LR-N04-0060, January 2004 Monthly Operating Report for Salem, Unit 1
| ML040550430 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 02/17/2004 |
| From: | Fricker C Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LR-N04-0060 | |
| Download: ML040550430 (3) | |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 f
FEB 1 7 2004 0m PSEG NuclearLLC LR-N04-0060 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLYPOPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit I Technical Specifications, the operating statistics for Januari 2004 ar~e being forwarded.
- Sincfely,
- a.
r
-i'l/ F Ass
,!is
,,;/.,1.t,,,,,
Saem~lla~nt,121~agr.;
r e t; li ` ;
Attachments.
C Distribution.
..\\;k i,.
W r. -
1, L
,i.
I i
I
- , I
.~.~
I J
I
,' -'\\j ,, -2,
95-2168 REV. 7/99
S..
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-272 Salem I 2/10/04 F. Todd (856) 339-1316 Reporting Period January 2004 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 1096 Month 744 744 151410 744 744 146697 0
0 0
804691 804691 149805339 UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/
F=FORCED (HOURS)
(1)
SHUlTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)
(1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H-Other 1-Manual 2-Manual Trip/Scram 3-Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
DOCKET NO.: 50-272 UNIT: Salem I DATE: 2110/04 COMPLETED BY: R. Ritzman TELEPHONE:
(856) 339-1445 Summary Of Monthly Operating Experience
- Salem I entered the month at approximately 82% power due to circulators being out of service for maintenance and waterbox cleaning.
- Salem I conducted several down powers to support circulator maintenance and condenser waterbox cleaning during the month. The unit remained above 80% reactor power throughout the month.
- At the end of the month, Salem I completed 104 days of continuous on-line operation.