IR 05000373/2002011
| ML023090215 | |
| Person / Time | |
|---|---|
| Site: | LaSalle |
| Issue date: | 11/03/2002 |
| From: | Dave Hills NRC/RGN-III/DRS/OLB |
| To: | Skolds J Exelon Generation Co |
| References | |
| IR-02-011 | |
| Download: ML023090215 (40) | |
Text
November 3, 2002
SUBJECT:
LASALLE COUNTY STATION NRC INSPECTION REPORT 50-373/02-11(DRS);50-374/02-11(DRS)
Dear Mr. Skolds:
On September 27, 2002, the NRC completed an inspection at your LaSalle County Station, Units 1 and 2. The enclosed report documents the inspection findings, which were discussed on September 27, 2002, with Mr. G. Barnes and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. Specifically, this inspection focused on the design and performance capability of the emergency diesel generators and their support systems to ensure that they were capable of performing their required safety-related functions. In addition, the inspection reviewed a sample of permanent plant modifications and changes made under 10 CFR 50.59.
Based on the results of this inspection, the inspectors identified three issues of very low safety significance (Green) that were determined to involve violations of NRC requirements. However, because of their very low safety significance and because they were entered into your corrective action program, the NRC is treating the issues as Non-Cited Violations in accordance with Section VI.A.1 of the NRC s Enforcement Policy. If you deny these Non-Cited Violations, in whole or in part, you should provide a response with a basis for your denial, within 30 days of the date of this inspection report, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with copies to the Regional Administrator, Region III; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the LaSalle County Station. In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
David E. Hills, Chief Mechanical Engineering Branch Division of Reactor Safety Docket No. 50-373; 50-374 License No. NPF-11; NPF-18
Enclosure:
Inspection Report 50-373/02-11(DRS);
50-374/02-11(DRS)
REGION III==
Docket No:
50-373; 50-374 License No:
NPF-11; NPF 18 Report No:
50-373/02-11(DRS); 50-374/02-11(DRS)
Licensee:
Exelon Generation Company, LLC Facility:
LaSalle County Station, Units 1 and 2 Location:
2601 N. 21st Road Marseilles, IL 61341 Dates:
September 9 through 27, 2002 Inspectors:
P. Lougheed, Engineering Inspector D. Chyu, Engineering Inspector G. Hausman, Engineering Inspector H. Walker, Engineering Inspector T. Bilik, Reactor Inspector, Trainee R. Echoles, Reactor Inspector, Trainee H. Anderson, Mechanical Contractor C. Baron, Mechanical Contractor Approved by:
David E. Hills, Chief Mechanical Engineering Branch Division of Reactor Safety
SUMMARY OF FINDINGS
IR 05000373/02-11(DRS), IR 05000374/02-11(DRS); Exelon Generation Company, LLC; on 09/09-27/02, LaSalle County Station; Units 1 & 2. Safety System Design and Performance Capability Inspection.
The inspection was a three week baseline inspection of the design and performance capability of the emergency diesel generators and associated support systems. In, addition, the biennial review of permanent plant modifications and 10 CFR 50.59 evaluations was concurrently performed. The inspection was conducted by regional engineering specialists, with mechanical consultant assistance. The inspection identified three issues of very low significance. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter 0609, Significance Determination Process (SDP). Findings for which the SDP does not apply may be Green, or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000.
Inspection Findings
Cornerstone: Mitigating Systems
- Green.
The inspection team identified a Non-Cited Violation (NCV) of 10 CFR Part 50,
Appendix B, Criterion III, Design Control, that applied to the air start systems for all the emergency diesel generators on both units. Specifically, the inspectors identified that the design basis requirement that the starting air systems have enough air to permit either five (Division 1 and 2 diesel generators) or three (Division 3 diesel generators) normal starts in rapid succession was not translated into specifications, procedures, and instructions. As a result, there was no objective evidence that the required starting air system capacity was being maintained.
The finding was greater than minor based on the potential that degradation of the design basis capability of a starting air system would not be detected by the licensee. Degradation of the design function impacts the base probabilistic risk assessment values used for diesel generator reliability. The finding was of low safety significance because it does not represent an actual loss of the starting air system safety function. (Section 1R21.1)
- Green.
The inspection team identified an NCV of 10 CFR Part 50, Appendix B, Criterion III, that applied to the fuel oil storage tanks for the high pressure core spray diesel generators on both units. Specifically, the inspectors identified that the licensee had incorrectly calculated the necessary volume for the fuel oil storage tanks.
The finding was greater than minor based on the number of deficiencies associated with the diesel generator fuel storage tank capacities requiring preparation of new calculations and corrections to existing calculations, the updated final safety analysis report, the technical specification bases, to procedures, and, possibly, to the technical specifications themselves.
The finding was of low safety significance because it did not represent an actual loss of the high pressure core spray diesel generator fuel oil storage volume as currently required by technical specifications. Furthermore, in the unlikely event that extended operation of the diesel generators was necessary, the licensee would likely be able to get fuel on site before the end of the seven day period. (Section 1R21.2)
- Green.
The inspection team identified an NCV of 10 CFR Part 50, Appendix B, Criterion III, that applied to all the emergency diesel generators on both units. The test control valves on the diesel heads of all five emergency diesels were replaced by valves having a different form, fit, and function. The licensee did not ensure that the change was commensurate with the original design.
The finding was greater than minor because it involved the licensee failing to implement a required regulatory process. The finding was of low safety significance because of a warning currently in the licensees procedure and the fact that the valves are only opened during surveillance. (Section 1R21.2)
REPORT DETAILS
REACTOR SAFETY
Cornerstone: Mitigating Systems
1R02 Evaluations of Changes, Tests, or Experiments
Review of Evaluations and Screenings for Changes, Tests, or Experiments
a. Inspection Scope
The inspectors reviewed twelve 10 CFR 50.59 evaluations and eleven screenings.
These documents were reviewed to ensure consistency with the requirements of 10 CFR 50.59. The inspectors used Nuclear Energy Institute (NEI) 96-07, Guidelines of 50.59 Evaluations, Revision 1, to determine acceptability of the completed evaluations, and screenings. The NEI document was endorsed by the NRC in Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments, November 2000. The inspectors also consulted Inspection Manual, Part 9900, 10 CFR GUIDANCE: 50.59. Documents reviewed during the inspection are listed at the end of the report.
b. Findings
No findings of significance were identified.
1R17 Permanent Plant Modifications
Review of Recent Permanent Plant Modifications
a. Inspection Scope
The inspectors reviewed five permanent plant modifications that were performed by the licensee's engineering staff during the last two years, all but one of which affected the emergency diesel generators or their associated support systems. Therefore, review of the modifications counted for completion of activities under both NRC Inspection Procedures 71111, Attachments 17 and 21. The modifications were reviewed to verify that the completed design changes were in accordance with specified design requirements and the licensing bases and to confirm that the changes did not affect the modified system or other systems' safety function. Calculations which were performed or revised to support the modifications were also reviewed. As applicable to the status of the modification, post-modification testing was reviewed to verify that the system, and associated support systems, functioned properly and that the modification accomplished its intended function. The inspectors also verified that the completed modifications did not place the plant in an increased risk configuration. The inspectors evaluated the modifications against the licensee's design basis documents and the updated final safety analysis report (UFSAR). The inspectors also used applicable industry standards, such as the American Society of Mechanical Engineers Code, to evaluate acceptability of the modifications.
b. Findings
No findings of significance were identified.
1R21 Safety System Design and Performance Capability
Introduction Inspection of safety system design and performance verifies the initial design and subsequent modifications and provides monitoring of the capability of the selected systems to perform design bases functions. As plants age, the design bases may be lost and important design features may be altered or disabled. The plant risk assessment model is based on the capability of the as-built safety system to perform the intended safety functions successfully. This inspectable area verifies aspects of the mitigating systems cornerstone for which there are no indicators to measure performance.
The objective of the safety system design and performance capability inspection is to assess the adequacy of calculations, analyses, other engineering documents, and operational and testing practices that were used to support the performance of the selected systems during normal, abnormal, and accident conditions. The inspection was performed by a team of inspectors that consisted of a team leader, three Region III inspectors, and two mechanical consultants.
The systems selected for review during this inspection were based upon:
- having a high probabilistic risk analysis ranking;
- having had recent significant issues;
- not having received recent NRC review; and
- being interacting systems.
The systems selected were the emergency diesel generators (including the high pressure core spray diesel), and their support systems: diesel generator cooling water, diesel fuel oil and diesel starting air.
The criteria used to determine the systems performance included:
- applicable technical specifications;
- applicable UFSAR sections; and
- the systems' design documents.
The following system and component attributes were reviewed in detail:
System Requirements Process Medium - water, fuel oil, electricity Energy Source - electrical power, fuel oil, air Control Systems - initiation, control, and shutdown actions Operator Actions - initiation, monitoring, control, and shutdown System Condition and Capability Installed Configuration - elevation and flow path operation Operation - system alignments and operator actions Design - calculations and procedures Testing - flow rate, pressure, temperature, voltage, and levels Components The common
- (0) diesel generator cooling water pump was selected for detailed review during the inspection. This component was specifically reviewed for component degradation due to the impact that its failure would have on the plant.
.1 System Requirements
a. Inspection Scope
The inspectors reviewed the updated final safety analysis report, technical specifications, system descriptions, drawings and available design basis information to determine the performance requirements of the emergency diesel generators and their associated support systems. The reviewed system attributes included process medium, energy sources, control systems, and operator actions. The rationale for reviewing each of the attributes was:
Process Medium: This attribute required review to ensure that the emergency diesel generators would supply the required loads following design basis events. To achieve this function, the inspectors also verified that the fuel oil system would transfer sufficient oil to maintain diesel operability, that the diesel generator cooling water system would transfer sufficient heat to maintain diesel operability, and that the air intake and exhaust system provided sufficient oxygen to support combustion.
Energy Sources: This attribute needed to be reviewed to ensure that the emergency diesel generators and associated support systems would start when called upon, and that appropriate valves would have sufficient power to change state when so required.
To achieve this function, the inspectors verified that the interactions between the diesel generators and their support systems were appropriate such that all components would start when needed.
Controls: This attribute required review to ensure that the automatic controls for starting the diesel generators, and associated systems, were properly established.
Additionally, review of alarms and indicators was necessary to ensure that operator actions would be accomplished in accordance with the design.
Operations: This attribute was reviewed because the operators took a number of actions during the monthly and quarterly surveillance tests that had the potential for affecting diesel generator automatic operation. In addition, the operating procedures for loss of offsite power or loss of vital boards permitted the operators to manually load the diesel generators with non-safety related loads. Therefore, operator actions played an important role in the ability of the emergency diesel generators and associated support systems to achieve their safety related functions.
b. Findings
Introduction:
Green. The inspectors identified a Non-Cited Violation (NCV) of 10 CFR Part 50, Appendix B, Criterion III Design Control, that applied to the air start systems for all of the emergency diesel-generators on both units. Specifically, the inspectors identified that the design bases for each of the Division 1, 2, and 3 emergency diesel-generator starting air systems were not translated into specifications, procedures, and instructions. As a result, there was no objective evidence that the required emergency diesel generator starting air system capacity was being maintained.
Discussion: The design basis for the air start system, as stated in the UFSAR and technical specification bases, is to have sufficient air to allow five normal starts in rapid succession (three starts for the high pressure core spray (HPCS) diesels) without use of the air compressors and with an initial air pressure of 200 psig. At the beginning of the inspection, the inspectors requested the calculations that sized the system. The licensee was not able to locate these analyses during the inspection, and determined that no calculations existed. The licensee stated the air start system was bought as a pre-specified unit and was tested during preoperational testing. The licensee provided copies of the preoperational tests which showed that the air start systems met the design basis at the time the plant was licensed. However, the inspectors noted several discrepancies between the preoperational and current conditions which could not be readily explained and which called into question the ability of the system to meet its design basis function.
The inspectors noted that, during the preoperational tests for Divisions 1 and 2, each bank of air experienced, on average, a 13 to 17 psig drop for the initial start. Recent Division 1 and 2 starts typically averaged an 18 to 22 psig drop. This would indicate that more air was being used per start and that the design basis might not be maintained.
For Division 3, a similar increase from 25 to 30 psig during preoperational testing to 30 to 35 psig during current testing was observed. However, it was not possible to make a direct comparison between the data for two reasons:
- (1) The preoperational tests were conducted using a single air bank while the tests at the time of the inspection used both banks (due to an unrelated abutment issue). The licensee provided some informal data, not regularly taken during the surveillance testing, that showed that the cranking time for the air start system had decreased since the time of the preoperational tests. The inspectors agreed that the cranking times had slightly decreased over time, as would be expected with the change to dual bank starts. However, while this data could show that the air start system was still accelerating the engine to 150 rpm in the same (or less) time, it could not explain the increased air usage. Furthermore, because the data was not consistently taken, the inspectors did not believe that it could be credited for showing that the design basis was properly translated into procedures.
- (2) The preoperational tests were conducted at 200 psig, while the current tests are conducted between 225 to 240 psig. Due to the licensee switching to starting on both air banks, the procedure requires the operators to drain the tanks down and allow them to refill if the tanks are more than five pounds off. This is done in order to ensure that both banks start at about the same pressure. Attempts, by both the inspectors and the licensee, to correlate the increased pressure drop to the increased starting air pressure were unsuccessful. The licensee prepared engineering change 338926; however after discussion with the inspectors, they withdrew it and planned to revise it.
Analysis:
Evaluation of this issue concluded that it is a design control deficiency resulting in a finding of very low safety significance (Green). The design control deficiency is due to the licensee neither having design calculations available that documented the starting air system design requirements, nor having testing acceptance criteria which would show that the design basis capability of the air start system was being maintained. The mitigating systems cornerstone was affected due to the potential undetected degradation of the design basis capability of a starting air system, with the associated potential effect on the starting capability for the emergency diesel-generator and on equipment that would be powered by the emergency diesel-generator. No other cornerstones were determined to be degraded as a result of this issue.
This finding was determined to be greater than minor based on the potential that degradation of the design basis capability of a starting air system would not currently be detected by the licensee. The design basis capability of the emergency diesel-generator starting air system was based on the capability to provide five (three) fast starts in rapid succession without the use of the starting air system compressor, with a minimum air receiver pressure of 200 psig.
Degradation of the design function impacts the base probalistic risk assessment values used for diesel generator reliability.
This finding was assessed as Green because it does not represent an actual loss of the starting air system safety function. Surveillance testing from preoperational/start-up tests to the most recent fast starts has demonstrated the current operability of the diesel generators to start within the required 13 seconds. Therefore, this issue was screened out of the significance determination process as Green.
Enforcement:
10 CFR Part 50, Appendix B, Criterion III, Design Control, states, in part, that measures be established to assure that applicable regulatory requirements and the design basis are correctly translated into specifications, drawings, procedures, and instructions.
Contrary to the above, as of September 27, 2002, the design basis for the emergency diesel-generator starting air systems was not correctly translated into plant documents, in that design calculations were not available and acceptance criteria were not included in surveillance and testing procedures to verify that the starting air system design basis capability was maintained. The licensee initiated condition report 124743 to address this issue.
Because of the low safety significance of this issue and because it is in the licensees corrective action program, the issue is being treated as a Non-Cited Violation, consistent with Section VI.A.1 of the NRC Enforcement Policy (NCV 50/373-2002-011-01; 50/374-2002-011-01).
.2 System Condition and Capability
a. Inspection Scope
The inspectors reviewed design basis documents and plant drawings, abnormal and emergency operating procedures, requirements, and commitments identified in the updated safety analysis report and technical specifications. The inspectors compared the information in these documents to applicable electrical, instrumentation and control, and mechanical calculations, setpoint changes and plant modifications. The inspectors also reviewed operational procedures to verify that instructions to operators were consistent with design assumptions.
The inspectors reviewed information to verify that the actual system condition and tested capability was consistent with the identified design bases. Specifically, the inspectors reviewed the installed configuration, the system operation, the detailed design, and the system testing, as described below.
Installed Configuration: The inspectors confirmed that the installed configuration of the emergency diesel generators and associated support systems met the design basis by performing detailed system walkdowns. The walkdowns focused on the installation and configuration of piping, components, and instruments; the placement of protective barriers and systems; the susceptibility to flooding, fire, or other environmental concerns; physical separation; provisions for seismic and other pressure transient concerns; and the conformance of the currently installed configuration of the systems with the design and licensing bases.
Operation: The inspectors performed procedure walk-throughs of selected manual operator actions to confirm that the operators had the knowledge and tools necessary to accomplish actions credited in the design basis. Additionally, the inspectors attended a simulator walk-through for selected diesel generator loading sequences.
Design: The inspectors reviewed the mechanical, electrical and instrumentation design of the emergency diesel generators and associated support systems to verify that the systems and subsystems would function as required under accident conditions. The review included a review of the design basis, design changes, design assumptions, calculations, boundary conditions, and models as well as a review of selected modification packages. Instrumentation was reviewed to verify appropriateness of applications and set-points based on the required equipment function. Additionally, the inspectors performed limited analyses in several areas to verify the appropriateness of the design values.
Testing: The inspectors reviewed records of selected periodic testing and calibration procedures and results to verify that the design requirements of calculations, drawings, and procedures were incorporated in the system and were adequately demonstrated by test results. Test results were also reviewed to ensure automatic initiations occurred within required times and that testing was consistent with design basis information.
Pre-operational test data was also reviewed to confirm initial design parameters that could not be tested under normal operations.
b. Findings
===.1
Introduction:
=
Green. The inspectors identified a second NCV of Criterion III that applied to the fuel oil storage tanks for the HPCS diesel generators on both units. Specifically, the inspectors identified that the licensee had incorrectly calculated the necessary volume for the fuel oil storage tanks.
Description:
Per the UFSAR, Section 9.5.4.2, the licensee is committed to American National Standard Institute (ANSI) N195-1976, Fuel Oil Systems for Standby Diesel-Generators, Section 5 (System Performance Requirements), Subsection 5.4 (Calculation of Fuel Oil Storage Requirements). Subsection 5.4 requires licensees to calculate the total fuel storage requirements based on calculating the expected time dependent loads, plus a ten percent margin. The standard also provides a conservative alternative for calculating the storage capacity by assuming that the diesel operates continuously for seven days at its rated capacity.
For the Division 1 and 2 diesel generator fuel oil storage tanks, the licensee chose to calculate the storage capacity by assuming that the diesels operated continuously at their rated capacities. For the Division 3 diesels, the licensee chose to determine a time-dependent load and to calculate the tank capacity on that basis.
The inspectors noted a number of problems associated with fuel oil storage tank and fuel consumption calculations. For example, the inspectors identified that the values in calculation DO-14 were based on a presumption that the HPCS pump would go to runout after a day and would remain in that condition. Furthermore, the calculation did not take into account the ten percent margin required by the ANSI standard.
Additional problems noted were:
- Calculation DO-7 appeared to have been superceded, at least in part, by calculations DO-11 and DO-14. However this wasnt recognized in any fashion.
- Similarly, calculation DO-8 was partially superceded by DO-13 and DO-15.
- Technical Specification 3.8.1.4 was non-conservative in relation to the design basis as described in calculation DO-15. The licensee concluded there was no operability problem as the tanks were always maintained above the low level setpoint and the DO-15 calculations were determined to be overly conservative.
- Procedure LOP-DO-02 contained errors related to incorrect diesel fuel oil transfer pump auto trip and auto start volume levels.
- There were no calculations to support the tables converting tank height in inches of water to gallon of fuel oil. These tables were posted on the doors of each day tank room and were included in procedures LOP-DO-01 and LOP-DO-02.
- UFSAR Table 8.3-1 had not been revised to correctly reflect the values in design calculation 4266/19AK19. In addition, the licensee did not have a calculation for the scenario of a loss of coolant accident on Unit 2 with a shutdown on Unit 1, even though that would result in a different loading on the 0 diesel generator than the case analyzed in 4266/19AK19.
- The loading calculated in 4266/19AK19 was 2717 kilowatts, which was well above the continuous loading of 2660 kilowatts, although within the 2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> loading. Procedure LOA-AP-101 did not contain any restrictions on loading the diesel generators, which negated the conservatism assumed in ANSI N-195.
Analysis:
Evaluation of this issue concluded that it is a design control deficiency resulting in a finding of very low safety significance (Green). The design control deficiency existed in that the licensee had not included the ANSI N-195 minimum margin of ten percent above the load profile results in the design calculations and subsequently had not translated adequate design basis requirements into specifications, procedures, and instructions to meet the licensees UFSAR commitment. The mitigating systems cornerstone was affected due to the failure to include adequate margin in the design basis minimum storage requirements for the HPCS emergency diesel generator fuel oil storage volume, with the associated potential effect of the inability of the storage volume to supply operation of each HPCS emergency diesel generator for the full seven day interval at the assumed loadings. This potential effect would impact the emergency diesel generator as well as the equipment that it would power during the seven day design interval. No other cornerstones were determined to be degraded as a result of this issue. Degradation of the design function impacts the base probalistic risk assessment values used for diesel generator reliability.
This finding was determined to be greater than minor based on the number of deficiencies associated with the diesel generator fuel storage tank capacities. These deficiencies will require preparation of new calculations, corrections to existing calculations, the UFSAR, the technical specification bases, and to procedures.
Changes to the technical specifications themselves may also be required. Therefore the criteria for a more than minor violation of design control was deemed to be met.
This finding was assessed as Green because it did not represent an actual loss of the HPCS diesel generator fuel oil storage volume as required by technical specifications.
Furthermore, the inspectors recognized that, in the unlikely event that extended operation of the diesel generators was necessary, the licensee would be able to get fuel on site before the end of the seven day period.
Enforcement:
10 CFR Part 50, Appendix B, Criterion III, Design Control, states, in part, that measures be established to assure that applicable regulatory requirements and the design basis are correctly translated into specifications, drawings, procedures, and instructions.
Contrary to the above, the licensee had not included the ANSI N-195 minimum margin in the design calculations of minimum HPCS emergency diesel generator fuel oil storage volume and subsequently had not translated adequate design basis requirements into specifications, procedures, and instructions to meet the licensees FSAR commitment.
The licensee initiated condition reports for each of the above problems during the inspection to address associated problems. A complete list of condition reports can be found in the list of documents at the end of the report.
Because of the very low safety significance of this issue and because the issues have been entered into the licensee's corrective action program, the finding is being treated as a Non-Cited Violation, consistent with Section VI.A.1 of the NRC Enforcement Policy (NCV 50/373-2002-011-02; 50/374-2002-011-02). This issue was determined to be sufficiently different from the issue on the air start system system such that it should be considered a separate violation rather than a separate example of a violation.
2.
Introduction:
Green. The inspectors identified an NCV of 10 CFR Part 50, Appendix B, Criterion III that applied to all of the emergency diesel generators on both units. The licensee replaced the vent control valves on the diesel generator heads with valves having different form, fit and function and did not apply a design control process commensurate to the original design.
Discussion: During a walkdown of the emergency diesel generators, the inspectors noted pressure test connection valves on the diesel cylinder heads that appeared different from the original. The licensee confirmed that the valves had been modified so the inspectors requested copies of the design change documents used for the installation of the equipment. The licensee responded that the valves were installed using the alternate parts replacement program. After some discussion, copies of the alternate parts replacement records and appropriate procedures were obtained.
During visual examination of the old and new valves, review of the alternate parts evaluation and review of the current surveillance procedure, the inspectors determined that the old and new valves had substantial differences and actually performed different functions. Therefore, the use of the alternate parts evaluation, where the part was assumed to have the same basic form, fit, and function, was not appropriate.
The inspectors noted that the original needle valve stem had to be completely removed to allow connection of test equipment. Once testing was completed, the test connections had to be removed, the valve stem installed and hand tightened in a clockwise direction to prevent flow. The replacement required an adapter for installation into the head. The valve then fitted onto the top of the adaptor and functioned as most valves, where the stems are not removed during operation. Instead a handwheel was turned to rotate the valve disc off its seat and allow flow to the test equipment, which could remain connected no matter the position of the valve. Another important difference introduced by this change in valve design was that the stem was required to be rotated clockwise for opening and counter clockwise for closing. This was different, not only from the original design, but also from the opening and closing of most valves.
Based on the documents reviewed, the inspectors concluded that a type of failure, not previously identified (i.e., ejection of the valve adapters), could have occurred with this type replacement valve. During discussions, licensee personnel stated that such an incident had occurred around 1998 at another plant where a cylinder test valve adapter was ejected from a diesel resulting in the inoperability of the diesel. The information had been distributed as industry experience type information. As a result of the industry experience notification, the licensee revised its procedures to add a warning to ensure that the valves were not over tightened.
Analysis:
Evaluation of this issue concluded that it was a design control deficiency resulting in a finding of very low safety significance. The design control deficiency was due to the licensee having failed to control the design modification process to the same degree as the original design. Because the licensee installed the new valves as an alternate parts replacement, a 10 CFR 50.59 screening or evaluation was not performed and drawings and procedures were not updated.
Because the licensee identified the potential for a new failure mode associated with this modification (as evidenced by warning in the surveillance procedures), the inspectors reviewed the issue against the requirements of 10 CFR 50.59 and discussed this issue with the cognizant individual in the Office of Nuclear Reactor Regulation for issues regarding 10 CFR 50.59. In either 1994 or 1998, the wording of 10 CFR 50.59 would have required the licensee to have submitted the modification for NRC review and approval, presuming the licensee had recognized at that time that a different failure mode had been introduced into the system.
However, in March 2001, a revised version of 10 CFR 50.59 took effect. The revised version permits changes to be made that introduce new failure modes, as long as those new failure modes do not result in "more than a minimal increase in the likelihood of a malfunction of equipment important to safety." Based upon the current warning in the licensees procedure and the fact that the valves are only opened during surveillances, the inspectors concluded that the modification would not result in more than a minimal increase and that the issue did not require further NRC review.
Enforcement:
10 CFR Part 50, Appendix B, Criterion III, Design Control, states, in part, that measures be established to assure that applicable regulatory requirements and the design basis are correctly translated into specifications, drawings, procedures, and instructions. It further states that design changes shall be subject to design control measures commensurate with those applied to the original design.
Contrary to the above, in December 1994, when the new valves were installed, the licensee did not apply the design change process commensurate with the original design in that they did not perform a 10 CFR 50.59 screening or evaluation nor did they update operating procedures or drawings. This led to a potential new failure mode not being evaluated properly. Because the issue involved a failure to implement a required regulatory process, application of the significance determination process was not appropriate. However, after consultation with NRC management, it was determined that the issue was of very low risk significance and should be assigned a color of "Green."
Because of the low safety significance of this issue and because it is in the licensees corrective action program, the issue is being treated as a Non-Cited Violation, consistent with Section VI.A.1 of the NRC Enforcement Policy (NCV 50/373-2002-011-03; 50/374-2002-011-03). The licensee entered this into their corrective action program as condition report 124850.
.3 Components
a. Inspection Scope
The inspectors examined the 0 diesel generator cooling water pump to ensure that component level attributes were satisfied. The attribute selected for review was component degradation, due to the impact that the pumps failure could have on the diesel generator.
Component Degradation: This attribute was verified through review of component repair histories and review of corrective action documents. The inspectors reviewed the attribute to verify the licensee was appropriately maintaining components in the emergency diesel generators and associated support systems
b. Findings
No findings of significance were identified.
OTHER ACTIVITIES (OA)
4OA2 Identification and Resolution of Problems
a. Inspection Scope
The team reviewed a sample of emergency diesel generator and associated support system problems that were identified by the licensee and entered into the corrective action program. The inspectors reviewed these issues to verify an appropriate threshold for identifying issues and to evaluate the effectiveness of corrective actions related to design issues. In addition, condition reports written on issues identified during the inspection were reviewed to verify adequate problem identification and incorporation of the problem into the corrective action system. The specific corrective action documents that were sampled and reviewed by the team are listed in the attachment to this report.
b. Findings
No findings of significance were identified.
4OA6 Meetings
Exit Meeting The inspectors presented the inspection results to Mr. G. Barnes, and other members of licensee management, on September 27, 2002. The licensee acknowledged the findings presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
KEY POINTS OF CONTACT Licensee Management G. Barnes, Site Vice President R. Chrzownski, Engineering R. Cockrel, Engineering T. Conner, Design Engineering Manager.
D. Czufin, Site Engineering Director D. Enright, Operations Manager T. Dao, Engineering F. Gogliotti, Plant Engineering Manager.
P. Holland, RA G. Kaegi, RA Manager T. Lanc, Engineering S. Landahl, Assistant Plant Manager W. McDonald, Design Engineering J. Shields, Design Engineering S. Stiles, NO Manager T. Simpkin, Cantera Licensing J. Drawley, Cantera Engineering Response Team Members W. Cockrel, Diesel System Engineer T. Dao, Diesel Generator Cooling Water System Engineer B. Davenport, Mechanical Contact P. Holland, Regulatory Assurance Contact W. McDonald, Response Team Leader E. Seckinger, Electrical Contact V. Shah, I&C Contact S. Smalley, Ventilation System Engineer J. Wieging, Operations Contact NRC B. Burgess, Chief, Branch 4, Division of Reactor Projects E. Duncan, Senior Resident Inspector D. Eskins, Reactor Engineer Z. Falevits, Acting Chief, Electrical Engineering Branch, Division of Reactor Safety LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED Opened and Closed 50-373/02-04-01; 50-374/02-04-01 NCV Failure to Translate Design Criteria for Five Normal Starts on Air Start System into Either Calculation or Test Acceptance Criteria 50-373/02-04-02; 50-374/02-04-02 NCV Failure to Incorporate Required Design Margin in Calculating Required Capacity of HPCS Diesel Fuel Oil Storage Tanks 50-373/02-04-03; 50-374/02-04-03 NCV Failure to Use Proper Design Control Process When Modifying Diesel Test Control Valves Discussed None LIST OF ACRONYMS USED ADAMS Agency-wide Document Access and Management System ANSI American National Standards Institute CFR Code of Federal Regulations CSCS Core Standby Coolant System DRS Division of Reactor Safety HPCS High Pressure Core Spray NEI Nuclear Energy Institute NCV Non-Cited Violation NRC Nuclear Regulatory Commission PARS Publicly Available Records System PSIG Pounds Per Square Inch Gauge RPM Revolutions Per Minute SDP Significance Determination Process UFSAR Updated Final Safety Analysis Report LIST OF
DOCUMENTS REVIEWED
1R02
Changes, Tests and Experiments
Number
Title
Revision/ Date
Condition Reports Reviewed During the Inspection
L2000-05979
Nuclear Safety Review Board Subcommittee Identified Need to
Revise 10 CFR 50.59 Safety Evaluation
October 24, 2000
L2001-00347
Engineering Rework of Backlog Drawing Incorporation
January 19, 2001
L2001-00953
Engineering Assessment of Design Change Package 9500452
CFR 50.59 Evaluation
February 15, 2001
CFR 50.59 Evaluations
L00-0886
Replace Existing Residual Heat Removal Service Water Sample
Pumps with New for the Process Radiation Detector
Revision 2
L01-0103
Update UFSAR Section 5.2.2.4.2.1 Design Pressure and
Temperature Downstream from the Crosby Main Steam
Safety-Relief Valves to 625 psig and 500F
July 11, 2000
L01-0214
Update UFSAR Discussion Regarding Moderate Energy Line
Breaks
July 11, 2000
L01-0227
Temporary Modification to Install an Alternate Method of
Determining Drywell Floor Drain Sump Flow Rates
Revision 1
L01-0254
Revise UFSAR Section 3.8.4.1.3 to Correct Errors and Clarify
Information
July 11, 2000
L01-0265
Remove Locking Devices to Allow Backdraft Damper to Operate
as Required for High Energy Line Break Outside Containment
Revision 0
L01-0282
Replacement of Centrifugal Residual Heat Removal Service
Water Process Radiation Pumps
Revision 2
L01-0612
Installation of 345 Kilovolt Revenue-Grade Metering
Revision 0
L01-0658
Jet Pump Vibration Fatigue Analysis
Revision 0
L02-0182
Increased Cooling Water Temperature Evaluation to a New
Maximum Allowable of 104 F
May 14, 2002
47478
Modification of Valves 1(2)DG036
August 5, 1992
9600195
Division 2 Residual Heat Removal Service Water Keepfill
October 30, 1996
CFR 50.59 Screenings
L00-1288
Defeat Diesel Generator Governor Auto Reset Feature
October 31, 2000
L01-0265
Remove Locking Devices to Allow Backdraft Damper to Operate
as Required for High Energy Line Break Outside Containment
Revision 0
L01-0712
Restore Original Flow Instrumentation and Disconnect
Revision 0
L02-0074
Instrument/Tubing Replacement for 1PI-DG122
Revision 0
L02-0206
Revision to Procedure LOP-AP-29 to Allow The Removal of
Cubicle Fuses Under No Load
Revision 0
L02-0235
Revision to Procedure LOS-HP-Q1 to Add a Step to the HPCS
System Inservice Test Procedure
Revision 0
Number
Title
Revision/ Date
L02-0256
Temporary Change to Bypass a Degraded Cell by Adding a
Temporary Cell in Unit 2 Division 2 125 Volt DC Battery
Revision 0
L02-0278
New Procedure LOA-UHS-001 Loss of Ultimate Heat Sink
Revision 0
L02-0316
Temporary Configuration Change to Remove the Disc from Valve
0DG005
September 6, 2002
510943
Modify 2A Diesel Generator Exhaust Expansion Joint Bolting/
Holes for Proper Alignment
February 23, 1999
49854
Increase the Thermal Overload Relay Setpoint for Various VD
and VY Fan Motors
March 16, 1996
1R17
Permanent Plant Modifications
Modifications
331943*
Install Wire Mesh Frame Assemblies to Diesel Generator
Exhaust Parapets on South Side of Diesel Generator Building
Revision 0
333905
Jet Pump Vibration Fatigue Analysis
Revision 0
334017*
Increase Cooling Water Temperature Evaluation to a New
Maximum Allowable of 104 F
Revision 0
334146*
1PI-DG-122 Diesel Generator Crankcase Pressure Indicator
Revision 1
334569*
0DG-ST-11 Line Replacement
Revision 0
Documents also reviewed for Attachment 1R21. Associated documents (calculations, drawings,
surveillances) are listed under that attachment.
1R21
Safety System Design and Performance Capability
Alternate Parts Replacements
Alternate Parts Replacement Form for Replacement of the
Cylinder Test Needle Valve with a V-line Indicator Valve
November 23, 1994
Q-93-099-21
Alternate Parts Replacement Form for Valve Indicator Adapter
March 30, 1994
Calculations
015521(EMD)
Reevaluate HPCS Oil Storage Tank Specification - Auxiliary
Building
October 23, 1978
20955(EMD)
Minimum Wall Evaluation for Line 1DG018A in Subsystem
Revision 3B
Typical Arrangement of Fuel Oil Tank Piping
April 21, 1975
Calculation of Fuel Oil Needed to Meet Seven Day Requirement
on Diesel Fuel Oil Tank
April 21, 1975
Hydrostatic Test Pressure and Temperature for Diesel Fuel Oil
Transfer Pumps
April 21, 1975
Elevation of Diesel Fuel Oil Day Tanks
April 21, 1975
Diesel Oil Storage Capacity
April 7, 1976
Diesel Oil Instrument Setpoints
August 1, 1977
Diesel Fuel Transfer Pump Net Positive Suction Head
December 9, 1976
Diesel Oil Orifice Sizing
December 9, 1976
Number
Title
Revision/ Date
Diesel Oil Storage and Day Tanks Available Capacity - HPCS
Diesel
08/ /89
HPCS Diesel Generator Day Tank Fuel Level for Running Diesel
Generator 50 minutes
10/ /90
HPCS Diesel Generator Fuel Oil Transfer Pump Start Switch
Instrument Setpoint
06/ /91
HPCS Diesel Fuel Storage Capacity Margin
March 14, 1990
Division 1 and 2 Diesel Generator Fuel Oil Day Tank Instrument
Setpoints
April 3, 1990
266/19AK15
Input Kilowatt Loading on 4160 Volt Switchgear 143 and 243
January 23, 1992
266/19AK19
Input Kilowatt Loading on 4160 Switchgear 141Y, 142Y and 242Y June 30, 1997
266/19AN14
Replacement of Diesel Generator 0 Cooling Water Pump Motor
0DG01P
October 31, 1988
266/19AN71
Second Level Undervoltage Relay Setpoint
December 20, 2001
266/19AZ21
Diesel Generator 0 Modified Feeder Breakers Closing Circuits
January 24, 1992
266/19AZ30
Degraded Voltage with a 2.5 Percent Boost at the Division 1 and
Unit Substation Transformers
August 17, 1999
266/19AZ31
Degraded Voltage with a 2.5 Percent Boost at the Division 1 and
Unit Substation Transformers
August 6, 1992
266/19D50
Division 1, 2 and 3 125 Volt DC Switchgear Breaker Control
Voltage Adequacy
April 9, 1997
266/19D55
Terminal Voltage for the Replacement of Diesel Generator 2B
Fuel Priming Pump Motor During Start and Run
September 22, 1994
97-195
Thermal Model of ComEd - LaSalle Station Diesel Generator
Jacket Water Coolers
May 14, 2002
97-197
Thermal Model of ComEd - LaSalle Station HPCS Diesel
Generator Coolers
May 14, 2002
ATD-0135
Change in Diesel Generator Cooling Water Flow to Low Pressure
Core Spray Motor Cooler Due to Check Valve Removal
May 22, 1992
CID-DO-02
Diesel Generator Day Tank Level Switches Instrument Margin
March 28, 1990
CID-DO-01
HPCS Diesel Fuel Oil Day Tank Low Level Setpoint
October 8, 1990
DG-07
Check Valve Flow Conditions for Diesel Generator System
August 6, 1987
DG-08
Net Positive Suction Head for HPCS Diesel Generator Fuel
Pumps
October 11, 1990
DG-12
Evaluation of Available Net Positive Suction Head as a Result of
Relocating Diesel Generator 2B Fuel Oil Priming Pump
September 6, 1994
DG-1
Diesel Generator Exhaust System Backpressure
December 14, 1976
DG-4
Diesel Generator Intake Pressure Losses
December 14, 1976
EQ-05
Temp and Humidity Profile for Reactor Building
May 1, 1987
EQ-07
Temperature and Humidity Profile Diesel Generator Rooms and
HPCS Rooms
May 8, 1981
Analysis of Safety-Related Loads During Loss of Coolant
Accident Block Start for LaSalle Unit 2
March 14, 2002
Justification for Eliminating Check Valves 0,1,2DG002 and
1(2)E22-F028
June 5, 1996
Number
Title
Revision/ Date
CSCS Pumps Suction Piping Volume, Flow Velocity Rates, and
Turnover Time for Suction Piping
July 2, 1996
Pressure Drop from External Source to the Diesel Generator
Heat Exchangers Through the Fire Protection System
June 30, 1996
Determination of Flow Correction Factors for Evaluating the
Performance of CSCS Equipment Cooling Service Water Pump
Operation
Revision 1
Orifice Sizing for Residual Heat Removal Service Water Keep Fill
Line
Revision 0
Evaluation for Required Minimum Thickness for Channel Covers
of Heat Exchangers 1DG01A and 0DG01A
March 1, 1997
Evaluation of 54 Inch CSCS Bypass Line
Revision 4
Ventilation Flow Rate Requirements for the Diesel Generator
Fuel Oil Day Tank and Storage Tank Rooms
September 27, 1997
LaSalle County Station CSCS Hydraulic Model
May 16, 2002
Determination of Velocities in CSCS Piping
December 12, 1997
Effects of Outside Air Temperature Greater than 95F System
Performance
May 22, 1998
Allowable Leakage for the Diesel Generator Air Start Subsystems March 5, 1998
2DG01A, 2A Emergency Diesel Generator Cooler Thermal Heat
Transfer Performance
February 16, 1999
HPCS Diesel Generator Cooling Water Pump Flow and Net
Positive Suction Head Requirements
March 24, 1999
Operability Evaluation of Subsystems 2CS63 and 2CS64 for
ER9900504
January 29, 1999
CSCS Cooling Water System Road Map Calculation
November 6, 2000
Torque Values for the Diesel Oil Tanks
March 21, 2000
Evaluation of 1B HPCS Emergency Diesel Generator Heat
Exchanger Test
September 29, 2000
VD-1A
Standby Diesel Generator Room Ventilation System
July 07, 1976
VD-1B
Diesel Fuel Storage Tank Room and Diesel Oil Day Tank Room
Ventilation System
July 07, 1976
VD-1C
Diesel Generator Room Ventilation System Duct Pressure Drops October 02, 1978
VD-2A
Standby Diesel Generator Room Ventilation System
July 01, 1976
VD-2B
Diesel Fuel Storage Tank Room and Diesel Oil Day Tank Room
Ventilation System
July 01, 1976
VD-2C
Diesel Generator Room Ventilation System Duct Pressure Drops October 02, 1978
VD-3A
HPCS Diesel Generator Room Ventilation System
July 07, 1976
VD-3B
HPCS Diesel Generator Fuel Storage Tank Room and Diesel Oil
Day Tank Room Ventilation System
July 07, 1976
VD-3C
HPCS Diesel Generator Cooling Water Pump, Switchgear and
Battery Rooms - Ventilation System
July 29, 1991
VD-3D
HPCS Diesel Generator Room Ventilation System Duct Pressure
Drops
October 03, 1978
Number
Title
Revision/ Date
VD-3E
Temperature and Relative Humidity versus Time Profile for
HPCS Diesel Generator Rooms
November 12, 1980
Condition Reports Reviewed During the Inspection
L2000-00241
1A Diesel Generator Failure to Start
January 19, 2000
L2001-03989
Failure to Measure Cetane Level for Diesel Fuel Oil
July 10, 2001
035277
Action Taken to Stop 2A Diesel Generator after Inadvertent Start
on September 13, 2000
September 22, 2000
043742
Amendment Request for Diesel Generator Allowed Outage Time
Extension Not Timely
February 2, 2001
113823
Diesel Generator Oil Circulating Pump Trip
June 30, 2002
114125
1A Diesel Generator Cooling Water Flow Adjustment Required
During LOS-DG-Q2
July 2, 2002
115477
Unable to Adjust 0A Diesel Fire Pump Engine Jacket Cooling
Water Temperature below 200F
July 10, 2002
20008
1VY02A As-Found Water Flow Lower than Surveillance Limit
August 20, 2002
20239
1B Diesel Generator Cooling Water Flow Discrepancy
August 22, 2002
20459
1A Diesel Generator Oil Circulating Pump Stopped Operating
August 24, 2002
21821
Apparent Stem-Disc Separation in 0DG005, Common Diesel
Generator Cooling Water Valve
September 5, 2002
21907
0DO01P (0 Diesel Generator Fuel Oil Transfer Pump) Failure
September 6, 2002
21972
Diesel Generator Fuel Oil Transfer Pump Power Loss Repeat
Failure
September 6, 2002
2009
LOP-DG-903 Surveillance Suspended
September 11, 2002
2320
Evaluate CSCS Service Water Components for Corrosion or
Erosion
September 10, 2002
2377
Diesel Generator Maintenance Window Extended Due to
Emergent Work
September 11, 2002
2495
UFSAR Figure 9.5-1 Incorrectly Identifies Division 1 Fuel Oil
Storage Tank as the Division 3 Fuel Oil Storage Tank
September 13, 2002
2506
Link Calculation DO-08 to DO-15
September 13, 2002
2518
Enhance Procedures LOA-FX-101(201) for Diesel Generator
Cooling Water
September 11, 2002
2520
Limiting Fuel Oil Specific Gravity
September 11, 2002
2522
American Petroleum Institute (API) Specific Gravity Checks
September 11, 2002
2525
Diesel Generator Load Rating
September 11, 2002
Condition Reports Written as a Result of the Inspection
2389
LOP-DG-02 Acceptance Criteria Is Non-conservative
September 13, 2002
2403
Sections of DO-7 Diesel Fuel Oil Tanks Capacity Calculation
Should Have Been Superceded by DO-11
September 13, 2002
2413
Sections of DO-08 Diesel Fuel Oil Instrument Setpoint
Calculation Should Have Been Superceded by DO-15
September 13, 2002
Number
Title
Revision/ Date
2504
UFSAR 8.3-1 Diesel Generator Maintenance Interval Ratings Are
Incorrect
September 13, 2002
2561
Diesel Generator Training Material Error
September 13, 2002
2679
Drawing 1E-2-4026AA Fuel Oil Transfer Pump Relay - Relay
Contact Errors
September 13, 2002
2688
Unit 2 Loading Analysis
September 13, 2002
2712
M2132 Diesel Fuel Oil Level - Configuration Control Drawing
Errors
September 13, 2002
2784
Diesel Fuel Oil Drawing Discrepancy and Inappropriate Units of
Measure
September 13, 2002
2799
M-85 and M-132 Drawing Errors Concerning Diesel Oil Tank
Capacities
September 13, 2002
2818
High Alarm Setpoints for Level Switches Not Wired or Calibrated
in the Plant - Configuration Control Problem
September 13, 2002
2888
UFSAR, Technical Specification Discrepancies with Diesel Oil
Calculation DO-7
September 13, 2002
23096
Clarification Needed UFSAR 9.5.5.1.1
September 16, 2002
23359
Diesel Generator Load Limits in Procedures Are Confusing
September 20, 2002
23467
Calculation Should Be Classified as Historical
September 20, 2002
23527
Calculation DG-07 Should Be Classified as Historical
September 20, 2002
23846
UFSAR Discrepancy on Diesel Generator Ventilation Intake
Location
September 20, 2002
23855
UFSAR Change Not Processed in Timely Manner
September 20, 2002
23875
Lack of Procedural Guidance on Diesel Generator Loading
above 2600 Kilowatts and Fuel Oil Consumption
September 23, 2002
24123
Diesel Generator Loading in LTS-500-109 Is Incorrect
September 23, 2002
24125
Design Basis Initiative Provided Incorrect Verification and
Validation Documents for Diesel Generator Air Storage Capacity
September 23, 2002
24137
Calculation L-1401 Should Be Historical
September 23, 2002
24142
Two Active Drawings Exist for Unit 1 and 2 HPCS Pump
Performance Curves
September 23, 2002
24277
No Supporting Calculations for Correlating Diesel Fuel Day Tank
Levels to Volume for Use on Station Placards and in Procedures
LOP-DO-01 and LOP-DO-02 Tables
September 24, 2002
24338
U2 HPCS Pump Brake Horsepower Load in Calculation AK15 Is
Incorrect
September 24, 2002
24503
UFSAR Figure 9.5-7 Needs to Be Revised to Show Only One
Ventilation System Inlet Filter
September 25, 2002
24537
Incorrect Calculation Reference in Procedures
September 25, 2002
24542
Calculation VD-3D Uses Non-conservative Flow Rate
September 25, 2002
24650
LMS-DG-03 Precautions C.1 and C.1.1 Are No Longer Correct
September 26, 2002
24655
Diesel Generator Cooling Water Strainer Backwash Flow
Acceptance Criteria Problems
September 26, 2002
24725
Acceptance Criterion Limits Non-conservative
September 26, 2002
Number
Title
Revision/ Date
24732
Technical Specifications For 50 Min Run Requires 250 Gallons;
Calculation DO-15 Requires 254.18 Gallons
September 26, 2002
24738
Values on Pages 4 and 7 of Calculation DO-08 Do Not Match
Procedure LOP-DO-02, Sections E.2 and E.3
September 26, 2002
24742
UFSAR Strainer Backwash Flow Low
September 26, 2002
24743
Limited Documentation to Demonstrate Five Start Criteria Is Met September 26, 2002
24828
Diesel Generator Air Flow Regulator Calibration
September 27, 2002
24833
Division 2 Diesel Generator CSCS Strainer Backwash Flow
September 27, 2002
24850
Parts Evaluation for Kiene Valves May Have Overlooked New
Failure Mode
September 27, 2002
Drawings
Schematic Diagram - 4160 Volt Switchgear 141Y Diesel
Generator 0 Feed Active Circuit Breaker 1413
Revision AB
Schematic Diagram - 4160 Switchgear 241Y Diesel Generator 0
Feed Active Circuit Breaker 2413
Revision Z
Schematic Diagram - System
Revision X
Schematic Diagram - Diesel Cooling Water Strainer
Revision D
Schematic Diagram - Diesel Generator 0 Engine Control
System
Revision T
Schematic Diagram - Diesel Generator 0 Engine Control
System
Revision U
Schematic Diagram - Diesel Generator 0 Engine Control
System
Revision V
Schematic Diagram - Diesel Generator 0 Engine Control
System
Revision Q
Schematic Diagram - Diesel Generator 0 Engine Control
System
Revision V
Schematic Diagram - Diesel Generator 0 Engine Control
System
Revision T
Schematic Diagram - Diesel Generator 0 Engine Control
System
Revision G
Schematic Diagram - Diesel Generator 0 Engine Control
System
Revision M
Schematic Diagram - Diesel Generator 0 Alarms
Revision Z
Part List Diesel Generator 0
Revision K
Schematic Diagram - Diesel Generator 0 Alarms
Revision L
Schematic Diagram - Diesel Generator 0 Field Conditioning
Relay A11
Revision A
Schematic Diagram - Diesel Generator 0 Engine Lube Oil Soak
Back Pump B7A
Revision C
Schematic Diagram - Unit 1,2 Diesel Generator 0 Alarm System Revision B
Loop Schematic Diagram - Diesel Generator System
Revision E
Schematic Diagram - Diesel Fuel Oil System
Revision U
Number
Title
Revision/ Date
Schematic Diagram - Diesel Fuel Oil System
Revision K
Schematic Diagram - Diesel Generator Room Ventilation
Revision M
Schematic Diagram - Diesel Generator Room Ventilation
Revision K
Schematic Diagram - Diesel Generator Room Ventilation
Alarms
Revision H
Schematic Diagram - Diesel Generator Room Ventilation
Revision F
Key Diagram 4160 Volt AC Switchgear 141Y
Revision D
Key Diagram 4160 Volt AC Switchgear 142Y
Revision D
Key Diagram 4160 Volt AC Switchgear 143
Revision B
Single Line Diagram Standby Generators and 4160 Volt Buses
Revision N
Schematic Diagram - 4160 Volt Switchgear 142Y Diesel
Generator 1A Feed Active Circuit Breaker 1423 System
Revision Y
Schematic Diagram - Diesel Generator System
Revision M
Schematic Diagram - Diesel Cooling Water Strainer
Revision J
Schematic Diagram - Diesel Generator 1A Generator Engine
Control System
Revision R
Schematic Diagram - Diesel Generator 1A Engine Control
System
Revision W
Schematic Diagram - Diesel Generator 1A Engine Control
System
Revision M
Schematic Diagram - Diesel Generator 1A Engine Control
System
Revision Q
Schematic Diagram - Diesel Generator 1A Engine Control
System
Revision K
Schematic Diagram - Diesel Generator 1A Engine Control
System
Revision N
Schematic Diagram - Diesel Generator 1A Engine Control
System
Revision K
Schematic Diagram - Diesel Generator 1A Engine Control
System
Revision L
Schematic Diagram - Diesel Generator 1A Alarms System
Revision Y
Schematic Diagram - Diesel Generator System
Revision K
Schematic Diagram - Diesel Generator 1A Field Conditioning
Relay
Revision A
Part List Diesel Generator 1A
Revision H
Loop Schematic Diagram - Diesel Generator System
Revision D
Schematic Diagram - Diesel Generator 1A Annunciator System Revision L
Schematic Diagram - Diesel Fuel Oil System
Revision T
Schematic Diagram - Diesel Fuel Oil System
Revision V
Schematic Diagram - Diesel Fuel Oil Alarms System
Revision R
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision N
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision G
Number
Title
Revision/ Date
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision L
Schematic Diagram - Diesel Generator Room Ventilation
Alarms
Revision H
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision F
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision G
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision E
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision H
Schematic Diagram - High Pressure Core Spray Diesel
Generation 1B Alarms
Revision Y
Schematic Diagram - 4160 Volt Switchgear 143 Normal Feed
Active Circuit Breaker 1432
Revision V
Schematic Diagram - 4160 Volt Switchgear 143 Auxiliary
Compartment
Revision S
Schematic Diagram - 4160 Volt Switchgear 143 Feed from
Diesel Generator 1B
Revision S
Schematic Diagram - High Pressure Core Spray Pump
Revision R
Schematic Diagram - 4160 Volt Switchgear 143 Feed to
Transformer 143-1
Revision G
Schematic Diagram - HPCS Diesel Generator 1B Protective
Relaying
Revision L
Schematic Diagram - HPCS Diesel Generator 1B Engine
Control
Revision X
Schematic Diagram - HPCS Diesel Generator 1B Engine
Control
Revision T
Schematic Diagram - HPCS Diesel Generator 1B Engine
Control
Revision R
Schematic Diagram - HPCS Diesel Generator 1B Engine
Control
Revision Q
Schematic Diagram - HPCS Diesel Generator 1B Engine
Control
Revision T
Schematic Diagram - HPCS Diesel Generator 1B Engine
Control
Revision R
Schematic Diagram - HPCS Diesel Generator 1B Engine
Control
Revision R
Schematic Diagram - HPCS Diesel Generator 1B Engine
Control
Revision R
Schematic Diagram - HPCS Diesel Generator 1B Engine
Control
Revision R
Schematic Diagram - HPCS 125 Volt DC Battery Charger 1C
Revision G
Schematic Diagram - HPCS Diesel Cooling Water Strainer
Revision G
Number
Title
Revision/ Date
Schematic Diagram - Speed Relay Tachometer Panel 4240
Revision F
Schematic Diagram - HPCS Diesel Generator 1B Engine
Control
Revision F
Key Diagram 4160 Volt Switchgear 241Y
Revision D
Key Diagram 4160 Volt Switchgear 242Y
Revision E
Key Diagram 4160 Volt Switchgear 243
Revision C
Single Line Diagram Standby Generators and 4160 Volt Buses
Revision L
Schematic Diagram - 4160 Volt Switchgear 242Y Diesel
Generator 2A Feed Active Circuit Breaker 2423
Revision U
Schematic Diagram - Diesel Generator System
Revision l
Schematic Diagram - Diesel Cooling Water Strainer
Revision H
Schematic Diagram - Diesel Generator 2A Engine Control
System
Revision M
Schematic Diagram - Diesel Generator 2A Engine Control
System
Revision U
Schematic Diagram - Diesel Generator 2A Engine Control
System
Revision N
Schematic Diagram - Diesel Generator 2A Engine Control
System
Revision P
Schematic Diagram - Diesel Generator 2A Engine Control
System
Revision M
Schematic Diagram - Diesel Generator 2A Engine Control
System
Revision M
Schematic Diagram - Diesel Generator 2A Engine Control
System
Revision K
Schematic Diagram - Diesel Generator 2A Engine Control
System
Revision K
Schematic Diagram - Diesel Generator 2A Alarms
Revision Y
Schematic Diagram - Diesel Generator
Revision K
Part List Diesel Generator 2A Alarms
Revision G
Schematic Diagram - Diesel Generator 2A Field Conditioning
Relay
Revision A
Loop Schematic Diagram - Diesel Generator
Revision E
Schematic Diagram - Diesel Fuel Oil System
Revision P
Schematic Diagram - Diesel Fuel Oil System
Revision T
Schematic Diagram - Diesel Fuel Oil Alarms System
Revision L
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision E
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision K
Schematic Diagram - Diesel Generator Room Ventilation
Alarms
Revision F
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision E
Number
Title
Revision/ Date
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision E
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision D
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision D
Schematic Diagram - Diesel Generator Room Ventilation
System
Revision G
Schematic Diagram - HPCS Diesel Generator 2B Engine
Control
Revision U
Schematic Diagram - 4160 Volt Switchgear 243 Normal Feed
Active Circuit Breaker 2432
Revision P
Schematic Diagram - 4160 Volt Switchgear 243 Auxiliary
Compartment
Revision Q
Schematic Diagram - 4160 Volt Switchgear 243 Feed from
Diesel Generator 2B
Revision R
Schematic Diagram - HPCS Pump
Revision P
Schematic Diagram - 4160 Volt Switchgear 243 Feed to
Transformer 2E22-S003
Revision E
Schematic Diagram - HPCS Diesel Generator 2B Protective
Relaying
Revision L
Schematic Diagram - HPCS Diesel Generator 2B Engine
Control
Revision R
Schematic Diagram - HPCS Diesel Generator 2B Engine
Control
Revision T
Schematic Diagram - HPCS Diesel Generator 2B Engine
Control
Revision P
Schematic Diagram - HPCS Diesel Generator 2B Engine
Control
Revision U
Schematic Diagram - HPCS Diesel Generation 2B Alarms
Revision V
Schematic Diagram - HPCS Diesel Generator 2B Engine
Control
Revision R
Schematic Diagram - HPCS Diesel Generator 2B Engine
Control
Revision U
Schematic Diagram - HPCS Diesel Generator 2B Engine
Control
Revision V
Schematic Diagram - HPCS Diesel Generator 2B Engine
Control
Revision P
Schematic Diagram - HPCS 125 Volt DC Battery Charger 2C
Revision G
Schematic Diagram - HPCS Diesel Cooling Water Strainer
Revision J
Schematic Diagram - Speed Relay Tachometer Panel 4240
Revision F
Schematic Diagram - HPCS Diesel Generator 2B Engine
Control
Revision K
74-2130-01
General Plan for Fuel Oil Storage Tanks 1(2)DO02T
Revision 5
74-2130-02
Inch Diameter Shell Manhole Cover - Fuel Oil Storage Tanks Revision 3
Number
Title
Revision/ Date
74-2130-03
Inch Diameter Roof Manhole Cover - Fuel Oil Storage Tanks Revision 2
74-2130-04
Four Inch Diameter Overflow Line - Oil Storage Tanks
Revision 4
74-2130-05
Two Inch Diameter Shell Coupling - Fuel Oil Storage Tanks
Revision 2
74-2130-06
Three Inch Diameter Vent Line - Fuel Oil Storage Tanks
Revision 3
74-2130-07
Diameter Fill Line - Fuel Oil Storage Tanks 1(2)DO02T
Revision 3
74-2130-08
Two Inch Diameter Roof Coupling - Fuel Oil Storage Tanks
Revision 2
74-2130-09
Two Inch Diameter Roof Coupling - Fuel Oil Storage Tanks
Revision 2
74-2130-10
11/2 Inch Diameter Roof Coupling - Fuel Oil Storage Tanks
Revision 3
74-2130-11
Platform - Fuel Oil Storage Tanks 1(2)DO02T
Revision 2
74-2130-12
Platform Details - Fuel Oil Storage Tanks 1(2)DO02T
Revision 2
74-2130-13
Ladder - Fuel Oil Storage Tanks 1(2)DO02T
Revision 4
74-2130-14
Shell - Fuel Oil Storage Tanks 1(2)DO02T
Revision 4
74-2130-15
Bottom - Fuel Oil Storage Tanks 1(2)DO02T
Revision 2
74-2130-16
Dome Roof - Fuel Oil Storage Tanks 1(2)DO02T
Revision 2
74-2130-17
Anchor Bolt Chairs - Fuel Oil Storage Tanks 1(2)DO02T
Revision 4
74-2130-18
Nameplate and Bracket - Fuel Oil Storage Tank 1DO02T
Revision 2
74-2130-19
Nameplate and Bracket - Fuel Oil Storage Tank 2DO02T
Revision 4
74-2130-20
11/2 Diameter Bubbler Pipe - Fuel Oil Storage Tanks 1(2)DO02T
Revision 3
74-2130-21
Internal Piping for 2 Inch Diameter Shell Coupling 1(2)DO02T
Revision 1
74-2130-22
Inch Diameter Drain and Sample Nozzle 1(2)DO02T
Revision 1
74-2130-23
Overflow Weir Assembly - Fuel Oil Storage Tanks 1(2)DO02T
Revision 1
74-2130-F
Anchor Bolt Setting Plan - Fuel Oil Storage Tanks 1(2)DO02T
Revision 3
74-2130-PC-1
Print Control Record - Fuel Oil Storage Tanks 1(2)DO02T
Revision 11
74-2131-01
Diesel Fuel Storage Tank General Plan
Revision 4
74-21311-A
Diesel Fuel Storage Tank Orientation
Revision 5
80653X1
Architectural Drawings (JW Doors, North American)
October 11, 1976
94-13640
Anchor Darling Wedge Gate Valve Drawing
Revision B2
A-24069
HPCS Diesel Oil Transfer Pump 1DO02P (J-2908)
December 22, 1977
A-466-1
Door Details
Revision F
BF-865-3
Erection Drawing - Diesel Generator Room Piping Ground Floor March 6, 1979
BF-865-4
Erection Drawing - Diesel Generator Room Piping Ground Floor March 6, 1979
BF-865-5
Erection Drawing
Revision C
C-74-187
HPCS Diesel Day Tank (J-2948)
February 28, 1994
C-74-188
Diesel Generator Day Tanks 0DO02T, 1DO05T and 2DO05T
February 28, 1994
EMD 645E4
Nuclear Service Engine Rating at Elevated Temperatures
June 11, 1992
FF-15303/4
Clarage Centrifugal Fan Size 361/2 Inches NH CCW-UBD
March 3, 1977
M-54-1
Piping and Instrumentation Drawing - Index and Symbols
Revision Y
M-54-2
Piping and Instrumentation Drawing - Index and Symbols
Revision C
M-54-3
Piping and Instrumentation Drawing - Index and Symbols
Revision E
M-54-4
Piping and Instrumentation Drawing - Index and Symbols
Revision A
M-54-5
Piping and Instrumentation Drawing - Index and Symbols
Revision A
Number
Title
Revision/ Date
M-83-1
Piping and Instrumentation Drawing - Diesel Generator Auxiliary
System
Revision AL
M-83-2
Piping and Instrumentation Drawing - Diesel Generator Auxiliary
System
Revision AA
M-83-3
Piping and Instrumentation Drawing - Diesel Generator Auxiliary
System
Revision AT
M-83-4
Piping and Instrumentation Drawing - Diesel Generator Lube Oil
System
Revision E
M-85
Piping and Instrumentation Drawing - Diesel Oil System
Revision AB
M-87-1
Piping and Instrumentation Drawing - CSCS Equipment Cooling
Water System
Revision AM
M-87-2
Piping and Instrumentation Drawing - CSCS Equipment Cooling
Water System
Revision AG
M-87-3
Piping and Instrumentation Drawing - CSCS Equipment Cooling
Water System
Revision J
M-132
Piping and Instrumentation Drawing - Diesel Oil System
Revision AA
M-134-1
Piping and Instrumentation Drawing - CSCS Equipment Cooling
Water System
Revision AC
M-134-2
Piping and Instrumentation Drawing - CSCS Equipment Cooling
Water System
Revision AA
M-134-3
Piping and Instrumentation Drawing - CSCS Equipment Cooling
Water System
Revision K
M-830-1
CSCS Piping
Revision AM
M-830-2
CSCS Piping
Revision AK
M-830-3
CSCS Piping
Revision AC
M-830-4
CSCS Piping
Revision W
M-830-5
CSCS Piping
Revision T
M-830-6
CSCS Piping
Revision W
M-830-7
CSCS Piping
Revision J
M-830-8
CSCS Piping
Revision D
M-830-9
CSCS Piping Miscellaneous Details
Revision A
M-865
Diesel Generator 0 Miscellaneous Tubing
Revision D
M-865-9
Diesel Generator Room Miscellaneous Section Piping
Revision M
M-930-1
CSCS Piping
Revision AA
M-930-2
CSCS Piping
Revision M
M-930-3
CSCS Piping
Revision T
M-930-4
CSCS Piping
Revision P
M-930-5
CSCS Piping
Revision R
M-930-6
CSCS Piping
Revision F
M-930-7
CSCS Piping
Revision G
M-930-8
CSCS Piping Miscellaneous Details
Revision A
M-1395-1
Diesel Generator Room Ventilation System Elevation 736'-6"
Revision A
M-1395-2
Diesel Generator Room Ventilation System Details
Revision A
Number
Title
Revision/ Date
M-1396
Diesel Generator Room Ventilation System Elevation 736-6"
Revision N
M-1444
Piping and Instrumentation Drawing - Diesel Generator Room
Ventilation System
Revision J
M-1445
Piping and Instrumentation Drawing - HPCS Diesel Generator
Room, Switchgear Room and Pump Room Ventilation System
Revision L
M-1446
Piping and Instrumentation Drawing - HPCS Diesel Generator
Room, Switchgear Room and Pump Room Ventilation Systems
Revision L
M-1447
Piping and Instrumentation Drawing - Diesel Generator Room
Ventilation System
Revision J
M-1465
Piping and Instrumentation Drawing - CSCS Equipment Cooling
System
Revision E
M-1591-3
Equipment Foundations Auxiliary Building
Revision R
M-2085-1
Controls and Instrumentation Drawing - Diesel Fuel Oil
Revision J
M-2085-2
Controls and Instrumentation Drawing - Diesel Fuel Oil
Revision E
M-2087
Controls and Instrumentation Drawing - CSCS Equipment
Cooling Water
Revision D
M-2132-1
Controls and Instrumentation Drawing - Diesel Fuel Oil
Revision A
M-2132-2
Controls and Instrumentation Drawing - Diesel Fuel Oil
Revision A
M-2134
Controls and Instrumentation Drawing - CSCS Equipment
Cooling Water
Revision D
M-3444-1
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision C
M-3444-2
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision C
M-3444-3
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision C
M-3444-4
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision C
M-3445-1
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision D
M-3445-2
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision C
M-3445-3
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision D
M-3445-4
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision C
M-3446-1
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision E
M-3446-2
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision D
M-3446-3
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision D
M-3446-4
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision D
Number
Title
Revision/ Date
M-3447-1
Controls and Instrumentation Drawing - Heating, Ventilation and
Air Conditioning
Revision D
M-3447-2
Heating, Ventilation and Air Conditioning Controls and
Instrumentation Drawing - Detail Diagram
Revision C
M-3447-3
Heating, Ventilation and Air Conditioning Controls and
Instrumentation Drawing - Detail Diagram
Revision C
VPF 3069-143
Report of Performance Test for Pump S/N 0972126 (Pump
Curve - Ingersoll-Rand)
Revision 1
0, 1A, and 1B Diesel Generator Exhaust Penthouse Screen
September 5, 2002
334017
Increased Cooling Water Temperature to a New Maximum
Allowable of 104F
Revision 0
334569
0DG-ST-11 Line Replacement (Lube Oil Sensing Line
Replacement)
December 27, 2001
337326
Temporary Modification - Temporary Repair to 2E22-S001 Heat
Exchanger Partition Plate
May 28, 2002
337814
Evaluation of Loss of 0 Diesel Generator Circulating Lube Oil
Pump
July 5, 2002
338718
Temporary Configuration Change to Remove the Disc from Valve
0DG005
September 6, 2002
338926
Diesel Generator Starting Air System Sizing - Five Start
Capability
September 24, 2002
338930
Diesel Generator Fuel Oil Storage Capacity Evaluation
September 23, 2002
Lesson Plans
011
Emergency Diesel Generators and Auxiliaries
November 14, 2000
065
Core Standby Cooling System Equipment Cooling Water
April 2, 2001
119
Plant Heating, Ventilation and Air Conditioning
Revision 2
Miscellaneous
44404
Receipt Inspection Diesel Generator Temperature Control Valves August 26, 1999
IST Pump Data
Inservice Test Data for Pumps from September 2000 to July
2002 Compiled from Inservice Testing Access' Database
N/A
IST-LAS-BDOC-
V-6
LaSalle - Inservice Testing Basis Document / 0 Diesel Generator
Fuel Transfer Pump 0DO01P
August 24, 2001
Letter
American Nuclear Society to Commonwealth Edison (Terry
OBrien): Request for Clarification on ANSI/ANS-59.51-1989
March 22, 1995
Letter
Sargent and Lundy Engineers to Stewart and Stevenson
Services, Inc: Sargent and Lundy Specification J-2544
July 24, 1979
LU2000-121
UFSAR Change Request - UFSAR Tables 9.4-15 and 9.4-16
August 21, 2000
LU2001-119
UFSAR Change Request, Change #4 - Diesel Generator
Facilities Ventilation System
December 3, 2001
Number
Title
Revision/ Date
MNGP-FP95-01 Report of the Fire Endurance and Hose Stream Testing of Two
Single, Fire Rated Door Assemblies with Excessive Clearances
Installed in a Concrete Block Wall
October 22, 1986
NES-MS-09.01
Diesel Generator Preventive Maintenance Basis Document
Revision 4
PRA Results
2001 Key LaSalle 1 and 2 Probabilistic Risk Assessment Results,
Including LaSalle Model 2001A General Results
N/A
TP-EXE-IST-00-
Exelon Inservice Testing Program Technical Position -
Classification of Diesel Oil Transfer Pumps as Skid Mounted
Components
Revision 1
Modifications
283
Install Stop Pin in Diesel Generator 1B Governor
Revision 0
43580
Install Heavy Duty Turbocharger
Revision 0
44934
Revise Diesel Generator Starting Circuit
Revision 0
46030
Diesel Generator Instrumentation Tubing Upgrade
Revision 0
46030
Diesel Generator Small Diameter Tubing Replacement
Revision 1
47004
Addition of an Interposing Relay in the 0 Diesel Generator Output
Breaker Closing Circuit
Revision 0
47010
Addition of an Interposing Relay in the 0 Diesel Generator Output
Breaker Closing Circuit
Revision 0
47478
Valve Changeout for Diesel Generator 2DG036
Revision 1
48023
1B Diesel Generator Run Solenoid Replacement
Revision 0
48640
Diesel Generator 2A Reverse Power Relay Replacement Exempt
Change
Revision 0
48720
Replace Diesel Generator 0 Ground Fault Relay
Revision 1
48844
Install Orifice in HPCS Full Flow Test Line
Revision 1
49699
Increase 2A Diesel Generator Room Ventilation Fan Setpoint
Tolerance
Revision 0
49703
Revise Power Transfer Logic for Diesel Generator 0 Room
Ventilation Fan
Revision 0
49854
Engineered Safety Features Division 1 Thermal Overload Heater
Settings for Continuous Duty Motors
Revision 0
50800
Modify 1B Diesel Generator Voltage Regulator Circuit Wiring
Revision 1
51093
Modify 2A Diesel Generator Exhaust Expansion Joint Bolting/
Holes for Proper Alignment
Revision 0
51432
Revise CC-AA-109 to Indicate That Operating Procedures Do
Not Require Revision Prior to Operating Authorization and to
Correct the Affected Alarm Procedure
Revision 2
51433
Defeat Diesel Generator 1A Governor Auto Reset Feature
Revision 2
9500452
Install Bypass Switches and Main Control Room Alarms to
Replace Unreliable Agastat Relays
Revision 1
9600195
Unit 1 Division 2 Residual Heat Removal Service Water Keepfill
Revision 2
9600567
Revise Design Change Package to Reflect Voltage Regulator
Model Number Change
Revision 1
Number
Title
Revision/ Date
Operability Evaluations
97058
Calculation Establishing the Design Basis for the 54 Inch Bypass
Line Cannot be Located
October 24, 1997
99002
High Current Recorded on Unit 1 Residual Heat Removal
Service Water Pumps
January 27, 1999
99015
Breaker for 0DG01P Failed to Close
January 14, 1999
01020
2A Emergency Diesel Generator Cylinder Exhaust Temperatures December 11, 2001
01023
Basis for Diesel Generator Operability with Regard to Minimum
Room Temperatures
January 3, 2002
2010
Diesel Generator Facilities Ventilation System Actuator
June 4, 2002
Preoperational Tests
LST-81-038
1A Diesel Generator Five Start Capacity Test
October 9, 1981
LST-81-057
Diesel Generator Five Start Capacity Test
October 27, 1981
LST-81-061
1B Diesel Generator Start Capacity Test
December 10, 1981
LST-81-082
2A Diesel Generator Five Start Capacity Test (Test Failure)
December 7, 1981
LST-81-083
2A Diesel Generator Five Start Capacity Test
March 26, 1982
LST-82-104
Diesel Generator 0, 1A, 1B, 2A Starts on Stored Air
March 30, 1982
LST-83-212
2B Diesel Generator Start Capacity Test
January 4, 1984
Procedures
CC-AA-103-2001 Setpoint Change Control
Revision 0
Control of Design Analyses
Revision 2
CC-AA-309-1001 Guidelines for Preparation and Processing Design Analyses
Revision 0
LES-GM-103
Inspection of 4.16 Kilovolt and 6.9 Kilovolt ITE Circuit Breakers
Revision 31
LES-RH-100
Unit 1 Residual Heat Removal System Division 1 Relay Logic
Revision 17
LIP-DG-501A
Unit 1 Diesel Generator 1A Fuel Oil Storage Tank Level Switch
and Indication Calibration
June 23, 2001
LIP-DG-501B
Unit 1 Diesel Generator 1B Fuel Oil Storage Tank Level Switch
and Indication Calibration
November 22, 2000
LIP-DG-503A
Unit 1 Diesel Generator 1A Fuel Oil Day Tank Level Switch and
Indication Calibration
November 5, 2001
LIP-DG-503B
Unit 1 Diesel Generator 1B Fuel Oil Day Tank Level Switch and
Indication Calibration
June 25, 2001
LIP-DG-603A
Unit 2 Diesel Generator 2A Fuel Oil Day Tank Level Switch and
Indication Calibration
November 2, 2001
LIP-DG-603B
Unit 2 Diesel Generator 2B Fuel Oil Day Tank Level Switch and
Indication Calibration
June 23, 2001
LMS-DG-03
Diesel Generator Air Start System Pressure Reducer Adjustment Revision 2
LOA-AP-101
Unit 1, AC Power System Abnormal
Revision 15
LOA-DG-101
Diesel Generator Failure, Unit 1
Revision 2
LOA-DG-201
Diesel Generator Failure, Unit 2
Revision 1
Number
Title
Revision/ Date
LOA-FX-201
Unit 2 Safe Shutdown with a Loss of Offsite Power and a Fire in
the Control Room or Auxiliary Electric Equipment Room
Revision 6
LOP-DF-01
Startup of Diesel Building Floor Drains
Revision 2
LOP-DF-02
Filling of Diesel Building Floor Drain Loop Seals
Revision 4
LOP-DG-01
Preparation for Standby Operation of Diesel Generators
Revision 29
LOP-DG-02
Diesel Generator Startup and Operation
Revision 31
LOP-DG-03
Diesel Generator Shutdown
Revision 21
LOP-DG-04
Diesel Generator Special Operations
Revision 33
LOP-DO-01
Receiving and Sampling New Diesel Fuel Oil
Revision 23
LOP-DO-02
Transferring Diesel Fuel Oil from Storage Tanks to Day Tanks
Revision 1
LOP-DO-03
Transferring Oil to the Diesel Fire Pump Day Tanks
Revision 14
LOP-DO-04
Treating Biological Growth in Diesel Fuel Oil
Revision 0
LOP-DO-05
Diesel Fire Pump Day Tank 0FP01TA/B Draining
Revision 3
LOP-VD-01
Startup and Operation of Ventilation System for Diesel
Generators 1(2)A and Associated Diesel Fuel Storage Rooms
Revision 7
LOP-VD-02
Startup and Operation of Ventilation Systems for 1(2)B Diesel
Generator, Diesel Fuel Storage, HPCS Switchgear and HPCS
Diesel Cooling Water Pump Rooms
Revision 10
LOP-VD-03
Startup and Operation of Ventilation Systems for Diesel
Generator 0 and Associated Diesel Fuel Storage Rooms
Revision 10
LOP-VD-04
Startup and Operation of HPCS Battery Room Ventilation System Revision 3
LOP-VD-05
Shutdown of Ventilation System for Diesel Generator 1(2)A and
Associated Diesel Fuel Storage Rooms
Revision 10
LOP-VD-06
Shutdown of Ventilation Systems for Diesel Generator 1(2)B,
HPCS Diesel Fuel Storage, HPCS Switchgear and Diesel
Generator Cooling Water Pump Rooms
Revision 11
LOP-VD-07
Shutdown of Ventilation Systems for Diesel Generator Room 0
and Associated Diesel Fuel Storage Room
Revision 11
LOP-VD-08
Shutdown of Ventilation System for HPCS Battery Room
Revision 4
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
Revision 46
LOS-DG-M2
1(2)A Diesel Generator Auxiliaries Operability Test
Revision 51
LOS-DG-M3
1(2)B Diesel Generator Auxiliaries Operability Test
Revision 50
LOS-DG-Q1
Diesel Generator Auxiliaries Inservice Test
Revision 36
LOS-DG-Q2
1(2)A Diesel Generator Auxiliaries Inservice Test
Revision 29
LOS-DG-Q3
1(2)B Diesel Generator Auxiliaries Inservice Test
Revision 37
LOS-DG-R0
Diesel Generator Twenty Four Hour Run Surveillance
Revision 0
LOS-DG-R1A
1A Diesel Generator Twenty Four Hour Run Surveillance
Revision 0
LOS-DG-R1B
1B Diesel Generator Twenty Four Hour Run Surveillance
Revision 0
LOS-DG-R2A
2A Diesel Generator Twenty Four Hour Run Surveillance
Revision 0
LOS-DG-R2B
2B Diesel Generator Twenty Four Hour Run Surveillance
Revision 0
LOS-DG-SR1
Diesel Generator Simultaneous Start Test
Revision 11
LOS-DG-SR2
Diesel Generator Action Statement Operability Test
Revision 15
LOS-DG-SR3
1(2)A Diesel Generator Action Statement Operability Test
Revision 19
Number
Title
Revision/ Date
LOS-DG-SR4
1(2)B Diesel Generator Action Statement Operability Test
Revision 15
LOS-DO-SR1
Diesel Fuel Oil Storage Tank Cleaning
Revision 10
LOS-DO-SR2
Diesel Fuel Oil Analysis Verification (New Fuel Oil)
Revision 4
LOS-DO-M1
Diesel Fuel Oil Monthly Analysis Verification (Stored Fuel Oil)
Revision 3
LOS-DO-SR1
Diesel Fuel Oil Storage Tank Cleaning
Revision 10
LOS-DO-SR2
Diesel Fuel Oil Analysis Verification (New Fuel Oil)
Revision 4
LOS-RH-Q4
Quarterly Surveillance for Cycling CSCS Bypass Line Isolation
Valve
Revision 2
LTS-200-29
1B Diesel Generator Flow Balance Test, Division 3
Revision 4
LTS-500-109
Integrated Division 1 Response Time Surveillance
Revision 12
LTS-500-209
Integrated Division 1 ECCS Response Time
Revision 8
LTS-600-23
CSCS Cooling Water Screen Bypass Supply Line and Circulating
Water Pump Inlet Bays Inspection
Revision 6
LTS-800-7
Diesel Generator Trips and Trip Bypass Logic Test
Revision 18
LTS-800-101
Diesel Generator Start and Load Acceptance Surveillance
Revision 8
LTS-800-104
Unit 0 Diesel Generator Twenty-Four Hour Run Surveillance
Revision 10
LTS-800-105
1A Diesel Generator Twenty-Four Hour Run Surveillance
Revision 9
LTS-1000-29
Watertight Door and Penetration Inspection
Revision 9
NEP-11-01
Procurement and Use of Items for Repair and Replacement of
Safety Related and Regulatory Related Equipment
Revision 0
Procurement Engineering Support Activities
Revision 0
Surveillances (Date Shown Is Date Surveillance Was Completed)
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
April 19, 2000
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
April 20, 2000
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
May 17, 2000
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
June 14, 2000
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
July 12, 2000
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
August 9, 2000
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
October 3, 2000
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
November 1, 2000
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
December 1, 2000
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
December 27, 2000
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
January 24, 2001
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
February 20, 2001
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
March 21, 2001
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
April 18, 2001
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
May 16, 2001
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
June 13, 2001
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
July 11, 2001
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
September 11, 2001
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
October 3, 2001
Number
Title
Revision/ Date
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
October 31, 2001
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
November 28, 2001
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
January 22, 2002
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
February 20, 2002
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
March 18, 2002
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
April 17, 2002
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
May 13, 2002
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
July 10, 2002
LOS-DG-M1
Diesel Generator Auxiliaries Operability Test
August 7, 2002
LOS-DG-M2
1A Diesel Generator Auxiliaries Operability Test
March 14, 2000
LOS-DG-M2
1A Diesel Generator Auxiliaries Operability Test
August 30, 2000
LOS-DG-M2
1A Diesel Generator Auxiliaries Operability Test
February 13, 2001
LOS-DG-M2
1A Diesel Generator Auxiliaries Operability Test
November 21, 2001
LOS-DG-M2
1A Diesel Generator Auxiliaries Operability Test
April 9, 2002
LOS-DG-M2
1A Diesel Generator Auxiliaries Operability Test
May 9, 2002
LTS-200-10
Low Pressure Core Spray Pump Motor Cooler Service Water
Side Flowrate Test
September 7, 2000
LTS-200-10
Low Pressure Core Spray Pump Motor Cooler Service Water
Side Flowrate Test
February 21, 2002
LTS-200-11
Diesel Generator Cooling Heat Exchanger Thermal Performance
Monitoring
October 23, 2000
LTS-200-11
Diesel Generator Cooling Heat Exchanger Thermal Performance
Monitoring
October 28, 2000
LTS-200-11
Diesel Generator Cooling Heat Exchanger Thermal Performance
Monitoring
September 5, 2002
LTS-200-229
2B Diesel Generator Flow Balance Test, Division 3
March 10, 2000
LTS-200-229
2B Diesel Generator Flow Balance Test, Division 3
August 24, 2000
LTS-200-27
Diesel Generator Cooling Water System Flow Test
January 31, 1999
LTS-200-27
Diesel Generator Cooling Water System Flow Test
March 2, 2001
LTS-200-27
Diesel Generator Cooling Water System Flow Test
April 24, 2001
LTS-200-28
1A Diesel Generator Flow Balance Test, Division 2
September 30, 1999
LTS-200-28
1A Diesel Generator Flow Balance Test, Division 2
August 9, 2001
LTS-600-19
Corbicula and Zebra Mussel Inspections
March 1, 2002
LTS-600-23
CSCS Cooling Water Screen Bypass Supply Line and Circulating
Water Pump Inlet Bays Inspection
March 27, 2000
Training Request Initiated as a Result of the Inspection
2-1386
Use of Calculation Blocks to Reference Input Documents and
Output Uses of the Calculation
September 26, 2002
Vendor Manuals
IB 6.2.2.7-1G
Installation/Maintenance Instructions, Medium-Voltage Power
Circuit Breakers
Revision 0
Number
Title
Revision/ Date
J-0220.000
Gould Pump VETIP Manual
March 19, 2001
J-0620.000
May 1974
J-0154
Grove Model 80-896 Flexflo Valve with Pilot Regulator
July 18, 1963
Work Orders
00449198-01
Repair Heat Exchanger Internal Coating and Partition Plate
Revision 0
00449199-02
Remove and Reinstall Strainer Motor
Revision 0
00449199-01
Strainer Tubes are Partially Clogged with Relic Shells
Revision 0
88050398-01
Diesel Generator Cooling Water Pump Motor Replacement
Revision 0
94062049 01
Diesel Generator Cylinder Valves Will Be Replaced with New
Style Valves
December 13, 1994
94062050 01
1A Diesel Generator Cylinder Valves Will Be Replaced with New
Style Valves
December 5, 1994
94062051 01
1B Diesel Generator Cylinder Valves Will Be Replaced with New
Style Valves
December 22, 1994
94062053 01
2A Diesel Generator Cylinder Valves Will Be Replaced with New
Style Valves
November 21, 1994
94083288 01
2B Diesel Generator Cylinder Valves Will Be Replaced with New
Style Valves
December 5, 1994
99103099 01
Unit 1 Diesel Generator 1A Fuel Oil Storage Tank Level Switch
and Indication Calibration
October 9, 2001
99118412 01
Diesel Generator 1A 24-Hour Run Surveillance
May 10, 2001
99147235 01
Unit 1 Diesel Generator 1B Fuel Oil Storage Tank Level Switch
and Indication Calibration
June28, 2001
99174451 01
Unit 1 Diesel Generator 1B Fuel Oil Day Tank Level Switch and
Indication Calibration
September 18, 2001
217636 01
Unit 1 Diesel Generator 1A Fuel Oil Day Tank Level Switch and
Indication Calibration
April 10, 2002