LR-N04-0256, May 2004 Monthly Operating Report for Salem Generating Station Unit 1

From kanterella
Jump to navigation Jump to search
May 2004 Monthly Operating Report for Salem Generating Station Unit 1
ML041740633
Person / Time
Site: Salem PSEG icon.png
Issue date: 06/14/2004
From: Fricker C
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N04-0256
Download: ML041740633 (3)


Text

PSEG Nuclear LLC__

P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JUN 1 4 2004 PSEG O NuclearLLC LR-N04-0256 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 1 Technical Specifications, the operating statistics for May 2004 are being forwarded.

Sincere%

Sa em Plant Manager Attachments C Distribution j'e

,--I'r 0 q 95-2168 REV. 7/99

DOCKET NO.: 50-272 UNIT: Salem 1 DATE: 6/7/04 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period May 2004 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1130 I Maximum Dependable Capacity (MWe-Net) 1096 l 7ili Month lYear-to-date lCumulative l No. of hours reactor was critical 58 2214 l152879 No. of hours generator was on line (service 0 2156 l148109 hours)

Unit reserve shutdown hours 0 0 0 Net Electrical Energy (MWH) 0 2381335 151381983 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 1 5/1/04 S 744 Hrs. C 4 16' Refuel Outage 5/31/04 _

(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-272 UNIT: Salem 1 DATE: 617/04 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 SummarV Of Monthly Operating Experience Salem 1 spent the entire month in a refueling outage. At the end of the month, the reactor was critical but the plant was not yet back on-line.