05000298/LER-2023-001, Valve Test Failures Result in Condition Prohibited by Technical Specifications
| ML23128A133 | |
| Person / Time | |
|---|---|
| Site: | Cooper |
| Issue date: | 05/08/2023 |
| From: | Dia K Nebraska Public Power District (NPPD) |
| To: | Office of Nuclear Reactor Regulation, Document Control Desk |
| References | |
| NLS2023023 LER 2023-001-00 | |
| Download: ML23128A133 (1) | |
| Event date: | |
|---|---|
| Report date: | |
| Reporting criterion: | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(v), Loss of Safety Function |
| 2982023001R00 - NRC Website | |
text
H Nebraska Public Power District "Always there when you need us" 10 CFR 50.73 NLS2023023 May 08, 2023 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Subject: Licensee Event Report No. 2023-001-00 Cooper Nuclear Station, Docket No. 50-298, DPR-46
Dear Sir or Madam:
The purpose of this correspondence is to forward Licensee Event Report 2023-001-00.
This letter does not contain regulatory commitments.
Sincerely, Kha 11 Dia Site Vice President
/jo
Attachment:
Licensee Event Report 2023-001-00 cc:
Regional Administrator w/attachment USNRC - Region IV Cooper Project Manager w/attachment USNRC - NRR Plant Licensing Branch IV Senior Resident Inspector w/attachment USNRC-CNS SRAB Administrator w/attachment NPG Distribution w/attachment INPO Records Center w/attachment via IRIS entry SORC Chairman w/attachment CNS Records w/attachment COOPER NUCLEAR STATION 72676 648A Ave/ P.O. Box 98 / Brownville, NE 68321 http://www.nppd.com
Abstract
On March 7 and March 8, 2023, two Target Rock safety relief valve (SRV) pilot assemblies, removed during Refueling Outage 32, failed to lift within Technical Specifications (TS) lift setpoint requirements. The pressure setpoint of the first failed pilot assembly was 1080 psig; the SRV pilot assembly lifted at 1166.4 psig. The pressure setpoint of the second failed pilot assembly was 1100 psig; the SRV pilot assembly lifted at 1186.1 psig. Three subsequent lifts were performed for the failed SRV pilot assemblies and the results were within the TS pressure setpoint tolerance.
The cause of the failure was determined to be corrosion bonding.
Although the setpoint lift pressures of the SRV pilot valve assemblies exceeded TS requirements, an analysis of the event concluded the thermal limits, and American Society of Mechanical Engineers overpressure transients, did not exceed allowable limits. Public safety was not at risk. Safety of plant personnel, and plant equipment, was not at risk. A TS Amendment to TS 3.4.3 will be submitted that will address the failure to meet the TS criteria for the Target Rock two-stage SRVs.
PLANT STATUS
- 2. DOCKET NUMBER 00298 YEAR J. LEK"
SEQUENTIAL NUMBER 2023 001 REV NO.
00 Cooper Nuclear Station was in Mode 1, Power Operation, at 100 percent power, when the event was discovered, i.e.,
March 8, 2023.
BACKGROUND The pressure relief system includes three American Society of Mechanical Engineers (ASME) code safety valves (SV)
[EIIS: SB] and eight safety relief valves (SRV) [EIIS: RV], all of which are located on the main steam lines [EIIS: SB] within the drywell [El IS: NH], between the reactor vessel [EIIS: RPV] and the first main steam isolation valve [EIIS: ISV]. The SVs provide protection against over pressurization of the nuclear system and discharge directly into the interior space of the drywell. The SRVs discharge to the suppression pool and provide three main functions: overpressure relief operation to limit the pressure rise and prevent safety valve opening, overpressure safety operation to prevent nuclear system over pressurization, and depressurization operation (opened automatically or manually) as part of the emergency core cooling system [EIIS: BJ, BM, BO].
Technical Specification (TS) Limiting Condition for Operation (LCO) 3.4.3 requires the safety function of seven SRVs and three SVs to be operable. The nominal set pressure tolerances for these valves are established in CNS TS Surveillance Requirement (SR) 3.4.3.1.
The SRVs installed at CNS are Target Rock Model 7567F, two-stage, pilot-actuated valves with pilot assemblies comprised of Stellite 21 pilot discs and Stellite 68 pilot body seats. The pilot assemblies had been in continuous service since installation in Refueling Outage (RE) 31, (Fall of 2020).
Corrosion bonding is an industry known problem with Target Rock Model 7567F two-stage relief valves in which the pilot valve bonds/sticks to the in-body seat, resulting in an increased pressure needed to lift the valve. After the corrosion bonding is "broken" following the initial lift, the subsequent lifts are within tolerance.
EVENT DESCRIPTION
In the Fall of 2022, three main SRV body/pilot assemblies and five SRV pilot assemblies were removed during RE32. In March 2023, the eight SRV pilot assemblies were as-found tested at National Technical Systems Laboratories.
The pressure setpoint for SRV pilot assembly serial number 387 is 1080 psig. The TS SR 3.4.3.1 as-found limit acceptance is 1080 +/- 3%. The first actual lift pressure of this SRV pilot assembly was recorded at 1166.4 psig, 8.0%
above the pressure setpoint. A second, third, and fourth lift was performed, and the results were 1088 psig, 1084 psig, and 1084 psig, all three within 3% of the pressure setpoint.
The pressure setpoint for SRV pilot assembly serial number 386 is 1100 psig. The TS SR 3.4.3.1 as-found limit acceptance is 1100 +/- 3%. The first actual lift pressure of this SRV pilot assembly was recorded at 1186.1 psig, 7.8%
above the pressure setpoint. A second, third, and fourth lift was performed, and the results were 1111 psig, 111 O psig, and 1109 psig, all three within 3% of the pressure setpoint.
BASIS FOR REPORT CNS is reporting this event as an operation or condition prohibited by plant TS per 10 CFR 50.73(a)(2)(i)(B), and also as a condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to mitigate the consequences of an accident as defined under 10 CFR 50.73(a)(2)(v)(D). Page_2_of_3_ (03-14-2023)
U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY 0MB: NO. 3150-0104 EXPIRES: 08/31/2023 LICENSEE EVENT REPORT (LER)
CONTINUATION SHEET (See NUREG-1022, R.3 for instruction and guidance for completing this form http://www.nrc.gov/read i ng-rm/doc-collections/nureqs/staff /sr1022/r3/)
FACILITY NAME X 050 Cooper Nuclear Station 052
SAFETY SIGNIFICANCE
- 2. DOCKET NUMBER YEAR 00298 2023
- 3. Lt:I"( NUIVIDCI"(
SEQUENTIAL NUMBER 001 REV NO.
00 CNS performed an Engineering Report (ER) documenting the impact of the RE32 SRV setpoint failures. The ER determined the ASME overpressure protection and core thermal limits would not have been exceeded. Public safety was not at risk. Safety to plant personnel and plant equipment was not at risk.
Based on the results of the ER, this event is not considered a Safety System Functional Failure nor a loss of safety function and will not be counted as a Safety System Functional Failure to the Nuclear Regulatory Commission (NRC) perform indicator since no loss of safety function occurred.
CAUSE
Corrosion bonding between the pilot disc and the in-body seat.
CORRECTIVE ACTIONS
The Boiling Water Reactor Owners Group (BWROG) Licensing Committee is actively developing a TS change via a Technical Specification Task Force {TSTF) Traveler such that the LCO and associated SR will be met if the safety function is met. CNS is following this BWROG initiative and utilizing the corrective action program to track the following actions:
- 1.
Track to completion the BWROG industry initiative to develop a TSTF Traveler for TS 3.4.3, including NRC approval, that would address the failure to meet TS criteria for the Target Rock two-stage SRVs.
- 2.
Submit a TS Amendment to TS 3.4.3 that would address the failure to meet TS criteria for the Target Rock two-stage SRVs. Following submittal, initiate a new CA for TS Change approval that also ensures a follow-on corrective action to implement the TS change.
PREVIOUS EVENTS Licensee Event Report (LER) 2021-002 On March 18 and March 20, 2021, two Target Rock SRV pilot assemblies failed to lift within TS lift setpoint requirements. The cause was corrosion bonding.
LER 2019-001-00 and LER 2019-001 On March 4, March 5, and March 6, 2019, three of eight Target Rock SRV pilot assemblies failed to lift within TS lift setpoint requirements. The cause was corrosion bonding.
LER 2017-002 In February and March, 2017, one Target Rock SRV pilot assembly failed to lift within TS lift setpoint requirements and another SRV pilot assembly was conservatively considered a failure due to lack of as-found lift pressure test data since it was inadvertently disassembled prior to performing the as-found lift pressure test. There were two causes for the failures; one of the SRV pilot assemblies failed due to corrosion bonding; the other SRV pilot assembly failed due to a lack of a barrier to prevent inadvertent disassembly of the SRV pilot prior to testing.
LER 2015-001-00 and LER 2015-001 On January 26 and February 11, 2015, five of eight Target Rock SRV pilot valve assemblies failed to lift within TS lift setpoint requirements. The cause was corrosion bonding.
LER 2011-005 On June 22, 2011, one of eight Target Rock SRV pilot valve assemblies failed to lift within TS lift setpoint requirements. The cause was corrosion bonding.
LER 2010-001 On January 12, 2010, two of eight Target Rock SRV pilot valve assemblies failed to lift within TS lift setpoint requirements. The cause was corrosion bonding. Page _3_ of _3_