Fail to Operators I

Operators Fail to Operators Fail to ()perators Fail to

to Open Upon Diagnose Level Decide to Leave Close SRVs Reestablish I Open Valve 258

Demand Decrease SRVs Open Given Decision HPCI

MO-25B-FAI LEVEL-DOWN SRV-STATUS CLOSE-SRVS RESTORE-HP OPEN-MO-25 # END-STATES


'-------....L------t--

OK

2 OK

HEP - HPCI Fails 3 CD

4 OK

~ HEP - SRV, 0,"" 5 CD

6 OK

~ HEP - SRV, 0,,""

7 CD

8 i CD

I RECOVERY-PATH - Combine Multiple Recoveries 10 25B Failure 2008/06/11 Page 36

8-18 Attachment 2