IR 05000336/2024011
ML24087A195 | |
Person / Time | |
---|---|
Site: | Millstone ![]() |
Issue date: | 04/01/2024 |
From: | Mel Gray NRC/RGN-I/DORS |
To: | Carr E Dominion Energy |
References | |
IR 2024011 | |
Download: ML24087A195 (1) | |
Text
April 1, 2024
SUBJECT:
MILLSTONE POWER STATION, UNITS 2 AND 3 - COMPREHENSIVE ENGINEERING TEAM INSPECTION - INSPECTION REPORT 05000336/2024011 AND 05000423/2024011
Dear Eric Carr:
On March 14, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Millstone Power Station, Units 2 and 3 and discussed the results of this inspection with James Petty, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety
Docket Nos. 05000336 and 05000423 License Nos. DPR-65 and NPF-49
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000336 and 05000423
License Numbers:
Report Numbers:
05000336/2024011 and 05000423/2024011
Enterprise Identifier: I-2024-011-0011
Licensee:
Dominion Energy, Inc.
Facility:
Millstone Power Station, Units 2 and 3
Location:
Waterford, CT
Inspection Dates:
February 26, 2024 to March 14, 2024
Inspectors:
J. Brand, Senior Reactor Inspector
P. Cataldo, Senior Reactor Inspector
J. Kulp, Senior Reactor Inspector
K. Mangan, Senior Reactor Inspector
E. Miller, Resident Inspector
B. Pinson, Senior Reactor Inspector
J. Schoppy, Senior Reactor Inspector
A. Turilin, Reactor Inspector
Approved By:
Mel Gray, Chief
Engineering Branch 1
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection at Millstone Power Station, Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21M - Comprehensive Engineering Team Inspection
The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Structures, Systems, and Components (SSCs) (IP Section 03.01)===
For each component sample listed below, the team reviewed licensing and design basis documents and a sampling of applicable operator actions, periodic testing results, corrective action program documents, internal and external operating experience, preventive and corrective maintenance work orders, modifications, and aging management programs.
Additionally, the team performed walkdowns of the component or procedure and conducted interviews with licensee personnel.
The team used the attributes contained in IP 71111.21M, Appendix A, Component Review Attributes, such as those listed below as guidance. Specifically, the team evaluated these attributes in the course of applying 71111.21M, Appendix B, Component Design Review Considerations and 71111.21M, Appendix C, Component Walkdown Considerations.
(1)2B Emergency Diesel Generator and associated 1E 4kV Switchgear
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Component installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- (2) Risk significant operator action - Establish High Pressure Recirculation during response to Small/Medium Loss of Coolant Accident (S/MLOCA) at Unit 3
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Component installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
(3)2B Emergency Diesel Generator Service Water Air Operated Valves (2-SW-231B and 2-SW-89B)
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Component installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- (4) Station Blackout Diesel Generator
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Component installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- (5) Risk significant operator action - Unit 2 Station Blackout Response
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Component installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- (6) Unit 2 "C" Service Water Pump (2SW-P5C)
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
- (7) Unit 3 "C" Containment Recirculation Spray Pump (3RSS*P1C)
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Component installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- (8) Unit 3 "B" Containment Recirculation Cooler (3RSS*E1B)
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Component installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- (9) Unit 3 Recirculation Spray to Safety Injection Suction Isolation Valve (3SIL*MV8804B)
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Component installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
(10)4.16KV Emergency Bus 34D and Switchgear (3ENS*SWG-B(-P))
- Electrical power will be available and unimpeded during accident/event conditions.
- Electricity including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Component installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
Modifications (IP Section 03.02) (5 Samples)
- (1) MP-DC-000-MP2-20-01157, MP2 Service Water Pump Differential Pressure Switch Change M2PDC-6475 6481 AND 6488
- (2) MP-DC-000-MP2-23-01029, Replace the Low Pressure Safety Injection (LPSI) Valve M22-SI-635 Motor M22-SI-635M
- (3) MP-DC-000-MP3-18-01082, Reserve Station Service Transformer Replacements
- (4) MP-DC-000-MP2-21-01162, MP2 Service Water Strainer High DP Alarm Update - PDC-6475, PDC-6481, AND PDC-6488
- (5) MP-DC-000-MP3-20-01126, Re-Gear MOVS 3SWP*MOV54B & D to Increase the Margin of these Valves
10 CFR 50.59 Evaluations/Screening (IP Section 03.03) (16 Samples)
- (1) MP-DC-000-MP3-17-00157, Unit 3 Open Phase Condition Detection System Protection Phase (Evaluation)
- (2) MP-DC-000-MP3-20-01102, MP3 Main Generator Stator Cooling System Turbine Trip Single Point Vulnerabilities (SPV) Removal (Evaluation)
- (3) MP-DC-000-MP3-20-01121, MP3 Measurement Uncertainty Recapture (MUR) - Main Generator Protection and Instrument Transformer Secondary Component Interface (Evaluation)
- (4) MP-DC-000-MP3-21-01113, Replace Unit 3 Reactor Coolant Pump A Seal with an Upgraded Flowserve NX Seal (Evaluation)
- (5) MP-DC-000-MP2-22-01135, Temporary Capacity Downgrade of the Unit 2 Spent Fuel Pool Cask Crane (M2H9) (Evaluation)
- (6) MP-ETE-000-ETE-NAF-2021-0128, Implementation of The Analytical Bases for Application of PAD5, FSLOCA, and Boration Update at Millstone Unit 3 (Evaluation)
- (7) MP-ETE-000-ETE-NAF-2023-0055, Implementation of the Updated Rod Ejection Dose Consequences Analysis Addenda (Evaluation)
- (8) MP-ETE-000-ETE-MP-2021-1036 (50.59 AP 50.59 SC), Unit 3 Battery 1, 2, 5 and 6 Capacity Documentation (Screen)
- (9) MP-ETE-000-ETE-MP-2023-1024 (50.59 AP 50.59 SC), MPS3 Safety Injection Accumulator Tank Minimum Service Temperature Rerate (Screen)
- (10) MP-PROC-MP-PT 31458G (50.59 AP), MP3 Emergency Diesel Generator B Protective Relay Trip Test (Screen)
- (11) MP-PROC-OPS-SP 3604A.5-034 (50.59 AP), Supplemental Position Verification for 3CHS*MV8109A, 3CHS8MV8109B, 3CHS*MV8109C, AND 3CHS*MV8109D Reactor Coolant Pump (RCP) Seal Supply Isolations (Screen)
- (12) MP-ETE-000-ETE-MP-2021-1131 (50.59 AP 50.59 SC), Water Level Receding Time During a Design Basis Flood (Screen)
- (13) MP-ETE-000-ETE-MP-2022-1087 (50.59 AP 50.59 SC), Evaluation of B Fire Water Storage Tank for Continued Functionality (Screen)
- (14) MP-ETE-000-ETE-MP-2023-1051 (50.59 AP), Appendix R Compliance Report Change from Specification to Report Document Type (Screen)
- (15) MP-DC-000-MP3-21-01113 (50.59 AP 50.59SC), Replace Unit 3 Reactor Coolant Pump A Seal with an Upgraded Flowserve NX Seal
- (16) MP-DC-000-MP3-18-01082 (50.59 SC 50.59 EV), Reserve Station Service Transformer Replacements
Operating Experience (IP Section 03.04) (3 Samples)
- (1) IN 19-01, Inadequate Evaluation of Temp Alterations
- (2) IN 20-04, Operating Experience Related to Failure of Buried Fire Protection Main Yard Piping
- (3) OPESS 2007-002, Analysis of Flooding Vulnerabilities
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On March 14, 2024, the inspectors presented the comprehensive engineering team inspection results to James Petty, Plant Manager, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or Date
71111.21M Calculations
2-001
MP2 SW Model and Design Basis Analysis
Revision 2
2-001
MP2 SW Model and Design Basis Analysis,
Addendum F
Revision 2
2-001
MP2 SW Model and Design Basis Analysis
Revision 0
21-ENG-
04521L2
PDC-6475, PDC-6481 and PDC-6488 Differential
Pressure Switch Setpoints
Revision 0
89-094-01074M3
MP3 Target Torque Calculation for 3SWP*MOV54A,
3SWP*MOV54B, 3SWP*MOV54C, 3SWP*MOV54D
Revision 8
2-079
NPSH Requirements and NPSH Available for MP2
SWS Pumps
Revision 1
2-079
NPSH Requirements and NPSH Available for MP2
SWS Pumps, Addendum A
Revision 1
97-ENG-
01912E2
4.16kV Switchgear Relay Settings
Revision 0
98-ENG-
2697M2
Service Water Pumps Acceptance Curve
Revision 1
CAL-96931-ME-
390
Temporary Main Hoist Wire Rope Substitution
Revision 0
ENG-03-ENG-
04035M2
MP2 Service Water System Design Basis Summary
Calculation
Revision
M3ASTREA-
04054R3
MP3 Rod Ejection Accident Doses Using AST
Revision 1
MP-CALC-ENG-
97-SBO-
2078M2
MP2 - Loss of Ventilation during SBO
Revision 01
P(R)-1115
MP3 Containment Recirculation Spray Pump Head
Calculation
Revision 0
PA-079-126-
01027E2
MP2 EDG Loading Calculation
Revision 3
RSS-ES-03705-
US(B)-359
Recirculation Spray Pump Performance
Revision 0
S-04225S3
MP3 Power Uprate Maximum Sump Water
Temperature Analysis for Recirculation Spray System
(RSS) Without Debris Transport, Addendum 5
Revision 0
US(B)-294
Revision 6
US(B)-361
MP3 Containment Recirculation System (RSS) and
Safety Injection System Hydraulic Analysis,
Addendum D
Revision 0
Corrective Action
Documents
0582302
1001478
1055547
1096359
1096885
1098849
1135980
1137806
1141604
1145954
1146036
1167768
1171142
1173666
1174770
1179887
1180467
202046
207655
22964
24447
24709
24886
25213
25851
231080
231465
233146
233537
235617
237781
245888
246105
246811
249454
253302
2565
537301
Corrective Action
Documents
Resulting from
Inspection
251835
251857
251866
251888
251918
251933
251939
251945
251956
252066
252084
252126
252133
252147
252149
252162
252188
252358
252393
252395
252408
252455
252458
252734
252963
253008
253372
253443
253473
253502
253503
253899
Drawings
203-26008
Piping and Instrumentation Diagram Service Water,
Sheet 2
Revision 123
203-29016
V2605-40 Vertical Single Stage Service Water Pump
General Arrangement, Sheet 3
Revision 4
205-25003
License Renewal Diagram - Operating and Hydraulic
Analysis Schematic
Revision 7
212-26912
Piping & Instrumentation Diagram Low Pressure
Safety Injection/Containment Recirculation, Sheet 3
Revision 38
Engineering
Changes
MP2-22-01135
Temporary Capacity Downgrade of the Unit 2 Spent
Fuel Pool Cask Crane (M2H9)
Revision 2
Engineering
Evaluations
ETE-MP-2020-
1078
Evaluation of Increased Strainer Differential Pressure
on MP2 Service Water Functionality
Revision 0
ETE-MP-2020-
1139
Evaluation of Elevated Service Water Strainer
Differential Pressure and Basis for ARP 2590E-
28/029/030
Revision 0
ISFSI-04023MG
ISFSI Evaluation of Underground Utilities for Haul
Path
Revision 1
Millstone Unit 2 Station Blackout Safe Shutdown
Scenario Document
Revision 2
Miscellaneous
203-047-001
Installation, Operation and Maintenance of Service
Water Dual Backwash Strainers
Revision 14
Design Basis Summary for the 4160V AC Electrical
Distribution System
Revision 1
Design Bases Summary for the Emergency Core
Cooling System
Revision 0
BKG EOP35 ES
1.3
Emergency Operating Procedure Background
Document
Revision 020-00
C OP 200.18 -
Attach 3
Unit 3 SFRM Operator Credited Actions
Dated 05/15/2020
DBS-2326A
Service Water System
Revision 1
MP-PROC-OPS-
Low Pressure Safety Injection Valve Operability Test -
Train A
Revision 23
OP 2612-005
Service Water POV Remote Position Indication IST
Facility 2 and Supplemental Position Verification
Indication
Dated 12/19/2022
and 04/22/2023
PIR1119548
IN1901 - Inadequate Evaluation of Temporary
Alterations
Dated 06/19/2019
SP 2613H
Facility 2 ESF Integrated Test
Dated 04/08/2023
and 01/17/2024
SP 2670
Diesel Generator 'B' HX D/P Determination
Dated 01/17/2024
NDE Reports
09012022-003
Millstone Buried Fire Protection Piping Exam - Final
Report
Dated 09/01/2022
Procedures
AOP 2560
Storms, High Winds and High Tides
Revision 25
AOP 2565
Loss of Service Water
Revision 7
AOP 3569
Severe Weather Conditions
Revision 27
AOP 3573
Radiation Monitor Alarm Response
Revision 29
COP 200.18
Time Critical Action Validation and Verification
Revision 15
EOP 2530
Station Blackout
Revision 019
EOP 2541,
Appendix 14
Supplemental Cooling on Loss of Ventilation
Revision 01
EOP 35 E-1
Loss of Reactor or Secondary Coolant
Revision 27
Transfer To Cold Leg Recirculation
Revision 20
IP-ENG-001
Standard Design Process
Revision 3
MP-PROC-000-
IP-ENG-001
Standard Design Process
Revision 3
MP-PROC-OPS-
ARP 2509E-028
SW Pump A Stnr Trouble
Revision 3
MP-PROC-OPS-
ARP 2509E-029
SW Pump B Stnr Trouble
Revision 3
MP-PROC-OPS-
ARP 2509E-030
SW Pump C Stnr Trouble
Revision 3
OP 2326A
Service Water System
Revision 36
OP 2348A
6,900 and 4,160 Volt Breaker Operation
Revision 7
SP 3606.3
Containment Recirculation Pump 3RSS*P1C
Operational Test
Revision 23
SP 3670.1
Plant Equipment Rounds - Outside
Revision 40
Work Orders
53102430529
53102723522
53102746810
53102820820
53102860677
53103020546
53103071138
53103071402
53103071489
53103071765
53103087024
53103104701
53103106509
203238189
203269001
203269015
203269018
203269084
203269097
203269292
203269326
203269594
203293720
203315731
203319105
203320123
203343325
203343993
203343995
203344518
203357232
203357375
203357417
203369082
203376673
203381437
203387529
203406548
53M20603055
53M20200742
53M20706092
53M20707126
53M20707127
53102621482
53102625294
203245858
203259639
M3 05 15754
53102528561
203244976
203245299
53M30712094
MP-WO-000-
53102344586
MP-WO-000-
53M30509462