3F0397-07, Monthly Operating Rept for Feb 1997 for Crystal River Unit 3

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Feb 1997 for Crystal River Unit 3
ML20136H121
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 02/28/1997
From: Dao T, Kunsemiller D
FLORIDA POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
3F0397-07, 3F397-7, NUDOCS 9703190057
Download: ML20136H121 (5)


Text

e .

92 Florida Power CORPORATION OYNS l

l

)

March 13, 1997 3F0397-07 I U. S. Nuclear Regulatory Commission Attn: Document Control Desk ,

Washington, DC 20555-0001

Subject:

Monthly Operating Report

Dear Sir:

Attached is the Crystal River Unit-3, February 1997 Monthly Operating Report. '

This report is being submitted in accordance with Technical Specification 5.7.1.2.

Sincerely,  :

~ 1

/

David F. Kunsemiller l Director, Nuclear Operations Site Support l

DFK/ff Attachment r I xc: Regional Administrator, Region 11

$ ( 1 Senior Resident Inspector ,

NRR Project Manager 9703190057 970228 PDR ADOCK 05000302 R PDR l[llUj$$$[lllllllll[ll))l CRYSTAL RNER ENEHGY COMPLEX: 15760 W Power Une St . Crystal River, Florida 344284708 . (352) 7954486 A Florida Progress Company

l OPERATING DATA REPORT DOCKET NO. 50-302 UNIT FLCRP-3 DATE MAR 3.1997 COMPLETED BY T V Dao AM TELEPHONE (352) 795-6486 1 OPERATING STATUS

1. UNIT NAME:. . . . . .. . . . . . . . . . . . CRYSTAL RIVER UNIT 3 J
2. REPORTING PERIOD:. . .. . . . ... . .. FEBRUARY  ;
3. LICENSED THERMAL POWER (MWt):. . . . . 2544 I
4. NAMEPLATE RATING (GROSS MWe):. . . .... . 890
5. DESIGN ELECTRICAL RATING (NET MWe):.. . ... ..-825' 1
6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe):.. 860-
7. MAXIMUM DEPENDABLE CAPACITY (NET MWe):. . 818
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER S THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

l

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe): N/A
10. REASONS FOR RESTRICTIONS,IF ANY: N/A THIS MONTH YR. TO DATE CUMULATIVE
11. HOURSIN REPORTING PERIOD 672.0 1,416.0 - 175,032.0 -
12. NUMBER OF HOURS REACTOR WAS CRITICAL 0.0 0.0 ' 117,416.2:
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 -0.0 ' 1,280.6 - l
14. HRS GENERATOR ON LINE 0.0 0.0 115,328.7 1
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 O.0 -
16. GROSSTHERMAL ENERGY GENERATED (MWH) 0~ 0- 268,847,210
17. GROSS ELECTR! CAL ENERGY GENERATED (MWH) 0 0 91.894,033 -
18. NET ELECTRICAL ENERGY GENERATED (MWH) -0 0 87,402,384
19. UNIT SERVICE FACTOR 0.0% 0.0% 65.9 %
20. UNIT AVAILABLE FACTOR 0.0% - 0.0% 65.9 %
21. UNIT CAPACITY FACTOR (using MDC net) 0.0% 0.0% 61.8 %
22. UNIT CAPACITY FACTOR (using DER net) 0.0% 0.0% 60.5 %
23. UNIT FORCED OUTAGE RATE 100.0 % 100.0 % 17.9 %
24. SHUTDOWNS SCHEDULED OVER NEXT SIX MONTHS (TYPE, DATE, AND DURATION OF EACH):

Continuation of the Design Basis issues outage (11 A) until December 31,1997 to implement modifications to improve various safety margins.

i 25. IF SHUTDOWN AT END OF REPORT PERIOD. ESTIMATED DATE OF STARTUP: DECEMBER 31,1997

26. UNITS IN TEST STATUS (PRIOR TO COMMERCI AL OPERATION):

l THIS ITEM IS NOT APPLICABLE TO CR-3 FORECAST ACHIEVED INITIAL CRITICAllTY NA NA

INITIAL ELECTRICITY NA NA l

COMMERCIAL OPERATION NA NA

c-. ..

l l

AVERAGE DAILY UNIT POWER LEVEL

, 1 l

DOCKET NO. 50-302 UNIT FLCRP-3 DATE MAR 3,1997 l COMFtETED BY T V Dao l TELEPHONE (352)795-6486 MONTH FEBRUARY DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1 1 0 17 0 2 0 18 0 3 0 19 0 4 0 20 0 I 5 0 21 0 6 0 22 -0 7- -0 23 0 8 0 24 0 I 9 0 25 -0 10 0 26 0 11 0 27 ~0 12 0 28 0 13 0 29 N/A 14 0 30 N/A~

15 0 31 N/A 16 0 INSTRUCTIONS:

On this format, list the daily average unit power level in MWe-Net for each day in the

! reporting month. Compute to the nearest whole megawatt.

l l

I P

l

UNIT SHUTDOWNS AND POWER REDUCTIONS ,

DOCKET NO. 50-303 UNIT FLCRP-3 ,

~

REPORT MONTH. FEBRUARY DATE MAR 3.1997 COMPLETED BY T V Dao TELEPHONE (3 %*) 795-6488  ;

NO. DATE TYPE (1) DURATION REASON (2) METHOD OF LICENSEE SYSTEM COMPONENT CAUSE AND CORRECTIVE HOURS SHUTTING EVENT CODE (4) CODE (5) ACTION TO PREVENT DOWN REACTOR (3) REPORT # RECURRENCE 97-02 970201 F 672 D 4 96-020-00 EE ENGINE Reactor remained in cold shutdown to 96-022-00 AB prepare for modifications to improve 96-022-01 AB various safety margins.

96-024-00 CH 96-024-01 CH 97-001-00 CH 1 2 3 4 5 F: FORCED REASON. METHOD EXHIBIT G -INSTRUCTIONS EXHIBfT I- SAME SOURCE S- SCHEDULED A-EQUtPMENT FAILURE 1-MANUAL FOR PREPARATION OF DATA B-MAINTENANCE OR TEST 2-tsAfiUAL SCRAM ENTRY SHEETS FOR LICENSEE C-REFUELING 3-AUTO SCRAM EVENT REPORT (LER) FILE D-REGULATORY RESTRCTION 4-CONTINUED (NUREG-0161)

E-OPERATOR TRAINING & 5-REDUCED LOAD LICENSE ADMINISTRATION 0-OTHER F-ADMHSTRATION G-OPERATONAL ERROR (EXP*JN)

H-OTHER

_ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ ______._____m

. .- MONTHLY OPERATIONAL

SUMMARY

STATEMENT l

I l

l DOCKET NO. 50 302 UNIT FLCRP-3 DATE ~ MAR 3,1997 COMPLETED BY T V Dao TELEPHONE (352)795-6486 MONTH: FEBRUARY

SUMMARY

STATEMENT:

Crystal River remained in cold shutdown through February 1997 to resolve the emergency diesel generator maximum electrical loading issue and to prepare for modifications to improve various safety margins.