A UNITED STATES 8"
%
NUCLEAR REGULATORY COMMISSION
$
$
REGION ll e,
1G1 MARIETTA ST N.W., SUITE 3100
%
ATLANTA, GEORGIA 303o3
- ens *
Report Nos. 50-416/82-22 and 50-417/S2-07
.
'
Licensee: Mississippi Power and Light Company Jackson, MS 39205 Facility Name: Grand Gulf Docket Nos. 50-416 and 50-417 License Nos. CPPR-ll8 and CPPR-119 Inspection at Grand Gulf site near Port Gibson, MS Inspector:
I Y~
~D A. B. Ruff Date Signed
_
V Y - E" b Approved by:_
T. E Colon, Section Chief Date Signed Engineering Inspection Branch Division of Engineering and Technical Programs SUMMARY Inspection on March 23-26, 1982 Areas Inspected This routine, unannounced inspection involved 24 inspector-hours on site in the areas of followup on licensee identified item, electrical and instrumentation, cables and terminations, work and work activities.
Results Of the areas inspected, no violations or deviations were identified.
8205040/3(o
[.
.
.
REPORT DETAILS 1.
Persons Contacted Licensee Employees
- G. B. Rogers, Site Manager
- T. H. Cloniger, Project Engineer
- B. C. Lee, QA Representative
- M. A. Lacey. QA Consultant S. Hutchins, Principal Electrical Engineer Other Organizations D. Tokach, QC Representative, Bechtel Power Corporation NRC Resident Inspector
- A. G. Wagner
- Attended exit interview 2.
Exit Interview The inspection scope and findings were summarized on March 26, 1982, with those persons indicated in paragraph 1 above.
3.
Licensee Action on Previous Inspection Findings Not inspected.
4.
Unresolved Items Unresolved items were not identified during this inspection.
5.
Licensee Identified Items (LII)
a.
(Closed) Item 416/79-33-02, " Instrumentation for the PGCC Not to Specifications (PRD 79-21 GE B.O.P. - PGCC)" (10 CFR 50.55(e)).
The final report was submitted on January 9,1981.
The report has been reviewed and determined to be acceptable.
The inspector held discussions with responsible licensee representatives, reviewed supporting documentation, and observed representative samples of work to verify that the corrective actions identified in the report have been initiated.
The instruments have been replaced by GE Field Disposition Instruction (FDI) WA0T and qualification testing is being tracked by MP&L's Corrective Action Request (CAR) 350.
I i
f
.
l
b.
(Closed) Item 416/CDR 81-37 " Defective Spare Woodward Governor for HPCS Diesel Generator" (10 CFR 50.55(e)). The final report was submitted on November 30, 1981. The report has been reviewed and determined to be acceptable.
The inspector held discussions with responsible licensee representatives, reviewed supporting documentation, to verify that the corrective action identified in the report has been completed.
The potentially defective drop lever spring in the Governor was replaced and documented on Maintenance Work Order (MWO) M 22047.
c.
(Closed)
Item 416/81-16-02 and 417/81-08-01 "CDR 416,417/81-14
" Unqualified Material in ASCO Valvc " (10 CFR 50.55(e)).
The final report was submitted on September 30, 1981.
The report has been reviewed. The inspector held discussions with responsible licensee representatives and reviewed supporting documentation. The licensee's documentation indicates that the subject valves are in the Hydraulic Control Unit (HCU) System and that if the valves were to fail they would fail in a safe manner.
In addition, the licensee in their NUREG 0588 response ( AECM 81/231 of 7-1-81) states that HCU Solenoid Valves are not Class IE and, therefore, are not required to be qualified for accident conditions in accordance with NUREG 0588.
d.
(Closed) Item 416/CDR 81-27 " Valve Closure Times" (10 CFR 50.55(e)).
The final report was submitted on January 9,1981. The report has been reviewed and determined to be acceptable.
The inspector held discussions with responsible licensee representatives, reviewed supporting documentation, and observed representative samp'es of work to verify that the corrective actions identified in the report have been completed.
The vent parts in the ASCO Solenoid Valves were too small to allow the cylinders of Henry Pratt Valves to exhaust fast enough to meet the operating time criteria. These solenoid valves were replaced by Construction Work Permit (CWP)-M41-E-47.
f 6.
Electrical and Instrumentation (Cables and Terminations II) - Observation of Work and Work Activities (Unit 1)
An examination was made on the following as-built drawings.
Selected portions in the electrical and instrumentation cables and terminations were examined to insure that the as-built drawing reflected the actual installation. Most of the selected portions used in this examination were determined by field change requests (FCR or FCN) and design change notices (DCN).
a.
1A-408-420, Rev.1, Seismic Conduit Support b.
1A-208-418, Rev.1, Seismic Conduit Support c.
1A-208-023, Rev. 2, Auxiliary Building Seismic Conduit Support d.
1 A-208-201, Rev.1, Auxiliary Building Seismic Conduit Support
-
.
..
.
e.
9645-E-1703, Rev.
Raceway Plan Containment Building -
Elevation 161' - 10", Area II Unit (DCN 23, 24, 27 and FCR-E-1759)
f.
Cable Pull Card 1A3CB21E (DCN 23)
9645-E-1161-13, Rev. 5 Schematic Diagram for B21 Automatic Depressurization System Safety / Relief Valves (FCR-E-1759)
h.
9645-E-0692, Rev. 27, Raceway Plan Containment Building - Elevation 189' - 0", Area 25A (FCR-E-1611 and DCN 32)
1.
FSK-I-0127G-974, Rev. 3, Wall Mounted Support for Pressure Transmitter (FCR-J-340)
j.
FSK-I-0127G-081-C, Rev. 4, Wall Mounted Support for Pressure Switch (FCN-5-568)
Within the areas examined there were no violations identified.