FVY-84-101, Requests Extension Until 841101 for Responding to Generic Ltr 84-15 Re Diesel Generator Reliability.Delay Due to Extensive Engineering Efforts Associated w/8-wk 1984 Refueling Outage

From kanterella
Jump to navigation Jump to search
Requests Extension Until 841101 for Responding to Generic Ltr 84-15 Re Diesel Generator Reliability.Delay Due to Extensive Engineering Efforts Associated w/8-wk 1984 Refueling Outage
ML20095D983
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 08/16/1984
From: Murphy W
VERMONT YANKEE NUCLEAR POWER CORP.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
FVY-84-101, GL-84-15, NUDOCS 8408240004
Download: ML20095D983 (1)


Text

x VERMONT YANKEE NUCLEAR POWER CORPORATION FVY 84-101

. RD 5, Box 169, Ferry Road, Brattleboro, VT 05301 ,,,,,,,.

p ENGINEERING OFFICE 1671 WORCESTER ROAD

  • FRAMINGHAM, MASSACHUSETTS 01701 August 16, 1984 U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Attention: Office of Nuclear Reactor Regulation Mr. D.G. Eisenhut, Director Division of Licensing

References:

a) License No. DPR-28 (Docket No. 50-271) b) Letter, USNRC to All Operating Licensees, Generic Letter 84-15, dated 7/2/84

Dear Sir:

Subject:

Diesel Generator Reliability - Generic Letter 84-15 By letter, dated July 2,1984 (Generic Letter 84-15), the NRC requested that certain information be provided for use in determining the reliability of diesel generators at all operating plants. The Generic Letter requested that we forward the requested information to you within 90 days. The letter also stated that should Licensees require additional time to respond to the request that notification be made to your office within 45 days.

The purpose of this letter is to inform you that we will need additional time to respond to your request. We have recently started up from our eight week 1984 refueling outage. Due to the extensive engineering effects associated with this outage (ie., completion of our Environmental Qualification Program in accordance with 10CFR 50.49), we were not able to address your request until post-start-up. For this reason, we request an extension until no later than November 1, 1984. This date is approximately 90 days folllowing restart from our refueling outage.

We trust that our request for this schedule extension is deemed acceptable; however, should you have any questions regarding this matter, please contact us.

Very truly yours, 8408240004 840816 p DR ADOCK 05000271 PDR ^^=

Warren P. urphy Vice Pres dent and 6

V WPM /dm Manager of Operations v