IR 05000298/2024005

From kanterella
Jump to navigation Jump to search
Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2024005)
ML24232A258
Person / Time
Site: Cooper 
(DPR-046)
Issue date: 08/22/2024
From: Jeffrey Josey
NRC/RGN-IV/DORS
To: Dia K
Nebraska Public Power District (NPPD)
References
IR 2024005
Download: ML24232A258 (1)


Text

August 22, 2024

SUBJECT:

UPDATED INSPECTION PLAN FOR COOPER NUCLEAR STATION (REPORT 05000298/2024005)

Dear Khalil Dia:

The enclosed inspection plan lists the inspections scheduled through June 30, 2026, for Cooper Nuclear Staton. The Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Agency Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)

component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 817-200-1148 with any questions you have regarding this letter.

Sincerely, Jeffrey E. Josey, Chief Reactor Projects Branch C Division of Operating Reactor Safety Docket No. 05000298 License No. DPR-46

Enclosure:

Inspection Plan cc w/encl: Distribution via LISTSERV Signed by Josey, Jeffrey on 08/22/24

ML24232A258 X SUNSI Review By: WSchaup ADAMS:

X Yes No Sensitive X Non-Sensitive Non-Publicly Available X Publicly Available Keyword NRC-002 OFFICE SPE:DORS/C BC:DORS/C NAME WSchaup JJosey SIGNATURE

/RA/

/RA/

DATE 8/22/2024 8/22/2024

Enclosure Prepared on 8/14/2024 1:20:28 PM Page 1 of 3 Site Inspection Activity Plan 07200066 - Cooper Nuclear Station (ISFSI)

07/01/2024 - 06/30/2026 I Cooper Triennial ISFSI Inspection (one-week during loading campaign) (Part 72)

Unit Start End Activity CAC Title Staff Count 8/1/2025 8/31/2025 IP 60855 001001 Operation Of An ISFSI

Site Inspection Activity Plan Prepared on 8/14/2024 1:20:28 PM 2 of 3 Cooper 07/01/2024 - 06/30/2026 II Security Access Control (.02), Security Plan Changes (.09), Security PIV (71151)

1 8/12/2024 8/16/2024 IP 71130.02 000734 Access Control

8/12/2024 8/16/2024 IP 71130.09 001656 Security Plan Changes

8/12/2024 8/16/2024 IP 71151 001338 Performance Indicator Verification Inservice Inspection-CNS

1 10/7/2024 10/16/2024 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

RP 1,3,PI

1 10/7/2024 10/11/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

10/7/2024 10/11/2024 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

10/7/2024 10/11/2024 IP 71151 000746 Performance Indicator Verification RP 5,6,7,8 - CNS

1 3/24/2025 3/28/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation

3/24/2025 3/28/2025 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment

3/24/2025 3/28/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program

3/24/2025 3/28/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation CNS 2025 Biennial PI&R

1 3/31/2025 4/4/2025 IP 71152B 000747 Problem Identification and Resolution

4/14/2025 4/18/2025 IP 71152B 000747 Problem Identification and Resolution Security Protective Strategy (71130.05) and Target Sets (71130.14)

1 4/28/2025 5/2/2025 IP 71130.05 000737 Protective Strategy Evaluation

4/28/2025 5/2/2025 IP 71130.14 000743 Review of Power Reactor Target Sets EP 2025 Program Inspection - CNS

1 5/12/2025 5/16/2025 IP 71114.02 000717 Alert and Notification System Testing

5/12/2025 5/16/2025 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System

5/12/2025 5/16/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes

5/12/2025 5/16/2025 IP 71114.05 000720 Maintenance of Emergency Preparedness

5/12/2025 5/16/2025 IP 71151 001397 Performance Indicator Verification MC&A - CNS

1 6/9/2025 6/13/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)

Security Access Control (71130.02), Security Plan Changes (71130.09), Security PIV (71151)

1 8/4/2025 8/8/2025 IP 71130.02 000734 Access Control

8/4/2025 8/8/2025 IP 71130.09 001656 Security Plan Changes

8/4/2025 8/8/2025 IP 71151 001338 Performance Indicator Verification Unit Start End Activity CAC Title Staff Count

Site Inspection Activity Plan Prepared on 8/14/2024 1:20:28 PM 3 of 3 III CNS 2025 INITIAL EXAM

1 8/3/2025 8/9/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

9/7/2025 9/13/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Cyber Security Inspection-CNS

1 9/14/2025 9/20/2025 IP 71130.10 000741 Cybersecurity CNS 2025 BRQ

1 10/5/2025 10/11/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Age-Related Degradation Inspection - Cooper

1 10/20/2025 10/24/2025 IP 71111.21N.04 001832 Age-Related Degradation

11/3/2025 11/7/2025 IP 71111.21N.04 001832 Age-Related Degradation RP 1,4,PI - CNS

1 11/3/2025 11/7/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

11/3/2025 11/7/2025 IP 71124.04 000728 Occupational Dose Assessment

11/3/2025 11/7/2025 IP 71151 000746 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - CNS

1 3/30/2026 4/3/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing

4/20/2026 4/24/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing IV Fire Protection Inspection - CNS

V EP Exercise & PI Inspection (2026) - CNS

1 5/18/2026 5/22/2026 IP 71114.01 000716 Exercise Evaluation

5/18/2026 5/22/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes

5/18/2026 5/22/2026 IP 71151 001397 Performance Indicator Verification CNS 2025 INITIAL EXAM

1 4/26/2026 5/2/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

6/7/2026 6/13/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

4/13/2026 5/1/2026 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)