November 2002 Monthly Operating Report for Salem Generating Station Unit 2
ML023600193
Person / Time
Site: Salem PSEG icon.png
Issue date: 12/13/2002
From: Waldinger L
Public Service Electric & Gas Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N02-0420
Download: ML023600193 (3)


Text

PSEG Nuclear LLC P 0 Box 236, Hancocks Bridge, New Jersey 08038-0236 DEC 1 3 2002 LR-N02-0420 o PSEG NuclearLLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for November 2002 are being forwarded.

Sincerely, Lon Waldinger Operations Director RAR Attachments C Distribution 37 95-2168 REV 7/99

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 12/9/02 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period November 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1131 Maximum Dependable Capacity (MWe-Net) 1092 Month Year-to-date Cumulative No. of hours reactor was critical 720 6959 119672 No. of hours generator was on line (service 720 6876 116214 hours)

Unit reserve shutdown hours 0 0 0 Net Electrical Energy (MWH) 802061 7533363 118354904 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)

(1) Reason (2) Method A - Equipment Failure (Explain) 1 -Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 12/9/02 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

"* Salem 2 began the month at 100% reactor power.

"* On November 23, power was reduced to approximately 70% due to an emergent 5014 500 KV Line Outage and was returned to 100% power on November 24.

"* At the end of the month, Salem 2 completed 197 days of continuous on line operation.