ML062140118

From kanterella
Jump to navigation Jump to search
IR 05000254-06-002 (Drs), 05000265-06-002 (Drs); 04/24/06 - 05/12/06; Quad Cities Nuclear Power Station (Qcnps), Units 1 and 2; Triennial Fire Protection Baseline Inspection
ML062140118
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 07/31/2006
From: Julio Lara
Engineering Branch 3
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
IR-06-002
Download: ML062140118 (42)


See also: IR 05000254/2006002

Text

July 31, 2006

Mr. Christopher M. Crane

President and Chief Nuclear Officer

Exelon Nuclear

Exelon Generation Company, LLC

Quad Cities Nuclear Power Station

4300 Winfield Road

Warrenville, IL 60555

SUBJECT: QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2

NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION

INSPECTION REPORT 05000254/2006002(DRS); 05000265/2006002(DRS)

Dear Mr. Crane:

On May 12, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed a triennial fire

protection baseline inspection at your Quad Cities Nuclear Power Station, Units 1 and 2. The

enclosed inspection report documents the inspection results, which were discussed at the end

of the on-site activities on May 12, 2006, and during a re-exit meeting held by telephone at the

conclusion of the inspection on June 29, 2006, with Mr. T. Tulon and other members of your

staff.

The inspection examined activities conducted under your license, as they relate to safety and to

compliance with the Commissions rules and regulations, and with the conditions of your

license. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel.

Based on the results of this inspection, six NRC-identified findings of very low safety

significance, all of which involved violations of NRC requirements were identified. However,

because these violations were of very low safety significance, and because the findings were

entered into the licensee's corrective action program, the NRC is treating these findings as

Non-Cited Violations in accordance with Section VI.A.1 of the NRCs Enforcement Policy.

Additionally, two licensee identified violations are listed in Section 4OA7 of this report.

If you contest the subject or severity of a Non-Cited Violation, you should provide a response

within 30 days of the date of this inspection report, with the basis for your denial, to the U. S.

Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC

20555-0001, with a copy to the Regional Administrator, U. S. Nuclear Regulatory Commission -

Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of

Enforcement, U. S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the

Resident Inspector Office at the Quad Cities Nuclear Power Station facility.

C. Crane -2-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter,

its enclosure, and your response (if any), will be available electronically for public inspection in

the NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's document system (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Julio F. Lara, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos. 50-254; 50-265

License Nos. DPR-29; DPR-30

Enclosure: Inspection Report 05000254/2006002(DRS); 05000265/2006002(DRS)

w/Attachment: Supplemental Information

cc w/encl: Site Vice President - Quad Cities Nuclear Power Station

Plant Manager - Quad Cities Nuclear Power Station

Regulatory Assurance Manager - Quad Cities Nuclear Power Station

Chief Operating Officer

Senior Vice President - Nuclear Services

Senior Vice President - Mid-West Regional

Operating Group

Vice President - Mid-West Operations Support

Vice President - Licensing and Regulatory Affairs

Director Licensing - Mid-West Regional

Operating Group

Manager Licensing - Dresden and Quad Cities

Senior Counsel, Nuclear, Mid-West Regional

Operating Group

Document Control Desk - Licensing

Vice President - Law and Regulatory Affairs

Mid American Energy Company

Assistant Attorney General

Illinois Emergency Management Agency

State Liaison Officer, State of Illinois

State Liaison Officer, State of Iowa

Chairman, Illinois Commerce Commission

D. Tubbs, Manager of Nuclear

MidAmerican Energy Company

C. Crane -2-

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

Julio F. Lara, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos. 50-254; 50-265

License Nos. DPR-29; DPR-30

Enclosure: Inspection Report 05000254/2006002(DRS); 05000265/2006002(DRS)

w/Attachment: Supplemental Information

cc w/encl: Site Vice President - Quad Cities Nuclear Power Station

Plant Manager - Quad Cities Nuclear Power Station

Regulatory Assurance Manager - Quad Cities Nuclear Power Station

Chief Operating Officer

Senior Vice President - Nuclear Services

Senior Vice President - Mid-West Regional

Operating Group

Vice President - Mid-West Operations Support

Vice President - Licensing and Regulatory Affairs

Director Licensing - Mid-West Regional

Operating Group

Manager Licensing - Dresden and Quad Cities

Senior Counsel, Nuclear, Mid-West Regional

Operating Group

Document Control Desk - Licensing

Vice President - Law and Regulatory Affairs

Mid American Energy Company

Assistant Attorney General

Illinois Emergency Management Agency

State Liaison Officer, State of Illinois

State Liaison Officer, State of Iowa

Chairman, Illinois Commerce Commission

D. Tubbs, Manager of Nuclear

MidAmerican Energy Company

DOCUMENT NAME:E:\Filenet\ML062140118.wpd

G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII RIII RIII RIII

NAME GHausman: ls MRing JLara

DATE 07/28/06 07/27/06 07/31/06

OFFICIAL RECORD COPY

C. Crane -3-

ADAMS Distribution:

DXC1

MXB

JXH11

RidsNrrDirsIrib

GEG

KGO

KKB

CAA1

LSL

C. Pederson, DRS

DRPIII

DRSIII

PLB1

JRK1

ROPreports@nrc.gov

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket Nos: 50-254; 50-265

License Nos: DPR-29; DPR-30

Report No: 05000254/2006002(DRS); 05000265/2006002(DRS)

Licensee: Exelon Generation Company, LLC

Facility: Quad Cities Nuclear Power Station (QCNPS), Units 1 and 2

Location: Cordova, IL

Dates: April 24, 2006 through May 12, 2006

Inspectors: G. Hausman, Senior Reactor Inspector, Lead

A. Dahbur, Reactor Inspector

D. Schrum, Reactor Inspector

Approved by: Julio F. Lara, Chief

Engineering Branch 3

Division of Reactor Safety

Enclosure

TABLE OF CONTENTS

SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1. REACTOR SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

1R05 Fire Protection (71111.05T) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

.1 Systems Required to Achieve and Maintain Post-Fire SSD . . . . . . . 4

a. Inspection Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

b. Findings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

b.1 Safe Shutdown Makeup Pump . . . . . . . . . . . . . . . . . . . . 5

b.2 RHR Service Water Cross-tie . . . . . . . . . . . . . . . . . . . . . 8

.2 Fire Protection of SSD Capability . . . . . . . . . . . . . . . . . . . . . . . . . . 11

.3 Post-Fire SSD Circuit Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

.4 Alternative SSD Capability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

.5 Operational Implementation of SSD Capability . . . . . . . . . . . . . . . 13

a. Inspection Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

b. Findings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

b.1 Fuse Repair . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

.6 Communications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

.7 Emergency Lighting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

.8 Cold Shutdown Repairs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

.9 Fire Barriers and Fire Zone/Room Penetration Seals . . . . . . . . . . . 16

.10 Fire Protection Systems, Features, and Equipment . . . . . . . . . . . . 18

a. Inspection Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

b. Findings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

b.1 Fire Pre-Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

b.2 Standpipes with Hose Connections . . . . . . . . . . . . . . . 20

b.3 Class A Fire Extinguishers . . . . . . . . . . . . . . . . . . . . . . 22

.11 Compensatory Measures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

4. OTHER ACTIVITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

4OA5 Other Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

4OA6 Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

4OA7 Licensee-Identified Violations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

.1 Appendix R SSD Battery Loads . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

.2 Post-Fire Operator Manual Actions . . . . . . . . . . . . . . . . . . . . . . . . 28

SUPPLEMENTAL INFORMATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

KEY POINTS OF CONTACT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED . . . . . . . . . . . . . . . . . . . . . A-2

LIST OF DOCUMENTS REVIEWED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-3

LIST OF ACRONYMS USED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-7

i Enclosure

SUMMARY OF FINDINGS

IR 05000254/2006002(DRS), 05000265/2006002(DRS); 04/24/06 - 05/12/06; Quad Cities

Nuclear Power Station (QCNPS), Units 1 and 2; Triennial Fire Protection Baseline Inspection.

This report covers an announced triennial fire protection baseline inspection. The inspection

was conducted by Region III inspectors. Based on the results of this inspection, six Green

findings associated with six non-cited violations were identified. The significance of most

findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual

Chapter (IMC) 0609, Significance Determination Process (SDP). Findings for which the SDP

does not apply may be Green or be assigned a severity level after NRC management review.

The NRCs program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.

A. Inspector-Identified and Self-Revealed Findings

Cornerstone: Mitigating Systems

Appendix R,Section III.G.2, having very low safety significance (Green) involving the

licensees failure to ensure, in the event of a severe fire, that one redundant train of

systems necessary to achieve and maintain hot shutdown conditions was free of fire

damage. Specifically, the licensee failed to ensure, in the event of a fire in any of the

III.G.2 fire areas, that one redundant train of reactor coolant inventory makeup water

remained free of fire damage. Instead the licensee credited the dedicated safe

shutdown makeup pump (SSMP) for reactor coolant inventory makeup water in the

III.G.2 fire areas. This finding was entered into the licensees corrective action program

as Issue Report (IR) 00502702, NRC Inspection Finding Concerning App R Redundant

Trains, dated June 22, 2006. The licensee plan to review the options for resolving this

issue, and pursue the appropriate resolution.

The finding was more than minor because this failure could have affected the mitigating

systems cornerstone objective and safe shutdown (SSD). Specifically, the licensee

failed to ensure one redundant train of reactor coolant inventory makeup water was

available, and instead relied on an alternate shutdown system without an analyses and

procedures that demonstrated full compliance with all of the requirements of 10 CFR

Part 50, Appendix R,Section III.G.3, and Section III.L, or requesting prior NRC

approval. The finding was not suitable for SDP evaluation, but has been reviewed by

NRC management and was determined to be a finding of very low safety significance.

(Section 1R05.1b.1)

having very low safety significance (Green) involving the licensee failure to ensure, in

the event of a severe fire, that one redundant train of systems necessary to achieve and

maintain hot shutdown conditions was free of fire damage. Specifically, the licensee

failed to ensure, in the event of a fire in Fire Areas TB-III, 13-1 or 24-1, that one

redundant train of residual heat removal service water (RHRSW) remained free of fire

damage. Instead the opposite units RHRSW train was cross-tied (i.e., an alternative

SSD activity) and credited for torus cooling during hot shutdown for a III.G.2 fire area.

1 Enclosure

In addition, the licensee failed to have an analyses and procedures that demonstrated

full compliance with all of the requirements of 10 CFR Part 50, Appendix R,

Section III.G.3, and Section III.L. This finding was entered into the licensees corrective

action program as IR 00502702, NRC Inspection Finding Concerning Appendix R

Redundant Trains, dated June 22, 2006. The licensee plan to review the options for

resolving this issue, and pursue the appropriate resolution.

The finding was more than minor because the failure to ensure one redundant train of

RHRSW was available for torus cooling for hot shutdown could have affected the

mitigating systems cornerstone objective and SSD. The finding was not suitable for

SDP evaluation, but has been reviewed by NRC management and was determined to be

a finding of very low safety significance. (Section 1R05.1b.2)

Instruction, Procedures, and Drawings, having very low safety significance (Green)

involving inadequate procedure steps. Specifically, The licensee failed to provide

adequate procedure steps in-accordance with Appendix R requirements for hot

shutdown and allowed the replacement (i.e., a repair) of breaker fuses prior to attaining

hot shutdown. Specifically, QCNPSs Procedure QOP 6500-10 Local Control of 4160

and 480 Volt Motor Operated Circuit Breaker, Revision 8, included a hot shutdown

repair to replace any circuit breakers control fuses that were believed to be blown due

to a fire-induced failure. This fuse replacement constituted a hot shutdown repair which

was not allowed by 10 CFR Part 50, Appendix R. Once identified, the licensee revised

procedure QOP 6500-10 and added steps to manually close breakers using a local

pushbutton. This finding was entered into the licensees corrective action program as

IR 00485702, Required SSDA Actions Not Contained in QCARP 0030-01, dated

May 2, 2006. The licensee revised procedure QOP 6500-10.

The finding was more than minor because the failure to include adequate procedure

steps could have affected the mitigating systems cornerstone objective and SSD.

Performing the repair activities could have delayed and/or complicated shutdown of the

plant. The finding was of very low safety significance because the licensee could have

manually charged the breakers spring and closed the breaker using the pushbutton

located at the breaker. (Section 1R05.5b.1)

  • Green. The inspectors identified a NCV of QCNPSs license condition for fire protection,

having very low safety significance (Green) involving the lack of complete and accurate

information in the QCNPSs fire pre-plans for various plant fire areas. Specifically, the

licensee failed to include important information in the fire pre-plans, such as hydrogen

and electrical hazards, to assist the fire brigade to fight a fire within those plant fire

areas. This finding was entered into the licensees corrective action program as

IR 00489175, Quality of Fire Preplans (2006 FP Triennial), dated May 11, 2006.

The finding was more than minor because the failure to provide adequate warnings and

guidance related to hydrogen and electrical hazards in the fire pre-plans could have

adversely impacted the fire brigades ability to fight a fire, thereby, increasing the

likelihood of a fire which would challenge SSD and could have affected the mitigating

systems cornerstone objective. The inspectors determined that this issue also affected

the cross-cutting area of Problem Identification and Resolution because the licensee

2 Enclosure

failed to identify the presence of hydrogen and oxygen hazards in Fire Areas RB-7 and

RB-19 during their review as part of the fire pre-plan improvement effort conducted as a

result of previously identified corrective action (IR 00221528). The finding was of very

low safety significance because of the extensive training provided to the fire brigade

members to deal with unexpected contingencies. (Section 1R05.10b.1)

  • Green. The inspectors identified a NCV of QCNPSs license condition for fire protection,

having very low safety significance (Green) involving adequacy of water pressure and

flow rate at standpipes with hose connections. Specifically, the licensee failed to

provide calculations to ensure that an adequate water pressure and flow rate were

available to meet the QCNPSs FPP requirements. Once identified, the licensee

entered the finding into their corrective action program as IR 00489160, Justification of

Fire Hose Pressure and Flow Meeting NFPA, dated May 11, 2006, and planned to

perform calculations to verify water flow at all affected standpipes with hose

connections.

The finding was more than minor because the failure to provide an adequate water

pressure and flow rate at standpipes with hose connections could hamper the fire

brigades ability to fight a fire, thereby, increasing the likelihood of a fire which would

challenge SSD and could have affected the mitigating systems cornerstone objective.

The finding was of very low safety significance because other defense-in-depth fire

protection elements remained unaffected in all fire areas. (Section 1R05.10b.2)

  • Green. The inspectors identified a NCV of QCNPSs license condition for fire protection,

having very low safety significance (Green) involving adequacy of number of Class A

fire extinguishers. Specifically, the licensee failed to have an adequate number of

Class A fire extinguishers available where significant fire hazards existed to meet the

NFPA 10 Code requirements to suppress and/or extinguish Class A fire hazards. This

finding was entered into the licensees corrective action program as IR 00489426,

Class A Fire Extinguisher Placement Improvements, dated May 12, 2006. The

licensee planned to evaluate putting more Class A fire extinguishers into the plant.

The finding was more than minor because failure to have an adequate number of

Class A fire extinguishers available could potentially escalate a small fire into a larger

fire since only standpipes with hose connections were available and their use required a

trained fire brigade to extinguish the fire. As a result, non-fire brigade personnel would

be prevented from moving quickly to suppress and/or extinguish a small fire and the

potential for an escalated fire could have affected the mitigating systems cornerstone

objective. The finding was of very low safety significance because most fire areas and

zones have fire detectors that would alarm in the control room and the fire brigade

would respond to a fire in these areas. In addition, other defense-in-depth fire

protection elements remained unaffected and a fire in these areas would not result in a

loss of dedicated SSD systems. (Section 1R05.10b.3)

B. Licensee-Identified Violations

Two violations of very low safety significance, which were identified by the licensee,

have been reviewed by the inspectors. Corrective actions taken or planned by the

licensee have been entered into the licensees corrective action program. These

violations and the licensees corrective action tracking numbers are listed in

Section 4OA7 of this report.

3 Enclosure

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Initiating Events and Mitigating Systems

1R05 Fire Protection (71111.05T)

The purpose of this inspection was to review the QCNPSs Fire Protection Program

(FPP) for selected risk-significant fire areas. Emphasis was placed on determining that

the post-fire safe shutdown (SSD) capability and the fire protection (FP) features were

maintained free of fire damage to ensure that at least one post-fire SSD success path

was available. The inspection was performed in accordance with the Nuclear

Regulatory Commissions (NRCs) regulatory oversight process using a risk-informed

approach for selecting the areas and attributes to be inspected. The inspectors with

assistance from a senior reactor analyst used the QCNPSs Individual Plant

Examination for External Events (IPEEE) to choose several risk-significant areas for

detailed inspection and review. The inspectors review of the following fire areas and/or

zones represented completion of four samples for the triennial FP inspection:

Fire Area Fire Zone Description

TB-III 8.2.6.A Unit 1 Turbine Building Ground Floor (South)

TB-III 8.2.7.A Unit 1 Turbine Building Mezzanine Floor (South)

13-1 8.2.8.B Unit 1 4-kV Bus 13-1 Switchgear Area (North)

24-1 8.2.8.C Unit 2 4-kV Bus 24-1 Switchgear Area (South)

For each of the selected fire areas and/or fire zones, the inspectors focused on the fire

protection features, the systems and equipment necessary to achieve and maintain safe

shutdown conditions, determination of licensee commitments, changes to the FPP, and

evaluated the licensees FPP against applicable NRC requirements.

.1 Systems Required to Achieve and Maintain Post-Fire SSD

Title 10 of the Code of Federal Regulations (CFR), Part 50, Appendix R,Section III.G.1,

required the licensee to provide FP features that were capable of limiting fire damage to

structures, systems, and components (SSCs) important to SSD. The SSCs that were

necessary to achieve and maintain post-fire SSD were required to be protected by FP

features that were capable of limiting fire damage to the SSCs so that:

  • one train of systems necessary to achieve and maintain hot shutdown conditions

from either the CR or emergency control station(s) was free of fire damage; and

  • systems necessary to achieve and maintain cold shutdown from either the CR or

emergency control station(s) could be repaired within 72-hours.

4 Enclosure

Specific design features for ensuring this capability were specified by 10 CFR Part 50,

Appendix R,Section III.G.2.

a. Inspection Scope

The inspectors reviewed the plant systems required to achieve and maintain post-fire

SSD to determine if the licensee had properly identified the components and systems

necessary to achieve and maintain SSD conditions for each fire zone selected for

review. Specifically, the review was performed to determine the adequacy of the

systems selected for reactivity control, reactor coolant inventory makeup, reactor heat

removal, process monitoring, and support system functions. This review included the

FP Safe Shutdown Analysis (SSA).

The inspectors also reviewed the operators ability to perform the necessary manual

actions for achieving SSD by reviewing procedures, the accessibility of SSD equipment,

and the available time for performing the actions.

The inspectors reviewed the QCNPSs Updated Final Safety Analysis Report (UFSAR)

and the licensees engineering and/or licensing justifications (e.g., NRC guidance

documents, license amendments, technical specifications, safety evaluation

reports (SERs), exemptions, and deviations) to determine the licensing basis.

b. Findings

b.1 Safe Shutdown Makeup Pump

Introduction: The inspectors identified a Non-Cited Violation (NCV) of 10 CFR Part 50,

Appendix R,Section III.G.2, having very low safety significance (Green) involving the

licensees failure to ensure, in the event of a severe fire, that one redundant train of

systems necessary to achieve and maintain hot shutdown conditions was free of fire

damage. Specifically, the licensee failed to ensure, in the event of a fire in any of the

III.G.2 fire areas, that one redundant train of reactor coolant inventory makeup water

remained free of fire damage. Instead, the licensee credited the dedicated safe

shutdown makeup pump (SSMP) for reactor coolant inventory makeup water in these

fire areas without having an analysis that demonstrated full compliance with all of the

requirement of 10 CFR Part 50, Appendix R, Section III.G.3, III.L or requesting prior

NRC approval.

Description: During the inspectors review of the licensees Appendix R analysis for the

selected fire zones, the inspectors identified that contrary to the NRC approved licensing

bases, as discussed in the SER dated December 1981, the licensee was relying upon

the SSMP as a redundant train for the reactor coolant inventory makeup in the event of

a severe fire in III.G.2 fire areas. Specifically, the SER dated December 1981, for the

QCNPS, Section 2.2, Areas Where Alternate Safe Shutdown Capability is Required,

stated . . . for those areas where a fire results in loss of the RCIC system, the licensee

has proposed to provide a new safe shutdown makeup pump as an alternate.

Section 2.3, (Section III.G.2 of Appendix R), stated . . . the licensee also indicated that

all other areas of the plant not required to have an alternate safe shutdown system will

comply with the requirements of Section III.G.2 of Appendix R, unless an exemption

5 Enclosure

request has been approved by the staff. Section 2.4, Alternate Safe Shutdown

System, stated . . . the alternate safe shutdown system required for those areas not

meeting Section III.G.2 or included in the exemption requests consists of a new safe

shutdown makeup pump and its associated support systems and instrumentation.

Section 3.1.2, Reactor Coolant Inventory, stated The RCIC and shutdown makeup

pump initially take suction from the CCST. Additional supply for the RCIC pump is

provided by the suppression pool and for the makeup pump by the service water

system. However, the NRC in April of 1988 revised Section 3.1.2 of this SER and

stated that Backup water supply source for the safe shutdown makeup pump will be

provided by the fire water system instead of the service water system as originally

indicated in the earlier SER Section 3.1.2. The inspectors could not find any other

documents from the NRC to the licensee indicating that the NRC had accepted the use

of the SSMP as a redundant system for Appendix R.

Prior to November 2000, the fire areas which were selected during this triennial FP

inspection, TB-III, 13-1 and 24-1, were classified as alternate shutdown areas because

of the potential fire damage to redundant RCIC system and the use of the alternate

SSMP system. As a result of the FP Optimization Project at QCNPS, in November of

2000, the licensee completed safety evaluation SE-00-098. Part of the objectives of the

optimization project were to reduce the number of the areas that require leaving the

main control room and reduce reliance on 10 CFR Part 50, Appendix R exemptions. In

order to accomplish these objectives, the licensee reclassified several fire areas from

Alternate to Redundant by reclassifying the SSMP from Dedicated to Redundant

per safety evaluation SE-00-098. The reclassification was based primarily on the

functional equivalence between RCIC and SSMP. The licensee concluded that this

change had no adverse impact on SSD and, therefore, did not require prior NRC

approval. The licensee also modified the control for the SSMP system, where injection

could be manually initiated from either the control room or remotely. This was changed

from the initial installation of the pump. After the change, all of the circuitry needed to

operate the SSMP was included in the SSA.

In Generic Letter (GL) 86-10 Implementation of Fire Protection Requirements, the

NRCs response to Question 3.8.3 Redundant Trains/Alternates Shutdown, stated, in

part, if the system is being used to provide its design function, it generally is considered

redundant. If the system is being used in lieu of the preferred system because the

redundant components of the preferred system do not meet the separation criteria of

Section III.G.2, the system is considered an alternate shutdown capability.

The inspectors review of SE-00-098 concluded that the licensees basis for the

reclassification was not appropriate, in that, based on the response to Question 3.8.3 in

GL 86-10, and that the backup water supply source for the SSMP was from the fire

water system, which was not a preferred source for reactor coolant inventory makeup

water, the SSMP met the criteria for an alternate and not a redundant system to RCIC.

The licensee response was that based on General Electric (GE) Nuclear Energy (NE)

document GE-NE-T43-00002-00-03-R01, BWROG [Boiling Water Reactor Owners

Group] Position on the Use of Safety Relief Valves and Low Pressure Systems as

Redundant Safe Shutdown Paths, a system was considered to be redundant when it

is used to provide its design function. The GE-NE document also indicated that based

on the information provided in NRC GL 81-12, the BWROG sees no requirement or

6 Enclosure

basis for limiting the systems that may be used as redundant SSD systems. The

inspectors reviewed the GE documents and could not find any justification in these

documents that considered the use of the SSMP, with the FP system as a backup

source, a redundant system for reactor coolant inventory makeup.

In addition, Subsection 3 of Section III.L Alternative and Dedicated Shutdown

Capability to 10 CFR Part 50 Appendix R required, in part, that the shutdown capability

shall be independent of the specific fire area(s) and shall accommodate postfire

conditions where offsite power is available and where offsite power is not available for

72-hours. Procedures shall be in effect to implement this capability. During the

inspection, the licensee did not have analyses or procedures that satisfied these

requirements. Instead, the licensee depended on offsite power supplied from the

opposite unit equipment. Therefore, the inspectors also concluded that the change

made by SE-00-098 was not appropriate and had adversely affected safe shutdown,

because the licensee did not have the required analyses and procedures. The licensee

entered this finding into the QCNPSs corrective action program as IR 00502702, NRC

Inspection Finding Concerning App R Redundant Trains, dated June 22, 2006. The

licensee plan to review the options for resolving this issue and pursue the appropriate

resolution.

Analysis: The inspectors determined that failure to ensure that one redundant train of

systems necessary to achieve and maintain hot shutdown conditions was free of fire

damage resulted in a performance deficiency warranting a significance evaluation. The

inspectors concluded that the finding was greater than minor in accordance with

IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue Screening, issued

on September 30, 2005. The finding involved the attribute of protection against external

factors (i.e., Fire) and could have affected the mitigating systems cornerstone objective

of ensuring the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences (i.e., core damage). Specifically, the

licensees failure to ensure, in the event of a fire in any of the III.G.2 fire areas, that one

redundant train of reactor coolant inventory makeup water remained free of fire damage

and instead credited the dedicated SSMP without demonstrating compliance with

Appendix R, Sections III.G.3 and III.L, did not provide the adequate level of safety

required per Appendix R to ensure SSD capability.

Since, the SSD path using the SSMP system did not meet the requirement of

Appendix R,Section III.G.2, but the SSD path was approved by the NRC as alternate,

the inspectors determined that the finding was not suitable for SDP evaluation. The

finding was reviewed by NRC management and was determined to be of very low safety

significance (Green).

Enforcement: 10 CFR Part 50.48, Fire Protection, and 10 CFR Part 50, Appendix R,

Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1,

1979, established specific FP features required to satisfy 10 CFR Part 50, Appendix A,

General Design Criterion 3, Fire Protection. Appendix R applies to licensed nuclear

power electric generating stations that were operating prior to January 1, 1979, which

included QCNPS.Section III.G.2 of Appendix R to 10 CFR Part 50 required, in part,

that where cables or the equipment of a redundant train of systems necessary to

achieve and maintain hot shutdown conditions are located within the same fire area

7 Enclosure

outside of primary containment, one of a specified means of ensuring that one of the

redundant trains is free of fire damage shall be provided.Section III.G.3 of Appendix R

to 10 CFR Part 50 required, in part, that alternative of dedicated shutdown capability

should be provided where the protection of systems whose function is required for hot

shutdown does not satisfy the requirement of paragraph III.G.2. Subsection 3 of

Section III.L. Alternative and Dedicated Shutdown Capability to 10 CFR Part 50,

Appendix R required, in part, that the shutdown capability shall be independent of the

specific fire area(s) and shall accommodate postfire conditions where offsite power is

available and where offsite power is not available for 72-hours. Procedures shall be in

effect to implement this capability.

Contrary to the above, in the event of a fire in any of these fire areas (TB-III, 13-1 or

24-1), the licensee failed to ensure that one of the redundant trains of reactor coolant

inventory makeup water remained free of fire damage. Instead, the licensee credited

the use of the dedicated SSMP for reactor coolant inventory makeup without having

analyses and procedures that demonstrated their full compliance with III.G.3 and III.L, or

requesting prior NRC approval. Once identified, the licensee entered the finding into

their corrective action program as IR 00502702, NRC Inspection Finding Concerning

App R Redundant Trains, dated June 22, 2006. Because this violation was of very low

safety significance and it was entered into the licensees corrective action program, this

violation is being treated as a NCV, consistent with Section VI.A.1 of the NRC

Enforcement Policy (NCV 05000254/2006002-01(DRS);05000265/2006002-01(DRS)).

b.2 RHR Service Water Cross-tie

Introduction: The inspectors identified a NCV of 10 CFR Part 50, Appendix R,

Section III.G.2, having very low safety significance (Green) involving the licensees

failure to ensure, in the event of a severe fire, that one redundant train of systems

necessary to achieve and maintain hot shutdown conditions was free of fire damage.

Specifically, the licensee failed to ensure, in the event of a fire in any of these Fire

Areas TB-III, 13-1 or 24-1 (III.G.2 Fire Area), that one redundant train of the residual

heat removal service water (RHRSW) system remained free of fire damage. Instead the

licensee credited the cross-tie of the RHRSW train from the opposite unit for torus

cooling during hot shutdown.

Description: The RHRSW system at QCNPS for each unit, consisted of two

independent and redundant subsystems (A Loop and B Loop). Each subsystem is

made of a header, two pumps, a suction source, valves, piping heat exchanger and

associated instrumentation. Each loop provided cooling water flow to the respective

loop of the RHR heat exchangers in the torus cooling and shutdown modes. The A

subsystems for Unit 1 and Unit 2 could be connected by a normally locked, isolated

cross-tie line. Similarly, the B subsystems could be connected by another normally

isolated cross-tie line. These lines could be used to supply RHRSW from Unit 1 to Unit

2 and vice-versa when required.

The inspectors reviewed QCNPSs SSA which indicated that, in the event of a severe

fire in Fire Area 13-1, a redundant shutdown method and/or systems would be utilized

for SSD of Unit 1. The analysis also indicated that, in the event of a fire in Fire

Area 13-1, Unit 1 4KV Switchgear 13-1 (Division I) and/or both divisions of 480 V

8 Enclosure

Switchgear (18 and 19) would be exposed. Division II of the Unit 1 RHR system would

be available for torus cooling and alternate shutdown cooling. However, the Unit 1

Division II RHRSW system was unavailable for a fire in Fire Area 13-1. This was due to

the 480V power feeds for the pump cubicle coolers being routed in this area. Therefore,

the analysis stated that Unit 1 RHRSW pumps may not be available for decay heat

removal. However, Unit 1 Division II RHRSW can be supplied by Unit 2 RHRSW Pump

via a Division II mechanical cross-tie. The analysis also verified that cubical coolers for

Unit 2, Division II RHRSW pumps were free of fire damage. The inspectors also

identified a similar issue in the event of a fire in Unit 2 Fire Area 24-1, in that the

shutdown method for this area used the Unit 1 RHRSW to shutdown Unit 2.

In addition, the inspectors noticed that the analysis also showed that, in the event of a

severe fire in Fire Area TB-III, Division I of the RHR system would be available for torus

cooling and alternate shutdown cooling. However, the AC power for RHR system would

have been provided from offsite power via the opposite unit (Unit 2 Bus 23) and cross-

tied to Unit 1 Bus 13-1. Similarly, the analysis also indicated that the Unit 1 Division I

RHRSW system may not be available for a fire in TB-III. This was due to the 4KV

power feeds for the pumps being routed in TB-III. Therefore, the analysis indicated that

Unit 1 RHRSW pumps may not be available for decay heat removal. However, the

analysis credited Unit 2 Division I RHRSW via a Division I mechanical crosstie valve.

Prior to November of 2000, Fire Areas TB-III, 13-1 and 24-1 were classified as an

alternate shutdown areas. As a result of the FP Optimization Project at QCNPS, the

licensee reclassified these fire areas from Alternate to Redundant when they

reclassifying the SSMP from Dedicated to Redundant per Safety Evaluation

SE-00-098. However, the licensee failed to evaluate whether RHRSW cross-tie from

the opposite unit met the requirement of 10 CFR Part 50, Appendix R, Section III.G.2.

10 CFR Part 50.48 Fire Protection required, in part, that each operating nuclear power

plant must have a fire protection plan that satisfies Criterion 3 of appendix A of 10 CFR Part 50. 10 CFR Part 50, Appendix R establishes fire protection features required to

satisfy Criterion 3 of appendix A with respect to certain generic issues for nuclear power

plants licensed to operate before January 1, 1979. 10 CFR Part 50, Appendix R, also

required, in part, that a fire protection program be established at each nuclear power

plant.Section III.G.2 of Appendix R stated, in part, that where cables or equipment that

could prevent operation or cause maloperation due to hot shorts, open circuits, or shorts

to ground, of redundant trains of systems necessary to achieve and maintain hot

shutdown conditions are located within the same fire area outside of primary

containment, one of three means of ensuring that one of the redundant trains is free of

fire damage shall be provided. The inspectors determined that the licensees shutdown

method in the event of a fire in any of these Fire Areas TB-III, 13-1 or 24-1, did not meet

the requirement of 10 CFR Part 50, Appendix R, Section III.G.2. Specifically, the

licensees shutdown methods in Fire Areas TB-III, 13-1 and 24-1 which used the

RHRSW system from the opposite unit instead of ensuring one of the redundant trains

of RHRSW from the respective unit with fire Unit 1 RHRSW was available. In addition,

Subsection 3 of Section III.L Alternative and Dedicated Shutdown Capability to 10 CFR Part 50, Appendix R required, in part, that the shutdown capability shall be independent

of the specific fire area(s) and shall accommodate postfire conditions where offsite

power is available and where offsite power is not available for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Procedures

9 Enclosure

shall be in effect to implement this capability. During the inspection, the licensee did

not have analyses or procedures that satisfied these requirements for Appendix R III.L.

The licensee justification was that Fire Areas TB-III,13-1 and 24-1 were alternate

shutdown areas based on the reliance on SSMP and not due to the RHRSW cross-tie.

The licensee also indicated that this method for SSD, which credited the RHRSW

cross-tie, was previously communicated to the NRC staff by letter dated December 18,

1984. The inspectors reviewed the licensees submittal and noticed that the RHRSW

cross-tie was only credited in alternate shutdown fire areas.. Therefore, the inspectors

concluded that the use of RHRSW cross-tie was only permitted for alternate shutdown

areas (i.e.,Section III.G.3), and would not meet the requirements of 10 CFR Part 50,

Appendix R,Section III.G.2. See Section 1R05.1b.1 of this inspection report for further

discussion of SSMP reclassification.

Analysis: The inspectors determined that failure to ensure that one redundant train of

systems necessary to achieve and maintain hot shutdown conditions was free of fire

damage resulted in a performance deficiency warranting a significance evaluation. The

inspectors concluded that the finding was greater than minor in accordance with

IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue Screening, issued

on September 30, 2005. The finding involved the attribute of protection against external

factors (i.e., Fire) and could have affected the mitigating systems cornerstone objective

of ensuring the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences (i.e., core damage). Specifically, the

licensees failure to ensure, in the event of a fire in any of these Fire Areas TB-III, 13-1

or 24-1, that one redundant train of RHRSW remained free of fire damage and instead

credited the RHRSW from the opposite unit, did not provide the adequate level of safety

required per Appendix R to ensure SSD capability.

Since, the SSD path using the RHRSW system from the opposite unit did not meet the

requirement of Appendix R,Section III.G.2, but it was credited in alternate shutdown

areas at Quad Cities plant, the inspectors determined that the finding was not suitable

for SDP evaluation. The finding was reviewed by NRC management and was

determined to be of very low safety significance (Green).

Enforcement: 10 CFR Part 50.48, Fire Protection, and 10 CFR Part 50, Appendix R,

Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1,

1979, establish specific FP features required to satisfy 10 CFR Part 50, Appendix A,

General Design Criterion 3, Fire Protection. Appendix R applies to licensed nuclear

power electric generating stations that were operating prior to January 1, 1979, which

includes QCNPS.Section III.G.2 of Appendix R to 10 CFR Part 50 required, in part, that

where cables or equipment of redundant trains of systems necessary to achieve and

maintain hot shutdown conditions are located within the same fire area outside of

primary containment, one of a specified means of ensuring that one of the redundant

trains is free of fire damage be provided.

Contrary to the above, in the event of a fire in any of these Fire Areas TB-III, 13-1 or 24-

1 (i.e., a III.G.2 area), the licensee failed to meet the requirement of Section III.G.2 of

10 CFR Part 50, Appendix R. Specifically, in the event of a fire in any of these areas,

the licensee credited the opposite Unit RHRSW system instead of ensuring one of the

10 Enclosure

redundant trains of RHRSW from the respective unit with fire was available. Once

identified, the licensee entered the finding into their corrective action program as

IR 00502702, NRC Inspection Finding Concerning App R Redundant Trains, dated

June 22, 2006. Because this violation was of very low safety significance and it was

entered into the licensees corrective action program, this violation is being treated as a

NCV, consistent with Section VI.A.1 of the NRC Enforcement Policy

(NCV 05000254/2006002-02(DRS);05000265/2006002-02(DRS)).

.2 Fire Protection of SSD Capability

Title 10 CFR Part 50, Appendix R, Section III.G.2, required separation of cables and

equipment and associated circuits of redundant trains by a fire barrier having a 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />

rating. If the requirements cannot be met, then alternative or dedicated shutdown

capability and its associated circuits, independent of cables, systems or components in

the area, room, or zone under consideration should be provided in accordance with

10 CFR Part 50, Appendix R, Section III.G.3.

a. Inspection Scope

For each of the selected fire areas, the inspectors reviewed the licensees Safe

Shutdown Capability Analysis (SSCA) and Safe Shutdown Systems Analysis (SSSA) to

ensure that at least one post-fire SSD success path was available in the event of a fire.

This included a review of manual actions required to achieve and maintain hot shutdown

conditions and make the necessary repairs to reach cold shutdown within 72-hours.

The inspectors also reviewed procedures to verify that adequate direction was provided

to operators to perform these manual actions. Factors, such as, timing, access to the

equipment, and the availability of procedures were considered in the review.

The inspectors also evaluated the adequacy of fire suppression and detection systems,

fire area barriers, penetration seals, and fire doors to ensure that at least one train of

SSD equipment was free of fire damage. To accomplish this, the inspectors observed

the material condition and configuration of the installed fire detection and suppression

systems, fire barriers, and construction details and supporting fire tests for the installed

fire barriers. In addition, the inspectors reviewed license documentation, such as,

deviations, detector placement drawings, fire hose station drawings, carbon dioxide

pre-operational test reports, smoke removal plans, fire hazard analysis reports, SSD

analyses, and National Fire Protection Association (NFPA) codes to verify that the fire

barrier installations met license commitments.

b. Findings

No findings of significance were identified.

.3 Post-Fire SSD Circuit Analysis

Title 10 CFR Part 50, Appendix R, Section III.G.1, required that SSCs important to SSD

be provided with FP features capable of limiting fire damage to ensure that one train of

systems necessary to achieve and maintain hot shutdown conditions is free of fire

damage. Options for providing this level of FP were delineated in 10 CFR Part 50,

11 Enclosure

Appendix R,Section III.G.2. Where the protection of systems whose function was

required for hot shutdown did not satisfy 10 CFR Part 50, Appendix R, Section III.G.2,

an alternative or dedicated shutdown capability and its associated circuits, was required

to be provided that was independent of the cables, systems, and components in the

area. For such areas, 10 CFR Part 50, Appendix R, Section III.L.3, specifically required

the alternative or dedicated shutdown capability to be physically and electrically

independent of the specific fire areas and capable of accommodating post-fire

conditions where offsite power was available and where offsite power was not available

for 72-hours.

a. Inspection Scope

On a sample basis, the inspectors evaluated the adequacy of separation provided for

the power and control cabling of redundant trains of shutdown equipment. This

investigation focused on the cabling of selected components in systems important for

SSD. The inspectors review also included a sampling of components whose

inadvertent operation due to fire may adversely affect post-fire SSD capability. The

purpose of this review was to determine if a single exposure fire, in one of the fire areas

selected for this inspection, could prevent the proper operation of both SSD trains.

The inspectors evaluated selected portions of licensees fuse/breaker coordination

analysis for ground faults on the 4160 Volt alternating current (Vac) and 480Vac

systems and the vital low-voltage ac and direct current (dc) power sources to determine

whether fire-induced faults on distribution system cables or buses could degrade

post-fire SSD capability. Specifically, the inspectors determined if selective coordination

existed between branch circuit protective devices and the upstream distribution panel

fuse/breaker feeders to ensure that in the event of a fire-induced short circuit, the fault

would be isolated before the upstream feeder fuse/breaker tripped.

b. Findings

No findings of significance were identified.

.4 Alternative SSD Capability

Title 10 CFR Part 50, Appendix R, Section III.G.1, required that SSCs important to SSD

be provided with FP features capable of limiting fire damage to ensure that one train of

systems necessary to achieve and maintain hot shutdown conditions is free of fire

damage. Options for providing this level of FP were delineated in 10 CFR Part 50,

Appendix R,Section III.G.2. Where the protection of systems whose function was

required for hot shutdown did not satisfy 10 CFR Part 50, Appendix R, Section III.G.2,

an alternative or dedicated shutdown capability independent of the area under

consideration was required to be provided. Additionally, alternative or dedicated

shutdown capability must be able to achieve and maintain hot standby conditions and

achieve cold shutdown conditions within 72-hours and maintain cold shutdown

conditions thereafter. During the post-fire SSD, the reactor coolant process variables

must remain within those predicted for a loss of normal alternating current power, and

the fission product boundary integrity must not be affected (i.e., no fuel clad damage,

rupture of any primary coolant boundary, or rupture of the containment boundary).

12 Enclosure

a. Inspection Scope

The inspectors reviewed the licensees systems required to achieve alternative SSD to

determine if the licensee had properly identified the components and systems necessary

to achieve and maintain SSD conditions. The inspectors also focused on the adequacy

of the systems to perform reactor pressure control, reactivity control, reactor coolant

inventory makeup, decay heat removal, process monitoring, and support system

functions.

b. Findings

No findings of significance were identified.

.5 Operational Implementation of SSD Capability

Title 10 CFR Part 50, Appendix R, Section III.L.2.d, required that the process monitoring

function should be capable of providing direct readings of the process variables

necessary to perform and control the functions necessary to achieve reactivity control,

reactor coolant inventory makeup, and decay heat removal.

a. Inspection Scope

The inspectors reviewed a sample of the actions defined in procedures QCOA 0010-12,

Fire/Explosion, Revision 27, QCARP 0050-01, SB-1-1 Injection with SSMP and Bring

the Unit to Cold Shutdown, Revision 10, and other procedures which were referenced

by procedure QCOA 0010-12. Procedure QCARP 0050-01 was the procedure for

performing a plant alternative shutdown from outside the Unit 1 CR. The inspectors

reviewed, on a sample bases, the ability of operators to perform procedure actions

within applicable plant shutdown time requirements. The inspectors also focused on the

feasability of the actions described in the procedure.

The inspectors reviews of the adequacy of communications and emergency lighting

associated with these procedures are documented in Sections 1R05.6 and 1R05.7 of

this report.

b. Findings

b.1 Fuse Repair

Introduction: The inspectors identified a NCV of 10 CFR Part 50, Appendix B,

Criterion V, Instruction, Procedures, and Drawings, having very low safety significance

(Green) involving inadequate procedure steps. Specifically, the inspectors identified

that Procedure QOP 6500-10, Local Control of 4160 and 480 Volt Motor Operated

Circuit Breaker, Revision 8, included repair steps to replace fuses for hot shutdown in

the event of a fire. This fuse replacement constituted a hot shutdown repair which did

not meet 10 CFR Part 50, Appendix R requirements.

Description: The breakers for Unit 1's Division 1 RHR pumps and Bus 13-1/23-1

cross-tie are required to be opened and closed to safely shutdown the unit in the event

of a fire in Fire Area TB-III. Each breaker had a cable routed in Fire Area TB-III, which

13 Enclosure

had the potential to cause the breakers control power fuses to be blown. This would

have prevented the electrical operation of the breakers but would not have prevented

local manual operation as documented in QCNPSs Appendix R analysis. During the

inspectors review of Procedure QCARP 0030-01 TB-III Injection With SSMP and

Bringing the Unit to Cold Shutdown, Revision 8, the inspectors noted that in

Steps D.11.e (e.g, closes Bus 23-1 and 13-1 cross-tie breaker) and D.11.f (e.g, closes

one of the RHR pumps 1A or 1B) the operator(s) were required to close the circuit

breaker per procedure QOP 6500-10. Procedure QOP 6500-10 included a step to

replace any fuses believed to be blown prior to operating the breaker from a local

control box. The inspectors determined that since one train of RHR system was

required for torus cooling, the fuse replacement specified in this step constituted a hot

shutdown repair.

Title 10 CFR Part 50, Appendix R, Section III. G.1.a, stated One train of systems

necessary to achieve and maintain hot shutdown conditions from either the control room

or emergency control station(s) is free of fire damage; . . . and Section III.G.1.b, stated

Systems necessary to achieve and maintain cold shutdown from either the control or

emergency station(s) can be repaired within 72-hours. Based on the above, the

inspectors determined that the breakers fuse replacement did not meet Appendix R

requirements, because it constituted a hot shutdown repair, and repair is only allowed

for systems necessary to achieve and maintain cold shutdown. As a result, the licensee

entered this finding into the stations corrective action program as IR 00485702,

Required SSDA Actions Not Contained in QCARP 0030-01, dated May 2, 2006. The

licensee revised Procedure QOP 6500-10 and added steps to manually charge

breakers spring and close the breaker using a pushbutton if the fuses are not available

due to fire damage.

Analysis: The inspectors determined that the failure to include adequate steps in

Procedure QOP 6500-10 that did not meet Appendix R requirements was a

performance deficiency warranting a significance evaluation. The inspectors concluded

that the finding was greater than minor in accordance with IMC 0612, Power Reactor

Inspection Reports, Appendix B, Issue Screening, issued on September 30, 2005.

The finding involved the attribute of Procedure Quality and could have affected the

mitigating systems cornerstone objective of ensuring the availability, reliability, and

capability of systems that respond to initiating events (fire) to prevent undesirable

consequences (i.e., core damage). Specifically, the failure to include adequate steps in

the procedure to manually operate switchgear breakers and instead included a repair to

achieve and maintain hot shutdown in the event of a fire could have delayed and

complicated shutdown of the plant.

The inspectors completed a significance determination of this finding using IMC 0609,

Significance Determination Process (SDP), dated November 22, 2005, Appendix F,

Fire Protection Significance Determination Process, dated February 28, 2005. The

inspectors assigned a degradation rating of low safety significance (Green) because the

licensees R analysis did not require the repair, and the operator(s) could have manually

closed the breaker instead of replacing the fuses. Therefore, this finding screened out

as having very low safety significance (Green).

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, stated, in part, that

activities affecting quality shall be prescribed by documented instructions, procedures,

14 Enclosure

or drawings of a type appropriate to the circumstances and shall be accomplished in

accordance with these instructions, procedures, or drawings. Title 10 CFR Part 50,

Appendix R,Section III. G.1.a, stated One train of systems necessary to achieve and

maintain hot shutdown conditions from either the control room or emergency control

station(s) is free of fire damage; . . . and Section III.G.1.b, stated Systems necessary

to achieve and maintain cold shutdown from either the control or emergency station(s)

can be repaired within 72-hours.

Contrary to the above, Procedure QOP 6500-10, Local Control of 4160 and 480 Volt

Motor Operated Circuit Breaker, Revision 8, included steps that were not appropriate to

the circumstances. Specifically, Procedure QOP 6500-10, included steps to replace the

switchgear breakers fuses prior to operation of the breaker from a local control box.

This fuse replacement constituted a hot shutdown repair which did not meet the

requirement of 10 CFR Part 50, Appendix R and could have delayed SSD of the plant in

the event of a fire. Once identified, the licensee entered the finding into their corrective

action program as IR 00485702, Required SSDA Actions Not Contained in

QCARP 0030-01, dated May 2, 2006. Because this violation was of very low safety

significance and it was entered into the licensees corrective action program, this

violation is being treated as a NCV, consistent with Section VI.A.1 of the NRC

Enforcement Policy (NCV 05000254/2006002-03(DRS);05000265/2006002-03(DRS)).

.6 Communications

For a fire in an alternative shutdown fire area, CR evacuation may be required and a

shutdown is performed from outside the CR. Radio communications are relied upon to

coordinate the shutdown of both units and for fire fighting and security operations.

Title 10 CFR Part 50, Appendix R, Section III.H., required that equipment provided for

the fire brigade include emergency communications equipment.

a. Inspection Scope

The inspectors reviewed, on a sample bases, the adequacy of the communication

system to support plant personnel in the performance of alternative SSD functions and

fire brigade duties.

b. Findings

No findings of significance were identified.

.7 Emergency Lighting

Title 10 CFR Part 50, Appendix R, Section III.J., required that emergency lighting units

with at least an 8-hour battery power supply be provided in all areas needed for

operation of SSD equipment and in access and egress routes thereto.

15 Enclosure

a. Inspection Scope

The inspectors performed a plant walkdown of areas in which a sample of the actions

would be performed as described in procedure QCARP 0050-01, SB-1-1 Injection with

SSMP and Bring the Unit to Cold Shutdown, Revision 10, and other procedures which

were referenced by procedure QCARP 0050-01. As part of the walkdowns, the

inspectors focused on the existence of sufficient emergency lighting for access and

egress to areas and for performing necessary equipment operations.

b. Findings

No findings of significance were identified.

.8 Cold Shutdown Repairs

Title 10 CFR Part 50, Appendix R, Section III.L.5, required that equipment and systems

comprising the means to achieve and maintain cold shutdown conditions should not be

damaged by fire; or the fire damage to such equipment and systems should be limited

so that the systems can be made operable and cold shutdown achieved within 72-hours.

Materials for such repairs shall be readily available onsite and procedures shall be in

effect to implement such repairs.

a. Inspection Scope

The inspectors reviewed the licensees procedures to determine if any repairs were

required to achieve cold shutdown. The inspectors determined that the licensee did

require repair of some equipment to reach cold shutdown based on the SSD methods

used. The inspectors reviewed the procedures for adequacy. The inspectors also

reviewed completed surveillances of the tools and equipment needed to reach cold

shutdown.

b. Findings

No findings of significance were identified.

.9 Fire Barriers and Fire Zone/Room Penetration Seals

Title 10 CFR Part 50, Appendix R, Section III.M, required that penetration seal designs

be qualified by tests that are comparable to tests used to rate fire barriers.

a. Inspection Scope

The inspectors reviewed the test reports for three-hour rated barriers installed in the

plant and performed visual inspections of selected barriers to ensure that the barrier

installations were consistent with the tested configuration. In addition, the inspectors

reviewed the fire loading for selected areas to ensure that existing barriers would not be

challenged by a potential fire.

16 Enclosure

17 Enclosure

b. Findings

No findings of significance were identified.

.10 Fire Protection Systems, Features, and Equipment

a. Inspection Scope

The inspectors reviewed the material condition, operations lineup, operational

effectiveness, and design of fire detection systems, fire suppression systems, manual

fire fighting equipment, fire brigade capability, and passive FP features. The inspectors

reviewed deviations, detector placement drawings, fire hose station drawings, carbon

dioxide system pre-operational test reports, and fire hazard analysis reports to ensure

that selected fire detection systems, sprinkler systems, portable fire extinguishers, and

hose stations were installed in accordance with their design, and that their design was

adequate given the current equipment layout and plant configuration.

b. Findings

b.1 Fire Pre-Plans

Introduction: The inspectors identified a NCV of QCNPSs Operating Licenses DPR-29

and DPR-30, Section h.3.F, having very low safety significance (Green) involving the

lack of pertinent information in the QCNPSs fire pre-plans for various plant fire areas.

Specifically, the licensee failed to include important information in the fire pre-plans,

such as, hydrogen and electrical hazards, to assist the fire brigade to fight a fire within

those plant fire areas.

Description: The inspectors reviewed the licensees corrective action documents

IR 00221528, Fire Brigade Turnout Gear /SCBA Location, dated May 12, 2004, and

IR 00478821, Fire Pre-plans [Fire Area] RB-19 and [Fire Area] TB-71 Have Incorrect

Information, dated April 14, 2006. Both issue reports were initiated as a result of the

NRC resident inspector identified problems associated with the QCNPSs fire pre-plans.

One of the licensees corrective actions associated with IR 00221528 was the

implementation of a plan to improve the fire pre-plans over a four year period. Each

cycle would be six-months with the first cycle beginning July 2004 thru December 2004.

The licensee maintained a log of the fire pre-plans reviewed during each cycle. The

licensees review of IR 00478821 noted that Fire Areas RB-7 and RB-19 needed

hydrogen and oxygen hazards added to the fire pre-plans.

The inspectors observed that Fire Area RB-7 was previously reviewed on July 8, 2004,

and Fire Area RB-19 was previously reviewed on December 20, 2005, as part of the fire

pre-plan improvement effort. The inspectors review identified that the licensees

corrective actions to improve the QCNPSs fire pre-plans were not adequate. Major fire

hazards, such as, hydrogen and oxygen hazards were missed during the licensees

review. In addition, the inspectors identified additional concerns regarding fire pre-plans

as follows: 1) pre-plans did not identify all potential hazards (e.g., the location of

electrical panels that could be a risk to the fire brigade); 2) pre-plans lacked adequate

18 Enclosure

information on damper and ventilation controls (e.g., which damper and/or ventilation

controls needed to be isolated or turned off and which must be left on to cool SSD

equipment); 3) some pre-plan drawings contained errors (e.g., the quantity of fire

fighting equipment available); 4) pre-plans failed to identify the electrical panels that

were not sealed (e.g., to prevent water, if used during fire fighting, from entering

unsealed electrical panels to eliminate potential damage to both trains of equipment;

5) pre-plans did not identify which hose reels were primary or secondary hose reels to

ensure that the correct hose reel was used in a fire area (e.g., correct nozzle, length of

hose, etc.); 6) pre-plans listed transient combustibles as a hazard, when transient

combustibles may no longer be in the fire area and should have been removed from the

fire pre-plan; 7) pre-plans listed cable insulation as a hazard when cable insulation is

normally located in most fire areas; and 8) pre-plans allowed a person with a radio to be

positioned at a sprinkler control valve, where in many cases the control valve located in

the fire area .

Fire pre-plan requirements were identified in the licensees, Fire Protection Report

Volume 1, Revision 17, dated October 2005, in Section 2.0, Fire Protection Program,

Paragraph 2.5.4, Fire Fighting Strategies, which stated Pre-fire plans are provided for

all safety-related areas of the plant. The fire pre-plans provided necessary information,

including a diagram showing where fire equipment is located to aid the fire brigade in

executing manual fire fighting operations. In addition, in procedure CC-AA-211, Fire

Protection Program, Paragraph 4.9, Fire Pre-Plans, the licensee stated, The plans

are designed to provide as much useful information as possible in a short amount of

time, . . .. and . . . they provide useful information for quickly determining the

emergency response strategies based on hazards and equipment in the area.

Analysis: The inspectors determined that failure to maintain complete and accurate fire

pre-plans was a performance deficiency warranting a significance evaluation. The

inspectors concluded that the finding was greater than minor in accordance with

IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue Screening, issued

on September 30, 2005. The finding involved the attribute of protection against external

factors (i.e., fire), where failure to provide adequate warnings and guidance related to

hydrogen and electrical hazards in the fire pre-plans could have adversely impacted the

fire brigades ability to fight a fire. This would increase the likelihood of a fire which

would challenge SSD and could have affected the mitigating systems cornerstone

objective of ensuring the availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences (i.e., core damage). The

inspectors determined that this issue also affected the cross-cutting area of Problem

Identification and Resolution because the licensee failed to ensure that issues

potentially impacting nuclear safety were identified and fully evaluated. The licensee

failed to identify and revise the presence of hydrogen and oxygen hazards in Fire Areas

RB-7 and RB-19 during their review as part of the fire pre-plan improvement effort

conducted as a result of previously identified corrective action (IR 00221528).

The inspectors completed a significance determination of this finding using IMC 0609,

Significance Determination Process, Appendix F, Fire

Protection Significance Determination Process, dated February 28, 2005. The finding

affected the Fire Prevention and Administrative Controls Category in the area of

19 Enclosure

compliance documentation. The inspectors assigned a degradation rating of low safety

significance because extensive training was provided to fire brigade members to deal

with unexpected contingencies. In addition, other defense-in-depth FP elements

remained unaffected and fire in this area would not result in a loss of dedicated SSD

systems. The inspectors review of the Initial Qualitative Screening concluded that this

finding was considered to be of very low safety significance (Green).

Enforcement: The QCNPSs Operating Licenses DPR-29 and DPR-30, Section h.3.F,

stated that the licensee shall implement and maintain in effect all provisions of the

approved QCNPSs FPP as described in the UFSAR for the facility and as approved in

the SER dated July 27, 1979, and subsequent SER supplements. Section h.3.F, also

stated that the licensee may make changes to the approved QCNPSs FPP without prior

approval of the Commission only if those changes would not adversely affect the ability

to achieve and maintain SSD in the event of a fire. The licensees procedure

CC-AA-211, Fire Protection Program, Paragraph 4.9, Fire Pre-Plans stated The

plans are designed to provide as much useful information as possible in a short amount

of time, . . . . and . . . they provide useful information for quickly determining the

emergency response strategies based on hazards and equipment in the area.

Contrary to the above, on May 11, 2006, the licensees fire pre-plans failed to provide

useful information for quickly determining the emergency response strategies based on

hazards and equipment in the area for effective fire fighting. Specifically, the licensee

failed to maintain acceptable fire pre-plans by not providing accurate and complete and

guidance related to hydrogen and electrical hazards in the fire pre-plans which could

have adversely impacted fire brigades ability to fight a fire. The inspectors concluded

this was a violation of the QCNPSs License Condition, Section h.3.F. Once identified,

the licensee entered the finding into their corrective action program as IR 00489175,

Quality of Fire Preplans (2006 FP Triennial), dated May 11, 2006. Because this

violation was of very low safety significance and it was entered into the licensees

corrective action program, this violation is being treated as a NCV, consistent with

Section VI.A.1 of the NRC Enforcement Policy (NCV 05000254/2006002-04(DRS);05000265/2006002-04(DRS)).

b.2 Standpipes with Hose Connections

Introduction: The inspectors identified a NCV of Operating Licenses DPR-29 and

DPR-30, Section h.3.F, having very low safety significance (Green) involving adequacy

of water pressure and flow rate at standpipes with hose connections. Specifically, the

licensee failed to provide calculations to ensure that an adequate water pressure and

flow rate were available to meet the QCNPSs FPP requirements.

Description: The inspectors were concerned that standpipes with hose connections had

the potential for an inadequate water pressure and flow rate to effectively fight a fire.

The licensee stated that calculations had been made to ensure that an adequate water

pressure and flow rate were available, however, the licensee could not locate the

supporting calculations.

20 Enclosure

In NFPA 14, Standpipe and Hose Systems, Revision 1974, the requirements for

standpipe systems in Class II service required that each standpipe shall be sized for a

minimum flow of 100 gallons per minute and that standpipes in excess of 50 feet in

height shall be at least 21/2 inches in size.

The inspectors review of the licensees NFPA Code Deviation 14-06, indicated that a

few standpipes serving multiple hose connections were less than four inches in diameter

and several connections to single hose stations were less than 21/2 -inch diameter. The

licensees justification stated that calculations had been completed to verify the

adequacy of the water supply from these small pipes. In addition, the inspectors noted

that in the QCNPSs Fire Protection Report comparison against NRC Branch Technical

Position 9.5.1, Appendix A to 9.5-1 Guidelines for Fire Protection, Paragraph E.3.(d),

the licensee stated that several standpipes serving single hose connections were less

than 21/2 inch in diameter and that calculations had been completed to verify the

adequacy of the water supply from the smaller pipes.

During this inspection, the licensee completed Calculation QDC-4100-M1534, Fire

Protection Hose Reel Supply Piping Pressure Drop; dated May 11, 2006, for one of the

more limiting two inch FP supply pipelines to demonstrate that the NFPA Code

requirements were met. However, the inspectors concluded that this calculation failed

to account for the more limiting 11/2 inch piping to the standpipes with hose connections

used in the QCNPSs turbine building. The inspectors review revealed that the

calculation did not account for the water supply pressure drop that would occur at either

the fire area sprinklers or the standpipes with hose connections when a concurrent

actuation was initiated. The inspectors review of the two inch piping calculation also

revealed that there was little or no margin in water flow rate in the 11/2 inch piping. As a

result, the licensee initiated IR 00489160, Justification of Fire Hose Pressure and Flow

Meeting NFPA, dated May 11, 2006, to include in their corrective actions a plan to

perform more extensive calculations to verify water pressure and flow rate at all effected

standpipes with hose connections.

Analysis: The inspectors determined that failure to provide supporting calculations to

demonstrate adequate water pressure and flow rate at standpipes with hose

connections was a performance deficiency warranting a significance evaluation. The

inspectors concluded that the finding was greater than minor in accordance with

IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue Screening, issued

on September 30, 2005. The finding involved the attribute of protection against external

factors (i.e., fire), where the lack of water pressure and flow rate at standpipes with hose

connections could hamper the fire brigades ability to fight a fire, thereby, increasing the

likelihood of a fire which would challenge SSD and could have affected the mitigating

systems cornerstone objective of ensuring the availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences

(i.e., core damage).

The inspectors completed a significance determination of this finding using IMC 0609,

Significance Determination Process, dated November 22, 2005, Appendix F, Fire

Protection Significance Determination Process, dated February 28, 2005. The finding

affected the Fire Prevention and Administrative Controls Category in the area of

compliance documentation. The inspectors assigned a degradation rating of low safety

significance because other defense-in-depth FP elements remained unaffected in all fire

21 Enclosure

areas. The inspectors review of the Initial Qualitative Screening concluded that this

finding was considered to be of very low safety significance (Green).

Enforcement: The QCNPSs Operating Licenses DPR-29 and DPR-30, Section h.3.F,

stated that the licensee shall implement and maintain in effect all provisions of the

approved QCNPSs FPP as described in the UFSAR for the facility and as approved in

the SER dated July 27, 1979, and subsequent SER supplements. Section h.3.F, also

stated that the licensee may make changes to the approved QCNPSs FPP without prior

approval of the Commission only if those changes would not adversely affect the ability

to achieve and maintain SSD in the event of a fire. In addition, the licensee stated in

Appendix A to 9.5-1 Guidelines for Fire Protection, Paragraph E.3.(d) that several

standpipes serving single hose connections were less than 21/2 inch in diameter and that

calculations had been completed to verify the adequacy of the water supply from these

smaller pipelines.

Contrary to the above, on May 11, 2006, the licensee failed to provide calculations to

ensure adequate water pressure and flow rate were available at standpipes with hose

connections for effective fire fighting. The inspectors concluded this was a violation of

the QCNPSs License Condition, Section h.3.F. Once identified, the licensee entered

the finding into their corrective action program as IR 00489160, Justification of Fire

Hose Pressure and Flow Meeting NFPA, dated May 11, 2006, and planned to perform

calculations to verify water flow at all effected standpipes with hose connections.

Because this violation was of very low safety significance and it was entered into the

licensees corrective action program, this violation is being treated as a NCV, consistent

with Section VI.A.1 of the NRC Enforcement Policy (NCV 05000254/2006002-05(DRS);05000265/2006002-05(DRS)).

b.3 Class A Fire Extinguishers

Introduction: The inspectors identified a NCV of QCNPSs Operating Licenses DPR-29

and DPR-30, Section h.3.F, having very low safety significance (Green) involving

Class A fire extinguishers. Specifically, the QCNPSs FPP did not have an adequate

number of Class A fire extinguishers available where significant fire hazards existed to

meet the NFPA 10 Code requirements to suppress and/or extinguish Class A fire

hazards.

Description: The inspectors reviewed Design Analysis WDC-4100-0691, Combustible

Loading Calculation for the Power Block, SBO Building, and Cribhouse, dated

February 18, 2005. This document showed large quantities of Class A combustibles

located in many areas of the plant. For example, Fire Zones 1.1.1.5, 1.1.1.6, and

8.2.7.A contained greater than 1000 pounds of Class A combustible materia..

During the inspectors plant walkdown, the inspectors observed that there were an

inadequate number of Class A fire extinguishers located throughout QCNPS where

22 Enclosure

significant fire hazards existed to meet the NFPA 10 Code requirements. For example,

fire zones 1.1.1.5, 1.1.1.6, and 8.2.7.A did not have Class A fire extinguishers present.

The NFPA 10 Code requirements were endorsed by the QCNPSs FPP. Specifically,

there were substantial amounts of Class A combustibles located in many areas of the

plant that would require a Class A fire extinguisher to suppress and/or extinguish this

type of fire hazard.

In Amendment Number 52 to the Facility Operating License (SER dated July 27, 1979),

Paragraph 4.3.3, Portable Fire Extinguishers, the SER stated in part, that portable dry

chemical and carbon dioxide extinguishers have been distributed throughout the plant.

The fire extinguishers meet the NFPA 10 Code requirements. The fire extinguisher

selections were made in accordance with the type of fire hazards to be protected

against at the QCNPS. In addition, the licensees responses to the Guidelines of

Appendix A to APCSB 9.5-1," Section E.6, Portable Extinguishers, stated in part, that

QCNPS complied with the NFPA 10 Code requirements for fire extinguishers. The NRC

originally approved the licensees statement of compliance with the NFPA Code during

the NRCs review of the licensee response to APCSB 9.5.1. The licensee subsequently

revised their statement of compliance with the APCSB 9.5-1 section for Class A fire

extinguishers and instead took credit for standpipes with hoses in lieu of the Class A fire

extinguishers. However, when the inspectors requested the licensees evaluation that

made this change to the QCNPSs FPP, the licensee could not locate the associated

documentation.

The inspectors noted during a review of NFPA 10, Portable Fire Extinguishers,

Revision 1975, that up to one-half of the complement of fire extinguishers may be

replaced by uniformly spaced small hose stations for use by the building occupants. In

addition, Section 1-1, Standard for Portable Fire Extinguishers, stated in part, that

portable fire extinguishers were intended as a first line of defense to cope with fires of

limited size. The fire extinguishers were needed even though the property is equipped

with automatic sprinklers, standpipes and hose, and other fixed fire protection

equipment. The NFPA Code further stated that Class A fires were fires of ordinary

combustible materials, such as wood, cloth, paper, rubber, and many plastics. In

Section 2-2.1, the NFPA Code required that fire extinguishers shall be selected for the

specific class or classes of fire hazards. Fire extinguishers for protecting Class A fire

hazards shall be selected from among water types, foam, loaded stream, and

multipurpose dry chemical.

The inspectors review of the QCNPSs NFPA Code Deviation 10-01 revealed that fire

extinguishers for Class A fire hazards were not distributed in accordance with the NFPA

Code. The licensees justification, for the NFPA Code deviation, stated that at QCNPS

the quantity of Class A combustibles was limited primarily to cable insulation and/or

transient combustibles, that proper distribution of standpipes with hose connections

were provided, and since trained on-site fire brigade personnel were present that the

limited distribution of Class A fire extinguishers was considered acceptable. As a result

of the inspectors review of Design Analysis WDC-4100-0691, the inspectors concluded

that the licensees NFPA Code Deviation 10-01, as stated above, contained an

inadequate justification for the number of Class A fire extinguishers in the plant.

23 Enclosure

Analysis: The inspectors determined that failure to have an adequate number of

Class A fire extinguishers available where significant fire hazards existed to meet the

NFPA 10 Code requirements to suppress and/or extinguish Class A fire hazards was a

performance deficiency warranting a significance evaluation. The inspectors concluded

that the finding was greater than minor in accordance with IMC 0612, Power Reactor

Inspection Reports, Appendix B, Issue Screening, issued on September 30, 2005.

The finding involved the attribute of protection against external factors (i.e., Fire), where

failure to have an adequate number of Class A fire extinguishers available could

potentially escalate a small fire into a larger fire since only standpipes with hose

connections were available and their use required a trained fire brigade to extinguish the

fire. As a result, non-fire brigade personnel would be prevented from moving quickly to

suppress and/or extinguish a small fire and the potential for an escalated fire could have

affected the mitigating systems cornerstone objective of ensuring the availability,

reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences (i.e., core damage).

The inspectors completed a significance determination of this finding using IMC 0609,

Significance Determination Process, dated November 22, 2005, Appendix F, Fire

Protection Significance Determination Process, dated February 28, 2005. The finding

affected the Fire Prevention and Administrative Controls Category in the area of

compliance documentation. The inspectors assigned a degradation rating of low safety

significance because most fire areas and fire zones have fire detectors that would alarm

in the control room. In addition, other defense-in-depth FP elements remained

unaffected and fire in this area would not result in a loss of dedicated SSD systems.

The inspectors review of the Initial Qualitative Screening concluded that this finding

was considered to be of very low safety significance (Green).

Enforcement: The QCNPSs Operating Licenses DPR-29 and DPR-30, Section h.3.F,

stated that the licensee shall implement and maintain in effect all provisions of the

approved QCNPSs FPP as described in the UFSAR for the facility and as approved in

the SER dated July 27, 1979, and subsequent SER supplements. Section h.3.F, also

stated that the licensee may make changes to the approved QCNPSs FPP without prior

approval of the Commission only if those changes would not adversely affect the ability

to achieve and maintain SSD in the event of a fire. Amendment Number 52 to the

Facility Operating License (SER dated July 27, 1979), required the QCNPS to maintain

Class A fire extinguishers in accordance with NFPA 10 Code requirements and that

Class A fire extinguishers would be available for the type of fire hazard present.

Contrary to the above, from May 24, 1985, to May 12, 2006, the licensee failed to

maintain Class A fire extinguishers in accordance with NFPA 10 Code requirements and

that Class A fire extinguishers were not available for the type of fire hazard present.

Specifically, no Class A fire extinguishers were located within Fire Zone 1.1.1.5, 1.1.1.6

and 8.2.7.A even though the fire zones contained more than 1000 ponds of Class A

combustible materials. Additionally, the licensees code evaluation 10-01 was not

consistent with the results in Design Analysis WDC-4100-0091. The inspectors

concluded this was a violation of the QCNPSs License Condition, Section h.3.F. Once

identified, the licensee entered the finding into their corrective action program as

IR 00489426, Class A Fire Extinguisher Placement Improvements, dated May 12,

2006. Because this violation was of very low safety significance and it was entered into

24 Enclosure

the licensees corrective action program, this violation is being treated as a NCV,

consistent with Section VI.A.1 of the NRC Enforcement Policy

(NCV 05000254/2006002-06(DRS);05000265/2006002-06(DRS)).

25 Enclosure

.11 Compensatory Measures

a. Inspection Scope

The inspectors conducted a minimal review to verify that adequate compensatory

measures were put in place by the licensee for out-of-service, degraded or inoperable

FP and post-fire SSD equipment, systems, or features. The inspectors also conducted

a minimal review on the adequacy of short term compensatory measures to compensate

for a degraded function or feature until appropriate corrective actions were taken.

b. Findings

No findings of significance were identified.

4. OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems

a. Inspection Scope

The inspectors reviewed the corrective action program procedures and samples of

corrective action documents to verify that the licensee was identifying issues related to

the FPP at an appropriate threshold and entering them in the corrective action program.

The inspectors reviewed these issues to verify an appropriate threshold for identifying

issues and to evaluate the effectiveness of corrective actions related to the FPP. In

addition, corrective action documents written on issues identified during the inspection

were reviewed to verify adequate problem identification and incorporation of the problem

into the corrective action system. The specific corrective action documents that were

sampled and reviewed by the team are listed in the attachment to this report.

b. Findings

No findings of significance were identified.

4OA5 Other Activities

(Closed) Unresolved Item 05000254/2003012-01(DRS);05000265/2003012-01(DRS):

Cable Ampacity Calculation Methodology

A Unresolved item (URI) was opened during the 2003 triennial FP inspection regarding

Calculation QDC-0000-E-0853, SLICE Cable Ampacity Multiplying Factors for Quad

Cities, Revision 0, dated December 2, 1999. Specifically, the inspectors were

concerned that the calculations methodology used to account for cable derating and/or

cable tray loading was correctly applied to potential overpowered cables. The URI was

opened pending further NRC review of the licensees calculation.

During this inspection, the inspectors reviewed the licensees activities associated with

cable ampacity derating and cable tray ampacity loading. The results of the inspectors

review indicated that the QCNPSs Calculation QDC-0000-E-0853 was not utilized at the

26 Enclosure

QCNPS. As a result, no further inspector concerns were identified with this calculation

at the present time. Since the calculation was not utilized at QCNPS, the inspectors

considered this URI closed.

4OA6 Meetings

.1 Exit Meeting

On May 12, 2006, at the end of the on-site inspection activities, the inspectors

presented the inspection results to Mr. T. Tulon and other members of licensee

management. The inspectors asked the licensee whether any materials examined

during the inspection should be considered proprietary. No proprietary information was

identified.

On June 29, 2006, at the conclusion of the inspection, a re-exit meeting conference call

was with Mr. T. Tulon and other members of licensee management to present the

inspection findings.

.2 Interim Exit Meetings

No interim exits were conducted.

4OA7 Licensee-Identified Violations

The following violations of very low safety significance (Green) were identified by the

licensee and are violations of NRC requirements which meet the criteria of Section VI of

the NRC Enforcement Policy, NUREG-1600, for being dispositioned as NCVs.

Cornerstone: Mitigating System

.1 Appendix R SSD Battery Loads

Criterion III Design Control, of 10 CFR Part 50, Appendix B, requires, in part, that

measures shall be established to assure that applicable regulatory requirements and the

design basis are correctly translated into specifications, drawings, procedures, and

instructions. Contrary to the above, the licensee did not have a design basis calculation

to verify that the 125Vdc battery/system can support the SSD loads during an

Appendix R fire for the period of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Specifically, the licensee did not consider the

additional loads lineup to battery 2 as a result of a fire in Fire Area 13-1. During normal

plant operating conditions, the 125Vdc battery 1 supplied Bus 1A (Unit 1 Division I) and

Bus 2B (Unit 2 Division II), battery 2 supplied Bus 2A (Unit 2 Division I) and Bus 1B

(Unit 1 Division II). In the event of a fire in Fire Area 13-1, both battery chargers for

battery 1 were considered unavailable. Procedure QCARP 0040-01 13-1 Injection with

SSMP and Bringing the Unit to Cold Shutdown included steps connected the Unit 2

Division II, 125Vdc Bus 2B, to battery 2. These steps in the procedure would have

lined-up all three 125Vdc divisions to battery 2. A calculation was not performed to

ensure that the 125Vdc battery/charger could have provided power to three divisions

simultaneously. The inspectors determined that the finding was more than minor

because it was associate with the Mitigating System Cornerstone attribute of Design

27 Enclosure

Control and affected the cornerstone objective of ensuring the capability of systems

needed to respond to initiating events to prevent undesirable consequences.

Specifically, the failure of the fuse or the battery/charger to supply the necessary loads

for 72-hours could potentially have complicated shutdown during a fire event. The

licensee discovered this finding during their Focus Area Self Assessment (FASA) and

tracked it through Action Tracking AT 426687-15. The licensee also entered this finding

into the stations corrective action program as IR 00492546. The inspectors determined

that the finding was of very low safety significance because the licensee completed

technical evaluation EC 360895 which ensured that the battery, main fuse and charger

number 2 were adequate to supply the loads lineup included in procedure

QCARP 0040-01.

.2 Post-Fire Operator Manual Actions

On March 6, 2006, the NRC published a Federal Register Notice (FRN, Vol. 71, No. 43,

Page 11169, 10 CFR Part 50, RIN 3150 AH54) that announced the withdrawal of a

proposed rule to 10 CFR Part 50, Appendix R, Paragraph III.G.2. The proposed rule

would have revised Paragraph III.G.2 of Appendix R to allow licensees to implement

acceptable operator manual actions combined with fire detectors and automatic fire

suppression capability as an acceptable method for ensuring the capability of a licensee

to bring a reactor to, and maintain it in, a hot shutdown condition. The NRC withdrew

the proposed rule stating that 10 CFR Part 50, Appendix R, Paragraph III.G.2, cannot

be reasonably interpreted to permit reliance upon operator manual actions in lieu of the

specific methods provided in the subparagraphs of Paragraph III.G.2, to ensure that one

of the redundant SSD trains in the same fire area is free of fire damage. Therefore, any

pre-1979 licensee (i.e., QCNPS) that is using operator manual actions instead of the

specific methods provided in the subparagraphs of Paragraph III.G.2, without an

NRC-approved exemption, is not in compliance with the regulations.

Contrary to the requirements of 10 CFR Part 50, Appendix R, Paragraph III.G.2, the

QCNPSs FPP permitted reliance upon operator manual actions in lieu of the specific

methods provided in the subparagraphs of Paragraph III.G.2, to ensure that one of the

redundant SSD trains in the same fire area is free of fire damage. The licensee

recognized that many of the QCNPSs FPP operator manual actions were without

NRC-approved exemptions. As a result, the licensee generated Issue Report

00464665, NRC Terminates Fire Protection Manual Action Rulemaking, date

March 10, 2006, to acknowledge withdrawal of the proposed rule and QCNPSs

nonconformance to the regulatory requirements. Since the licensee did not dispute that

a violation of regulatory requirements had occurred, enforcement discretion has been

exercised in accordance with EGM 98-002, Revision 2, dated February 2, 2000. The

licensee has initiated corrective actions to resolve this finding within a reasonable time

frame in accordance with the published EGM and FRN. Therefore, this finding is of very

low safety significance.

ATTACHMENT: SUPPLEMENTAL INFORMATION

28 Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

W. Beck, Regulatory Assurance Manager

D. Boyles, Operations

D. Bucknell, FP Engineer

J. Burkhead, Quad Cities Nuclear Oversight

R. Buttke, Design Engineering

T. Fuhs, Regulatory Assurance

J. Garrity, Outage Control

L. Geerts, Fire Marshal

R. Gideon, Plant Manager

D. Gullott, Corporate Licensing

T. Hanley, Dresden Director of Site Engineering

K. Moser, Quad Cities Director of Site Engineering

C. Pragman, Corporate Fire Protection

J. Rathman, Design Engineering

S. Reynolds, Fire Protection System Engineer

T. Scott, Operations

P. Simpson, Corporate Licensing

M. Taylor, Corporate Fire Protection

T. Tulon, Site Vice President

M. Wagner, Regulatory Assurance

D. Wolf, Design Engineering

NRC

L. Kozak, RIII Senior Reactor Analyst

M. Kurth, Resident Inspector

J. Lara, RIII Engineering Branch 3 Chief

K. Stoedter, Senior Resident Inspector

A-1 Attachment

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000254/2006002-01(DRS); NCV SSMP Credited as a Redundant System for an

05000265/2006002-01(DRS) Appendix R III.G.2 Fire Area (Section 1R05.1b.1)05000254/2006002-02(DRS); NCV Failure to Ensure One Redundant Train of RHRSW

05000265/2006002-02(DRS) Free of Fire Damage (Section 1R05.1b.2)05000254/2006002-03(DRS); NCV Procedure Included Unapproved Fuse Repair for

05000265/2006002-03(DRS) Appendix R (Section 1R05.5b.1)05000254/2006002-04(DRS); NCV Failure to Maintain Acceptable Pre-Fire Plans05000265/2006002-04(DRS) (1R05.10b.1)05000254/2006002-05(DRS); NCV Failure to Have a Calculation for Hose Stations That Did

05000265/2006002-05(DRS) Not Meet Code Requirements to Ensure Adequate

Water Pressure and Flow Rate (1R05.10b.2)05000254/2006002-06(DRS); NCV Failure to Meet NFPA Code Requirements for Class A

05000265/2006002-06(DRS) Fire Extinguishers (1R05.10b.3)

Closed

05000254/2006002-01(DRS); NCV SSMP Credited as a Redundant System for an

05000265/2006002-01(DRS) Appendix R III.G.2 Fire Area (Section 1R05.1b.1)05000254/2006002-02(DRS); NCV Failure to Ensure One Redundant Train of RHRSW

05000265/2006002-02(DRS) Free of Fire Damage (Section 1R05.1b.2)05000254/2006002-03(DRS); NCV Procedure Included Unapproved Fuse Repair for

05000265/2006002-03(DRS) Appendix R (Section 1R05.5b.1)05000254/2006002-04(DRS); NCV Failure to Maintain Acceptable Pre-Fire Plans05000265/2006002-04(DRS) (1R05.10b.1)05000254/2006002-05(DRS); NCV Failure to Have a Calculation for Hose Stations That Did

05000265/2006002-05(DRS) Not Meet Code Requirements to Ensure Adequate

Water Pressure and Flow Rate (1R05.10b.2)05000254/2006002-06(DRS); NCV Failure to Meet the NFPA Code Requirements for

05000265/2006002-06(DRS) Class A Fire Extinguishers (1R05.10b.3)05000254/2003012-01(DRS); URI Cable Ampacity Calculation Methodology

05000265/2003012-01(DRS) (Section 4OA5)

Discussed

None.

A-2 Attachment

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply that the NRC inspectors reviewed the documents in their entirety, but rather, that

selected sections of portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

CALCULATIONS

Number Description or Title Date or Revision

9198-13-19-1 Calc for SLICE Cable Ampacity Multiplying Factors for the August 24, 1994

Dresden and Quad Cities Stations, Rev 0

DQAMPAC Revised Cable Tray Power Cable Ampacities (S-141A) April 24, 2006

Ver 1.1

QDC-0000- SLICE Cable Ampacity Multiplying Factors for QCNPS, Rev 0 December 2, 1999

E-0853

QDC-3300- Determine Usable Volume in CCSTs for SSMP or RCIC 1

M-0542 following an App R Fire Event

WDC-4100- Combustible Load Calc for Pwr Block, SBO Bldg and Crib February 18, 2005

0691 Hse

CORRECTIVE ACTION PROGRAM DOCUMENTS ISSUED DURING INSPECTION

Number Description or Title Date or Revision

00483345 FP Report Volume 1 Part 2.1-2 Needs Correction April 26, 2006

00483355 Inconsistent Information in the SSDR April 26, 2006

00483752 Discrepancies Have Been Identified in the FHA Table 2.1-2 April 27, 2006

00485387 NFPA Code Deviations Improvement May 1, 2006

00485413 Measure Currents Flowing in Cables May 1, 2006

00485702 Required SSDA Actions Not Contained in QCARP 0030-01 May 2, 2006

00487902 SLICE Program Cable Ampacity Issues May 8, 2006

00488593 Update FP NFPA Deviations May 10, 2006

00489145 Missing Reference Letter for FP NFPA Code Deviations May 11, 2006

00489160 Justification of Fire Hose Pressure and Flow Meeting NFPA May 11, 2006

00489175 Quality of Fire Preplans (2006 FP Triennial) May 11, 2006

00489285 Relay Setting Changed Without Revising Calculation May 11, 2006

00489426 Class A Fire Extinguisher Placement Improvements May 12, 2006

00492546 No Calc for 125Vdc QCARP Lineup May 22, 2006

00502702 NRC Inspection Finding Concerning App R Redundant Trains June 22, 2006

CORRECTIVE ACTION PROGRAM DOCUMENTS ISSUED PRIOR TO INSPECTION

Number Description or Title Date or Revision

00040209 Q2000-04344 Certain FP Commitments in the 1979 December 12, 2000

00113343 Incomplete App R Revisions to Tray Routing Numbers June 26, 2002

00180384 Cable Ampacity Input Discrepancies in SLICE Database October 10, 2003

00182702 Deficiency Identified in Calculation QDC-0000-E-0853 October 24, 2003

A-3 Attachment

CORRECTIVE ACTION PROGRAM DOCUMENTS ISSUED PRIOR TO INSPECTION

Number Description or Title Date or Revision

00218683 Existing Cables Not Populated in the SLICE Database May 4, 2004

00221528 Fire Brigade Turnout Gear/SCBA Location May 12, 2004

00230758 Wrong Unit Designation on Fire Pre-Plan TB-71 June 23, 2004

00293853 Discrepancy On Fire Pre-plan TB 112 Information January 25, 2005

00464665 NRC Terminates FP Manual Action Rulemaking March 10, 2006

00478821 Fire Pre-plans RB-19 and TB-71 Have Incorrect Information April 14, 2006

DRAWINGS

Number Description or Title Date or Revision

4E-7573C S/D ATWS Recirc Pump Trip Sys Div I and II - 0

Part 3

4E-6613A S/D MOVs 1/2-2901-6 and 7 SSD System F

4E-1344 S/D 4160V Buses 13-1 and 14-1 Main Feed J

Breakers

M-3 General Arrangement Main Floor Plan K

M-4 General Arrangement Mezzanine Floor Plan H

M-6 General Arrangement Basement Floor Plan C

M-70 Diagram of SSMP System W

QDC-0000-E-1038, App R AC Distribution Diagram 0

Attach F

QDC-0000-E-1038, App R 250Vdc Distribution Diagram, Rev 0 November 14, 2000

Attach F, Pg 2 of 3

QDC-0000-E-1038, App R 125Vdc Distribution Diagram, Rev 0 November 13, 2000

Attach F, Pg 3 of Final

ENGINEERING ACTION PLANS

Number Description or Title Date or Revision

00-00-24, Rev 0 SLICE Program and Backlog Reduction February 19, 2001

00-00-24, Rev 1 SLICE Program and Backlog Reduction March 28, 2001

00-00-24, Rev 2 SLICE Program and Backlog Reduction October 15, 2004

ENGINEERING CHANGES (ECs)

Number Description or Title Date or Revision

354100 001 Abandonment of CO2 Hose Reels December 9, 2005

0000360804 Address Triennial Fire Inspection Tray Ampacity Issues May 9, 2006

Related to Tray Nodes 261M1, 320B, 323M, 325B, and 329B

0000360805 Evaluate SLICE Cable Ampacity Issues in Response to May 8, 2006

Triennial FP Inspection Request

EVALUATIONS

Number Description or Title Date or Revision


Portable Fire Extinguishers (NFPA 10 and 10A) May 24, 1985

A-4 Attachment

EVALUATIONS

Number Description or Title Date or Revision


Std for Installation of Standpipe and Hose Systems (NFPA 14) June 19, 1985


Fire Doors in Nuclear SR Areas April 9, 1987


FP Survey of HVAC Systems in Computer/Nuclear SR Areas 8

IMPAIRMENT/REMOVAL PERMITS

Number Description or Title Date or Revision


List of Plant FP Impairments April 26, 2006

PROCEDURES

Number Description or Title Date or Revision

CC-AA-211 Fire Protection Program 2

CC-AA-302 Control of the Cable Management Database 2

QCOA 0010-12 Fire/Explosion 27

QCARP 0030-01 TB-III Injection with SSMP and Bringing the Unit to Cold 8

SD

QCARP 0040-01 13-1 Injection with SSMP and Bringing the Unit to Cold 7

SD

QCARP 0040-02 24-1 Injection with SSMP and Bringing the Unit to Cold 9

SD

QCARP 0050-01 SB-1-1 Injection with SSMP and Bring the Unit to Cold 10

SD

QCMMS 4100-61 Fire Door Inspection 11

QCOP 2900-02 SSMP System Start Up 18

QOP 6500-10 Local Control of 4160 and 480V MOV Circuit Breakers 8 and 9

REFERENCES

Number Description or Title Date or Revision


Pre-fire Strategies for Reactor Bldg and Turbine Bldg April 26, 2006

FPR Vol 1 and 2 QCNPSs Fire Protection Report October 2005

GE Spec 22A2501 GE Specification for Domestic Turnkey Projects 0

GE-NE-T43-00002 Original SSD Paths for the BWR 1

-00-01-R01

GE-NE-T43-00002 BWROG Position on the Use of Safety Relief Valves 1

-00-03-R01 and Low Pressure Systems as Redundant SSD Paths

NFPA 14 Standpipe and Hose Systems 1974

NFPA 10 Portable Fire Extinguishers 1975

Q-ECDS-960134 QCNPS Cable Ampacity Report July 30, 1996

SandL LTR ComEd SLICE Discrepancy Resolution Project December 23, 1999

D-3477E

SandL LTR ComEd QCNPS Ampacity Evaluation Info July 2, 1996

Q-2148E

NUREG/CR-6681 Ampacity Derating and Cable Functionality for August 2000

(SAND2000-1825) Raceway Fire Barriers

SandL Program DQAMPAC Users Manual - Revised SLICE Ampacity August 31, 1995

No. 03.7.528-1.1 Software

A-5 Attachment

A-6 Attachment

LIST OF ACRONYMS USED

AC or ac Alternating Current

ADAMS Agency-Wide Document Access and Management System

App Appendix

ATTN Attention

BWROG Boiling Water Reactor Owners Group

CFR Code of Federal Regulations

CR Control Room

DC or dc Direct Current

DPR Demonstration Power Reactor

DRP Division of Reactor Projects

DRS Division of Reactor Safety

FP Fire Protection

FPP Fire Protection Program

GL Generic Letter

FRN Federal Register Notice

IMC Inspection Manual Chapter

IP Inspection Procedure

IPEEE Individual Plant Examination of External Events

IR Inspection Report

k kilo

LLC Limited Liability Company

MOV Motor Operated Valve

NFPA National Fire Protection Association

NRC Nuclear Regulatory Commission

NRR Office of Nuclear Reactor Regulation

NUREG NRC Technical Report Designation

PARS Publicly Available Records

QCNPS Quad Cities Nuclear Power Station

RIII Region III

RHRSW Residual Heat Removal Service Water

S/D Schematic Diagram

SandL Sargent and Lundy

SD Shutdown

SDP Significance Determination Process

SER Safety Evaluation Report

SLICE Sargent and Lundy Interactive Cable Engineering

SR Safety Related

SSA Safe Shutdown Analysis

SSCA Safe Shutdown Capability Assessment

SSCs Structures, Systems and Components

SSD Safe Shutdown

SSMP Safe Shutdown Makeup Pump

SSSA Safe Shutdown System Analysis

UFSAR Updated Final Safety Analysis Report

URI Unresolved Item

A-7 Attachment

A-8 Attachment