Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 f

FEB 1 7 2004 0m PSEG NuclearLLC LR-N04-0060 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLYPOPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit I Technical Specifications, the operating statistics for Januari 2004 ar~e being forwarded.

Sincfely,
a.

r

-i'l/ F Ass

,!is

,,;/.,1.t,,,,,

Saem~lla~nt,121~agr.;

r e t; li ` ;

Attachments.

C Distribution.

..\\;k i,.

W r. -

1, L

,i.

I i

I

, I

.~.~

I J

I

,' -'\\j ,, -2, 

95-2168 REV. 7/99

S..

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-272 Salem I 2/10/04 F. Todd (856) 339-1316 Reporting Period January 2004 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 1096 Month 744 744 151410 744 744 146697 0

0 0

804691 804691 149805339 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS)

(1)

SHUlTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)

(1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H-Other 1-Manual 2-Manual Trip/Scram 3-Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-272 UNIT: Salem I DATE: 2110/04 COMPLETED BY: R. Ritzman TELEPHONE:

(856) 339-1445 Summary Of Monthly Operating Experience

  • Salem I entered the month at approximately 82% power due to circulators being out of service for maintenance and waterbox cleaning.
  • Salem I conducted several down powers to support circulator maintenance and condenser waterbox cleaning during the month. The unit remained above 80% reactor power throughout the month.
  • At the end of the month, Salem I completed 104 days of continuous on-line operation.