DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 09/04/97 COMPLETED BY:

F.

Todd TELEPHONE:

(609) 339-1316 OPERATING DATA REPORT OPERATING STATUS 1

Reporting Period August 1997 Hours in Report 744 Period 2

Currently Authorized Power Level (MWt) 3293 Max Dependable Capacity (MWe-Net) 1031 Design Electrical Rating (MWe-Net) 1067 3

Power level to which restricted (if any) (MWe Net)

None 4

Reason For Restriction (if any)

This Month Yr To Cu_mulative Date 5

No. of hours reactor was critical 744 5831 79554 6

Reactor reserve shutdown hours 0.0 0.0 0.0 7

Hours generator on line 744 5831 78391 8

Unit reserve shutdown hours 0.0 0.0 0.0 9

Gross thermal energy generated (MWH) 2048709 18307867 250176114 10 Gross electrical energy generated (MWH) 672460 6116560 83010773 11 Net electrical energy generated (MWH) 638897 5863474 79342870 12 Reactor Service factor 100.0%

100.09 84.8%

13 Reactor availability factor 100.0V 100.0%

84.8%

14 Unit Service Factor 100.0V 100.0t 83.6%

15 Unit Availability Factor 100.0V 100.0%

83.6%

16 Unit Capacity Factor (MDC) 83.34 97.5V 82.0%

17 Unit Capacity Factor (DER) 80.5%

94.2k 79.3%

18 Unit Forced Outage Rate 0.0%

0.0%

4.1%

19 Shutdowns scheduled over next 6 months (type, date, duration):

Refueling Outage, September 13, 1997, 55 Days (The outage was scheduled to begin on September 13, but began on September 11 due to a manual plant scram.)

20 If shutdown at end of report period, estimated date of Startup R

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 09/04/97 COMPLETED BY:

F.

Todd TELEPHONE:

(609) 339-1316 OPERATING DATA REPORT UNIT SHUTDOWNS AND POWER REDUCTIONS MONTH AUGUST 1997 METHOD OF SHUTTING DOWN THE TYPE REACTOR OR F= FORCED DURATION REASON REDUCING CORRECTIVE NO.

DATE S= SCHEDULED (HOURS)

(1)

POWER ACTION / COMMENT (2) 0

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 09/04/97 COMPLETED BY:

F. Todd TELEPHONE:

(609) 339-1316 AVERAGE DAILY UNIT POWER LEVEL MONTil-AUGUST 1997 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)

(MWe-Net)

.1 915 17 841 2

907 18 848 3

902 19 852 4

902 20 844 5

903 21 839 6

901 22 840 7

890 23 838 8

889 24 834 9

883 25 829 10 876 26 822 11

-872 27 816 12

,867 28 813 13 859 29 810 14 861 30 808 15 855 31 801 16 842

=

DOCKET No.: 50-354 UNIT: Hope Creek DATE: 09/04/97 COMPLETED BY:

R. Ritzman TELEPHONE:

(609) 339-1445 REFUELING INFORMATION HONTH AUGUST 1997 1.

Refueling information has changed from last month:

Yes X

No 2.

Scheduled date for next refueling (RF07) : 9/13/97 (The outage was scheduled to begin on September 13, but began on September 11 due to a manual plant scram.)

3.

Scheduled date for restart following refueling:

11/5/97 4A. Will Technical Specification changes or other license amendments be required?

Yes X

No B.

Has the Safety Evaluation covering the COLR been reviewed by the Station Operating Review Committee (SORC)?

Yes No X

If no, when is it scheduled?

To Be Determined for Cycle 8 COLR 5.

Scheduled date (s) for submitting proposed licensing action:

A License Change Request was submitted to the NRC on July 16, 1997 6.

Important licensing considerations associated with refueling:

The above required LCR concerns the Technical Specification Safety Limit Minimum Critical Power Ratio for Cycle 8.

7.

Number of Fuel Assemblies:

A.

Incore 764 B.

In Spent Fuel Storage 1472 8.

Present licensed spent fuel storage capacity: 4006 Future spent fuel storage capacity:

4006 9.

Date of last refueling that can be discharged to spent fuel pool assuming the present licensed capacity:

5/3/2006(EOC13)

(Does allow for full-core off-load)

(Assumes 244 bundle reloads every 18 months until then)

(Does not allow for smaller reloads due to improved fuel)

DOCKET NO.: 50-354 UNIT:

lope Creek j

DATE: 09/04/97 COMPLETED BY:

F. Todd TELEPHONE:

(609) 339-1316 MQNTHLY OPERATING SUMIMBY MONTH AUGUST UJl The Hope Creek Generating Station started the month at e

88% power, continuing the end of cycle coast down.

  • At the end of the month, the unit was at 78% power and had been on-line for 297 days.