Forwards Insp Rept 50-443/99-05 on 990621-0801.One Violation Re Failure to Include Multiple Components within Scope of ISI Test Program Was Identified & Being Treated as NCV, Consistent with App C of Enforcement Policy
ML20211H065
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 08/25/1999
From: Anderson C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Feigenbaum T
NORTH ATLANTIC ENERGY SERVICE CORP. (NAESCO)
Shared Package
ML20211H070 List:
References
50-443-99-05, NUDOCS 9909020006
Download: ML20211H065 (3)


See also: IR 05000443/1999005

Text

-

.,

7

August 25, 1999

Mr. Ted C. Feigenbaum

Executive Vice President and Chief Nuclear Officer

- Seabrook Station .

hlorth Atlantic Energy Service Corporation

clo Mr. James Peschel

P.O. Box 300

Seabrook, NH 03874

SUBJECT: NRC INSPECTION REPORT NO. 50-443/99-05

Dear Mr. Feigenbaum:

This refers to the inspection completed on August 1,1999 at the Seabrook Nuclear Power

Station. The enclosed report presents the results of this inspection.

The Station was operated safely during the period. Good performance was noted during routine

operations, and in response to emergent equipment problems. A conservative approach to

- operations was demonstrated by the decision to replace the "D" service water pump, and by the

formation of an Event Team to review the post-accident sampling system performance. In

contrast to the generally good performance, the transfer of the plant heat loads to the service

water emergency cooling tower was not conducted well which resulted in unplanned entries into

two Technical Specification action statements. The immediate corrective actions for this event

appeared appropriate, including a self-assessment performed to improve future performance of

"

this activity.

Based on the results of this inspection, the NRC has determined that a Severity Level IV

violation of NRC requirements occurred. The violation involved the failure to include multiple

components within the scope of the inservice test program. This violation is being treated as

Non-Cited W>lation (NCV), consistent with Appendix C of the Enforcement Policy. The NCV is

described in the subject inspection report. If you contest the violation or severity level of the

NCV, you should provide a response within 30 days of the date of this inspection report, with the

basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington DC 20555-0001; with copies to the Regional Administrator, Region 1; the Director,

Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-

0001; and the NRC Resident inspector at the Seabrook facility.

i

9909020006 990825

PDR ADOCK 05000443

G PDR

OFFICIAL RECORD COPY IE:01

. . . . _ . . . . . .

.. . .

_. ...

. _ _ _ _ _ __

j

_

..

'

Mr. Ted C. Feigenbaum 2

In accordance with 10 CFR 2.790 of the NRC " Rules of Practice," a copy of this letter and its '

enclosures will be placed in the NRC Public Document Room.

' Sincerely,

Original Signed by:

Clifford J. Anderson, Chief

Projects Branch 5

Division of Reactor Projects

Docket No. 50-443

License No: NPF-86 I

Enclosure: NRC Inspection Report No. 50-443/99-05

cc w/ encl:

B. D. Kenyon, President - Nuclear Group

J. S. Streeter, Recovery Officer - Nuclear Oversight

. W. A. DiProfio, Station Director - Seabrook Station

R. E. Hickok, Nuclear Training Manager - Seabrook Station

D. E. Carriere, Director, Production Services

L. M. Cuoco, Esquire, Senicr Nuclear Counsel

W. Fogg, Director, New Hampshire Office of Emergency Management

D. McElhinney, RAC Chairman, FEMA RI, Boston, Mass

R. Backus, Esquire, Backus, Meyer and Solomon, New Hampshire

D. Brown-Couture, Director, Nuclear Safety, Massachusetts Emergency

Management Agency

F. W. Getman, Jr., Vice President and General Counsel - Great Bay Power Corporation

R. Haliisey, Director, Dept. of Public Health, Commonwealth of Massachusetts

Seacoast Anti-Pollution League

D. Tefft, Administrator, Bureau of Radiological Health, State of New Hampshire

S. Comley, Executive Director, We the People of the United States

W. Meinert, Nuclear Engineer

!

.

'

Mr. Ted C. Feigenbaum 3

Distribution w/ encl:

H. Miller, RA/J. Wiggins, DRA

C. Anderson, DRP

R. Summers, DRP

R. Junod, DRP

._ Region I Docket Room (with concurrences)

PUBLIC

Nuclear Safety Information Center (NSIC)

NRC Resident inspector

Distribution w/enci(VIA E-MAIL):

M. Tschiltz, RI EDO Coordinator

E. Adensam, PD l-3, NRR

J. Harrison, PD l-3, NRR

J. Clifford, NRR ,

R. Correia, NRR (RPC) I

D. Screnci, PAO, ORA -

Inspection Program Branch, NRR (IPAS)

DOCDESK

l

l

DOCUMENT NAME: G:\ BRANCH 5\3-SB\lNSPEC~nSEA9905.WPD l

To receive a copy of this document, indicate in the box: "C" = Copy wHhout attachment /endoeure "E" = Copy with I

enachmenvenoo.ure w = wecopy I

OFFICE Rl/DRP l Rl/DRP ,

d

NAME RLorson r jo /, / CAnderson (l

DATE 081)199 081.h99

OFFICIAL RECORD COPY

I