LR-N03-0224, April 2003 Monthly Operating Report for Salem Generating Station Unit 2

From kanterella
Jump to navigation Jump to search
April 2003 Monthly Operating Report for Salem Generating Station Unit 2
ML031420573
Person / Time
Site: Salem PSEG icon.png
Issue date: 05/14/2003
From: Waldinger L
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N03-0224
Download: ML031420573 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 MAY 1 4 2003 O PSEG NuclearLLC LR-N03-0224 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for April 2003 are being forwarded.

Sincerely, Lon Waldinger Operations Director JCN Attachments C Distribution

,,-,'T

) 6 0 95-2168 REV. 7/99

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 5/5103 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period April 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1131 Maximum Dependable Capacity (MWe-Net) 1092 Month Year-to-ciate Cumulative No. of hours reactor was critical 717 2810 123226 No. of hours generator was on line (service 705 2797 119755 hours)

Unit reserve shutdown hours 0 0 0 Net Electrical Energy (MWH) 781894 3137839 122326814 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE

.___ _ _ _ _ _REACTOR (2) 1 4/1/03 F 14 H 4 Multiple circulators ols due to high grass levels 3/31/03 (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H- Other

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 5/5/03 COMPLETED BY: J. Naale TELEPHONE: (856) 339-3171 Summary Of Monthly Operating Experience

  • On April 1 the Unit returned to power from a shutdown due to 4 circulators out of service.