February 2004 Monthly Operating Report for Salem, Unit 1
ML040830629
Person / Time
Site: Salem PSEG icon.png
Issue date: 03/11/2004
From: Fricker C
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N04-0110
Download: ML040830629 (3)


Text

PSEG Nuclear LLC

- - - 3 P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 MAR 1 1 2004 0 PSEG Nuclear LLC LR-N04-01 10 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT i DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit I Technical Specifications, the operating statistics for February 2004 are being forwarded.

Sincerely, Carl a. Fricker Salem Plant Manager Attachments C Distribution

,<0eD 95-216S REV. 7/99

0, I .

DOCKET NO.: 50-272 UNIT: Salem 1 DATE: 3/5/04 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period February 2004 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1130 Maximum Dependable Capacity (MWe-Net) 1096 Month Year-to-date Cumulative No. of hours reactor was critical 696 1440 152106 No. of hours generator was on line (service 696 1440 147393 hours)

Unit reserve shutdown hours 0 o0 0 Net Electrical Energy (MWH) 772011 1576702 150577350 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION)

F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)

_ _ =

(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-272 UNIT: Salem 1 DATE: 3/5/04 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

  • Salem 1 entered the month at 100% power.
  • Salem 1 conducted several down powers to support circulator maintenance and condenser waterbox cleaning during the month. The unit remained above 80% reactor power throughout the month.
  • At the end of the month, Salem 1 completed 133 days of continuous on-line operation.