LR-N06-0078, January 2006 Monthly Operating Report for Salem, Unit 2

From kanterella
Jump to navigation Jump to search
January 2006 Monthly Operating Report for Salem, Unit 2
ML060540432
Person / Time
Site: Salem PSEG icon.png
Issue date: 02/16/2006
From: Joyce T
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N06-0078
Download: ML060540432 (4)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 FEB 1 6 2006 LR-N06-0078 o PSEG Nuclear LLC United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT SALEM GENERATING STATION - UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for January 2006 are being forwarded.

Sincerely, Thomas P. Joyce Site Vice President Salem Generating Station Attachments C Distribution 4-) d L-11 

-1 95-2168 REV. 7/99

Document Control Desk LR-N06-0078 FEB 16i200 C:

Mr. S. Collins, Administrator-Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. S. Bailey, Licensing Project Manager - Salem U. S. Nuclear Regulatory Commission Mail Stop 08B1 Washington, DC 20555 USNRC Senior Resident Inspector - Salem (X24)

Mr. K. Tosch, Manager IV Bureau of Nuclear Engineering PO Box 415 Trenton, New Jersey 08625

I DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

5 0-3 11 Salem 2 02 /03/0 6 J. Hiles (856)339-3068 Reporting Period: January OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH)

Unplanned Transients >20%

Month Year-to-date Cumulative 1131 1116 744 744 144615 744 744 140898 0

0 0

X 850994 850994 145821371 0

0 UNIT SHUTDOWNS METHOD OF TYPE SHUTTING F=FORCED DURATION REASON DOWN THE CORRECTIVE NO.

ElATE S=SCHEDULED (HOURS)

(1)

REACTOR ACTION/COMMENT (2)

(1) Reason (2)

Method A

B C

D E

F G

H Equipment Failure (Explain)

Maintenance or Test Refueling Regulatory Restriction Operator Training/License Examination Administrative Operational Error (Explain)

Other 1 -

Manual 2 -

Manual Trip 3 -

Automatic Trip/Scram 4 -

Continuation 5 -

Other (Explain)

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-311 Salem 2 02/08/2006 J.Wearne (856) 339-5081 Summary of Monthly Operating Experience

  • Salem 2 began the month at approximately 100% power and remained at approximately 1(10% throughout the month.