LR-N980302, Monthly Operating Rept for May 1998 for Hope Creek Generating Station,Unit 1

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for May 1998 for Hope Creek Generating Station,Unit 1
ML20249B599
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 05/31/1998
From: Bezilla M, Ritzman R, Todd F
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
LR-N980302, NUDOCS 9806230358
Download: ML20249B599 (4)


Text

. *

- ~

. ~O PSEG Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038 0236 Nuclear Business Unit 1

I JUN 121998 LR-N980302 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

. MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION UNIT 1 DOCKET NO. 50-354 in compliance veith Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for May 1998 are being forwarded. No changes, tests, and experiments were implemented during May 1998 that require a summary to be forwarded to you pursuant to the requirements of 10CFR50.59(b).

Sincerely,

) FoZ M 6G2)LLJ)

Mark B. Bezilla General Manager-Hope Creek Operations RAR/mw Attachments C Distribution '

. . en

/<c at o 9806230358 980531 PDR ADOCK 05000354 R PDR The powerisin voor hands.

95-2166 REV 6.94

1 INDEX i . .

NUMBER SECTION OF PAGES l

Operating D a ta Report. . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 l

i Monthly Ope ratin9 S u mma y. .. . . . . . . . ... . . ... .... .. . . ... . .. . . .. .. .. . . .. . . . . . . . . . . . . . . . . . . . . . . .. 1 l

I i-

~

DOCKET NO.: 50-354 l

. . UNIT: Hope Creek DATE: 06/10/98 COMPLETED BY: F.Todd TELEPHONE: (609)339-1316 i Reporting Period May 1998 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net) 1031 Month Year-to-date Cumulative No. of hours reactor was critical 744 l 3623 l 84163 l l No. of hours generator was on line (service 744 3623 82693 hours)

Unit reserve shutdown hours 0 l0 l0 l Net Electrical Energy (MWH) 776164 l 3752270 l 83649422 l l

UNIT SHUTDOWNS l NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE F= FORCED (HOURS) (1) SHUTTING ACTION / COMMENT j S= SCHEDULED DOWN THE 1 l REACTOR (2)

N/A l

(1) Reason (2) Method l A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip / Scram C - Refueling 3 - Automatic Trip / Scram D - Regulatory Restriction 4 -Continuation E - Operator Training / License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

~

DOCKET NO.: 50-354

, . UNIT: Hope Creek DATE: 06/10/98 COMPLETED BY: R. Ritzman TELEPHONE: (609) 339-1445 Summary Of Monthly Operating Experience

. Hope Creek entered the month of May at approximately 100% reactor power.

  • Reactor power was reduced on May 30 for control rod pattern adjustments.

Reactor power was returned to 100% later that day.

. At the end of the month, Hope Creek had completed its 169 consecutive day of continuous power operation.