LR-N04-0302, June 2004 Monthly Operating Report from Salem Generating Station Unit 1
| ML042030259 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 07/13/2004 |
| From: | Fricker C Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LR-N04-0302 | |
| Download: ML042030259 (6) | |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JUL 1 3 2004 o PSEG Nuclear LLC LR-N04-0302 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 1 DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 1 Technical Specifications, the operating statistics for June 2004 are being forwarded.
Sincerel r. Fricker Sa m Plant Manager Attachments C Distribution
'e -ZA 95-2168 REV. 7/99
DOCKET NO.:
UNIT:
. DATE:
COMPLETED BY:
TELEPHONE:
50-272 Salem 1 7/8/04 F. Todd (856) 339-1316 Reporting Period June 2004 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 a-_
1096 Month Year-to-date Cumulative 695 2909 153575 619 2775 148727 0
0 0
605322 2986657 151987305 UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/
F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 1 611/04 S
71.6 Hrs.
C 4
16k Refuel Outage 613/04 2
6119/04 F
13.0 Hrs.
B I
Digital EHC Driver Card Failure 6/19104 3
6123104 F
16.5 Hrs.
B 1
Repair #11 Exciter Bearing 6 /2 5 /0 4 (1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
DOCKET NO.: 50-272 UNIT: Salem 1
,,DATE:
7/8104 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience
- Salem Unit One began the month off-line due to a refuel outage.
- The unit was placed on-line on June 3 and reached 100% power on June 10.
- On June 17, power was reduced to approximately 46% for maintenance on a charging pump check valve. On June 18, power was further reduced to approximately 17% and taken off-line due to a Digital Electro-Hydraulic Control Driver Card Failure. The plant was placed back on-line on June 19 and power was restored to 100% on June 20.
- On June 23, power was reduced to approximately 17% and the plant was taken off-line to repair an Exciter Bearing. The plant was placed back on-line on June 24 and power was restored to 100% on June 25.
- On June 29, power was reduced to approximately 85% due to a 500kv emergency line outage and remained there at the end of the month.
- At the end of the month, Salem 1 completed 6 days of continuous on-line operation.
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JUL 1 3 2004 LR-N04-0303 o PSEG NuclearLLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for June 2004 are being forwarded.
S'ncre J. Fricker S lem Plant Manager Attachments C Distribution 95-2168 REV. 7/99
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-311 Salem 2 7/8/04 F. Todd (856) 339-1316 Reporting Period June 2004 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1131 1116 Month Year-to-date I Cumulative 720 4132 131966 719 4113 128425 0
0 0
795668 4581965 131866552 UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTIONI F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 2 6/1/04 F
1 hr.
A 4
2B 230 Vital Bus Transformer Failure 611104 (1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual TriplScram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
DOCKET NO.: 50-311 UNIT: Salem 2 ADATE: 7/8/04 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience Salem Unit 2 started the month in an outage due to a 230 Vital bus transformer failure. The unit came n-line on June 1, reaching 100%
power on June 2.
- On June 29, power was reduced to approximately 59% due to a 500kv line outage. Power was restored to 100% on June 30.
- At the end of the month, Salem 2 completed 29 days of continuous on-line operation.