LR-N17-0134, In-Service Inspection Activities, 90-Day Report

From kanterella
Jump to navigation Jump to search
In-Service Inspection Activities, 90-Day Report
ML17240A114
Person / Time
Site: Salem PSEG icon.png
Issue date: 08/28/2017
From: Martino P
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N17-0134
Download: ML17240A114 (5)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, NJ 08038-0236 PSEG ASME Code Case N-532-5 LR-N17-0134 AUG 2,8 2017 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington DC 20555-0001 Salem Generating Station Unit 2 Renewed Facility Operating License DPR-75 NRC Docket No. 50-311

Subject:

In-Service Inspection Activities- 90-Day Report This letter submits the Owner's Activity Report for In-Service Inspection (lSI) activities conducted at the Salem Generating Station Unit 2 during the twenty-second refueling outage.

This report is submitted in accordance with Code Case N-532-5, "Repair/Replacement Activity Documentation Requirements and In-Service Summary Report Preparation and Submission Section XI, Division 1," and within its ninety day reporting requirement. to this letter contains the required Salem Unit 2 Owner's Activity Report.

There are no commitments contained in this letter.

Should you have any questions regarding this submittal, please contact Mr. Thomas Cachaza at 856-339-5038.

Sincerely,

~¥/ttJD"wt&f-1 r /OrL I'MAMAJo.

Patrick Martino Plant Manager- Salem Salem Generating Station Enclosure

LR-N17-0134 Page 2 cc: Mr. D. Dorman, USNRC -Administrator-Region 1 Mr. R. Ennis, USNRC -Licensing Project Manager-Salem Mr. P. Finney, USNRC Senior Resident Inspector Mr. P. Mulligan, Chief, NJBNE Mr. T. Cachaza, Salem Commitment Tracking Coordinator Mr. L. Marabella, Corporate Commitment Tracking Coordinator Mr. M. Washington, Chief Inspector- Occupational Safety and Health Bureau of Boiler and Pressure Vessel Compliance LR-N17-0134 Salem Unit 2 Owner's Activity Report - S2RF022 In Accordance With ASME Section XI Code Case N-532-5

FORM OAR-1 OWNER'S ACTIVITY REPORT ReportNumber~S~2~R~F~0~2~2~-------------------------------------------------------

Piant Salem Generating Station Unit No. _,2=---------- Commercial service date October 13, 1981 Refueling outage no. _.2"-'2...__ _ _ _ _ ___

(If applicable)

Current inspection interval lSI -Fourth (41h). CIS I - Second (2nd)

(1st, 2nd, 3rd, 4th, other)

Current inspection period lSI -Second (2nd). CIS I - Second (2nd)

(1st, 2nd, 3rd)

Edition and Addenda of Section XI applicable to the inspection plans._.2..,0~0"-4"-"'E'""d"'it,_,io"-'n.,__ _ _ _ _ _ _ _ _ _ _ __

Date and revision of inspection plans lSI Revision 2, February 2016 (CISI Revision 1. July 2015)

Edition and Addenda of Section XI applicable to repair/replacement activities, if different than the inspection plans _ _ __

Same as lSI Plans

  • Code Cases used for inspection and evaluation: N-460 N-532-5 & N-706-1

~~~~~(ff~~~pli~ca~blo~,i~nc~lud~ln~g~~.~~~m~od-rrl-ed_ey_C_as_a_N~-~-a-nd-la-ter-re-vl-slo-ns_)__________

CERTIFICATE OF CONFORMANCE I certify that (a) the statements made in this report are correct; (b) the examinations and tests meet the Inspection Plan as required by the ASME Code,Section XI; and (c) the repair/replacement activities and evaluations supporting the completion of S2RF022 n XI. (retueun 9 outage number)

CERTIFICATE OF INSERVICE INSPECTION l, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and employed by Hartford Steam Boiler of Hartford. CT have inspected the items described in this Owner's Activity Report, and state that, to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section XI.

By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair/replacement activities and evaluation described in this report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.

Christooher M Mi~ ~ *-~~mmission NB 15537 A N I R Inspector's Signature

~~~(~Na~tio~nawiB~oa~rd~N~um~b~erwan~d~En-doc-s-em-en_ij___________

Date 8(1'(('2-0()

FORM OAR-1 OWNER'S ACTIVITY REPORT TABLE1 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE Exam Item Item Description Evaluation Description Category Number B-N-1 B13.10 Reactor Pressure Vessel Operability Assessment for As-Found Clevis Insert Bolts Lower Radial Support at Salem Unit 2 and Postulated Condition at Salem Unit 1 Clevis Assembly at 60°, - Order 70193788 two Clevis Insert Bolts were identified as degraded TABLE2 ABSTRACT OF REPAIR/REPLACEMENT ACTIVITIES REQUIRED FOR CONTINUED SERVICE Item Description of Date Repair/Replacement Code Class Description Work Completed Plan Number 2 Section XI Augmented Replaced 12" Residual 06/03/2017 60130174 Surface examination Heat Removal Piping from revealed surface indications 2RH26 to Containment that exceeded atceptance Penetration #16 criteria on 12" Residual Heat Removal system piping due to Chloride Stress Corrosion Cracking 3 Service Water leakage was Replaced 0.37S" stainless 10/13/2016 60127558 identified in 0.37S" stainless tubing and fittings to steel tubing and weld for the 22SW7S flow transmitter 22SW7S 22 CFCU Outlet Flow Transmitter, <1 dpm 3 Service Water leak directly Replaced 0.2SO" stainless 9/24/2016 60131369 downstream of valve tubing and fittings to 2SW446 on 0.250" stainless 2SW446 steel tubing off of 25 CFCU outlet piping.

1 Reactor Vessel Internals Replaced 9 degraded 06/03/2017 60130323 Baffle-Former Bolt 100% Baffle-Former Bolts and Visual and Ultrasonic (UT) an additional120 anti-examinations (832 Bolts), UT cluster Baffle-Former examinations identified 9 Bolts

~~--------~-------- ----------------------- ----

-degradedli~----

---~~----

1 No. 21 Steam Generator A total of 4 tubes were 05/28/2017 50169603 Tubing Eddy Current repaired, (3 tubes Inspections plugged, 1 tube plugged and stabilized) 1 No. 22 Steam Generator A total of 3 tubes were 05/28/2017 50169660 Tubing Eddy Current repaired, (3 tubes rnspecti'ons prugged) 1 No. 23 Steam Generator A total of 5 tubes were 05/28/2017 50169661 Tubing Eddy Current repaired, (3 tubes Inspections plugged, 2 tubes plugged and stabilized) 1 No. 24 Steam Generator A total of 2 tubes were 06/25/2017 50169657 Tubing Eddy Current repaired, (1 tube plugged, Inspections 1 tube plugged and stabilized)