December 2005 Monthly Operating Report for Salem Generating Station Unit 2
ML060300326
Person / Time
Site: Salem PSEG icon.png
Issue date: 01/16/2006
From: Joyce T
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N06-0016
Download: ML060300326 (4)


Text

1

.: A. PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JAN I 6 2006 O PSEG Nuclear LLC LR-N06-001 6 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT SALEM GENERATING STATION - UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for December 2005 are being forwarded.

Sincerely, Thomas P. Joyce Site Vice President Salem Generating Station Attachments C Distribution "I't'-Z-Lf 95-2168 REV. 7/99

A.

Document Control Desk M r i; 2006 LR-N06-00 16 C: Mr. S. Collins, Administrator - Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. S. Bailey, Licensing Project Manager- Salem U. S. Nuclear Regulatory Commission Mail Stop 08B1 Washington, DC 20555 USNRC Senior Resident Inspector - Salem (X24)

Mr. K. Tosch, Manager IV Bureau of Nuclear Engineering PO Box 415 Trenton, New Jersey 08625

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 01/10/06 COMPLETED BY: J.Wearne TELEPHONE: (856) 339-5081 Reporting Period: December OPERATING: DATA REPORT Month Year-to-date Cumulative Design Electrical Rating (MWe-Net) 1131 _ _l l Maximum Dependable Capacity (MWe-Net) 1116 _ _ _ _I No. of hours reactor was critical 744 7936 143871 No. of hours generator was on line 744 7897 140154 (service hours)

Unit reserve shutdown hours 0 0 1O 0 Net Electrical Energy (MWH) 844504 8886027 144970377 Unplanned Transients >20% 1 1 UNIT SHUTDOWNS METHOD OF TYPE SHUTTING F=FORCED DURATION REASON DOWN THE CORRECTIVE NO. DATE S=SCHEDULED (HOURS) (1) REACTOR ACTION/COMMENT (2)

(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 01/10/06 COMPLETED BY: J.Wearne TELEPHONE: (856) 339-5081 Summary of Monthly Operating Experience

  • Salem 2 began the month at approximately 100% power.
  • On 12/12/05, power was reduced to approximately 89% for turbine valve testing. Power was subsequently reduced to approximately 64% power due to the 22 West Reheat Stop Valve 22RS 11 not reopening. Repairs were made to the valve and power was returned to approximately 100% on 12/16/05 and remained at 100% for the rest of the month.